CAIR and CAMR Permitting - Region 7

Document Sample
CAIR and CAMR Permitting - Region 7 Powered By Docstoc
					CAIR and CAMR Permitting
EPA Region 7 Workshop Kansas City, Kansas August 16, 2007 Robert Miller

What is a CAIR or CAMR Permit?


The portion of the title V permit that contains the CAIR or CAMR applicable requirements Should be a complete and separable portion of the title V permit All CAIR requirements will be contained in one portion of the title V permit; CAMR requirements in another portion





What Sources are Required to Have a CAIR or CAMR Permit?
 Any

CAIR or CAMR source required to have a title V permit must have a CAIR or CAMR permit required to have a title V permit? No CAIR or CAMR permit required either

 Not

Who Administers the CAIR and CAMR Permits?


The title V permitting authority administers CAIR and CAMR permits Under CAIR and CAMR, the title V permitting authority administers CAIR and CAMR permits regardless of whether a State has an approved CAIR SIP or CAMR State plan So, the title V permitting authority always receives CAIR and CAMR apps, acts upon them, and administers the CAIR and CAMR portions of the title V permit





When Must CAIR and CAMR Permit Applications be Submitted?
 For

CAIR NOx Annual and CAIR NOx Ozone, 18 months or such lesser time before January 1, 2009 CAIR SO2 and CAMR, 18 months or such lesser time before January 1, 2010 apps submitted with the title V renewal application

 For

 Renewal

A Complete CAIR or CAMR Permit App Consists of:
 Identification

of the CAIR or CAMR source of the units subject to CAIR

 Identification

or CAMR
 The

CAIR or CAMR standard requirements

What Do the Standard Requirements Say?
 Permitting

requirements

 Monitoring,

reporting, and recordkeeping requirements

 Allowance

holding requirements

 Excess

emission requirements

 Recordkeeping

and reporting requirements

CAIR and CAMR Permit Content


CAIR and CAMR permits contain what is in the CAIR and CAMR permit applications: – Identification of the source – Identification of the units – Standard requirements Most CAIR and CAMR permits will closely resemble other CAIR and CAMR permits No allowance allocations in the CAIR or CAMR permit





CAIR-CAMR Permit Issuance Deadlines and Permit Terms
 CAIR

and CAMR portions of the title V permits are incorporated into title V permits in accordance with the permitting authority’s title V regs and CAMR permit terms coordinated with the overall title V permit term

 CAIR

CAIR and CAMR Permit Mods
 Incorporation

of CAIR and CAMR requirements into existing title V permits governed by permitting authority’s title V regs

 Modifications

to CAIR and CAMR portions of title V permits also governed by permitting authority’s title V regs