Process Improvement Production Layout
Document Sample


Process Improvement
Production Layout
Sub Assy Key Data
Employees: 15 (Labour intensive operation)
Number of Parts per day: 23 000 Parts / Day
Customers:
Ford
BMW
Volkswagen
Nissan
Toyota
General Motors
Products Produced At Sub Assy
Anchors
Comfort loops
Second Systems
Steering Disk
R27 Retractor
AGB95 Retractors
AGB95 Retractors
Problem Statement Layout
• Multi level production facility
• Waiting for lift (Line Feeders)
• Waiting for parts (Operators)
• No Material Handling path (Long Distances)
• Low Productivity
• 5C / Housekeeping
Team Members
• David Kretschmer
• Gary Ting Chong
• Deon Eulitz
• Mark Heering
• Mark Hiep
• Piet de Weerdt
• Otto Hellet
• Floyd Golden
• Pieter vd Walt
• Johan vd Merwe
Photos Before
Layout Before
nd
2 Floor – Sub Assy
n g
Buckles vi
c ei
QC Lab Re
Belts
y
(Sub Assy)
s
Stores
As
b
Su
Despatch
Ground Floor: Receiving, QC Lab, Stores, Sub Assy, Despatch
st
1 Floor: Belts, Buckles, Airbags, Sub Assy
nd
2 Floor: Sub Assy
Photos After
Layout After
B
A
1
1
2
3
2
4
3
5
6
4b
4b
5
3
2
Reduce Waiting Time
Target 25%
6000
5500
5000
4500
4000
Cost (R/day)
3500
3000
2500
2000
1500
1000
500
0
Dec05 Jan06 Feb06 M ar06 Apr06 M ay06 Jun06 Jul06 Aug06 Sep06 Oct 06 Nov06 Dec06 Jan07
Red Green Cost
Improve Productivity
Target 6%
100
95
90
85
80
75
70
65
60
55
%
50
45
40
35
30
25
20
15
10
5
0
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Green Red 2005 2006
Material Handling
Target 25%
150
140
130
120
110
Meters traveled
100
90
80
70
60
50
40
30
20
10
0
Dec05 Jan06 Feb06 Mar 06 Apr 06 May06 Jun06 Jul 06 Aug06 Sep06 Oct06 Nov06 Dec06 Jan07
Red Green Meters
Summary
• Reduced Quality Cost – Damaged parts due to excessive material
handling (Saving of R5 000 per month)
• Reduced Line feeding Cost R56 721/month
• Improve Productivity – 8%
• Reduced Time Waiting (Operator Time) – 2 280 man min/month
(R50 160)
• Reduced Traveling Distance – 69 Metres/Stock replenishment
(Improved by 50%)
• Safety / Housekeeping – Improved by installing proper racking
Payback
• Cost to Implement:
– Labour R10 841
– Material R31 500
Total R42 341
• Payback:
Implementation R 42 341
Lost profit R111 881
Payback 1.64 Weeks