					                                                                                                                             STEEL
      STATE                         FUEL                           ASPHALT CEMENT                          Future                       Retroactive             PORTLAND CEMENT                OTHER                         NOTES                         CONTACT
Alabama             Platt's Oilgram; any change             ADOT index; any change                                                                                                                             fuel & AC PAC started in 3/2000
Alaska                                                                                                                                                                                                         none at this time                  John Lohrey 8/29/2005
Arizona
Arkansas            none                                                                                                                                                                                       none at this time;                 Kevin Thornton, System
                                                                                                                                                                                                                                                  Administrator, Construction
                                                                                                                                                                                                                                                  Division, Arkansas State
                                                                                                                                                                                                                                                  Highway and Transportation
                                                                                                                                                                                                                                                  Department, Little Rock, AR,
                                                                                                                                                                                                                                                  (501) 569-2245

California                                                  Caltrans uses an index for AC                                                                                                                                                         Dietz 8/23/2005
                                                            published at:
                                                            http://www.dot.ca.gov/hq/esc/oe/a
                                                            sphalt_index/astable.html. Used
                                                            on contracts when there are at
                                                            least 50 working days and at
                                                            least 4500 tonnes of paving
                                                            asphalt
Colorado            Yes - 3/31/2006
Connecticut                                                 Ongoing for active projects, 5 %  started 6/2004. Applicable      No retroactive adjustment.        none                                                                              Keith Lane 10/4/2005
                                                            trigger.                          only for "Structural Steel"
                                                                                              items with a minimum 50,000
                                                                                              lbs as the threshhold. Ongoing
                                                                                              on active projects. No index is
                                                                                              used. Material is paid as a
                                                                                              separate item based on
                                                                                              special provisions. Net weights
                                                                                              are required to be shown on
                                                                                              shop drawings.
Delaware            High Sulfur No. 2 Diesel Fuel,          Monthly price index, use only PG None                             Certain projects, both state      None                    Labor, one project     No opt in or opt out provision     Wilgus 8/23/2005
                    monthly price index, 5 % trigger,       64-22 as the index, no trigger %,                                 only and Fed-aid. Was only                                only, effective 4th
                    specific work items only, usage         apply to projects with minimum                                    used for a limited time period.                           calendar year and
                    factors for category of work item       quanties of mix                                                   Adjustment with State funds                               beyond, 10% trigger,
                                                                                                                              only.                                                     based on prevailing
                                                                                                                                                                                        wage rates only,
                                                                                                                                                                                        includes all subs.
District of Columbia none                                   Yes                                 none                           none                             none                    none                                                      Ardeshir Nafici , 202-671-
                                                                                                                                                                                                                                                  4612, 8/9/2006
Florida             Monthly price indexed at terminals in Monthly price indexed at              started 3/2004, ended          State only, started 3/2004,      None                    Considering a general Fuel and AC PAC started in 2000; David Chason, Construction
                    Florida, 5% trigger;                     terminals in Florida, 5% trigger   12/2004, ongoing on active     ended 12/2004, ongoing on                                contract price          Contractor no option of accepting Final Estimates Manager,
                    http://www.dot.state.fl.us/specification                                    projects, 5% trigger           active projects, 5% trigger                              adjustment clause       or rejecting PAC                  850-414-4171,
                    soffice/2004BK/D009.doc.pdf                                                                                                                                         based on PPI                                              David.chason@dot.state.fl.us
                                                                                                                                                                                        www.dot.state.fl.us/con
                                                                                                                                                                                        struction/PPI/Producer
                                                                                                                                                                                        PriceIndex.htm

