									                                                                                       Status of Major Railway Projects of North Eastern (NE) Region
                                                                                                                       (As on end of July'2010)
New line from Jiribam to Imphal (98 Km) (Tupul) (National Project)
Sl Name of project    Length    Estimated     Whether      Funding        Year of sanction of   Original target of      Whether detailed project report           Whether land acquisition done                 Whether Forest/                 Whether utility shifting done
No.                   of Rly.     Cost       declared as    pattern             project            completion                     prepared                               (up to Jujy'10)                 environment/wildlife clearances
                     Line (KM) (Rs. in Crs.)  National                                                                                                                                                             obtained
                                               Project
1         2               3          4             5           6                   7                     8                               9                                        10                                    11                                       12
1 New line from          84      3123.52       National    Rly. 25%             2003-04              March'11        Yes.                                         654.462 hect.out of total scope of                    NA                       Utility shifting will be done as
  Jiribam to                                    Project    ABS: 75%                              (Jiribam-Tupul)     Jiribam-Tupul                                 1160.56 hect. in Jiribam - Tupul                                               work progresses and is not
  Imphal (Tupul)                                                                                                     ●Pt. I detailed estimate for survey                      section.                                                                       constraint.
                                                                                                                     sanctioned for Rs. 7.66 Cr. in Jan'05.
                                                                                                                     ●Pt. II detailed estimate for 26.5 Kms
                                                                                                                     sanctioned for Rs. 483.3 Cr. in June'08.
                                                                                                                     ●Pt. III detailed estimate for 28.659 Kms
                                                                                                                     sanctioned for Rs. 663.8 Cr. in Jan'09.
                                                                                                                     ●Pt. IV & Final detailed estimate for the
                                                                                                                     balalce 28.8 Kms under process in
                                                                                                                     Railway Board.
                                                                                                                     Tupul-Imphal
                                                                                                                     ●Final location survey in progress.
                                                                                                                     Detailed Estimate will be submitted to
                                                                                                                     Rly. Bd. for sanction in Dec'10.




             Construction progress (in %) up to July'10                    Milestones to be       Final date of         Constraints/reasons for delay in          Steps proposed to be taken by           Specific requirements action                       Remarks
      Earthwork     Minor      Major       Tunneling             Track     achieved during       commissioning                  implementation                       the state for empediting              expected from the Central
                   Bridges    Bridges                           linking   construction, along                                                                               completion.                Ministriss for expediting completion
                                                                            with timelines



           13           14          15           16               17              18                    19                                    20                                     21                                   22                                     23
          29%          23%          1%         0.04%       ,-         Jiribam-Tupul              Jiribam-Tupul:      ●FLS by RITES took almost 5 years to        State to ensure:                      ●Deployment of a dedicated Battallion   (i) It is not possible to factor in
   (127.26 lakh cum (20 out of (Substructur (15 m out of              section                         Mar'14         complete due to security problem &                  ●Fearless working             of security by BSF/CRPF for the         the delays that may be caused
     out of 439.61     89)      e work in     37623 m)       Will be ●Earthwork & Minor          Tupul-Imphal:       difficult hilly terrain.                    conditions, free of extorsion,        projectt.                               due to security related issues
      lakh Cum)                progress at                  taken up Br.: Mar'13                      Mar'16         ●Severe insurgency, frequent bandhs,        bandhs, economic blockades to         ●Improvement of NH-53 including         and other hinderances viz.
                                 2 major                       on     ●Major Bridge: Dec'13                          economic blockades on N.H -53 & N.H -       enable Rly to carryout work           strengthening /rebuilding of 7 weak     economic blockade etc. in this
                                 bridges)                  completio ●Tunnels: Dec'13                                39 etc.                                     uninteruptedly.                ●      bridges by BRO.                         region due to uncertainity. The
                                                              n of    ●Track linking: Feb'14                         ●Almost non-existent feeder roads for       Strengtheing and blacktopping of                                              delay, if any, on such account
                                                           formation. ●Commissioning:                                reaching project sites in the interior of   Uchathal-Leisabethal road near                                                will have to be considered at
                                                                      Mar'14                                         difficult hilly terrain.                    Jiribam.                                                                      appropriate time as per
                                                                      Tupul-Imphal section                           ●Due to 7 weak bridges on NH-53 and                  ●Strengtheing and                                                    prevailing conditions.
                                                                      ●FLS : Dec'10                                  very poor road condition, movement of       blacktopping of Noney- Maranching                                             (ii) Time lines will need review
                                                                      ●Sanction of Detailed                          heavy machinery and material is not         road between Noney-Tupul and                                                  considering security scenario
                                                                      estimate : March'11                            possible to site from Silchar side and      extension of the same up to                                                   and geological conditions.
                                                                      ●Land Acquisition:                             NH-39 is not available due to frequent      haochong.
                                                                      June'11                                        economic blockade                           ●Setting up a hospital at Noney for
                                                                      ●Earthwork & Minor                                                                         trauma care as thousands of
                                                                      bridges: Feb'14.                                                                           workers are engaged on hundreds
                                                                      ●Major bridges:Feb'14.                                                                     of heavy machinery. No medical
                                                                      ●Tunnels: Dec'15.                                                                          facilty existing within 2-3 hrs. of
                                                                      ●Track linking: Feb'16.                                                                    travel from project site.
                                                                      ●Commissioning:
                                                                      Mar'16.
                                                                                        Status of Major Railway Projects of North Eastern (NE) Region
                                                                                                                           (As on end of July'2010)
Rail-Cum-Road Bridge over river Brahmaputra near Bogibeel with link lines on North & South Bank (72 Km).
Sl Name of project       Length    Estimated     Whether      Funding      Year of sanction of      Original target of      Whether detailed project report             Whether land acquisition done                      Whether                  Whether utility shifting done
No.                      of Rly.      Cost      declared as    pattern           project               completion                     prepared                                 (up to June'10)                   Forest/environment/wildlife
                        Line (KM) (Rs. in Crs.)  National                                                                                                                                                            clearances obtained
                                                  Project
1         2                 3           4             5           6                 7                      8                                  9                                        10                                    11                                    12
2 Rail – Cum -           74 Kms     3230.01       National    Rly: 25%           1997-98                March'12                             Yes                                      Yes.                                   NA                                    NA
  Road Bridge                                      Project    ABS: 75%                                                                                                  505.94 hect. out of total scope of
  over    river                                                                                                                                                                   505.94 hect.
  Brahmaputra
  near Bogibeel
  with link lines
  on North      &
  South Banks.

