									                                            FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 1: Cedar Dell

Funding Source:                        University - UMBA/HEFA/Other

Project Location:                      Cedar Dell Residence Halls, Main Campus

Project Type:                          BR


Justification:             Our Cedar Dell Residence Halls are wood-framed apartment-style living quarters that were first occupied
                           in 1988. Over the years mechanical, electrical, and plumbing maintenance problems have been escalating
                           and envelope repairs to roofing and siding are needed to keep water problems in check. A Fall 2006 study
                           by Kaestle Boos, through the UMBA, indicated that repairs could be completed on the current residence
                           facilities that would extend their useful life by 20-25 years.




                                                                                       Associated   Campus                Estimated
 Proposed Project Components                         Estimated Costs                    Program     Location              Completion
Cedar Dell South Repairs                                                  $11,000,000 SL          West Res Halls                2008
Cedar Dell West Repairs                                                    $9,000,000 SL          West Res Halls                2008
Cedar Dell West Repairs                                                    $2,000,000 SL          West Res Halls                2009

Total Est. Project Costs                                                  $22,000,000


Project Description:     This project will require the rehabilitation of the existing Cedar Dell residence halls including roofing
                         repairs and replacements, siding repairs, hvac upgrades, interior finishes repaired or replaced, drainage
                         issues addressed.



Earliest Commencement Date:                          Under construction

Study/Feasibility Explanation:                        Study completed

Est. Project Duration:                        Projected completion in FY2009
                                             FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 2: Library Renovations

Funding Source:                        State - G.O. Bonds or Supplemental funds
                                       University - Private Fundraising

Project Location:                      Library, Main Campus

Project Type:                          BR


Justification:             The growth in student population and the changes in the way libraries are used by students and faculty has sparked
                           us to renovate existing space to accommodate growing university archives and special collections and to expand the
                           building to enclose 15-20,000 additional square feet of space below a bridge to the second floor in order to create
                           seminar and team presentation practice space as well as a small internet cafe. It is expected that the costs associated
                           with this work will be significantly offset by private donations to the university.The Library Building was first
                           occupied in 1972. The 34-year-old building is ready for a complete rehabilitation including re-pointing and
                           masonry repairs; replacement of mechanical/electrical/plumbing systems; bathroom upgrades to address
                           deteriorated finishes, fixtures, and current ADA requirements; and, within a few years, elevator rehabilitation and
                           roof replacement. At the same time, the increasing use of computers have increased electrical demand in the
                           building and this change is forcing us to install a larger electric service entrance, additional emergency engine
                           capacity, and increased cooling capacity.




                                                                                                                      Campus         Estimated
  Proposed Project Components                         Estimated Costs                      Associated Program         Location       Completion
Bathroom Rehab                                                                $988,000    TL                       Library                 2009
Elevator Rehab                                                                $104,000    TL                       Library                 2010
HVAC Phase I                                                                  $936,000    TL                       Library                 2009
HVAC Phase II                                                                 $936,000    TL                       Library                 2010
HVAC Phase III                                                                $936,000    TL                       Library                 2011
HVAC Phase IV                                                                 $936,000    TL                       Library                 2012
HVAC Phase V                                                                  $936,000    TL                       Library                 2012
HVAC Phase VI                                                                 $936,000    TL                       Library                 2012
Electrical Upgrade                                                           $1,438,000   TL                       Library                 2009
Flooring                                                                      $746,000    TL                       Library                 2010
Windows                                                                      $1,100,000   TL                       Library                 2010
Infill Addition                                                              $8,008,000   TL                       Library Bridge          2010

Total Est. Project Costs                                                   $18,000,000


Project Description:   A series of infrastructure contracts to upgrade the Library Facility to current norms has started with some cosmetic
                       work, the replacement of the zoned fire alarm system, the replacement of the emergency diesel engine, and the
                       upgrade of several of the toilet rooms. Initial work also included the construction of Archival space on the
                       Mezzanine level with occupancy projected for the fall of 2008. The funding requested here is planned to continue
                       the program with replacement/upgrade of the existing 35-year old mechanical plant and conversion of the current
                       air conditioning system to a geothermal system in a phased project on a floor-by-floor basis in order to keep the
                       library building in service. This project will also cover the mechanical and cosmetic upgrade of the three cable
                       elevators serving the ground floor and the five above-grade floors; the upgrade of the existing switchboard and the
                       replacement of the transformer to bring more electrical power into the building to serve computers; the completion
                       of the replacement of the wall-to-wall carpeting with new carpet tiles; and the installation of window treatments,
                         of the replacement of the wall-to-wall carpeting with new carpet tiles; and the installation of window treatments,
                         glass film, and storm windows to control solar glare and improve energy efficiency. DCAM is currently doing initial
                         planning work for this series of projects.

                         An Infill Project will add student gathering and meeting space, and will create a more distinctive and accessible
                         entrance. The Infill Project is being managed in conjunction with UMBA and design work is projected to begin in
                         the fall of 2008.




Earliest Commencement Date:                              FY2009

Study/Feasibility Explanation:             Study being conducted with DCAM

Est. Project Duration:                           ongoing through FY2012
                                            FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 3 - Repair Four Oldest Dormitories

Funding Source:                       University - Local Funds
                                      University - UMBA/HEFA/Other

Project Location:                     East Campus Dormitories, Main Campus

Project Type:                         DM


Justification:           J. Louis Roberts Residence Hall was first occupied in 1972. Chestnut Hall followed in 1973. In 1976
                         Mapleridge and Elmwood Halls were completed. In the ensuing 30 years serious envelope problems
                         (windows, masonry, and roofing) have developed and mechanical/electrical/plumbing systems have
                         deteriorated and often no longer meet occupancy code requirements due to upgrades of the building
                         code and federal ADA legislation.




                                                                                        Associated       Campus         Estimated
 Proposed Project Components                          Estimated Costs                    Program         Location       Completion
Masonry Repointing Repair                                                  $2,000,000   SL           East Res Halls           2009
Window Replacements                                                        $3,000,000   SL           East Res Halls           2009
Roofing Replacement                                                        $2,000,000   SL           East Res Halls           2010
MEP/Interior Upgrades                                                     $25,000,000   SL           East Res Halls           2013
MEP/Interior Upgrades                                                     $43,000,000   SL           East Res Halls           2018

Total Est. Project Costs                                                  $75,000,000


Project Description:     The work in each residence hall will include roof replacement, window and exterior door replacement,
                         masonry repairs, increasing the electrical service entrance capacity, installation of air conditioning,
                         complete renovation of bathrooms and kitchenettes, installation of sprinklers, suite/elevator/stairwell
                         revisions to meet current code requirements, installation of new flooring/ceilings/wall coverings, and
                         renovations of common areas on first floors.



Earliest Commencement Date:                               FY2009

Study/Feasibility Explanation:               Study required for work after 2010

Est. Project Duration:                                FY2009-FY2016
                                          FY09 Capital Project Description


Campus:                                 Dartmouth

Project Name:                           Priority 4: Marine Fisheries Building

Funding Source:                         University - Private Fundraising

Project Location:                       SMAST Campus, New Bedford

Project Type:                           NC


Justification: The Division of Marine Fisheries currently occupies inadequate space in several locations in southeastern Massachusetts but h as
               identified funds to contstruct a new 10,000 square foot office building on the same site as our Center for Marine Science on the
               cove in New Bedford in order to improve their working conditions and in order to gain synergies with our research staff and
               research facilities at the same site. Both groups of marine scientists will share lab space and presentation space in the ex isting facility
               and both groups will utilize the existing pier.

                At the same time, our own SMAST group has been growing and will need space for personnel growth. Many of these additional
                people have already been brought into the work group and are currently accommodated in leased space in Fairhaven. The leased
                space is somewhat expensive and inconveniently located inland, away from the main work group and away from access to the ocea n.