Georgia             none                                    Yes - included on projects with a none                             none                             none                    none                   have a draft spec for asphalt index 8/18/2006; Gregory T. Mayo,
                                                            duration of greater than one year                                                                                                                                                      P.E., State Construction
                                                            (365 days), the ceiling is a 75%                                                                                                                                                       Engineer, Georgia
                                                            increase, and it takes effect from                                                                                                                                                     Department of
                                                            the letting.                                                                                                                                                                           Transportation, Office of
                                                                                                                                                                                                                                                   Construction,
                                                                                                                                                                                                                                                   greg.mayo@dot.state.ga.us ,
                                                                                                                                                                                                                                                   Office (404) 656-5306

Hawaii              none                                                                   0.05 none                           none                             Yes - 5% trigger value reinforcing steel       PAC started in March 2000




              a62411a6-586e-466c-93bc-93bde979bf64.xls                                                                                  page 1 of 6                                                   AASHTO Subcommittee on Construction, Informal Survey August 2005
                                                                                                                                     STEEL
           STATE                         FUEL                             ASPHALT CEMENT                             Future                       Retroactive              PORTLAND CEMENT                  OTHER                     NOTES                             CONTACT

Idaho                    5% +/- trigger after first 365 days:      5% +/- trigger after first 365 days:
                         price must be adjusted up or down         price must be adjusted up or
                         based on difference between invoice       down based on difference
                         price and original quoted price; if the   between invoice price and
                         change is in excess of 20% after first    original quoted price; if the
                         365 days: use three contemporary          change is in excess of 20% after
                         quotes instead of invoice price;          first 365 days: use three
                         maximum of 180%.                          contemporary quotes instead of
                                                                   invoice price; maximum of 180%.

Illinois                 none                                      none                                   Started Jan 21, 2006            none                             none                      none                                                      Roger Driskell 8-25-2006;
                                                                                                          Optional, a 5% trigger, for                                                                                                                          Roger.Driskell@illinois.gov
                                                                                                          steel pay items with a contract
                                                                                                          value greater than $10,000

Indiana                  none                                    none                                     none                           none                              none                      none                                                      Kuchler 8/24/2005
Iowa                     Adjustment based on CPI of No. 2        none                                     none                           none                              none                      none               We were advised the "opt in" and
                         High Sulfur Diesel. Adjustment starts                                                                                                                                                          "opt out" clause could not be used
                         after a change of $0.15 from base                                                                                                                                                              on Federal Aid projects. The
                         price, and applies only to excavation                                                                                                                                                          website listed in the spreadsheet is
                         items. http://www.erl.dot.state.ia.us/.                                                                                                                                                        also correct. However, you will
                         Section 2103.                                                                                                                                                                                  have to click on GS-01010 dated
                                                                                                                                                                                                                        April 18, 2006 and then click on
                                                                                                                                                                                                                        Section 2103 to get to the Fuel
                                                                                                                                                                                                                        Adjustment section.
                                                                                                                                                                                                                                                             Smythe 8/24/2005
Kansas                   monthly rack average given for NO2-       Yes-July 2006 Asphalt Material                                                                          None                                         Kansas does allow bidders the        Rissky 8/16/2006;
                         HS Fuel, St. Louis, reported by           Index (AMI) based on Asphalt                                                                                                                         option to accept or decline the fuel RoyR@ksdot.org
                         AXXIS Petroleum, Inc., Axxis Price        Weekly Monitor published by                                                                                                                          adjustment and Asphalt price
                         Service. Adjustments are made for         Poten & Partners. Special Prov.                                                                                                                      adjustment clause in their bid
                         any change, plus or minus.                http://www.ksdot.org/burconsmain                                                                                                                     proposal. However, once bids are
                                                                   /specprov/pdf/90p-0295-r01.pdf                                                                                                                       opened, the bidders can not
                                                                   5000 Ton minimum to include in                                                                                                                       change their choice.
                                                                   contract
Kentucky                 OPIS; ±5%; see notes                      Kentucky Terminal prices; ±10%;                                       10% increase not to exceed        None (had a clause in                        The fuel and liquid asphalt PACs Dexter Newman 8/24/2005
                                                                   see notes                                                             50% of bid price; allowed only    the early 1990's but                         apply only to contracts with
                                                                                                                                         on active projects bid prior to   was seldom used, as                          quantities exceeding threshold
                                                                                                                                         January 23, 2004                  price fluctuations were                      values for specific items; and one
                                                                                                                                                                           mild)                                        of the following time conditions: A)
                                                                                                                                                                                                                        a calendar date contract for which
                                                                                                                                                                                                                        the NTP was issued in a year other
                                                                                                                                                                                                                        than the specified completion date;
                                                                                                                                                                                                                        B) a working day contract with
                                                                                                                                                                                                                        more than working 75 days; or C) a
                                                                                                                                                                                                                        calendar day contract with more
                                                                                                                                                                                                                        than 180 calendar days.

