Chill Water Pump Pre and Post Start Check

Document Sample
Chill Water Pump Pre and Post Start Check Powered By Docstoc
					                                                  CHILL WATER PUMP PRE AND POST
                                                                    START CHECK
CONTRACTOR                                                                            DATE

CONTRACT NO.                                    MOTOR: CODE

     #                         DESCRIPTION                          DATE      STATUS               REMARKS
         PREOPERATION CHECKOUT
1.       VIBRATION ISOLATORS
2.       PUMP INSTALLED LEVEL
3.       PUMP/MOTOR CLEANED
4,       POWER CONNECTIONS COMPLETED
5.       SAFETY DISCONNECT COMPLETED
6.       THERMAL OVERLOAD IN PLACE
7.       CHILLER INTERLOCK CONTROLS COMPLETE
8.       LUBRICATE OIL LUBRICATED BEARINGS
         REMOVE, CLEAN FLUSH AND LUBRICATE GREASE LUBRICATED
9.
         BEARINGS
10.      DISCONNECT COUPLING AND BUMP MOTOR FOR PROPER ROTATION
11.      CHECK PUMP FREE ROTATION BY HAND
12.      CONNECT COUPLING AND CONFIRM ALIGNMENT
13.      OPEN VALVES AND PRIME THE PUMP
14.      DISCONNECT CHILLER INTERLOCK CONTROL
15.      START PUMP


         POST START
1.       MOTOR ROTATION CORRECT
2.       VIBRATION
3.       UNUSUAL NOISE
4.       BEARING NOISE OR EXCESSIVE HEAT
5.       MOTOR AMPERAGE
6.       MOTOR VOLTAGE
7.       RPM


         SHUT DOWN
         CONNECT CHILLER INTERLOCK CONTROL


         LOCKOUT DISCONNECT AS NEEDED

         READY FOR SUSTAINED SERVICE




RPSC SIGNATURE                                                                  DATE
NSF SIGNATURE                                                                   DATE


Form EN-MPS-712b         FEMC / RPSC                  Page 1 of 1    Revision 18/10/06 Approved by Wayne L. Cornell