                                                                                       Associated
 Proposed Project Components                        Estimated Costs                     Program            Campus Location Estimated Completion
New Building                                                      $20,000,000 R                           New Bedford                      2014

Total Est. Project Costs                                              $20,000,000


Project Description:      We are currently starting planning for the new facilities in conjunction with DCAM. The study phase will include
                          consideration of a vertical addition or a horizontal addition to the current building as well as the possibility of construct ing
                          a free-standing second building on the site. All exterior finishes will be chosen with an eye to withstanding a harsh
                          oceanfront environment.

Earliest Commencement Date:                              FY2009

Study/Feasibility Explanation:            Study being conducted with DCAM

Est. Project Duration:                              FY2009-FY2014
                                                 FY09 Capital Project Description


Campus:                             Dartmouth

Project Name:                       Priority 5 - ADA and Interior Access Immediate Needs

Funding Source:                     University - Local Funds
                                    State - G.O. Bonds or Supplemental funds

Project Location:                   Main Campus

Project Type:                       CO


Justification:         The campus was largely built using the old Massachusetts ADA code in force during the 70's and 80's, but federal
                       ADA legislation is more stringent. This project is designed to address our need to improve ramp angles, install
                       additional handrails, install fire-alarm-activated hold-open devices on corridor smoke-doors, and improve flooring
                       surfaces to make the campus universally accessible. In addition the existing elevated press box at the football field is
                       not accessible to wheelchair users.



                                                                                                      Associated      Campus     Estimated
  Proposed Project Components                             Estimated Costs                              Program        Location Completion
Immediate Safety Needs                                                                    $500,000   BI             Various            2011
Important Safety Needs                                                                    $904,000   BI             Various            2018
Press Box                                                                                 $260,000   BI             Tripp Center       2010
CVPA Atrium Renovation                                                                    $156,000   BI             CVPA               2011
Site Ramps                                                                                $364,000   BI             Site               2018

Total Est. Project Costs                                                                $2,184,000


Project Description:   The proposed work includes paving or reflooring where tripping hazards have been discovered, installation of hold-
                       open devices on corridor smoke doors, and installation of automatic door openers on all buildings not already so
                       equipped. This work would be pursued using various small contracts to address specific needs. An additional
                       contract would re-construct the elevated press box at the football field and equip it with a lift for reporters and
                       cameramen who are mobility-impaired.



Earliest Commencement Date:                                     FY2009

Study/Feasability Explanation:            ADA shortcomings documented; design required

Estimated Project Duration:                                FY2009-FY2018
                                          FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 6 -Basic Infrastructure Repairs

Funding Source:                        University - Local Funds
                                       State - G.O. Bonds

Project Location:                      Main Campus, Various Buildings

Project Type:                          DM


Justification:           Academic Buildings range in age from 13 to 35 years old and existing mechanical, electrical, plumbing and envelope
                         systems are coming to the end of their useful lives. Our recently finalized master plan suggested that we would
                         need to spend over $300M in order to address all infrastructure maintenance needs. While the campus has largely
                         maintained or replaced any failing roofs, older masonry is in need of repointing or replacement and sealing.
                         Electrical systems have generally reached capacity due to increasing electrical demand from the growth in computer
                         usage. Mechanical systems have also reached capacity due to the high heat loads involved in computer usage.
                         Older plumbing piping is frequently so deteriorated that it requires replacement. Fire alarm systems, fire
                         suppression systems, and elevators are all due for replacement and/or upgrades.



                        During the first five years of this 10-year plan, the most urgent envelope and MEP repairs and upgrades will be
                                                                                        Associated                            Estimated
   Proposed Project Components                      Estimated Costs                       Program        Campus Location Completion
Lab Rehab Phase II                                                      $1,040,000 BI                   SENG                            2009
Lab Rehab Phase III                                                     $1,560,000 BI                   SENG                            2010
Lab Rehab Phase IV                                                      $1,560,000 BI                   SENG                            2011
Lab Rehab Phase V                                                       $1,560,000 BI                   SENG                            2012
HVAC Phase III                                                          $1,144,000 BI                   SENG                            2009
HVAC Phase IV                                                           $1,144,000 BI                   SENG                            2010
HVAC Phase V                                                            $1,144,000 BI                   SENG                            2011
HVAC Phase VI                                                           $1,144,000 BI                   SENG                            2012
HVAC Phase VII                                                          $1,040,000 BI                   SENG                            2013
Theater Lighting Upgrade                                                   $260,000 BI                  Auditorium                      2009
Fire Alarm Upgrade                                                         $146,000 BI                  Textile                         2009
Reroofing                                                                  $416,000 BI                  Dion                            2009
Install Egress Doors                                                       $104,000 BI                  Tripp                           2009
Repaving Parking Lots                                                      $520,000 BI                  Various                         2009
Repaving Walkways                                                          $520,000 BI                  Site                            2009
Soffit Replacement                                                         $312,000 BI                  Various                         2010
Window Repaint/Caulk                                                       $322,000 BI                  SENG et al.                     2010
Sewerage Infiltration Rep.                                                 $208,000 BI                  Site                            2010
Fire Alarm Upgrade                                                         $167,000 BI                  Auditorium                      2010
Fire Alarm Upgrade                                                         $146,000 BI                  Violette                        2010
HVAC Phase I                                                            $1,040,000 BI                   CVPA                            2011
HVAC Phase II                                                           $1,040,000 BI                   CVPA                            2012
Bathroom Rehab.                                                         $1,560,000 BI                   SENG                            2011
Emergency Lighting Alts.                                                   $240,000 BI                  SENG                            2012
Generator Upgrade                                                          $156,000 BI                  SENG                            2012
Fire Door Replacement                                                      $624,000 BI                  Various                         2013
Generator Upgrade                                                          $156,000 BI                  Liberal Arts                    2013
Emergency Lighting Alts.                                                   $177,000 BI                  Liberal Arts                    2013
Bathroom Rehab.                                                            $520,000 BI                  Liberal Arts                    2013
Masonry Repairs                                                          $2,600,000   BI                    Various                         2013
Window Storms & Film                                                     $2,600,000   BI                    Various                         2015
Masonry Repairs                                                          $2,600,000   BI                    Various                         2015
Corridor Reflooring                                                      $1,040,000   BI                    Various                         2015
Interior Signage                                                          $104,000    BI                    SENG                            2015
Atrium Rehab.                                                             $364,000    BI                    Dion                            2015
Art Studio Rehab.                                                        $1,560,000   BI                    CVPA                            2016
Generator Upgrade                                                         $156,000    BI                    Violette                        2016
Fire Alarm Upgrade                                                        $292,000    BI                    Tripp                           2016
Generator Upgrade                                                         $156,000    BI                    Tripp                           2016
Reroofing                                                                 $260,000    BI                    SMAST                           2016
MEP Deferred Maintenance                                                $30,000,000   BI                    Various                         2018

Total Est. Project Costs                                                $61,702,000


Project Description:       This proposal includes funding to address unique infrastructure needs as well as to initiate, continue, or complete
                           infrastructure renewal work across the campus.

                           Unique Infrastructure Work
                           Our sewerage outflow lines are currently being infiltrated by groundwater in various locations causing an average
                           of $250,000 per annum in excess sewerage costs; this funding will investigate the sources of infiltration and
                           waterproof manholes and leaking lines. The current theater lighting system is 35 years old and is no longer fully
                           functional or repairable and this funding is planned to cover the installation of a replacement system. 28 -year-old
                           art studios currently have original finishes and window treatments; this funding is planned to upgrade finishes and
                           built-in casework. At the Tripp Center, we will add egress doors to the gymnasium in order to increase allowable
                           occupancies for commencement, concerts, or other large-scale events.

