Monthly Project Management Report

Description

Monthly Project Management Report document sample

Document Sample
scope of work template
							MONTHLY PROGRESS REPORT
    Current Measure I Bond Projects


           March 2008


                 Prepared by the
            Project Management Team
                             TABLE OF CONTENTS


Introduction

     Executive Summary                              page 3

Capital Projects - Construction
     Community Education Building                   page 5

     Science/Health Occupations Complex             page 7

Capital Projects – Planning/Design
     Public Safety Complex                          page 9

     Child Care Addition                            page 10

     One Stop Student Services Building             page 11

     Industrial Technology Modernization/Addition   page 12

Scheduled Maintenance Projects
     LVC EMS Upgrade & HVAC Repair                  page 13

Technology Projects
     Mainframe Replacement                          page 14

     Equipment Modernization                        page 15
                                   EXECUTIVE SUMMARY


                                    CAPITAL PROJECTS

CONSTRUCTION:

Community Education Building: This project is substantially complete. All closeout items
and change orders have been submitted to DSA (Division of the State Architect) for approval.
Of the $6,771,500 budget, a total of 100% has been expended and the percent of construction
contract changes is 2.4%.

Science/Health Occupations Complex: All three phases of construction are substantially
complete. Submission, review, and approval of remaining closeout documentation and DSA
change orders continue. An energy rebate of $20,359 from PG&E was received in March for
this project increasing the contingency budget. Of the revised $18,453,460 budget, a total of
99% has been expended and the percent of construction contract changes remains at 6%.

PLANNING/DESIGN:

Public Safety Complex: The project architect, MVE Institutional, has begun preliminary plans
for the project. Preliminary design workshops are being scheduled and site utility and soils
surveys are being procured. Preliminary design is planned to be completed in the fall of 2008.
The new budget for this project is $46,163,902, with a total of 0.4% expended thus far.

Childcare Addition: MVE Institutional completed the final project proposal (FPP) in December
2007, and presented the conceptual design to the board of trustees on January 29, 2008. The
FPP was approved by the board at the March 18, 2008 meeting. MVE will begin preliminary
design in conjunction with the development of the public safety project. Of the $6,500,000
project budget, a total of 0.6% has been expended.

One Stop Student Services Center: Steinberg Architects has completed preliminary plans
and district review of these plans by the project stakeholders will occur in April. Design approval
will be sought at the April 15, 2008 board meeting. Working drawings will commence after the
estimate, district review, and a value engineering session are all completed. The DSA submittal
remains scheduled for September 2008. Of the current project budget of $39,257,000, a total
of 2% has been expended.

Industrial Technology Modernization/Addition: BFGC Architects has completed an initial
project proposal (IPP) for the project which was presented to the board on January 29, 2008.
The project’s estimated budget is $22,100,000; however, BFGC’s initial estimate shows a
project cost of $26,400,000 for the entire program included in the IPP. This project is currently
on hold pending the outcome of a November 2008 bond election to meet estimated additional
funding requirements.



                SCHEDULED MAINTENANCE AND OTHER PROJECTS
LVC Energy Management System (EMS) Upgrade & HVAC Repair: The EMS upgrade
project completed construction in February 2008. Authorization to file the notice of completion
was approved by the board on March 18, 2008, and subsequently filed on March 19, 2008. Of
the current $625,000 budget, 90% has been expended. This project will be removed from the
monthly report next month.



Monthly Progress Report                                                                          3
March 2008
Building N Roof Phase III: Bidding and award of the construction contract was completed this
month. At the March 18, 2008 meeting, the board approved awarding the construction contract
to Best Contracting Services, Inc. in the amount of $298,393. Of the current budget of
$406,733, a total of 11.3% has been expended.

Audio Visual Systems for Science and Community Education: Bidding and award of the
construction contract was completed this month. At the March 18, 2008 meeting, the board
approved awarding the construction contract to Brannon Inc., dba Smith Electric Service in the
amount of $718,500.00. The current budget for this project is $1,580,000.