Louisiana                adjustments provided for                  price adjustment clause for                                                                                                                                                                 Brian Buckel, LADOT&D;
                         approximately 30 work items; 5%           asphalt cement (May 2006)                                                                                                                                                                   (BrianBuckel@dotd.la.gov)
                         trigger value; index based on the         optional at bid time; 5% trigger;                                                                                                                                                           8/9/2006
                         minimum price quotations for              index based on average AC price
                         unleaded gasoline and No. 2 diesel        FOB at terminal or refinery
                         fuel listed for the New Orleans area
                         in Platt's Oilgram and Price Report
Maine                                                              average N.E. Barge Price, FOB,                                                                                                                                                              Robert Watson 8/31/2005
                                                                   as listed in the Asphalt Weekly
                                                                   Monitor; 5%




                   a62411a6-586e-466c-93bc-93bde979bf64.xls                                                                                       page 2 of 6                                                   AASHTO Subcommittee on Construction, Informal Survey August 2005
                                                                                                                        STEEL
      STATE                           FUEL                        ASPHALT CEMENT                        Future                       Retroactive           PORTLAND CEMENT          OTHER                     NOTES                            CONTACT

Maryland            None; considering a fuel provision     MDSHA index; 5% and 15% - see                                                                   None                                 The Asphalt Trigger Value is 5%     David Beaulieu 8/24/2005;
                    (September 2005)                       notes                                                                                                                                for contracts scheduled to be       Harrison 9/12/2005
                                                                                                                                                                                                paved during more than one
                                                                                                                                                                                                construction season or with an
                                                                                                                                                                                                estimated mix quantity of 10,000
                                                                                                                                                                                                tons or more. For contracts
                                                                                                                                                                                                scheduled to be paved within one
                                                                                                                                                                                                construction season and having an
                                                                                                                                                                                                estimated mix quantity of less than
                                                                                                                                                                                                10,000 tons the adjustment is
                                                                                                                                                                                                based on a fluctuation above 15%.