                           Infrastructure Renewal Completions
                           This funding is planned to complete several sub-categories of campus renewal work: repaving and widening
                           asphaltic pedestrian walkways, repainting and recaulking all window frames, replacement of all original exterior
                           tectum soffits with trowelled-on plaster, replacement and upgrade of HVAC and fume hood systems at SENG,
                           reroofing the last deteriorated roofs on campus at our Dion Building and our School of Marine Science and
                           Technology (SMAST) Building, and renovating the last major atrium on campus in the Dion Building.
                                                          2008-2012
                           Infrastructure Renewal Continuations
                           This funding is planned to further progress in several sub-categories of campus renewal work: repaving our 35
                           year old parking lots (Lot 10); installing solar film and storm windows on all campus windows (Liberal Arts and
                           SENG and Library et al.); replacing exposed aggregate corridor flooring with cleanable, smooth unitary flooring
                           (Liberal Arts and SENG et al.); installing ADA-compliant interior signage and wayfinding (SENG); replacing
                           corridor fire and smoke doors and keeping them on hold-opens tied to the fire alarm system to improve
                           handicapped access (Liberal Arts and SENG et al.), replacing the original zoned fire alarm systems with modern
                           addressable systems reporting via radio to our Public Safety headquarters (Auditorium, Violette, Textile, and
                           Tripp); and bathroom rehabilitations to green, touchless standards (SENG, first floor of Liberal Arts).

                           Infrastructure Renewal Initiations
                           This funding is planned to start sub-categories of campus renewal work in several new areas: replacing the
                           original emergency diesel generators with gas-fired generators of greater capacity to carry important
                           uninterruptible equipment including elevators, research incubators and freezers, and higher priority computer
                           systems (Liberal Arts, SENG, Violette, Tripp); rewiring emergency lighting circuits to meet current code standards
                           as required by electrical system upgrades (Liberal Arts and SENG) (see Priority 19 below); Laboratory Upgrades
                           (this work would be initiated with a series of teaching laboratory rehabilitations in SENG which would include the
                           installation of new epoxy flooring, new casework, new fume hoods, new eyewash/shower stations, new hazmat
                           collection centers, as well as lab-specific freezers, dehumidification, or other specialized built-in equipment); and
                           the first phase of a three phase project to upgrade/replace mechanical systems at our CVPA Building.
Earliest Commencement Date:                        FY2009

Study / Feasability Explanation:   These projects have been identified by our 2005 Facilities Master Plan and almost all require design.
                                   Two projects are already designed and several projects require studies.


Est. Project Duration:                         FY2009-FY2012
                                                            FY09 Capital Project Description


Campus:                                 Dartmouth

Project Name:                           Priority 7 - Classroom Upgrades and Learning Space Improvements

Funding Source:                         State - G.O. Bonds
                                        University - Private Fundraising
                                        University - Local Funds

Project Location:                       Academic Buildings, Main Campus

Project Type:                           RV

                         Most classrooms, labs, studios, and other common areas used by students are located in buildings that are thirty or more years old. Normal
Justification:           wear and tear has taken its toll on our older buildings. Finishes have deteriorated; original steel mesh window curtains hav e been damaged
                         and removed; fixed seating and tables are damaged beyond repair. Teaching pedagogy has changed from the lecture formats of old to more
                         modern group discussion and team-oriented methods of today and this change lessens the functionality of most of our tiered lecture hall
                         environments. Computers and sophisticated audio-visual equipment is now required for the typical classroom. This project is consistent
                         with our Facilities Master Plan Classroom Utilization study which suggested that renovation of our existing classrooms would result in
                         better, more efficient classroom utilization.

                         The campus has embarked on a program to make all general use classrooms technology equipped, to replace seating, flooring and other
                         interior improvements; and to improve lighting and other environmental factors impacting learning. To date, we have successf ully
                         introduced technology to all general use clasrooms, replaced flooring and seating in many, converted most tiered seating clas srooms to more
                         flexible classrooms and repaired and improve various Atria to become accessible study spaces. The funds requested here will a llow us to
                         continue to repair and replace flooring and to replace remaining fixed seating in tiered classrooms.




                                                                                                                             Associated         Campus    Estimated
  Proposed Project Components                                         Estimated Costs                                         Program           Location  Completion
Classroom Upgrades                                                                                         $3,120,000   TL                    Main Campus       2015
Studio Upgrades                                                                                            $1,040,000   TL                    Main Campus       2015
Common Area Upgrades                                                                                       $1,040,000   TL                    Main Campus       2015
Flooring                                                                                                   $4,160,000   TL                    Main Campus       2015
Fixed Seating                                                                                             $2,080,000    TL                    Main Campus       2015

Total Est. Project Costs                                                                                 $11,440,000


Project Description:     For classrooms, labs and studios, renovation work will involve replacing fixed seating and refinishing fixed tables, filling in tiered classrooms
                         with light-weight concrete fill to create flat classrooms, installing teaching technology, reflooring, installing new window tre atments, repairing
                         masonry walls or repainting, installing new ceiling grids and lighting in some areas, installing clocks and white boards and pull-down
                         projection screens. Common area corridor upgrades include locker removals, repair of masonry and clerstory windows, replacin g smoke
                         doors, installation of improved lighting, replacement of tectum ceiling tiles, and reflooring with lineoleum or carpeting. C ommon area atria
                         upgrades include reupholstering concrete seating areas, installation of new flooring and lighting and audio-visual equipment for
                         presentations, installation of new window treatments, installation of new furniture and small cafe-style dining centers in selected areas. This
                         work is largely complete on the first floors of our oldest academic buildings, the Liberal Arts Building and the Science and Engineering
                         Building, but needs to be extended to our Center for Visual and Performaing Arts Building as well as smaller academic buildin gs and also to
                         the second floor academic classrooms and studios. These funds are planned to continue our program of upgrading classroom lear ning
                         environments. The work planned will include covering exposed aggregate classroom flooring with unitary materials (epoxy or s heet
                         linoleum) to improve appearance and cleanability and to replace all fixed seating in tiered classrooms with modern ergonomic seating.




Earliest Commencement Date:                                                FY2009

Study / Feasability Explanation:         2005 Master Plan. No study or design required.


                                        FY 2009-FY2015 (Projects must be phased to accommodate academic
Est. Project Duration:                  schedule)
                                            FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 8 - Liberal Arts Air Conditioning

Funding Source:                        State - G.O. Bonds

Project Location:                      Liberal Arts Building, Main Campus

Project Type:                          RV


Justification:           The Liberal Arts Building was constructed in 1966 as the first major academic building on the
                         campus. Air conditioning was not installed as an amenity at that time. Since the building is now
                         used throughout the year, air conditioning is seen as a necessity. To address this need, many small
                         window units have been installed in faculty office areas and some administrative centers and
                         computer labs have been provided with small split systems. These stop-gap measures are both
                         unsightly and wasteful of energy. Additionally, this building now has reached maximum electrical
                         usage and the addition of any power-consuming equipment will require an upgrade to the electric
                         service entrance and switchboard additions, emergency engine upgrades, and new feeders and
                         distribution panels.



                    Since there is no available space to install a chiller and air handling equipment, either a new
                                                                                     Associated Campus            Estimated
 Proposed Project Components                     Estimated Costs                      Program      Location Completion
HVAC Phase I                                                             $1,040,000 BI            Liberal Arts          2009
HVAC Phase II                                                            $1,040,000 BI            Liberal Arts          2010
HVAC Phase III                                                             $936,000 BI            Liberal Arts          2011

Total Est. Project Costs                                                   $3,016,000


Project Description:     Since there is no available space to install a chiller and air handling equipment, a geothermal cooling
                         system will be constructed. Conditioned air distribution will utilize existing concrete ducts that are
                         integrated into the structure of the building. The project is planned to be implemented in three
                         phases for each of the three wings of the building. The needed electrical service upgrade must be
                         completed prior to the initiation of this project.


Earliest Commencement Date:                               FY 2009

Study / Feasability Explanation: Included in Facilities Master Plan. Study and Design required prior to commencement.