                               TECHNOLOGY PROJECTS:

Phoenix Project: The second migration test of the financial data from the mainframe to the
new IFAS system was completed. A meeting was held with Santa Barbara County Office of
Education to discuss interfaces between payroll and new human resources (HR)/payroll
system. Kickoff meetings with the student system implementation teams were held.
Development hardware for the new student system was purchased. A Phoenix Project team
room was setup. Of the $6,500,000 budget, a total of 48.8% has been expended.

Technology & Instructional Equipment Modernization: Auto repair training systems,
language arts student lab computers, fine arts high-definition film and video equipment, PCPA
set design software, and a couple replacement faculty computers were purchased. Of the
$11,850,000 budget, a total of 18.5% has been expended.




Monthly Progress Report                                                                     4
March 2008
CAPITAL PROJECTS                                           Community Education Building


                          COMMUNITY EDUCATION BUILDING




A. PROJECT TEAM

   •   Project Manager:             URS Corporation
   •   Architect/Engineer:          Phillips Metsch Sweeney Moore Architects
   •   Construction Manager:        Bachini-Deferville Management
   •   General Contractor:          SOLPAC, Inc., dba Soltek Pacific
   •   Equipment Consultant:        Dovetail Design Consultants

B. CONSTRUCTION

   The Community Education building is substantially complete. Final change orders have
   been submitted to DSA (Division of the State Architect) for approval. All closeout
   documentation has been submitted, with the exception of the as-built drawings from the
   architect, which will be completed upon approval of the final DSA change orders.

C. EQUIPMENT

    The furniture vendor is nearing completion with final punch-list items. All additional scope
    requests have been compiled into a report and are being evaluated against the remaining
    budget.

D. FUNDING/BUDGET

       •   Funding:
             o State funds                                                $ 5,000,000
             o Bond funds                                                 $ 1,500,000
             o Measure I bond funds augmentation (CM amendment)           $ 171,500
             o Measure I bond funds augmentation (12/03/07)               $    49,500
             o Parking fee funds                                          $    50,500
                                                            Total         $ 6,771,500

       •   Budget:
              o Construction contract                                     $5,744,500
              o Soft costs                                                 $ 725,300
              o Contingency                                                $ 301,700
                                                                  Total   $ 6,771,500

Monthly Progress Report                                                                       5
March 2008
CAPITAL PROJECTS                                            Community Education Building

     •     Percent Expended - 100%
         (contract earned + soft costs expenditures + contingency allocated)




   E. CONTINGENCY

         •   Starting contingency balance                   $ 284,700
             Contingency augmentation (12/03/07)            $ 32,500
                                                            $ 301,700

         •   Remaining contingency balance                  $   1,944


         •   Percent of changes - 2%
             (change orders vs. original contract)




Monthly Progress Report                                                                6
March 2008
CAPITAL PROJECTS                                     Science/Health Occupations Complex

                     SCIENCE/HEALTH OCCUPATIONS COMPLEX




A. PROJECT TEAM

         •     Project Manager:        URS Corporation
         •     Architect/Engineer:     Phillips Metsch Sweeney Moore Architects
         •     Construction Manager:   Bachini-Deferville Management
         •     General Contractor:     Straub Construction, Inc.
         •     Equipment Consultant:   Dovetail Design Consultants

B. CONSTRUCTION

     The three phases of construction have been substantially completed. Building punchlist
     items and ADA accessibility into the M100 restroom were substantially completed in March.
     Thirteen (13) Division of the State Architect (DSA) change orders have been approved,
     three (3) DSA change orders are currently under review, and one (1) DSA change order is
     pending submission. A final contract change order has been drafted, but requires direction
     from DSA prior to finalizing and seeking board approval. Submission and review of
     remaining closeout documentation continues.

C. EQUIPMENT

     The furniture vendor is nearing completion with final punch-list items. All additional scope
     requests have been compiled into a report and are being evaluated against the remaining
     budget.