             Construction progress (in %) up to July'10                    Milestones to be           Final date of         Constraints/reasons for delay in            Steps proposed to be taken by           Specific requirements action                   Remarks
      Earthwork     Minor      Major       Tunneling            Track      achieved during           commissioning                  implementation                         the state for expediting              expected from the Central
                   Bridges    Bridges                          linking    construction, along                                                                                    completion.                 Ministries for expediting completion
                                                                            with timelines



            13              14         15           16           17                  18                    19                                 20                                         21                                   22                                     23
         96.6%            96.2%      94.1%     No tunnel in    49.9%      ●Chalkhowa-                   March' 14        ●The progress of the projects is              ●State Govt. to ensure law & order    ●Fund allotment as per requirement.    Timeline may be reviewed after
   (278.76 lakh cum      (98 out    (16 out      project.      (45.40     Moranhat (44 Km) rail                          frequently disturpted due to                  and security at work sites for                                                finalisation of tender for super
   out of total scope    of 103)     of 17)                   Km out of   link on South Bank -                           militant/antisocial activities in the area,   uninterupted working.                                                                     structure.
     of 288.52 lakh                                            91.01)     Completed.                                     extortion demands by militant/antisocial      ●Assam PWD(NH) to expedite
          cum)                                                            ●South Guide bund -                            elements, disturbances at work sites          construction of approach road links
                                                                          Completed.                                     and security threats to Rly. officials and    on North & South banks and timely
                                                                          ●Raising &                                     contractor personal.                          complete it to match completion of
                                                                          strengthening of                               ●Meagre allotment of fund in the initial      main bridge.
                                                                          Dykes - completed.                             years upto 2005-06.
                                                                          ●North Guide bund -
                                                                          June'11.(Work
                                                                          completed upto safe
                                                                          level of 105 m RL)
                                                                          ●Main Bridge
                                                                          Substructure - June'13.
                                                                          ●Main Bridge
                                                                          Superstructure -
                                                                          March' 14.
                                                                          ●Track linking &
                                                                          commissioning -
                                                                          March' 14.
                                                                                            Status of Major Railway Projects of North Eastern (NE) Region

                                                                                                                               (As on end of July'2010)


New line from Sivok-Rangpo (National Project) (44.39 Km)
Sl Name of project      Length    Estimated     Whether          Funding       Year of sanction of      Original target of      Whether detailed project report         Whether land acquisition done      Whether forest/environment/wildlife     Whether utility shifting done
No.                     of Rly.      Cost      declared as        pattern            project               completion                     prepared                             (up to July'10)                    clearances obtained
                       Line (KM) (Rs. in Crs.)  National
                                                 Project