Massachusetts       MassHighway index; 10% trigger;        MassHighway index; any change;
                    used on contracts > 2 years and        used on contracts with >1000
                    $10M                                   tons of HMA
Michigan                                                                                                                                                   None                                 MDOT is not currently utilizing any Jason Gutting 8/16/2006;
                                                                                                                                                                                                price adjustment clauses. Industry 517-322-6630;
                                                                                                                                                                                                has recently requested meetings to guttingj@michigan.gov
                                                                                                                                                                                                discuss fuel and steel adjustment
                                                                                                                                                                                                clauses.
Minnesota           Opis Energy Group - Rack Fax, 25%, none - under consideration           new contracts - ENR index, no none                             none              none                                                    Nancy Sannes, Estimating
                    no optoin                                                               option;                                                                                                                                  Unit, (651) 296-0807,
                                                                                                                                                                                                                                     nancy.sannes@dot.state.mn.
                                                                                                                                                                                                                                     us
Mississippi         Platt's Oilgram; any change            Monthly Avg. Quote from AC       None                             None                          None              None               Contractor cannot opt in or out of a Bard Lewis 8/23/2005
                                                           Suppliers, Any Change                                                                                                                PAC, State sets PAC
Missouri            Yes, SS. 109.14; adjustment for
                    Class A Ex.,unclassified Ex, Class C
                    Ex, embankment, bituminous
                    pavement, concrete pavement;
                    Based on Platts Oilgram Pad 2;
                    optional bidding.
Montana             Yes, fuel only*                        none                             -                                                                          20% -                    * spec for fuel (unleaded gas and        Michael Kulbacki, 10/5/2005
                                                                                                                                                                                                diesel); SP for burner fuel; no
                                                                                                                                                                                                provisions for AC; MDT Spec. 109.11
                                                                                                                                                                                                requires contractor to identify (10 max)
                                                                                                                                                                                                items during preconstruction
                                                                                                                                                                                                conference.
Nebraska            1980's - Platt's Oilgram               NO                               NO                               NO                            NO                                   Fuel adjustment is udes only for
                                                                                                                                                                                                excavation items. No change on      Claude Oie 8/9/2006; 402-
                                                                                                                                                                                                the first 10%                       479-4532
Nevada              OPIS +/- 20% of BP                     OPIS +/- 25% of BP               ENR - 20-city avg for Grade      NO                            NONE              NONE               Fuel & Steel clauses must be in
                                                                                            60, #4 Reinforcing Bars and                                                                         contract, then requested to enact
                                                                                            Hot rolled carbon steel plate.                                                                      by contractor. Fuel is retroactive.
                                                                                            +/- 10% of BP                                                                                       Steel escalation will only apply
                                                                                                                                                                                                from the period of time the unusual
                                                                                                                                                                                                price for steel began until the end
                                                                                                                                                                                                of the contract. Asphalt Esc is
                                                                                                                                                                                                from the beginning of contract to
                                                                                                                                                                                                the end. Clauses allow for
                                                                                                                                                                                                increase or decrease. BP
                                                                                                                                                                                                (Benchmark Price at time of bid
                                                                                                                                                                                                opening)
New Hampshire       NHDOT Index based on terminal          NHDOT Index based on terminal    none                             none                          none              None               no contractor option provided       Ted Kitsis 8/22/2005
                    price in NH; 10% trigger; PAC dated    price in NH; 10% trigger; PAC
                    7-14-04                                dated 2-24-97
New Jersey          NJ North or South Index 5%             NJ North or South Index 5%       NO                               Under review if supplier meets N/A              N/A                AC and Fuel Clauses in the Std     Ron Maruca 8/22/2005
                                                                                                                             financial hardship tests                                           Spec for adj over 5% change but
                                                                                                                                                                                                less than 50% change in index
New Mexico          None                                   Bid Price +/- 10% based on       None                             None                          None                                 Escalation for AC used on all      Onstott 8/23/2005
                                                           established price index                                                                                                              projects with at least 500 tons AC
                                                                                                                                                                                                expected to last over more than
                                                                                                                                                                                                one season. No contractor option.




              a62411a6-586e-466c-93bc-93bde979bf64.xls                                                                               page 3 of 6                                        AASHTO Subcommittee on Construction, Informal Survey August 2005
                                                                                                                           STEEL
       STATE                          FUEL                       ASPHALT CEMENT                            Future                        Retroactive            PORTLAND CEMENT          OTHER                         NOTES                          CONTACT

