                                                                                  CC Ditch Lining Case Study

 14.09.09 Case Study : Chipping Sodbury
                                                                                                          Start : 0m
In September 2009, a 140m section of ditch was lined using Concrete Cloth
by AMCO, (Amalgamated Construction). The project was commissioned by
Network Rail to provide drainage at the top of a railway embankment in
Chipping Sodbury, Gloucestershire.

This was the first time AMCO had used CC for ditch lining and the project
was heralded as a major success. CC was significantly quicker and easier
to install than conventional concrete slab construction, reducing the project
cost and time on site. The Concrete Cloth was supplied in man portable rolls
for ease of use on a site with limited access.

“Concrete Cloth is incredibly quick and easy to use. It allowed us to line over
100m of ditch in less than 8 hours, with the minimum of man power and plant                                   09:06
equipment. The time and expense saved, means I will have no hesitation in
recommending Concrete Cloth for future projects.”
                               Andrew Gurd, Drainage/Construction Manager                                      16m
                                            Amalgamated Construction Ltd




                                                                                                              09:34

                                                                                                               32m




                                                                                                              10:06

                                                                                                       Finish : 140m




                                                                                                              12:02


For further information, please contact :
Concrete Canvas Ltd. (UK)                                                                        Tel : 0845 680 1908
Unit 3, Block A22,                                                                Email : info@concretecanvas.co.uk
Treforest Ind. Estate,
CF37 5SP, UK                                                                               www.concretecanvas.co.uk
                                                                    TM                              Concrete Cloth (CC)
                                                                                       Method Statement : Ditch Lining 2/4

 Lining of Ditches using Concrete Cloth

Concrete Cloth (CC) can be rapidly unrolled to form a
hardened, water proof concrete ditch or tank lining. It will
conform to a range of ditch profiles and curves and requires
no specialist plant equipment for installation. CC has a
minimum design life of over 10 years and is significantly
quicker and less expensive to install compared to
conventional concrete ditch lining. Two men should be able to
line a 60° 300mm V-ditch in 15 minutes/8m length.


  Technical Background

CC consists of a 3-dimensional fibre matrix containing a
specially formulated dry concrete mix. A PVC backing on one
surface ensures the material is completely water proof. The
material can be hydrated either by spraying or by being fully
immersed in water. Once hydrated the material remains
flexible and workable for 2 hours and gains 80% of its 28 day
strength in the first 24 hours. CC is available in 3 thicknesses,
4, 8 and 13mm. CC8 (8mm) is recommended for most ditching
applications.




 Ditch Design

CC comes in a standard roll width of 1.1m and this should be taken into account when designing the ditch profile in order to
minimise wastage. For the best results we recommend using a 60 degree V-ditch profile which can be dug using a standard
bucket attachment. A minimum of 100mm should be allowed at overlaps between layers of Cloth and at the edge of the ditch.
Figures 1-3 show ditch profiles using 1, 2 and 3 layers of CC.
Fig. 1                              Fig. 2                                                  Fig. 3

                                                                                                     100                                                   100



                                             100
                                                                          100
                                                                                                               CC Layer 1                CC Layer 2



     100
                                                       CC Layer 1
                                                                                                                                                      0
                                                                                                       90




                                                                                                                                                      90




                                                                                                                            CC Layer 3
                                                                                                           0




             CC Layer
                                                                         0
                                               60




                                                                         60




                                                          CC Layer 2
                                                 0
     30




                        0
                        30
         0




                                                                                                                                900
                                                             600
               300
                        Substrate                                               Substrate                                                                        Substrate

300mm x 300mm x 300mm ditch         600mm x 600mm x 600mm ditch                             900mm x 900mm x 900mm ditch
1 Cloth Layer                       2 Cloth Layers                                          3 Cloth Layers
100mm edge overlap                  130mm edge overlap                                      150mm edge overlap



For further information, please contact :
Concrete Canvas Ltd. (UK)                                                                                           Tel : 0845 680 1908
Unit 3, Block A22,                                                                                   Email : info@concretecanvas.co.uk
Treforest Ind. Estate,
CF37 5SP, UK                                                                                                  www.concretecanvas.co.uk
                                                       TM                       Concrete Cloth (CC)
                                                                   Method Statement : Ditch Lining 3/4

Method Statement

                                                                 1. Ground Preparation
                                                            1.
                                                                 The ditch should be dug to give the desired V-profile. The ditch
                                                                 should have smooth, flat sides that have been well tamped.
                                                                 Loose soil, soft ground, protruding rocks or voids may result in
                                                                 the CC becoming damaged and could lead to distortion of the
                                                                 ditch profile. Vegetation should be removed as it can rot and
                                                                 form voids underneath the CC.
     30




                    0
                  30
     0




           300




                                                                 2. Unroll CC
                                                            2.
                                            Direction of
                                            water flow
                                                                 CC can either be supplied in man portable lengths
                                                                 (8 linear metres, 105.6kg), for manual application, or large rolls
                                                                 (120 linear metres, 1400kg) if plant equipment is available. The
                                                                 application process is the same for either method. Unwrap the
                                                                 CC, taking note of the roll direction as indicated on the packaging.
                                                                 Ensure that the fibrous surface of the CC is facing upwards and
                                                                 the water impermeable PVC membrane is in contact with the
                                                                 ground. Align the CC roll with the ditch and simply unroll down it’s
                                                                 entire length. Manually press and position the Cloth into the ditch
                                                                 starting at the outflow point.