Est. Project Duration:                                FY2009-FY2011
                                                             FY09 Capital Project Description


Campus:                                 Dartmouth

Project Name:                           Priority 9 - Central Facilities Building and Retrofit of Vacated Space

Funding Source:                         State - G.O. Bonds

Project Location:                       East End, Main Campus

Project Type:                           NC


Justification:           At present Facilities and Auxiliary Services work groups occupy significant amounts of space in various buildings across the campus: Liberal Arts
                         Building (Facilities Shops), Science and Engineering Building, (Facilities Shops), Library (Custodial Services), College of Visual and Performing
                         Arts (Print Shop and Central Mail Distribution Unit), Foster Administration Building (administrative personnel for both Facilities and Auxiliary
                         Services), Residence Halls (Residence Housing Staff). The various groups are shoe-horned in, making normal storage and work activities
                         impossible to carry out. There is no covered storage area for vehicles. The broad distribution of personnel makes managerial oversight awkward.
                         Most importantly, these staff functions are occupying valuable spaces needed for our core academic functions.

                         Additionally, there is only one entrance to the campus. The location of the new facilities building (as determined in the Master Plan) enables the
                         easy creation of a second entrance to the campus. The need for the second campus entrance was identified in both the Master Plan and in the
                         Emergency Response Plan




                                                                                                                                                  the second Estimated
                       Initially the plan calls for building two modular buildings (one for garage functions and vehicular and equipment storage,Campus for the Print
  Proposed Project Components                                       Estimated Costs                                   Associated Program         Location    Completion
Facilities Building                                                                                     $8,840,000 TL                         Main Campus          2010
Retrofit Vacated Space                                                                                  $2,600,000 TL                         Main Campus          2011
Chase Road Exit                                                                                         $1,250,000 TL                         Site                 2010

Total Est. Project Costs                                                                                 $12,690,000


Project Description:     Initially the plan calls for building two modular buildings (one for garage functions and vehicular and equipment storage, the second for the Print
                         Shop, Mail Distribution Center, Facilities Shops, and administrative units) at the east end of the campus in an area not visible from the main
                         academic buildings and Ring Road but close to the existing steam plant building. The work will include the construction of parking for assigned
                         personnel and a new emergency egress road to Chase Road. The creation of the Chase Road Exit adddresses the serious second egress issues
                         raised in the campus Facilities Master Plan, as well as the campus Emergency Response Plan. The Chase Road Exit construction would entail a new
                         two-lane roadway from the Ring Road to Chase Road on the eastern edge of the campus meeting all Massachusetts Highway Department standards
                         including curbing and lighting. This road would provide access to the proposed Facilities Building site and would also provide a secondary
                         vehicular egress from the campus in case of emergency evacuation of the site. After Auxiliary Services and Facilities functions are moved into the
                         new building, the spaces they have vacated will be retrofit for use by academic units for storage, meeting rooms or offices.



Earliest Commencement Date:                                               FY2009

Study / Feasability Explanation:       Included in 2005 Facilities Master Plan. Programming completed; some additional study and design required prior to
                                       commencement. The project study is presently being conducted in conjunction with DCAM.

Est. Project Duration:                                                FY2009-FY2011
                                                            FY09 Capital Project Description


Campus:                                          Dartmouth

Project Name:                                    Priority 10 - Landscaping and Lighting Improvements

Funding Source:                                  University - Local Funds
                                                 State - G.O. Bonds

Project Location:                                Main Campus

Project Type:                                    O


Justification:            The Master Plan recommends upgrading landscaping and lighting and suggests a number of specific improvements that
                          would improve nighttime security, improve the liveliness of the central academic quadrangle, and improve access around
                          campus to achieve universal accessibility.


                          In the initial stages, this project will involve carrying out contracts to improve lighting between dormitory areas, parking

                                                                                                             Associated        Campus Estimated
       Proposed Project Components                                   Estimated Costs                           Program         Location Completion
Site Lighting Additions/Improvements                                                               $832,000 BI                 Site           2013
Site Signage                                                                                     $1,000,000 BI                 Site           2018

Total Est. Project Costs                                                                         $1,832,000


Project Description:     In the initial stages, this project will involve carrying out contracts to improve lighting between dormitory areas, parking
                         lots, the main academic quadrangle, and the athletic center. The second component of this project is planned to
                         implement a site signage and wayfinding program in its entirety. A study for the exterior signage program has been
                         completed and implementation would be initiated as soon as funds are made available.



Earliest Commencement Date:                                               FY 2009

Study / Feasability Explanation:          Included in Facilities Master Plan. Study completed, design required prior to commencement of
                                          project.

Est. Project Duration:                                                FY2008-FY2018
                                             FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 11 - Roadway Improvements

Funding Source:                        State - G.O. Bonds or Supplemental funds

Project Location:                      Main Campus

Project Type:                          DM


Justification:         Original asphaltic pavements are now approximately 35 years old and are deteriorated beyond
                       possible repair. This project addresses a rehabilitation of the ring road. The campus population
                       has grown significantly over the years and many students, faculty, and staff use the edges of the
                       ring road for biking, jogging, or walking but this creates potential safety conflicts with vehicular
                       traffic. The heavy roadway edge traffic also kills plantings and creates an unkempt appearance.
                       Finally, the roadway is underlit and this creates potential security problems for nighttime users.




                     This project would re-pave all original asphalt for parking lots and pedestrian walkways that have
                                                                                     Associated Campus Estimated
  Proposed Project Components                     Estimated Costs                      Program Location Completion
Ring Road Repaving                                                       $5,720,000 BI            Site              2015

Total Est. Project Costs                                                     $5,720,000


Project Description: The rehabilitation of the existing ring road would re-pave the roadway, install an inner ring of
                     lighting to double the illumination on the roadway, create several new pedestrian crossings with
                     pavement warning lights and flashing signals activated by pedestrian movement, create a new
                     sidewalk and bikepath for the use of pedestrians and cyclists, and install curbing to keep the
                     pedestrian and vehicular traffic flows safely separated.



Earliest Commencement Date:                                FY 2009

Study / Feasability Explanation:        Included in 2005 Facilities Master Plan. Would require design and regulatory
                                        approvals prior to commencement.

Est. Project Duration:                                FY2013 - FY2015
                                             FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 12 - Energy/Water Savings Project

Funding Source:                        University - UMBA/HEFA/Other

Project Location:                      Main Campus

Project Type:                          O


Justification:           Most of the original buildings on campus were designed just prior to the energy crisis of the 1970's and the
                         buildings are therefore not very energy efficient. At the same time, plumbing fixtures of this era used much
                         more water than their current counterparts. Additionally, since energy-savings technology like Energy
                         Management Systems, Variable Frequency Drives, and thermopane glass were not available at the time of
                         construction, the campus is poorly equipped to make significant improvements without a substantial infusion of
                         funds.




                                                                                                               Campus    Estimated
  Proposed Project Components                           Estimated Costs                   Associated Program   Location  Completion
Performance Contract                                                         $14,560,000 BI                  Main Campus       2011

Total Est. Project Costs                                                     $14,560,000


Project Description:     We propose to work with the Department of Capital Asset Management to let an Energy and Water
                         Conservation Performance Contract. While the technical details of such a contract cannot be known prior to
                         receipt of contractor proposals, it is expected that the work will include at least a co -generation plant, a centrally-
                         monitored energy management system including new mechanical and electrical actuating devices and sensors,
                         VFDs, motion-detector activated lighting, water-saving plumbing fixtures, and perhaps a plan to utilize
                         rainwater for non-potable water sources. If economically attractive, window modification or replacement might
                         also be possible.


Earliest Commencement Date:                                 FY2009

Study/Feasibility Explanation:                Included in Performance Contract

Est. Project Duration:                                  FY2009-FY2011
                                           FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 13 - Power Plant Upgrades/MEP

Funding Source:                       University - Local Funds
                                      State - G.O

Project Location:                     Steam Plant, Main Campus

Project Type:                         DM


Justification:          The existing steam plant was brought on line in 1966 with three large and one small boiler and a direct buried
                        steam supply and condensate return system. All insulated equipment is covered in asbestos-containing
                        material. The steam supply lines and the condensate return lines were poorly welded and have been failing at
                        an accelerated pace. The original boiler controls can no longer be repaired due to unavailability of parts.
                        One of the two original 40,000 gallon fuel tanks has developed a leak and cannot be used.




