									Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                        Del Name & #                          Dur. Est.   Critically   Skill
                                                                                                                                                          Depend
1.0 Phase Initiate – Obtaining agreement on the business                                                N/A
          requirement and charting the project.
1.1 Activity Develop the Business Requirement – Establish a common              N/A
             understanding of the base requirements that are to be addressed by
             the project.
1.1.1 Task        Create the Product Description – define, scope, and give context to the product & Product Description                                                PM
                  services that the project will be chartered to develop, deliver, and support.
1.1.2 Task        Prepare and Review the Product Description – depending on audience                    Project Proposal, Document Approval
                  preference, summarizes the content of the product description into an executive
                  summary and deliver it or prepare and conduct a review of the product description.
                  Obtain approval to charter a project that will assign initial planning resources to
                  develop the project plan.
1.2 Activity Charter the Project – Obtain the commitment and agreement            N/A
             between the sponsor and project team indicating how the project will
             be conducted and who needs to be involved.
1.2.1 Task        Create the Project Charter – define the mission, authority, and level of project      Project Charter                                                PM
                  planning and controls necessary for the project, and indicate the personnel or
                  groups expected to be involved in the project. Assign the project manager,
                  sponsor, and any required resources to complete the overall project planning.
               Project Proposal Approved by
1.2.1.1 Milestone                                                                                       N/A                                                            PM


2. Phase           Plan – Creation and approval of the core work plan and                               N/A

                   facilitating plans which will guide project execution and
                   control.
2.1 Activity Develop the Core Work Plan (CWP) – The development of the work N/A
             scope, supporting schedule, budget, and project organization that
             focuses and guides the project work effort.
2.1.1 Task        Develop the Scope Statement – Develop the scope statement with the customer           CWP – Scope Statement                                          PM
                  that indicates an agreement on work scope, project objectives and measurements,
                  hi-level deliverables, assumptions, and completion criteria.



c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                       1
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                           Del Name & #                            Dur. Est.   Critically   Skill
                                                                                                                                                               Depend
2.1.2 Task        Develop the WBS – Define the work Activities, sequencing, effort estimates, and          CWP – WBS                                                        PM
                  deliverables. Indicate the type of resource (people, equipment, materials, facilities)
                  needed to complete the work activities. Review and obtain agreement of the WBS
                  work activities with the customer, sponsor, and management of other groups
                  expected to support the project.
2.1.3 Task        Develop the Project Schedule – Develop approximate cost estimates of all the             CWP – Schedule and Budget Projection                             PM
                  types of resources. Build a project schedule from the WBS and cost estimates.
                  Produce a time-phased cost budget from the schedule.
2.1.4 Task        (Note) On large projects a feasibility study maybe a major phase prior to detailed       CWP – Feasibility and Recommendations
                  planning. On very small or maintenance project the feasibility may be limited to
                  cost/benefit assumption and recommendations. This project is considered a small
                  project.
                  Determine the Project Feasibility and Recommendation – Approximate and
                  define the life span of the product or service being delivered. Approximate and
2.1.5 Task        define a dollar value for soft and hard benefits and any cost framework to describe
                  Organize Project & Staff Acquisition – provide an overall reduction or avoidance         CWP – Organization                                               PM
                  the roles, responsibilities and membership of the Project. Obtain the staff needed for
                  the core team and staff need from other groups in the organization that will be cross-
                  committed to the project. Obtain from management commitment of all non-
                  contracted personnel. (Note– any contracted staff is acquired via the contract
                  activity, however none are planned for this project.)
2.2 Activity Develop the Facilitating Plans for Controls (FPC) – The plans for                             N/A
             ongoing work required to ensure that the project can anticipate
             possible problems, solve, and make coordinated work plan
             adjustments.
2.2.1 Task        Risk Management – Determine which risks are likely to affect the project,                FPC – Risk Id and Mgmt
                  evaluate potential risk outcomes and indicators, define plan to respond to key risks
                  indicators.
2.2.2 Task        Change Management – Outline a simple change management process to                        FPC – Chg Mgmt
                  coordinate approved changes in the project plan.
2.2.3 Task        Project Standards, Approval, And Document Controls – Define and setup the       FPC – Stds, Apvls, Cntls
                  documentation standards, document storage locations, project notebook, document
                  approval and promotion process, and securities.