D.       BUDGET/FUNDING

     •       Funding
                o State funds                              $ 14,658,000
                o Measure I Bond funds                     $ 3,500,000
                o Measure I Bond augmentation (9/20/07)    $    175,000
                o State funds (site concrete)              $    100,101
                o PG&E energy rebate                       $     20,359
                                                 Total     $ 18,453,460
Monthly Progress Report                                                                        7
March 2008
CAPITAL PROJECTS                                    Science/Health Occupations Complex

       •   Budget
           o Construction contract                         $ 15,698,000
           o Soft costs                                    $ 1,662,799
           o Contingency                                   $ 1,092,661
                                                Total      $ 18,453,460

       •    Percent expended - 99%
           (contract earned + soft costs expenditures + contingency allocated)




E. CONTINGENCY

   •   Starting contingency balance                         $ 797,201
   •   Contingency augmentation (9/20/07)                   $ 175,000
   •   State funds site concrete                            $ 100,101
   •   PG&E energy rebate                                   $ 20,359
                                                Total       $1,092,661

   •   Remaining contingency balance - $ 16,278

   •   Percent of changes - 6%
       (change orders + construction change directives vs. original contract)




Monthly Progress Report                                                              8
March 2008
CAPITAL PROJECTS                                                       Public Safety Complex

                             PUBLIC SAFETY COMPLEX




A. PROJECT TEAM

   •   Project Manager:                      URS Corporation
   •   Architect/Engineer:                   MVE Institutional Inc.
   •   Construction Manager:                 TBD
   •   General Contractor:                   TBD
   •   Equipment Consultant:                 TBD

B. PLANNING/DESIGN

The project architect, MVE Institutional, has begun preliminary plans for the project. Preliminary
design workshops are being scheduled and site utility and soils surveys are being procured.
Preliminary design is planned to be completed in the fall of 2008. The new project for this
project is $46,163,902, with a total of 0.4% expended thus far.

C. PRELIMINARY SCHEDULE

   Milestones – Planning

       Final Project Proposal                           Winter        2007        COMPLETE
       Begin Preliminary Plans                          Spring        2008        COMPLETE
       Complete Preliminary Plans                       Fall          2008

D. BUDGET/FUNDING

   • Revised budget:                                $ 46,163,902
   • Funding:
      Measure I Bond funds                          $ 26,000,000
      Measure I bond augmentation (2/20/08)         $ 20,163,902

   •   Expended:                                   $     180,172 – 0.4%




Monthly Progress Report                                                                         9
March 2008
CAPITAL PROJECTS                                                         Child Care Addition

                               CHILD CARE ADDITION




A. PROJECT TEAM

   •   Project Manager:             URS Corporation
   •   Architect/Engineer:          MVE Institutional Inc.
   •   Construction Manager:        TBD
   •   General Contractor:          TBD
   •   Equipment Consultant:        TBD

B. PLANNING/DESIGN

MVE Institutional completed the final project proposal (FPP) in December 2007, and presented
the conceptual design to the board of trustees on January 29, 2008. The FPP was approved by
the board at the March 18, 2008 meeting. MVE will begin preliminary design in conjunction with
the development of the public safety project. Of the $6,500,000 project budget, a total of 0.6%
has been expended.

C. PRELIMINARY SCHEDULE

   Milestones – Planning

       Initial Project Proposal                    Summer    2007        COMPLETE
       Final Project Proposal                      Winter    2007        COMPLETE
       Begin Preliminary Plans                     Spring    2008
       Complete Preliminary Plans                  Fall      2008

D. BUDGET/FUNDING

   •   Estimated budget:                           $ 6,500,000
   •   Funding:
       Measure I Bond funds                        $ 6,500,000

   •   Expended:                                   $     40,100 – 0.6%



Monthly Progress Report                                                                     10
March 2008
CAPITAL PROJECTS                                      One Stop Student Services Building