 1         2                3           4               5             6                 7                       8                               9                                         10                                   11                                 12
 7 New line from          44.39      3380.57        National     Rly: 25%        2008-09 (suppl.)            Dec'15          Detailed Estimate under process in        Land acquisition proposal being     Applied for forest clearance (for 5    Not yet. But no constraint for the
   Sivok to Rangpo                                   Project     ABS: 75%                                   (Tentative)      Railway Board.                            prepared for first 5 Km.            Km)where alignment is final.           project


               Construction progress (in %) up to July'10                      Milestones to be           Final date of        Constraints/reasons for delay in         Steps proposed to be taken by         Specific requirements action                    Remarks
        Earthwork     Minor      Major       Tunneling             Track       achieved during           commissioning                 implementation                      the state for expediting            expected from the Central
                     Bridges    Bridges                           linking     construction, along                                                                                completion.               Ministries for expediting completion
                                                                                with timelines

            13              14          15              16           17                  18                    19                              20                                       21                                    22                                 23
    Review of alignment by the consultant appointed by IRCON is in            Will be decided in              Dec'15                           NIL                     ●Forest clearance on Priority.      ●Fund allotment as per requirement.    Project has been entrusted to
    progress. IRCON have award and contract for alignment design and          consultation   with                                                                      ●Land acquisition on Priority. 
    ● Expediting forest clearance.         M/s.IRCON for execution. MOU
    Geological investigation on 16-7-10 and Geophysical investigation for     IRCON after review                                                                                                                                                  as approved by Railway Board
    tunnel No. 1 on 14-7-10. Application for forest clearance for survey of   and finalisation of                                                                                                                                                 signed with IRCON on 7-5-10.
    land acquisition has been made to State Govt.                             alignment.




                                                                                            Status of Major Railway Projects of North Eastern (NE) Region
                                                                                                                               (As on end of July'2010)

New line from Harmuti to Itanagar (20 Km)
Sl Name of project      Length    Estimated     Whether          Funding       Year of sanction of      Original target of      Whether detailed project report         Whether land acquisition done                    Whether                   Whether utility shifting done
No.                     of Rly.      Cost      declared as        pattern            project               completion                     prepared                             (up to July'10)                 Forest/environment/wildlife
                       Line (KM) (Rs. in Crs.)  National                                                                                                                                                           clearances obtained
                                                 Project
 1          2               3          4            5              6                 7                     8                              9                                      10                                          11                                    12
 9 New BG line           20 Km      160.48         No         Rly: 100%           1996-97               March'12      Detail estimate sanctioned by Railway    103.10 hect. land received out of                        Not required.             Will be done as work progresses
    from Harmuti to                                                                                                   Board on 31-01-2008                      total scope of 150.00 hect. No land                                                      and it not a constraint.
    Naharlagun of                                                                                                                                              received in Assam portion.
    Harmuti -
    Itanagar project.
Note: Government of Arunachal Prodesh has agreed to terminate the Railway line at Naharlagan station as communicated Vide letter no. TPT/RL/16/2009/514 dated 17-03-2010.

               Construction progress (in %) up to July'10                      Milestones to be           Final date of        Constraints/reasons for delay in         Steps proposed to be taken by         Specific requirements action                    Remarks
                                                                               achieved during           commissioning                 implementation                      the state for expediting            expected from the Central
      Earthwork         Minor         Major        Tunneling       Track      construction, along                                                                                completion.               Ministries for expediting completion
                        Bridges      Bridges                      linking       with timelines
          13               14           15             16            17                18                       19                              20                                     21                                     22                                  23
                         40.9%       10.7%      Not involved.        NIL      ●Earthwork & Minor            March'12         ● Delay in land acquisition by Govt. of   ● Expeditious land acquisition by   ●Resolving dispute of onwership of     (i) No land in Assam handed
        37.1%%         (18 out of (substructur                     (will be   bridge - Jan'12                                Assam. Out of 6 LA cases, in 5 cases      Govt. of Assam                      land at State boundary between         over till date for execution.
(14.85 lakh cum out of    total   e of 4 out of                   taken up    ●Major bridge - Feb'12.                        4(1) & 6(1) Notification issued but       ● Resolving dispute of onwership    Arunachal Pradesh & Assam.             (ii) Target will have to be
   40.00 lakh cum)      scope of total scope                         on       ●P.way work - Mar'12.                          cancelled due to iincorrect land          of land at State boundary between   ●Allotmemnt of fund as per             reviewed based upon land
                        44 nos.) of 12 major                     completio                                                   schedule. Now fresh section 4(1) & 6(1)   Arunachal Pradesh & Assam.          requirement.                           acquisition.
                                    bridges.)                        n of                                                    Notification to be issued. In one case,
                                                                 formation)                                                  with DC/Lakhimpur, section 4(1) & 6(1)
                                                                                                                             Notification is under process.
                                                                                                                             ● Dispute of onwership of land at State
                                                                                                                             boundary between Arunachal Pradesh &
                                                                                                                             Assam.
                                                                        Status of Major Railway Projects of North Eastern (NE) Region
                                                                                               (As on end of July'2010)
Gauge Conversion of Lumding-Silchar-Jiribam, Badarpur to Baraigram & Baraigram to Kumarghat (368.46 Km) (National Project)
Sl       Name of           Length    Estimated    Whether    Funding            Year of        Original         Whether detailed     Whether land acquisition                Whether              Whether utility
No.       project          of Rly.      Cost     declared as pattern          sanction of      target of     project report prepared   done (up to July'10)          Forest/environment/w          shifting done
                          Line (KM) (Rs. in Crs.) National                      project       completion                                                               ildlife clearances
                                                   Project                                                                                                                   obtained