New York             Avg. FOB for No. 2 fuel oil and       Avg. FOB terminal price for         Producer Price Index for         Producer Price Index for     No                   -                                                          Herritt 8/23/2005
                     unleaded gas in New York,             unmodified PG 64-22 binder W/O      shredded carbon scrap steel      shredded carbon scrap steel
                     Philadelphia, Detroit & Boston;       anti-stripping agent;               (WPU 10121193) from Bureau       (WPU 10121193) from Bureau
                     $0.03/liter                           $10.00/metric ton                   of Labor Statistics; 5%, min     of Labor Statistics; 5%, min
                                                                                               $1000                            $1000
North Carolina       Base Price Index                      Base Price Index                    None                             None                         None                 None                                                        DeWitt 8/24/2005
North Dakota         NDDOT Base Price Index                None                                None                             None                         None                                         SP for motor fuel adjustment only, Cal Gendreau 8/23/2005
                                                                                                                                                                                                          updated April 2002.
                                                                                                                                                                                                          http://www.state.nd.us/dot/docs/co
                                                                                                                                                                                                          nstruction/SPapril12_2002.pdf
Ohio                 Yes - 3/1/2006                        Average of area suppliers; % AC BLS and AMM index, 5% min            Actual change in cost as        None                                      http://www.dot.state.oh.us/construc Roger Ryder 9/7/2005
                                                           trigger. Contractor has no option.                                   verified.                                                                 tion/OCA/default.htm

Oklahoma             None                                  beginning with the June, 2006       None                             None                            None                                                                         George Raymond 8/9/2006;
                                                           letting, Oklahoma began using an                                                                                                                                                  (405)521-2561
                                                           Asphalt
                                                           Cement Price Adjustment Clause
                                                           in all contracts that include
                                                           asphalt pay
                                                           items. OkDOT uses a monthly
                                                           index from Asphalt Weekly
                                                           Monitor ® furnished
                                                           by Poten & Partners, Inc. with an
                                                           adjustment is triggered at +/- 3%
                                                           change
                                                           in the index.
Oregon               OPIS LISTING. 25% trigger. Must       POTEN INDEX. 10% trigger.           Yes - Started October 2005.      For Projects executed between None                                        State House Bill 2077 became        Kevin Brophy, Construction
                     meet a minimum qualifier to be        Must meet a minimum qualifier to    Selected steel bid items only.   April 1, 2003 through                                                     effective July 20, 2005. Part 2     Claims Specialist, (503)-986-
                     included in a Project.                be included in a Project.           10% trigger. Index values are    September 30, 2005 only.                                                  covers retroactive steel escalation 6627 ; 8/10/2006
                                                                                               from the BLS Final               Based on actual change in                                                 for Projects executed between
                                                                                               IDWPUSISTEEL1, PPI, non-         cost as verified.                                                         April 1, 2003 through September
                                                                                               seasonally adjusted index.                                                                                 30, 2005. Part 6 of this bill
                                                                                                                                                                                                          mandated that a steel
                                                                                                                                                                                                          escalation/de-escalation program
                                                                                                                                                                                                          would be established on ALL
                                                                                                                                                                                                          ODOT administered Projects.




Pennsylvania         Yes, at +/- 5%                        Yes, at +/- 10%                     None                             None                            None              None                    considering a concrete pavement    Tucker Ferguson 8/29/2005
                                                                                                                                                                                                          clause April 2006
Puerto Rico                                                                                                                     USDOL Bureau of Labor &                           A proposal to include   Steel clause implemented aprox.    Jose Torres 8/24/2005
                                                                                                                                Statistics (PPI) Series                           guard rail is being     On 06/04
                                                                                                                                WPU101704; 15% trigger                            considered
Rhode Island         Base Price vs. Period Price.       Base Price vs. Period Price            For use on selected large        on selected projects,                                                                                        N. Marzano and John
                     Adjustment has to exceed                                                  projects; Base Index vs.         retroactive indexing may take                                                                                McAvoy 8/23/2005; update
                     $250/month for payment to be made.                                        Current Index. Factors based place, following the                                                                                             by McAvoy 8/9/2006
                                                                                               on Bureau of Labor Statistics specification established for
                                                                                               Producer Price Index for "hot "future" projects (not
                                                                                               rolled bars, plates & structural applicable to Federal-aid
                                                                                               shapes." 10% trigger value.      projects)

South Carolina       Yes, see notes.                       Yes; revised in 2006 to allow       No                               No                              None                                      Fuel adjustments apply to only the Danny Shealy 8 29 2005
                     http://www.scdot.org/doing/pdfs/index additional items of work                                                                                                                       items identified in the special
                     es/Fuel/Fuel09_01_05.pdf                                                                                                                                                             provisions for each contract.