c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                            2
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                       Del Name & #                        Dur. Est.   Critically   Skill
                                                                                                                                                       Depend
2.2.4 Task        Communication Plan and Management – Outline a plan that identifies “who”          FPC – Comm. Plan & Mgmt
                  needs “what” communications, in “what” media, “how” often and by “whom”.
2.2.5 Task        Status Reporting – Define how status will be reported, by whom, how often, and in FPC – Status Rptg
                  what formats and media.
2.2.6 Task        Procurements & Contracting – Determine what to procure and when, document            FPC – Proc. & Cntrkg
                  requirements and identify potential sources.
2.2.7 Task        Quality Assurance – Identify the project’s relevant quality standards and determine FPC- QA
                  how to satisfy them.
2.2.8 Task        Time Tracking – Determine what level to track time at, how time will be tracked,     FPC – Time Tracking
                  how frequently, and administer the time tracking activities.
2.2.9 Task        Issue and Decision Management – Determine process for raising and resolving          FPC – Iss. & Decision Mgmt
                  project issues that impact the scope, schedule, cost or quality of the project.
2.3 Activity Develop the Project Plan – Integrating the results of the other                           N/A
             planning activities into a coherent document to guide the project
             execution and control.
2.3.1 Task        Plan Integration – Summarize and incorporate the outputs of the planning             Project Plan
                  activities into a single reference document – the <project name> Project Plan. The
                  plan is the reference document for work to be performed by all involved in the
                  project and must be made easily accessible to all in electronic format.
2.3.2 Task        Plan Presentation and Review – Distribute, review and obtain approval of the         Presentation, & Document Approval
                  project plan from the project directing authoritie(s) and managers who have staff
                  assigned to the project.
2.3.2.1 Milestone and Schedule Approved by
               Plan                                                                                    N/A                                 0                        PM

3.0 Phase         Execution                                                                            N/A
                  This version of an Incremental Release Lifecycle Model is a combination of
                  Traditional Waterfall and Spiral Development. The Business Requirements and
                  Conceptual Design are established for the entire system. Based on the
                  Implementation Strategy each System Function (Product Component) is cycled
                  through Functional Design, Construction, and Implementation. When all Functions
                  for a Release are complete, the system is assembled and following successful
                  Acceptance Tests by the customers is moved into Production. Implementation
                  Cycles overlap and the process is improved through each iteration.


c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                    3
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                         Del Name & #                                     Dur. Est.   Critically   Skill
                                                                                                                                                                      Depend
                  This model was intentionally created to be consistent with the other DHS OIS
                  lifecycle models.
                  The following activities, tasks and deliverables should be reviewed for each project
                  on a case-by-case basis. Projects may utilize this model and adapt or tailor to the
                  specific needs of the project. This means that not all activities and tasks are
                  necessary for every project, and that additional activities and tasks may need to be
                  included.
                  Specific deliverables depend on the tools and techniques used by the development
                  staff and on the existing documentation. The deliverables listed are examples of
                  possible deliverables.
3.1 Activity      Feasibility Study                                                                      N/A
                   Note: Requirements definition is an extension of the process started in the
                  Feasibility Study. Please see the Feasibility Lifecycle model to determine if all or
                  some of the steps are necessary.

3.2 Activity      Define Requirements                                                                    N/A
                  The purpose of this phase is to establish a common understanding between the
                  customers and the software project of the customers’ requirements that will be
                  addressed by the software project. All system development work should be
                  traceable to the various levels of requirements, i.e. product description, project
                  objectives, hi-level requirements. Changes to the Requirements should be
                  managed according to their impact on the project’s cost, schedule, and quality
                  (scope). Note: Requirements definition is an extension of the process started in
                  the feasibility study, if one was performed.
3.2.1 Task        Identify and describe the business area(s) to be affected by the new system            Updates Feasibility Study
3.2.1.1 Subtask      Refine the Feasibility Study with increasing detail to:                             Updated Requirements Traceability Matrix or
                                                                                                         Stakeholder List
3.2.1.2 Subtask      Identify additional Stakeholders - groups impacted by the system development.       Context Diagram
3.2.1.3 Subtask      Define the current business processes                                               Procedure flow diagrams
3.2.1.4 Subtask      Define the current technology – infrastructure, applications and databases          Descriptions of existing reports and documents
3.2.1.5 Subtask      Define the external system interfaces and primary data exchanges.                   Candidates for procedural change
3.2.1.6 Subtask      Identify the sources and destinations of each primary data exchange.                Business Rules
3.2.1.7 Subtask      Identify and prioritize candidates for procedural change and automation.            Business Use Cases