                      While we remove and replace ACM as needed for repairs and to correct for friable asbestos releases, the first
                                                                                                         Campus        Estimated
  Proposed Project Components                   Estimated Costs                Associated Program        Location Completion
Generator Upgrade                                                   $156,000 BI                        Steam Plant             2010
Emergency Lighting Alts                                               $21,000 BI                       Steam Plant             2010
HVAC Phase I                                                      $1,150,000 BI                        Steam Plant             2018
Bathroom Rehab                                                        $63,000 BI                       Steam Plant             2009
Asbestos Abatement                                                  $520,000 BI                        Steam Plant             2009
Rebuild Boiler #3                                                     $26,000 BI                       Steam Plant             2009
Replacement of UST                                                  $475,000 BI                        Steam Plant             2009
Repair of Steam Lines                                             $1,700,000 BI                        Steam Plant             2018
Upgrades of Controls                                                $260,000 BI                        Steam Plant             2009

Total Est. Project Costs                                                  $4,371,000

Project Description:   This funding is planned to cover the replacement of the existing diesel emergency engine, the separation of
                       emergency lighting circuits necessitated by the work outlined in Priority 14, renovation of the bathrooms to
                       meet current green, touchless standards, and the first phase of a five phase plan to upgrade our high-pressure
                       steam plant.

                       While we remove and replace ACM as needed for repairs and to correct for friable asbestos releases, the first
                       part of our plan would remove all asbestos-containing insulation from the building in a systematic way.

                       We have also repaired all steam leaks in the distribution system and have replaced the failed main condensate
                       return line as well as the adjacent steam supply line up to the main campus. Thus at present, no urgent work
                       is needed on the steam distribution system, but it may safely be predicted that additional leaks will occur in the
                       next five years so we plan to spend some significant monies to replace these lines when the failures occur.

                       Several of the boilers have in the recent past been upgraded and this work is planned to be completed in the
                       coming year but controls need complete replacement due to unavailability of parts and the fire box on one of
                       the boilers has deteriorated to the point where a rebuilding is required.

                       Proposed funding would also replace the leaking underground fuel storage tank so that redundant fuel sources
                         Proposed funding would also replace the leaking underground fuel storage tank so that redundant fuel sources
                         would be available at all times.




Earliest Commencement Date:                               FY 2009

Study / Feasability Explanation:      Included in Facilities Master Plan. Design required prior to commencement.

Est. Project Duration:                                FY2009-FY2018
                                                                           FY09 Capital Project Description


Campus:                                                             Dartmouth

Project Name:                                                       Priority 14 - PCB Transformer Replacements

Funding Source:                                                     State - G.O. Bonds

Project Location:                                                   Main Campus

Project Type:                                                       CO


Justification:           All transformers on campus were originally cooled using a PCB coolant. When required by law to stop using PCB coolants, all
                         dormitory transformers were removed and new PCB-free transformers were installed. But in academic buildings, the old
                         transformers were flushed and refilled with PCB-free coolant. We have found through our annual testing that PCB levels continue
                         to creep upwards over time and we intermittently have to re-flush and re-fill the academic building transformers. At the same time,
                         our growth and our increased use of technology has led to an increased demand for electricity in our academic buildings. This
                         project will allow us to address both of problems.



                                                                                 We plan to replace transformers on a prioritized basis with those transformers showing
                                                                                                                       Associated       Campus       Estimated
            Proposed Project Components                                             Estimated Costs                     Program         Location Completion
PCB Transformer Replacements/Electrical Upgrades                                                            $410,000 BI              Liberal Arts          2009
PCB Transformer Replacements/Electrical Upgrades                                                            $550,000 BI              SENG                  2010
PCB Transformer Replacements/Electrical Upgrades                                                             $63,000 BI              Steam Plant           2011

Total Est. Project Costs                                                                                   $1,023,000


Project Description:       As current plans to replace all high-voltage feeders are implemented this coming year, it will be possible to increase electrical
                           power capacity in our most electrically overloaded buildings. Each of these upgrades will involve the installation of a new, larger
                           transformer and a new, larger main disconnect switch in a new switchboard section. This work will replace transformers that
                           once contained PCB-coolant with completely clean transformers and will provide for additional power in buildings which
                           currently have run out of electrical capacity completely. This work will be required in order to install air conditioning in the
                           Liberal Arts Building, and to provide functional growth in the SENG and Steam Plant buildings as we rehabilitate their
                           mechanical systems.



Earliest Commencement Date:                                                              FY2009

Study / Feasability Explanation: Included in Facilities Master Plan. Requires completion of the feeder project and design prior to commencement.


Est. Project Duration:                                                              FY2009-FY2011
                                               FY09 Capital Project Description


Campus:                                     Dartmouth

Project Name:                               Priority 15 - Elevator Upgrades

Funding Source:                             State - G.O. Bonds

Project Location:                           Main Campus

Project Type:                               CO


Justification:           Elevators on the main campus except for our newest buildings range in age from 12 to 40 years old.
                         They were all designed to comply with the ADA code in effect at the time they were built but federal
                         ADA legislation has provided additional guidance and not all of our elevators are in complete
                         conformance with the stricter federal requirements. In addition all of the academic building elevators
                         utilize electromechanical technology and have deteriorating cab interiors except for the elevators
                         installed during the last 5 years. Some elevators have not been upgraded for Fireman's Recall function
                         and most elevators will not be sent to the nearest floor in the event of a power outage.




                        While all required jack replacements on hydraulic elevators have been completed and elevator
                                                                                                         Campus Estimated
     Proposed Project Components                       Estimated Costs              Associated Program Location Completion
Mechanical Elevator Upgrades                                             $312,000 BI                    Various       2012
Interior Finishes Elevator Upgrades                                    $1,040,000 BI                    Various       2012

Total Est. Project Costs                                                   $1,352,000


Project Description:     While all required jack replacements on hydraulic elevators have been completed and elevator
                         maintenance has kept all campus elevators operational, this project would systematically correct ADA
                         deficencies, install Fireman's Recall features, renovate cabs, add the capacity to return to the nearest floor
                         in the event of a power failure, and, in some cases, upgrade the electromechnical controls.



Earliest Commencement Date:                                  FY2010

Study / Feasability Explanation:        Included in Facilities Master Plan. Project is scoped, but needs development of
                                        performance specifications prior to commencement.

Est. Project Duration:                                  FY2010 - FY2012
                                       FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 16 - Asbestos Removal

Funding Source:                       University - Local Funds
                                      State - G.O. Bonds

Project Location:                     Academic Buildings, Main Campus

Project Type:                         CO


Justification:           Most of the academic buildings were built in a time frame when asbestos was widely used to insulate
                         mechanical plant systems so asbestos-containing materials exist throughout most buildings. The campus
                         continues to routinely remove asbestos-containing materials used on mechanical systems, flooring, and
                         finishes.



                     The campus will continue to abate small amounts of asbestos as needed to complete repair work or address
                                                                                                                  Estimated
 Proposed Project Components               Estimated Costs              Associated Program Campus Location Completion
Asbestos Abatement                                            $100,000 BI                     Acad Bldgs                 2012
Asbestos Abatement                                            $300,000 BI                     Res. Halls                 2012

Total Est. Project Costs                                           $400,000


Project Description:     The campus will continue to abate small amounts of asbestos as needed to complete repair work or address
                         releases of friable asbestos but a more systematic, larger scale abatement process was begun two years ago.
                         This funding would remove all asbestos containing materials from our highest priority residence halls and
                         academic buildings.


Earliest Commencement Date:                          FY2009

Study/Feasability Explanation:         Included in Facilities Master Plan.

Est. Project Duration:                           FY2009-FY2012
                                        FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 17: IT Upgrades

Funding Source:                       University - Local Funds

Project Location:                     Main Campus

Project Type:                         IT

Justification:           In order to implement Peoplesoft, the campus will need to keep up with various system upgrades.




                                                                                 Associated     Campus    Estimated
  Proposed Project Components                     Estimated Costs                 Program       Location  Completion
System Upgrades                                                     $2,080,000 BI             Main Campus       2013

Total Est. Project Costs                                            $2,080,000


Project Description:     System upgrades for Peoplesoft.