               a62411a6-586e-466c-93bc-93bde979bf64.xls                                                                                 page 4 of 6                                             AASHTO Subcommittee on Construction, Informal Survey August 2005
                                                                                                                              STEEL
        STATE                         FUEL                         ASPHALT CEMENT                             Future                        Retroactive            PORTLAND CEMENT              OTHER                          NOTES                           CONTACT

South Dakota          Yes, for Burner Fuel, Diesel Fuel,     No                                   No                               No                              No                    No                                                            Jason Humphrey, (605) 773-
                      and Unleaded fuel. Oil Price                                                                                                                                                                                                     4391, 8/9/2006
                      Information Service; Base Price vs.
                      Period Price, Adjustment made
                      outside the 15% trigger value.
                      Applied to pay items by formula.
Tennessee             TDOT index (two component index,       TDOT index (posted terminal          none                             none                            none                                                                                Donoho 8/22/2005
                      Producer Price Index and price         prices), Index must exceed 5%
                      TDOT pays for fuel), Index must        diff. to make adjustments; April
                      exceed 5% diff. to make adjustments    2006 indexing liquid asphalt for
                                                             short term (< 6 month) projects
Texas                 none                                   none                                 none                             none                            none                  none                     Texas has no escalation clauses.     Thomas R. Bohuslav ,
                                                                                                                                                                                                                  And no current plans for             512.416.2559
                                                                                                                                                                                                                  implementation of escalation
                                                                                                                                                                                                                  clauses.
Utah                  Yes - based on price per barrel for  Yes - similar to fuel index; use the
                      West Texas Intermediate Crude; 15% West Texas Sour index for crude
                      trigger value; adjustment limited to oil
                      5%; only apply adjustments to items
                      having a value of $100,000 or more.

Vermont               Fuel price adjustment is applied       AC adjustment; index calculated No                                    No                              no, but a fuel         Earth Work see                                               Mark Richter 8/30/2005;
                      separately to ACP, PCC, & Earth        by VAOT based on 3 or more                                                                            adjustment is provided comments                                                     David Hoyne, VAOT, Hoyne,
                      Work items with 5% trigger; fuel       major oil company terminals                                                                           for PCC paving                                                                      David.Hoyne@state.vt.us
                      index from the "Energy Information     supplying Vermont; 10 % trigger;                                                                                                                                                          8/10/2006
                      Administration for New England"
Virginia              New Special Provision for Optional     YES: Base Index vs. Current          Optional: contractor must        YES: Contracts that were        NO                    None                     The Price Index the Department is    Dick Kiefer, Scheduling &
                      Fuel Price Adjustment implemented      Index. Applied to designated bid     select to use steel adjustment   awarded prior to 5/31/04 with                                                  using for steel is based on The      Contract Division, Virginia
                      1/06. Effects 120 bid items and uses   items only. Modified Special         clause at time of bid            steel raw material shipped                                                     U.S. Department of Labor, Bureau     Department of
                      diesel fuel prices as published by     Provision July 06 to require quote   submission.       See Notes      after 12/1/03. could be                                                        of Labor Statistics, Producers       Transportation, 804-786-
                      the U. S. Department of Energy. No     from AC supplier to paving           This Special Provision has a     considered. See Notes                                                          Price Index (PPI)                    3837,
                      trigger for increases or decreases.    contractor. Supplier quotes from     10% trigger.                                                                                                                                         Richard.Kiefer@VDOT.Virgin
                      Contractor must opt in or out within   low bidder used to establish one                                                                                                                                                          ia.gov
                      21 days of bid opening.                index statewide. No trigger.

