									                                                                                          Project Profile


Baggage Handling Systems: Hartsfield‐Jackson Atlanta 




                                                                      At ‐ A ‐ Glance 
International Airport                                                                    Owner: 
                                                                                         Hartsfield‐Jackson 
As the world’s busiest airport, Hartsfield/Jackson International                         Atlanta International 
Airport (ATL) in Atlanta, Georgia serves over 88 million                                 Airport 
passengers a year.  Any construction done onsite promises to 
                                                                                         Location: 
be difficult with aggressive timelines.  So when the Airport 
                                                                                         Atlanta, GA 
                                           Commission began 
                                           building a new 
                                                                                         Terminal Size: 
                                           international terminal, 
                                                                                         1.2 million square feet 
                                           it was known that the 
                                           project would be 
                                                                                         Duration: 
                                           challenging and it                            2009—present 
                                           would test any 
                                           organization’s 
                                                                                         Total CCC Project Value: 
                                           capabilities.                                 $7.8 million US Dollars 
The new terminal, Terminal F, would be over 1.2 million square 
feet and require an extensive, state‐of‐the‐art baggage handling                         Project Scope: 
system.  Because of our reputation for safe, on‐time, and on‐                            Installed over 11.7 linear 
budget projects, Delta turned to Commercial Contracting                                  miles of conveyors, 20 
Corporation to undertake this massive project. 
                                                                                         baggage claim units, and 
                                                                                         17 make‐up units 
Since March of 2009 CCC has been diligently working to get the  
baggage handling systems (BHS) up and running.  As the sole                              Safety: 
mechanical installer of the BHS, we have installed over 11.7                             Over 126,000 man hours 
linear miles of conveyor and have also installed 20 baggage                              of work performed 
claim units and 17 baggage make‐up units.                                                without a single lost 
                                                                                         time injury 
To date, CCC has worked over 126,000 man‐
hours without a single lost time incident and the 
project value has topped $7 million US Dollars.  
Work is scheduled to be completed by 2012. 