                   ONE STOP STUDENT SERVICES BUILDING




A. PROJECT TEAM

   •    Project Manager:            URS Corporation
   •    Architect/Engineer:         Steinberg Architects
   •    Construction Manager:       TBD
   •    General Contractor:         TBD
   •    Equipment Consultant:       TBD

B. PLANNING/DESIGN:

Steinberg Architects has completed preliminary plans and district review of these plans by the
project stakeholders will occur in April. Design approval will be sought at the April 15, 2008
board meeting. Working drawings will commence after the estimate, district review, and a value
engineering session are all completed. The DSA submittal remains scheduled for September
2008. Of the current project budget of $39,257,000, a total of 2% has been expended.

C. PRELIMINARY SCHEDULE
   Milestones – Programming / Preliminary Plans (P)

       Begin programming                     Summer        2007         COMPLETE
       Program review                        Summer        2007         COMPLETE
       Preliminary plan submittal            Fall          2007         COMPLETE
       Receive working drawings funds        Spring        2008

D. BUDGET/FUNDING

   •   Estimated Budget:                          $ 39,257,000

   •   Funding:
       Measure I bond funds                     $ 7,800,000
       Measure I bond fund augmentation (02/08) $ 14,900,000
       Other Funds                              $ 16,557,000

   •   Expended:                                 $     787,070 – 2%
Monthly Progress Report                                                                    11
March 2008
 CAPITAL PROJECTS                         Industrial Technology Modernization/Addition

          INDUSTRIAL TECHNOLOGY MODERNIZATION/ADDITION




A. PROJECT TEAM
   •   Project Manager:              URS Corporation
   •   Architect/Engineer:           BFGC Architects Planners, Inc.
   •   Construction Manager:         TBD
   •   General Contractor:           TBD
   •   Equipment Consultant:         TBD

B. PLANNING/DESIGN

 BFGC Architects has completed an initial project proposal (IPP) for the project which was
 presented to the board on January 29, 2008. The project’s estimated budget is $22,100,000;
 however, BFGC’s initial estimate shows a project cost of $26,400,000 for the entire program
 included in the IPP. This project is currently on hold pending the outcome of a November 2008
 bond election to meet estimated additional funding requirements.

C. PRELIMINARY SCHEDULE

    Milestones – Programming (P)

         Input evaluation                          Summer      2007      COMPLETE
         Presentation of project scope             Fall        2007      COMPLETE
         Complete IPP                              Winter      2007      COMPLETE

D. BUDGET/FUNDING

    •   Estimated budget:                          $ 22,100,000

    •   Funding:
        Measure I bond funds                       $ 22,100,000

    •   Expended:                                  $     65,908 – 0.3%



 Monthly Progress Report                                                                   12
 March 2008
SCHEDULED MAINTENANCE                                LVC EMS Upgrade & HVAC Repair

       LOMPOC VALLEY CENTER EMS UPGRADE & HVAC REPAIR




A. PROJECT TEAM

   •   Project Manager:            URS Corporation
   •   Architect/Engineer:         Kruger Bensen Ziemer Architects
   •   Construction Manager:       Bachini-Deferville Management
   •   General Contractor:         CTAC, Inc.

B. CONSTRUCTION

The EMS upgrade project completed construction in February 2008. Authorization to file the
notice of completion was approved by the board on March 18, 2008 and was filed on March 19,
2008. This project will no longer be appearing in the monthly report after this month.

