									Dismantle and Transportation of Punt Dumper, Weigh Hopper and Feeder Table From
                               Skeldon and Enmore
Item                         Description                            Qty   Unit   Rate   Amount
    1 Preliminaries & General Items

  1.1 Provide temporary buildings for Site Office,
      Contractor's Storage and accommodation
      of workers.                                                         item

  1.2 Provide warning signs and safety barriers for the
      benefit of passers-by and persons not
      engaged on the works.                                               Item

  1.3 Provide for the protection of all sections of
      the works.                                                          Item

  1.4 Provide labour for the removal construction plant,
      surplus materials, temporary materials and debris
      from the site on completion of the works and
      leaving the site in a clean and tidy condition.                     Item

  1.5 Insurance
      Provide for insurance for the works:
      (a) Contractor's All Risk                                           Item
      (b) Employer's Liability                                            Item
      (c) Public Liability                                                Item

  1.6 Performance Bond
      Provide for an unconditional Bank Guarantee
      to the value of ten percent of the Contract price.                  item

  1.7 Advance Bond
      Provide for an unconditional Bank Guarantee
      to the value of ten percent of the Contract price.                  item

  1.8 Provide for the safety and health of workers on
      site in compliance to statutory regulation.                         item

  1.9 Provide at all times during the duration of the project for
      a qualified and experienced supervisor and all other staff
      necessary for the satifactory completion of the works.              Item

 1.1.0 Provide for cost in connection with Contractor's
       statutory requirements for contribution to the
       National Insurance Scheme in respect of
       Contractors Employees.                                             Item

       Total Carried Forward
Dismantle and Transportation of Punt Dumper, Weigh Hopper and Feeder Table From
                               Skeldon and Enmore

Item                       Description                             Qty   Unit   Rate   Amount
       Total Brought Forward
    2 Works
  2.1 Provide labour and tools to demolish reinforced conrete
      wall between weigh hopper stanchions to facilitate
      the removal of stanchions.                                         item

  2.2 Provide labour and hand tools such as spanners,
      hacksaw and blades, chipping hammers, wire brushes,
      safety gear for workmen for the safe dismantling of punt
      dumper, weigh hopper and feeder table.
      Sum to cater for marking structural members. Note
      Marking of members is essential to facilitate ease
      of re-erection. Packing of small parts in crates,
      providing materials for the fabrication of timber crates
      and strapping of members to maintain alignment.
      Lifting equipment, Oxyacetylene set with gas and
      cutting torch, Arc welding plant, welding plant cable and
      electrodes, wire rope slings will be provided by Guysuco.          item

  2.3 Provide a sum for labour and materials for the
      construction of a temporary bridge and remove on
      completion of the works. Rate to include for the                   item
      reinstatement of any private or public ways damaged by
      such temporary works

  2.4 Provide a sum for the transportation of punt dumper,
      weigh hopper, feeder table and accessories. Sum to
      include for the offloading of punt dumper, weigh hopper
      and feeder table and equipment for offloading. Punt dumper         item
      dumper, Weigh hopper and Feeder Table to offloaded
      as directed by Guysuco's Representative

  2.5 Provide a provisional sum for works that may be
      deemed necessary but are not included in the bill of        prov   sum             500,000
      quantities.

       Total Value Of Work Complete

								