Earliest Commencement Date:                                              2009

Study/Feasibility Explanation:        Not applicable

Est. Project Duration:                2009-2013
                                           FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 18 - Biomanufacturing Building

Funding Source:                       Other (State Economic Development)

Project Location:                     Fall River

Project Type:                         NC


Justification:           The Commonwealth of Massachusetts has funded an economic stimulus bill that would fund a large-scale
                         biomanufacturing operation in support of our collaboration with UMass Lowell, Tufts, Worcester
                         Polytechnic Institute, Nova Biomedical, Antigenics, Cambrex and Genzyme. The aim of the collaborative
                         partners is to improve the quality, cost, and productivity of biomanufacturing in the Commonwealth.




                                                                                                             Campus Estimated
  Proposed Project Components                         Estimated Costs                   Associated Program   Location Completion
Biomanufacturing Bldg.                                                  $10,000,000 R                        Off-Site      2011

Total Est. Project Costs                                                $10,000,000


Project Description:     This project must be a public/private venture located in Fall River.


Earliest Commencement Date:                               FY2009

Study/Feasibility Explanation:                     Study needs to be done.

Est. Project Duration:                                FY2009-FY2011
                                            FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 19 - Research Extension Phase II

Funding Source:                        University UMBA/HEFA/Other

Project Location:                      Main Campus

Project Type:                          NC


Justification:           The recently completed Research Extension Building did not include a fit-out of
                         laboratory benches and support infrastructure for the first floor of research space.




                                                                                                          Estimate
                                                                                      Associate              d
                                                                                         d      Campus Completi
  Proposed Project Components                         Estimated Costs                 Program Location       on
First Floor Fit-Out                                                        $1,900,000 R         Res. Ext.     2009

Total Est. Project Costs                                                   $1,900,000


Project Description:     The fit-out work will include benches, air handling and distribution, fume hood
                         installation, and other interior work as required.

Earliest Commencement Date:                               FY2009

Study/Feasibility Explanation:            Study completed; project in construction

Est. Project Duration:                         Projected completion in 2009
                                              FY09 Capital Project Description


Campus:                              Dartmouth

Project Name:                        Priority 20 -Network and Telecom Infrastructure

Funding Source:                      University - Local Funds
                                     State - G.O. Bonds or Supplemental funds

Project Location:                    Main Campus

Project Type:                        IT


Justification:         The campus will need to upgrade its IT infrastructure to maintain the same level of service while technology
                       changes.




                                                                                             Associated     Campus    Estimated
  Proposed Project Components                          Estimated Costs                        Program       Location  Completion
Campus Wiring Upgrade                                                           $1,040,000   BI           Main Campus       2010
Infrastructure Operations                                                         $512,000   BI           Main Campus       2010
Digital Signage System                                                             $60,000   BI           Main Campus       2011
Distance Learning Classroom                                                        $50,000   BI           Main Campus       2011
Campus WiFi                                                                       $700,000   BI           Main Campus       2012
Network Security                                                                  $350,000   BI           Main Campus       2011

Total Est. Project Costs                                                        $2,712,000



                       Campus Wiring Upgrade: Recable campus with CAT6 copper and single mode fiber. This will enable the
Project Description:   campus to utilize VOIP and emerging technologies. 1/2 of the campus is using CAT3 cable that provides a
                       only maximum speed of 10 megabits per second (Mbps) versus 1000 Mbps with CAT6. By upgrading the
                       cable plant with CAT6 to every desktop, speeds can be increased up to gigabit and thus improve networks for
                       the academic buildings and residence halls.

                       Infrastructure Operations: Acquisition of network equipment to provide campus network redundancy and
                       interconnection with regional networks. Upgrade of infrastructure to support digital services, i.e., video
                       streaming, audio, file sharing, etc.; virtualize servers for email, calendaring, DNS, DHCP, Log Analysis.
                       Chassis replacement to improve network speed for the Arts and Science Building and Library.

                       Digital Signage System: Implementation of a campuswide digital signage system to support campus
                       communications including emergency notifications, campus messaging, and area-specific messaging.

                       Distance Learning Classroom: Acquisition of technology to allow classrooms to operate as Distance
                       Learning Facilities.

                       Campus WiFi (Wireless): Deployment of campus wide, high speed wireless network. This will provide
                       secure, ubiquitous wireless access.

                       Network Security: Acquisition of PCI Compliance Firewall and Dragon Network Defense.
Earliest Commencement Date:        FY2009

Study / Feasability Explanation:   Not applicable

Est. Project Duration:             FY2009-FY2012
                                                 FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 21: Charlton College of Business, Phase II

Funding Source:                        University - Private Fundraising

Project Location:                      Charlton Building, Main Campus

Project Type:                          NC


Justification:           The recently completed Charlton College of Business houses only office spaces and some meeting space. To
                         complete the project, we will need to integrate academic space -- in particular case study classrooms, trading
                         floor classroom, auditoria. This will be accomplished by building a 22,000 square foot addition to the current
                         Charlton College of Business.




                                                                                               Associated   Campus    Estimated
 Proposed Project Components                               Estimated Costs                      Program     Location  Completion
Renovation/Addition                                                                $14,000,000 TL         Main Campus       2015

Total Est. Project Costs                                                           $14,000,000


Project Description: Construction of an addition to the Charlton College of Business to provide academic spaces.


Earliest Commencement Date:                                    FY2009

Study/Feasibility Explanation:                              Study needed

Est. Project Duration:                                     FY2009-FY2015
                                         FY09 Capital Project Description


Campus:                              Dartmouth

Project Name:                        Priority 22: ATMC Acquisition

Funding Source:                      Other

Project Location:                    ATMC, Fall River Campus

Project Type:                        O


Justification:      The ATMC is currently located in a building under a long term lease with MDFA
                    which requires yearly legislative allocations. An outright purchase would allow the
                    campus greater flexibility in the use and financial support of the facility.



                                                                                                 Estimate
                                                                            Associate               d
                                                                               d       Campus Completi
 Proposed Project Components                     Estimated Costs            Program Location        on
Building Purchase                                               $11,400,000 R         Fall River     2010

Total Est. Project Costs                                           $11,400,000


Project Description:     Purchase of building.

Earliest Commencement Date:                          FY2009

Study/Feasibility Explanation:                    Not applicable

Est. Project Duration:                           FY2009-FY2010
                                           FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 23: Multipurpose Field House

Funding Source:                       University - Private Fundraising

Project Location:                     Athletic Complex, Main Campus

Project Type:                         BR


Justification:           The largest indoor space on campus for major events like commencement or student concerts is the gym which is
                         designed for a maximum occupancy of 1600 people. Lack of indoor areas for team practice space is also a
                         problem during winters and poor weather conditions.




                                                                                                                  Campus    Estimated
  Proposed Project Components                       Estimated Costs                    Associated Program         Location  Completion
Field House                                                           $20,800,000 SL                            Main Campus       2014

Total Est. Project Costs                                              $20,800,000


Project Description:     The funding for this project would cover the construction of a 75,000 square foot field house adjacent to existing
                         the Tripp Athletic Center and all necessary relocations of surrounding athletic fields and parking lots.



Earliest Commencement Date:                             FY2011

Study/Feasibility Explanation:             Documented in 2005 Master Plan

Est. Project Duration:                             FY2011-FY2014
                                                   FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                           Priority 24: Locker and Training Room Renovations

Funding Source:                        State - G.O. Bonds

Project Location:                      Tripp Athletic Center, Main Campus

Project Type:                          RV


Justification:           The existing facilities were built in 1971 and are no longer adequate for our growing student population. Additionally
                         they are awkwardly arranged and require visitors to pass through locker rooms or go outside and around the building
                         to get from one side of the building to the other.