c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                   4
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                      Del Name & #                                        Dur. Est.   Critically   Skill
                                                                                                                                                                      Depend
                                                                                                      Business Actors
3.2.2 Task      Develop Business Requirements                                                         N/A
3.2.2.1 Subtask   Follow the project’s requirement management plan to:
3.2.2.2 Subtask   Gather stakeholder needs from all stakeholders. Synthesize and Prioritize.          Glossary
3.2.2.3 Subtask      Define Requirements – transform stakeholder needs into well-defined high-level   Use Cases
                     requirements.
3.2.2.4 Subtask      Validate Requirements – evaluate each requirement and determine relative         Requirements Document
                     priority.
3.2.2.5 Subtask      Analyze Requirements – refine and categorize high-level requirements with        Requirements Baseline
                     greater precision and detail. Categories include: functional, data, use,
                     performance, security, business and technical standards, operational, legal.
3.2.3 Task                                                                                            N/A
                Reevaluate initial development approach, impact analysis, costs and benefits
3.2.3.1 Subtask   The following bullets must be done in collaboration with NCS, CSS, P&P, SA, SSI,
                  and AMS. Refine the Feasibility Study with increasing detail to:
3.2.3.1.1 Subtask Ensure that the development approach recommended in the Feasibility Study is        Updated Cost Benefit Analysis (feasibility study)
                  still valid.
3.2.3.1.2 Subtask Ensure that OIS cross-sections agree and can support the technical solution and     Detailed plan for the next phase(s)
                  development.
3.2.3.1.3 Subtask Ensure that cost benefits assumptions are still valid.                              OIS Approved Exception Request
3.2.3.1.4 Subtask Ensure that external interfaces (projects and systems) are accurately stated.       N/A

3.2.4 Task      Conduct walkthrough                                                                   N/A
3.2.4.1 Subtask  Ensure that requirements are clear, complete, and comprehensive                      Issues, resolutions, changes, etc…
3.2.4.2 Subtask                                                                                       OIS Sections and Business Sign-off(s) indicating
                 Collect concurrence agreements from Major OIS Sections and Business                  concurrence
3.2.5 Task      Obtain formal user and sponsor concurrence                                            N/A
3.2.5.1 Subtask  Decision point for the Steering Committee:                                           Formal acceptance of the Project Plan &
                                                                                                      Requirements
3.2.5.2 Subtask      For approval of the work completed                                               N/A
3.2.5.3 Subtask      To authorize continued work on the project.                                      N/A
3.3 Activity Conceptual Design                                                                        N/A




c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                   5
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                          Del Name & #                                         Dur. Est.   Critically   Skill
                                                                                                                                                                           Depend
                  The purpose of this phase is to develop the high-level Conceptual Design and
                  Implementation Strategy. The Conceptual Design is developed based on applicable
                  standards and best practices and is used to incorporate the business requirements
                  into the system design. The Implementation Strategy identifies the potential release
                  strategies for the Steering Committee decision on how to deliver the system.

3.3.1 Task        Develop the Conceptual Design.                                                          Conceptual Data Model

3.3.1.1 Subtask      Identify best practices for the system being developed.                              Conceptual Process Model

3.3.1.2 Subtask      Define the system’s basic functionality and information exchanges.                   Technology Architecture

3.3.1.3 Subtask      Identify the inputs, outputs, and triggers for each system function.                 Use Cases (refined)


3.3.1.4 Subtask      Work with NCS, P&P, CSS, SA, SSI, and AMS identify the hardware and                  Storyboards
                     software to develop and operate the new system.