Washington            Piloted a fuel clause on a single    A new special provision will be    None                                 None                            None                  In April 2004 WSDOT      none at this time; working on        Kevin Dayton 8/22/2006;
                      project in 2005                      included in select projects                                                                                                   revised payment for      developing a fuel PAC                DaytonK@WSDOT.WA.GOV
                                                           beginning September 2006. The                                                                                                 "material on hand" for
                      In March of 2006 a temporary fuel    provision will be included in                                                                                                 steel products. The
                      price adjustment was added for Force projects that are either multiyear                                                                                            change allowed
                      Account calculations. The operating or will not begin for 6 months or                                                                                              payment for raw
                      cost for equipment is increased by   more after advertisement. The                                                                                                 materials paid for by
                      12% to cover the increasing price of adjustment is based on an index                                                                                               the contractor,
                      fuel.                                price at the time the project is                                                                                              previously payment
                                                           advertised. Changes (+/-)                                                                                                     was made after the
                                                           greater than 10% will result in a                                                                                             item had been
                                                           payment or credit based on the                                                                                                fabricated.
                                                           tons of HMA placed.

West Virginia         OPIS; 5% fuel trigger. Contractor      Average of area suppliers; 10 %      None                             None                            None                  None                     New special provision in works to
                      has no option.                         AC trigger. Contractor has no                                                                                                                        eliminate fuel and AC triggers and
                                                             option.                                                                                                                                              minimum adjustable
                                                                                                                                                                                                                  quantities.New PRS has auto-calc
                                                                                                                                                                                                                  capabilities;great savings in time
                                                                                                                                                                                                                  and manual calc work.
Wisconsin             Yes - for common excavation, rock                                                                                                                                                                                                Steve Krebs, 8/17/2006;
                      ex., marsh ex. Borrow, select borrow                                                                                                                                                                                             steven.krebs@dot.state.wi.us
                      and subbase; 15% trigger value;
                      Indext based on No. 2 fuel oil in US
                      Oil Week for Green Bay, Madison ,
                      Milwaukee and Minneapolis




                a62411a6-586e-466c-93bc-93bde979bf64.xls                                                                                   page 5 of 6                                                 AASHTO Subcommittee on Construction, Informal Survey August 2005
                                                                                               STEEL
     STATE                           FUEL                     ASPHALT CEMENT          Future           Retroactive   PORTLAND CEMENT          OTHER                          NOTES                         CONTACT

Wyoming            Yes, see notes.                      Yes, 10% trigger value   No              No                  No                Clause for materials      Fuel adjustment began in 2004 for Eisenhart 307-777-4459;
                                                                                                                                       and supplies for select   motor fuels and burner fuels.         8/23/2005; 8/9/2006
                                                                                                                                       items, such as fabric,    Adjustment applies when prices
                                                                                                                                       fence, seeding and        indices are outside of 85% to
                                                                                                                                       pipe - April 2006         115% of bid price; adjustment is
                                                                                                                                                                 made by formula, by type of fuel.
                                                                                                                                                                 Contractor, in their bid proposal
                                                                                                                                                                 must declare if contract will or will
                                                                                                                                                                 not include Fuel Adjustment.
                                                                                                                                                                 Starting in our October 2005,
                                                                                                                                                                 material cost adjustments will be
                                                                                                                                                                 proposed for corrugated metal
                                                                                                                                                                 pipes, reinforced concrete pipes,
                                                                                                                                                                 geotextiles, geogrid, paving fabric,
                                                                                                                                                                 wood fence posts, fence wire, seed
                                                                                                                                                                 and mulch. An overrun of more
                                                                                                                                                                 than 25 percent from original
                                                                                                                                                                 quantity or a price change of plus
                                                                                                                                                                 or minus of 15 percent from
                                                                                                                                                                 original quoted price will trigger a
                                                                                                                                                                 price adjustment..
Federal Lands




             a62411a6-586e-466c-93bc-93bde979bf64.xls                                                  page 6 of 6                                   AASHTO Subcommittee on Construction, Informal Survey August 2005

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:21
posted:3/18/2011
language:English
pages:6
Description: Cpi Clause in Contract document sample