                                                                                                  Associated               Estimated
  Proposed Project Components                               Estimated Costs                        Program Campus Location Completion
Athletics Alterations                                                                  $3,120,000 SL         Main Campus         2016

Total Est. Project Costs                                                               $3,120,000




Project Description:     The project is planned to reprogram and reconfigure the existing locker rooms and training rooms to accommodate
                         more students and to provide a new passage through the building so that visitors can get from the lobbies and gym to
                         the swimming pool without passing through one of the locker rooms.



Earliest Commencement Date:                                      FY2012

Study / Feasability Explanation:       Included in Facilities Master Plan. Requires study and design prior to commencement.

Est. Project Duration:                                      FY2014 - FY2016
                                                            FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 25: Non-critical HVAC, Infrastructure and Envelope Repairs

Funding Source:                       University - Local Funds
                                      University - UMBA/HEFA/Other

Project Location:                     Main Campus

Project Type:                         DM


Justification:           Academic Buildings range in age from 12 to 34 years old and existing mechanical, electrical, plumbing and envelope systems ar e coming to
                         the end of their useful lives. Our recently finalized master plan suggested that we would need to spend over $300M in order to address all
                         infrastructure maintenance needs. While the campus has largely maintained or replaced any failing roofs, older masonry is in need of
                         repointing or replacement and sealing. Electrical systems have generally reached capacity due to increasing electrical deman d from the
                         growth in computer usage. Mechanical systems have also reached capacity due to the high heat loads involved in computer usag e. Older
                         plumbing piping is frequently so deteriorated that it requires replacement. Fire alarm systems, fire suppression systems, an d elevators are all
                         due for replacement and/or upgrades.




                                                                                                                                           Campus    Estimated
  Proposed Project Components                                         Estimated Costs                                 Associated Program   Location  Completion
Infrastructure Repairs                                                                                     $3,120,000 BI                 Main Campus       2011
Infrastructure Repairs                                                                                       $520,000 BI                 Main Campus       2016

Total Est. Project Costs                                                                                   $3,640,000


Project Description:     This project is planned to continue with the highest priority work not completed under Priority #5.

Earliest Commencement Date:                                               FY2010

Study/Feasibility Explanation:              Identified in 2005 Master Plan but most require study and design.

Est. Project Duration:                                                FY2011-FY2016
                                                FY09 Capital Project Description


Campus:                             Dartmouth

Project Name:                       Priority 26: Athletic Field Replacement

Funding Source:                     State G.O./Supplemental

Project Location:                   Center of Track, Tripp Athletic Center, Main Campus

Project Type:                       O

Justification:                      The existing soccer field located on the inside of the oval track was over-compacted and does not
                                    drain rainwater adequately.



                                                                                                Associated   Campus    Estimated
 Proposed Project Components                              Estimated Costs                        Program     Location  Completion
Rebuild Soccer Field                                                                   $819,000 SL         Main Campus       2015

Total Est. Project Costs                                                               $819,000


Project Description: The existing soils would be removed and a new soccer field would be installed with appropriate compaction to
                     allow proper drainage.

Earliest Commencement Date:                                   FY2014

Study/Feasibility Explanation:          Functionality problem documented; design required

Est. Project Duration:                                    FY2014-FY2015
                                         FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 27: Fitness Center Expansion

Funding Source:                       University - Private Fundraising

Project Location:                     Tripp Athletic Center, Main Campus

Project Type:                         RV


Justification:           The Fitness Center Addition, built about 8 years ago, has proven to be extremely popular with
                         students and is heavily used by all members of the UMD community to the point where it is
                         frequently too crowded and customers need to be turned away.




                                                                                 Associated   Campus    Estimated
  Proposed Project Components                      Estimated Costs                Program     Location  Completion
Fitness Center Addition                                              $5,000,000 SL          Main Campus       2011

Total Est. Project Costs                                             $5,000,000


Project Description:     The Fitness Center Addition would approximately double the capacity of the existing fitness
                         center by expanding the building to the north.

Earliest Commencement Date:                            FY2010

Study/Feasibility Explanation:                     Study required

Est. Project Duration:                            FY2010-FY2011
                                         FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 28: Campus Center Addition

Funding Source:                        University - Private Fundraising

Project Location:                      Campus Center, Main Campus

Project Type:                          BR


Justification:           The campus master plan recommends the construction of additions to the Campus Center
                         Building to accommodate the growing needs of our larger student population. Many work units
                         serving students are scattered in classroom buildings or the Foster Administration Building.
                         Some additional space recommended in the master plan would add to the building on the east
                         side to accommodate student organizations that cannot currently be assigned dedicated space and
                         to centralize class registration, student counseling, and other student -oriented functions in one
                         building. Other additional space recommended in the master plan would add to the building on
                         the west side to accommodate additional dining room space.




                                                                                Associated   Campus    Estimated
 Proposed Project Components                       Estimated Costs               Program     Location  Completion
Building Addition                                                  $16,400,000 SL          Main Campus       2016

Total Est. Project Costs                                            $16,400,000


Project Description:      The construction would add a one bay layer of building to both the east and west sides of the
                          building and reprogram and reconfigure the internal space allocations. It is contemplated that the
                          new walls will primarily be an energy-efficient thermopane glass system so as to preserve much of
                          the original architecture of the building.


Earliest Commencement Date:                             FY2013

Study/Feasibility Explanation:              2005 Master Plan; study required

Est. Project Duration:                             FY2013-FY2016
                                                    FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 29: New Bedford Incubator

Funding Source:                       State - G.O. Bonds or Supplemental funds

Project Location:                     New Bedford

Project Type:                         O


Justification:           The legislature authorized the establishment of a biotechnology incubator center in New Bedfo




 Proposed Project Components                                  Estimated Costs
New Bedford Incubator                                                                      $5,000,000

Total Est. Project Costs                                                                   $5,000,000


Project Description:     Establish a biotechnology incubator site in the City of New Bedford.


Earliest Commencement Date:                                       FY2009

Study/Feasibility Explanation:                                Study Required

Est. Project Duration:                                        FY2010-FY2013
ncubator center in New Bedford, Massachusetts.




                                  Estimate
            Associate                d
               d        Campus    Completi
            Program     Location     on
            O         New Bedford     2013
                         Establish a biotechnology incubator Admissionsa Department, Campus Police, and space for bu
                          At present, Admissions occupies academicthe City of New Bedford. highly visible New Bedfo
                          The legislature authorized the establishment of biotechnology not
                                                       FY09 Capital building space that is
                         Initially a Visitor Center housing the site in Project Description incubator center into visitorsstu


Campus:                                Dartmouth

Project Name:                          Priority 30: Taunton Life Sciences Center

Funding Source:                        State - G.O. Bonds or Supplemental funds

Project Location:                      Taunton

Project Type:                          O


Justification:           The legislature authorized the establishment of a life sciences center in Taunton, Massachusetts
                         with Bristol County Community College.




 Proposed Project Components                                    Estimated Costs
Taunton Life Sciences Center                                                                  $5,000,000

Total Est. Project Costs                                                                      $5,000,000


Project Description:     Establish a life sciences center in the City of Taunton in conjunction with Bristol County Comm


Earliest Commencement Date:                                         FY2009

Study/Feasibility Explanation:                                  Study Required

Est. Project Duration:                                         FY2010-FY2013
mpus Police, and space for but would be very
not highly visible New Bedford, Massachusetts.
ncubator center into visitorsstudent greeters and




ter in Taunton, Massachusetts in conjunction




                                       Estimate
             Associate                    d
                d        Campus        Completi
             Program     Location         on
             O         Taunton             2013




on with Bristol County Community College.
                                                     FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 31: Visitor Center and Retrofit of Vacated Space

Funding Source:                       State - G.O. Bonds or Supplemental funds

Project Location:                     Main Campus Entrance

Project Type:                         NC


Justification:           At present, Admissions occupies academic building space that is not highly visible to visitors but would be very useful for e xpansion of
                         nearby academic units. Campus Police occupy some space in residence halls and all administrative space in the steam plant bu ilding on the
                         eastern end of the ring road. This situation is not ideal in terms of force management or Public Safety's ability to monitor traffic in and out
                         of campus.