                                                                  3. Peg down Cloth
                                                            3.
                                                                 Once the CC has been positioned, it should be pegged at 2m
                                                                 intervals along it’s length and at every joint to prevent uplift. It
                                                                 is recommended to use Ø18mm 350mm roller road pins which
                                                                 can be purchased from Concrete Canvas Ltd. The pegs
                                                                 should be hammered or driven through the unset cloth approx.
                                                                 50mm from the edge of the material ensuring that the hook is
                        2m                                                                          facing outwards from the
                                                                                                    ditch and driven into the soil
                                                                                            350     (see left).



                                                                  4. Joining adjacent CC layers
                                                            4.
                                            Direction of
                                            water flow           When positioning subsequent CC rolls, ensure that there is at
                                                                 least a 100mm overlap between layers. Also ensure all
                                                                 overlaps are in the direction of water flow to minimise leakage
                                                                 at the joints. Joints can be sealed to withstand over 3m of
                                                                 water pressure.

                                                                 If a completely waterproof seal is required, we recommend
            100                                                  using a jointing compound such as Tremflex 40, made by
                                                                 Tremco. This should be applied after the Cloth has set – see
                                                                 “CC Joint sealing Guide” for more details.




For further information, please contact :
Concrete Canvas Ltd. (UK)                                                                       Tel : 0845 680 1908
Unit 3, Block A22,                                                               Email : info@concretecanvas.co.uk
Treforest Ind. Estate,
CF37 5SP, UK                                                                              www.concretecanvas.co.uk
                                                           TM                               Concrete Cloth (CC)
                                                                               Method Statement : Ditch Lining 4/4

Method Statement cont.


                                                                5.           5. Hydration

                                                                            Once positioned, CC can be hydrated by spraying with water
                                                                            (sea water may be used). Do not jet water directly onto the
                                                                            cloth to avoid washout. An excess of water should be used as
                                                                            CC cannot be over hydrated. Ideally, the ditch outlet should
                                                                            be temporarily blocked and the entire ditch filled so that the
                                                                            water pressure forces the cloth to conform to the ditch profile.
                                                                            If this is not possible the ditch should be re-sprayed after 4 – 6
                                                                            hours. CC8 requires a minimum of 6 lt/sqm of water.

                                                                            Sandbags should be placed on top of overlapped joints to
                                                                            ensure good contact between layers during setting.

                                                                             6. Junctions and Terminals
                                                                6.
                                                                            CC is very easy to shape before setting and can be easily
                                                                            manipulated to form ditch junctions and terminals. It can be
                                                                            cut using a “snap off” type disposable knife.

                                                                            Please refer to the “CC Health and Safety Data Sheet” for
                                                                            guidance on safe handling of Concrete Cloth.




                                                                             7. Setting
                                                                7.
                                                                            Once hydrated, CC remains workable for approx. 2 hours. In
                                                                            warm climates, working time may be reduced. CC will harden
                                                                            to 80% of its 28 day strength in 24 hours and is ready for use.

                                                                            CC has a wide range of other applications within the civil
                                                                            sector including track way, dust suppresion, building cladding
                                                                            and roofing applications. If you require any further information
                                                                            or have ideas on alternative applications please contact
                                                                            info@concretecanvas.co.uk



FAQS

Q. Can CC be laid in the rain?

A. Yes – however once wet it will only remain workable for 2 hours

Q. Can CC be laid in very cold conditions?

A. CC can be laid at temperatures below freezing but requires a special method. If the temperature is below or likely to fall below freezing in the
first 24 hours please contact Concrete Canvas Ltd. for technical advice.

Q. What is the shelf life of packaged CC and how should it be stored prior to use?

A. CC is supplied in air tight PE packaging film and has an unopened shelf life of over 2 years. CC should be stored in dry conditions, under
cover and away from direct sunlight. It should remain in its sealed packaging until ready for use.


For further information, please contact :
Concrete Canvas Ltd. (UK)                                                                                   Tel : 0845 680 1908
Unit 3, Block A22,                                                                           Email : info@concretecanvas.co.uk
Treforest Ind. Estate,
CF37 5SP, UK                                                                                          www.concretecanvas.co.uk

				
DOCUMENT INFO
Shared By:
Categories:
Stats:
views:101
posted:5/13/2011
language:Italian
pages:4