 1           2                3             4               5         6            7              8                      9                           10                          11                       12
 1    Gauge                367.79        3846.09          Yes       Rly :       1996-97       March'2009               Yes.              500.39 hect. out of total   3.6 hect. land which      Existing MG line is
      Conversion of          Km                       Declared as   25%                                          Revised detailed        scope of 509.810 hect.      was acquired and          crossing BG alignment
      Lumding –                                        a National   ABS :                                     estimate sanctioned by     acquired.                   handed over by N. C.      at      about     60
      Silchar –                                        Project in   75%                                         Rly. Bd. on 7.5.10.                                  Hills is being disputed   locations.Work in these
      Jiribam,                                            2004                                                                                                       as forest land by         locations will be done
      Badarpur to                                                                                                                                                    Forest Deptt. of Assam    in Mega block of 6
      Baraigram &                                                                                                                                                    Govt. Proposal for the    months.
      Baraigram –                                                                                                                                                    same has been
      Kumarghat                                                                                                                                                      submitted to Forest
                                                                                                                                                                     Deptt. in July'2009 and
                                                                                                                                                                     is under process.



                    Construction progress (in %) up to July'10             Milestones to     Final date of     Constraints/reasons        Steps proposed to be             Specific                 Remarks
      Earthwork           Minor         Major          Tunneling     Track  be achieved      commissionin          for delay in            taken by the state for    requirements action
                          Bridges      Bridges                      linking    during              g             implementation           expediting completion.      expected from the
                                                                           construction,                                                                             Central Ministries for
                                                                             along with                                                                                   expediting
           13                 14             15            16      17             18              19                      20                           21                     22                        23
         94.6%              91.6%      Substructure      50.3%   18.9% ●Dayang Br. -           Dec'2013      ●Severe        militant     ●Condition of road and Allotment of fund as        ●All targets are subject
(641.16 lakh cum out of   (597 Nos.    - 77.9%         (5357.60  (71.63   June'11                            activities and security     weak/dammaged bridges to per requirement.          to        tangible
        677.83)           out of 652   (74 Nos. out   Rm out of Km out of ●Tunnel-10 -                       problems during period      be improved to facilitate                          improvement in road
                            Nos.)      of 95 Nos.)    10650 Rm) 387.56 m) Oct'13                             2006 to 2009 and steep      smooth movement of heavy                           condition       and
                                       Superstructu                       ●Barak Br. -                       rise in steel prices.       constuction    machinary                           weak/dammaged
                                       re - 39.2%                         June'11                            ●Very      bad     road     equipments & materials.                            bridges by Dec'10.
                                       (51 Nos. out                       ●Br. No. - 543 -                   condition         and       ●Early approval of forest                          ●Resolution of issues
                                       of 130 Nos.)                       Dec'11                             weak/dammaged road          land due to which work of                          mentioned in Column
                                                                                                             bridges between Lank &      Br. No. 127 & 129 is                               21.
                                                                                                             Lumding, Lumding &          presently suffering..
                                                                                                             Haflong and Silchar to      ●Early land acquisition and
                                                                                                             Haflong. As detailed in     handing over to Railway.
                                                                                                             Annex - I.                  ●State Govts. to make
                                                                                                             ●The delay in acquisition   necessary arrangement for
                                                                                                             of forest land for Bridge   stocks of food grains, POL,
                                                                                                             no. 127 & 129. Forest       etc. to cater Mega block
                                                                                                             Department clearance        period.
                                                                                                             awaited.
                                                                                                             ●Land acquisition in
                                                                                                             Cachar, Hailakandi and
                                                                                                             Karimganj districts.

								