                                                                                                                                                        Estimated
  Proposed Project Components                                  Estimated Costs                               Associated Program         Campus Location Completion
Visitor Center Building                                                                    $13,500,000 BI                               Main Campus           2014
Retrofit                                                                                    $2,080,000 BI                               Main Campus           2015

Total Est. Project Costs                                                                   $15,580,000




Project Description: Initially a Visitor Center housing the Admissions Department, Campus Police, and space for student greeters and university di splays would
                     be built at the main campus entrance. The work would include the creation of an associated parking lot and landscaping. Thi s prominently
                     placed building is planned to reflect architectural standards that are compatible with the cast -in-place concrete architecture of the main
                     campus. After Admissions and Campus Police move into the new building, retrofit of the vacated spaces in the Auditorium Addi tion and
                     the Steam Plant Building will be completed for the use of the academic community or the Steam Plant and future co -generation plant
                     managerial staff.


Earliest Commencement Date:                                        FY2014

Study/Feasibility Explanation:                        2005 Master Plan; study required

Est. Project Duration:                                              3 years
                                            FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 32: New Campus Center Plaza

Funding Source:                       State - G.O. Bonds or Supplemental funds

Project Location:                     Academic Quadrangle, Main Campus

Project Type:                         O


Justification:            The master plan called for reconfiguring the central academic quadrangle with landscaping and the removal of
                          concrete hardscape to facilitate better use of the space for large outdoor gatherings and social events.




                                                                                                                   Campus    Estimated
  Proposed Project Components                        Estimated Costs                      Associated Program       Location  Completion
Site Improvements                                                         $2,457,000 BI                          Main Campus       2016

Total Est. Project Costs                                                  $2,457,000


Project Description:     The plans show concrete steps being removed and additional plantings being installed as well as regrading the area
                         which will accommodate mowers and other grounds equipment that needs to be used on all the various levels of the
                         academic quadrangle.



Earliest Commencement Date:                               FY2016

Study/Feasibility Explanation:               2005 Master Plan; design required

Est. Project Duration:                                    2 years
                                             FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 33: Renovation Campus Auditorium

Funding Source:                       State - G.O. Bonds or Supplemental funds

Project Location:                     Auditorium

Project Type:                         RV


Justification:           The existing auditorium has poor acoustics, poor lines of sight, and poor lighting. Due to cost-cutting during the
                         original design, the auditorium room was truncated and three classrooms were installed in the balcony areas. The
                         balcony classrooms are used but do not provide suitable acoustics or lighting for a classroom setting.




                                                                                                             Campus    Estimated
  Proposed Project Components                          Estimated Costs                  Associated Program   Location  Completion
Alterations                                                                 $11,170,000 TL                 Main Campus       2016

Total Est. Project Costs                                                    $11,170,000


Project Description: The project would involve a complete revamp of lighting in the building and would remove the three classrooms,
                     reconfigure balconies and add acoustic treatment to improve conditions for presenting plays and other artistic
                     performances.

Earliest Commencement Date:                                FY2015

Study/Feasibility Explanation:                2005 Master Plan; study required

Est. Project Duration:                                     3 years
                                             FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 34: Resident Dining Hall Expansion

Funding Source:                       University - UMBA/HEFA/Other

Project Location:                     Resident Dining Hall, Main Campus

Project Type:                         BR


Justification:           The existing Resident Dining Hall is inadequate for the growing residential student population.




                                                                                         Associated   Campus    Estimated
 Proposed Project Components                           Estimated Costs                    Program     Location  Completion
Addition                                                                     $5,670,000 SL          Main Campus       2016

Total Est. Project Costs                                                     $5,670,000


Project Description:     This project would put an addition on the existing building to accommodate a greater number of
                         residential students who dine in this building three times a day.

Earliest Commencement Date:                                FY2015

Study/Feasibility Explanation:                          Study required

Est. Project Duration:                                      3 years
                                               FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 35: Group II Dion Engineering Phase I

Funding Source:                       State - G.O. Bonds or Supplemental funds

Project Location:                     Science and Engineering Building, Main Campus

Project Type:                         NC


Justification:           As the campus grows, additional classroom and faculty office space will be required in the future. The master plan suggests
                         that building two new academic buildings will be appropriate within the 10-year time frame of this capital plan. This
                         priority represents the first of those buildings.




                                                                                                                          Campus    Estimated
 Proposed Project Components                            Estimated Costs                         Associated Program        Location  Completion
Addition                                                                       $22,600,000 TL                           Main Campus       2015

Total Est. Project Costs                                                       $22,600,000


Project Description:     This contract is planned to cover the construction of a new academic building to house classrooms, faculty offices,
                         laboratories and all necessary support space.

Earliest Commencement Date:                                  FY2013

Study/Feasibility Explanation:                  2005 Master Plan; study required

Est. Project Duration:                                       3 years
                                                FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 36: Group II Dion Engineering Phase II

Funding Source:                        State - G.O. Bonds or Supplemental funds

Project Location:                      Science and Engineering Building, Main Campus

Project Type:                          NC


Justification:           As the campus grows, additional classroom and faculty office space will be required in the future. The master plan
                         suggests that building two new academic buildings will be appropriate within the 10-year time frame of this capital plan.
                         This priority represents the second of those buildings.



                                                                                                                                      Estimate
                                                                                                                                         d
                                                                                                                            Campus    Completi
 Proposed Project Components                              Estimated Costs                         Associated Program        Location     on
Addition                                                                         $19,000,000 TL                           Main Campus     2017

Total Est. Project Costs                                                         $19,000,000


Project Description:       This contract is planned to cover the construction of a new academic building to house classrooms, faculty offices,
                           laboratories and all necessary support space.

Earliest Commencement Date:                                   FY2016

Study/Feasibility Explanation:                    2005 Master Plan; study required

Est. Project Duration:                                         3 years
                                            FY09 Capital Project Description


Campus:                                Dartmouth

Project Name:                          Priority 37: Centennial Drive Quadrangle

Funding Source:                        State - G.O. Bonds or Supplemental funds

Project Location:                      Centennial Drive, Main Campus

Project Type:                          O


Justification:           The existing entrance to the academic core from the ring road is both uninviting and not very functional. It is
                         a stretch of two-lane road hemmed in closely by parking lots and culminating in blank fluted block walls
                         stretching up three to four stories above the roadway.




                                                                                            Associated         Campus    Estimated
 Proposed Project Components                          Estimated Costs                        Program           Location  Completion
Centennial Drive Alts.                                                     $4,780,000 BI                     Main Campus       2017

Total Est. Project Costs                                                   $4,780,000


Project Description:      This project will be undertaken after the additions/alterations to the Resident Dining Hall, the Campus
                          Center, and the Auditorium are completed. At that time it will be possible to design a roadway with some
                          attractive pedestrian space and plantings that will culminate in one of the facades of the renovated buildings
                          in a more attractive manner.

Earliest Commencement Date:                                FY2010

Study/Feasibility Explanation:                2005 Master Plan; study required

Est. Project Duration:                                     3 years
                                           FY09 Capital Project Description


Campus:                               Dartmouth

Project Name:                         Priority 38: DCE Forensics Laboratory

Funding Source:                       University - Local Funds

Project Location:                     Unknown

Project Type:                         BR


Justification:           The Department of Medical Laboratory Science, part of our College of Arts and Science, does not
                         currently have suitable lab space to teach modern forensics to our students.




                                                                                     Associated          Campus Estimated
 Proposed Project Components                        Estimated Costs                    Program           Location Completion
Lab Alterations                                                           $819,000 Med-Lab Science      TL              2018

Total Est. Project Costs                                                  $819,000


Project Description:     If space becomes available for this function, the project will involve renovations to several thousand
                         square feet of space to house modern forensic equipment and tools in a setting that is similar to a
                         commercial or publicly operated forensics laboratory.

Earliest Commencement Date:                              FY2010

Study/Feasibility Explanation:                       Study required

Est. Project Duration:                                   3 years

								
To top