C. BUDGET

   • Budget:                                                   $ 625,000

   • Funding:
     2006-07 Block Grant AB 1801                               $ 109,112
     Measure I bond scheduled maintenance (SM) funds           $ 190,888
     Measure I bond SM funds augmentation (7/17/07)            $ 325,000

   • Expended                                                  $ 561,963 – 90%




Monthly Progress Report                                                                  13
March 2008
TECHNOLOGY PROJECTS                                                         Phoenix Project

                                    PHOENIX PROJECT




A. PROJECT TEAM
   •   Project Management Services: Strata Information Group (SIG)
   •   College Steering Committees (IFAS-11 members) (Student 24-members)
   •   Vendors: SunGard Bi-Tech (Financial and Human Resources System) and SunGard Higher
       Education (Student System)

B. STATUS

A second practice migration of the financial data from the mainframe to the new servers was
completed. Data cleanup, workflows, new forms, and business process reviews are well under way
for the financial system. User training on the new financial system will start in May. A meeting was
held with the county who runs the college payroll to discuss opportunities to improve the current
process with the new system. The county is producing an MOU for this work. Kickoff meetings with
the various student functional implementation teams were held. Hardware to install a development
system was purchased.

C. SCHEDULE

   Bi-Tech IFAS - Financial
      Installation of IFAS upgrade                 October        2007 COMPLETE
       IFAS financial data migration               December       2007 COMPLETE
      Start IFAS user training                     May            2008
      Move to new IFAS financial (Go Live)         July           2008

   Bi-Tech IFAS – Human Resources and Payroll
      Define data standards and rules      May                    2008
      IFAS HR data migration/data entry    June                   2008
      Move to new IFAS HR (Go Live)        October                2008

   SunGard Higher Ed - Student Information System
      Selection of student ERP vendor        November             2007 COMPLETE
      Signed student ERP agreements          December             2007 COMPLETE
      Purchase of student development system March                2008 COMPLETE
      Schedule Planning                      April                2008

D. BUDGET

   •   Budget:                                     $6,500,000
   •   Funding:
       Measure I bond funds                        $6,500,000

   •   Expended:                                   $3,171,979 – 48.8%

Monthly Progress Report                                                                      14
March 2008
                                                              Technology & Instructional
TECHNOLOGY PROJECTS                                            Equipment Modernization


  TECHNOLOGY & INSTRUCTIONAL EQUIPMENT MODERNIZATION




A. PROJECT TEAM

   •    Project Managers: Director, Information Technology Services, and Associate Dean,
        Learning Resources
   •    College Technology Advisory Committee (TAC)
   •    Vendors: Various

B. STATUS

   Based upon recommendations of TAC, auto repair training systems for students, language
   arts student laptop computers, high definition camcorders, projectors, and sound system for
   fine arts film students, PCPA set design CAD software, and a couple replacement faculty
   computers were purchased. There is $270,000 remaining for spring 2008 purchases from
   this year’s budget allocation.

C. SCHEDULE

       Purchase Science and Community Ed computers                     July           2007
       TAC 2007-2008 first meeting                                     September      2007
       TAC review of 2007-2008 modernization requests           Oct - November        2007
       Purchase fall 2007 modernization recommendations                December       2007
       Spring 2008 first meeting                                       February       2008
       TAC complete review of 2007-2008
       modernization requests                                           March         2008
       Purchase spring 2008 modernization
       recommendations                                                  April         2008

D. BUDGET

  •    Budget:                             $11,850,000
  •    Funding:
        Measure I bond funds               $11,850,000

  • Expended:                             $ 2,188,172 – 18.5%
Monthly Progress Report                                                                      15
March 2008

						
Related docs
Other docs by lyz94630
Monthly Report on Purchases
Views: 24  |  Downloads: 0
Monthly Rental Agreement House
Views: 9  |  Downloads: 0
Mortgage Application Process
Views: 8  |  Downloads: 0
Monthly Product Strategy Report Project - PDF
Views: 17  |  Downloads: 0
Mortgage Applications in Italian Language
Views: 32  |  Downloads: 0
Monthly Project Schedule
Views: 12  |  Downloads: 0
Montoya V Dot American States Insurance Company
Views: 18  |  Downloads: 0
Moose Officer Training
Views: 16  |  Downloads: 0
Mortgage Account Information
Views: 5  |  Downloads: 0
Monthly Rental Contract
Views: 7  |  Downloads: 0