									Jubail United Petrochemical Company (United)                                                Site Safety Procedures Manual
United Olefins Complex Project                                                                            Rev 1, July 2001
Jubail, Saudi Arabia                                                                                           Page 1 of 4




                                                      TABLE OF CONTENTS


     MANAGEMENT STATEMENT
           1.         Mission Statement


     ADMINISTRATIVE
           2.         Safety and Accident Prevention
           3.         Discipline
           4.         New Hire Orientation
           5.         Accident Reporting and Investigation
           6.         Near Miss
           7.         Recordkeeping Requirements
           8.         Safety Action Plans / Safety Task Assignment / Supervisor’s Safety Logbook / Safe Work Plans
           9.         Weekly Safety Assessment
           10.        Safety Audit
           11.        Daily Safety Monitoring (Safety Discrepancy Logbook)
           12.        Emergency Services
           13.        Medical Facility and First Aid Supplies
           14.        Emergency Evacuation Plan
           15.        Severe Weather Plan
           16.        Security
           17.        Subcontractor Requirements / Responsibilities
           18.        Housekeeping
           19.        Hazardous Waste Management
           20.        Competent Person Designation


     PERSONAL PROTECTIVE EQUIPMENT
           21.        Personal Protective Equipment
           22.        Fall Protection Devices
           23.        Static Lines /Horizontal Life lines
           24.        Respiratory Protection Program


     OPERATIONS
           25.        Compressed Gas and Oxygen Cylinders
           26.        Barricade Program
           27.        Permits

D:\Docstoc\Working\pdf\87a284d1-3f1f-48ee-972c-402e9dff69b4.doc            GENERAL SITE CONDITIONS AND SAFETY PROCEDURES
Jubail United Petrochemical Company (United)                                             Site Safety Procedures Manual
United Olefins Complex Project                                                                         Rev 1, July 2001
Jubail, Saudi Arabia                                                                                        Page 2 of 4



           28.        Hot Work
           29.        Cold Work
           30.        Confined Spaces
           31.        Night Work
           32.        Hazardous Energy Control (Tag out and Lock out)
           33.        Grounding Conductor / Assured Grounding
           34.        Live Electrical (High Voltage)
           35.        Hot Tapping
           36.        First Line Breaks
           37.        Control of Radiation Hazards (Radiography)
           38.        Powder Actuated Tools
           39.        Hand and Power Tools
           40.        Excavation and Trenching
           41.        Portable Ladder Control and Inspection
           42.        Scaffolding
           43.        Suspended Work Basket / Platform
           44.        Open Hole / Grating Removal
           45.        Steel Erection
           46.        Reinforcing Steel (Rebar)
           47.        Concrete Operations
           48.        Rigging
           49.        System / Equipment Testing
           50.        Piping Pressure Testing
           51.        Equipment Preservation (Nitrogen Blanketing)
           52.        Abrasive Blasting
           53.        Fire Prevention / Protection
           54.        Flammable and Combustible Liquids
           55.        Mobile Equipment
           56.        Equipment Operator Training
           57.        Crane Operator Qualification and Licensing
           58.        Motor Vehicles
           59.        Powered Industrial Trucks (Forklifts)
           60.        Mobile Cranes
           61.        Tower Cranes
           62.        Crane Lift Procedure
           63.        Crane Work Near Overhead Electric & hazardous Pipelines
           64.        Piling Operations

D:\Docstoc\Working\pdf\87a284d1-3f1f-48ee-972c-402e9dff69b4.doc          GENERAL SITE CONDITIONS AND SAFETY PROCEDURES
Jubail United Petrochemical Company (United)                                             Site Safety Procedures Manual
United Olefins Complex Project                                                                         Rev 1, July 2001
Jubail, Saudi Arabia                                                                                        Page 3 of 4



           65.        Standby Man
           66.        Temporary Facilities
           67.        High Pressure Water Cleaning (HPWC)
           68.        Pre-commissioning and Start-up
           69.        Office Safety


     OCCUPATIONAL HEALTH
           70.        Eating and Sanitation
           71.        Hearing Conservation (Occupational Noise)
           72.        Hazard Communication
           73.        Bloodborne Pathogens
           74.        Lead Exposure Control
           75.        Asbestos Handling Procedures
           76.        Non-Friable Asbestos Handling
           77.        Inorganic Arsenic Exposure Control
           78.        Normally Occurring Radioactive Material (TENORM)
           79.        Benzene
           80.        Hydrogen Sulfide
           81.        Heat Stress
           82.        Illumination


     TRAINING
           83.        Instruction and Craft Specific Training


     ENVIRONMENTAL
           84.        Environmental

     RECORDS RETENSION
           85.        Records Management (Retention)




D:\Docstoc\Working\pdf\87a284d1-3f1f-48ee-972c-402e9dff69b4.doc          GENERAL SITE CONDITIONS AND SAFETY PROCEDURES

								