3.3.1.5 Subtask      Work with NCS to determine the network(s) that will support the application.         N/A


3.3.2 Task        Define application standards (i.e., determine how functions and data will be            Description of distribution strategy
                  distributed, screen formats, common software functions, etc…).

3.3.2.1 Subtask      Identify how system functions will be distributed geographically and technically     Description of alternatives considered
                     (across platforms).

3.3.2.2 Subtask   Define the application tiers (i.e, presentation, business logic, database) in terms     Application Design Standards
                  of technology and function.
3.3.2.3 Subtask   Describe standards for each application tier (i.e., Presentation tier will use Secure   N/A
                  Sockets Layer (SSL), Cascading Style Sheets, error handling, naming
                  conventions, ODBC vs. JDBC, etc…).
3.3.3 Task      Define environmental controls (e.g., security, contingency planning, restart              Specifications for security, contingency and back-
                recovery).                                                                                up/restart requirements.

3.3.3.1 Subtask      Identify the security features of the system.                                        Use Case definition



c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                        6
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                         Del Name & #                                      Dur. Est.   Critically   Skill
                                                                                                                                                                       Depend
3.3.3.2 Subtask      Create contingency plan and/or revise existing contingency plans.                   N/A

3.3.3.3 Subtask      Plan back-up and recovery processes.                                                N/A

3.3.4 Task        Define audit and control functions (error control, control totals, etc.).              Audit and control specifications
3.3.4.1 Subtask      Identify and describe the controls to be built into the system and used to ensure   *Audit trail capture and reporting requirements
                     that data integrity is maintained.
                                                                                                         *Use Case definition
3.3.5 Task        Define common software functions                                                       Common routine/ software tool specifications
3.3.5.1 Subtask      Identify the requirements to be automated                                           Identification of existing reusable code to use


3.3.5.2 Subtask   Identify the software functions that will be developed as common routines or           N/A
                  software tools.
3.3.6 Task      Create product delivery plan (for phased delivery)                                       Product delivery plan
3.3.6.1 Subtask   Identify the functions to be delivered in the planned versions of the system.          *Implementation Strategy
                Note: This activity is included for use in large development efforts in which there is *Release Strategy
                need to deliver the product in phases or versions instead of as the result of a single
                project.
3.3.7 Task      Estimate storage, telecommunications and/or processor impacts                          *Hardware and communications resource
                                                                                                       acquisition requirements.                           .
                Note: If the system requires the acquisition of new hardware and network               *Updates to Technology Architecture
                resources (as opposed to increased capacity) see the Hardware and LAN
                Acquisition/Installation project type.
3.3.7.1 Subtask   Determine the impact of processing and storage volumes on the hardware (data N/A
                  storage, processor capacity) and on communications resources.
3.3.8 Task      Reevaluate development approach, impact analysis, costs and benefits.                  Updates to previous deliverables (i.e., Plan,
                                                                                                       Schedule, Cost/Benefit, etc…).

3.3.8.1 Subtask   Ensure that the approach recommended in the Feasibility Study is still valid, given    N/A
                  the design results.
3.3.8.2 Subtask   Ensure that cost benefits assumptions are still valid.                                 N/A
3.3.8.3 Subtask   Ensure that impacts on other projects and systems are accurately stated.               N/A
3.3.8.4 Subtask   Revise approach and cost benefits statements as appropriate.                           N/A
3.3.9 Task      Prepare a Conceptual Design Report                                                       Conceptual Design Report



c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                    7
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                          Del Name & #                                       Dur. Est.   Critically   Skill
                                                                                                                                                                         Depend
3.3.9.1 Subtask      Compile and summarize the previous deliverables into a comprehensive report.         N/A

3.3.10 Subtask       Conduct walkthrough                                                                  Issues, resolutions, changes, etc…


3.3.10.1 Subtask Ensure that the various aspects of the design fulfill the requirements and comply        Sign-off(s) indicating concurrence.
                 with standards.
3.3.11 Subtask       Obtain formal user, technical and sponsor concurrence                                Formal approval of Conceptual Design Report and
                                                                                                          Implementation Strategy.

3.3.11.1 Subtask Decision point for the Steering Committee:                                               OIS Sections and Business Sign-off(s) indicating
                                                                                                          concurrence.

3.3.11.2 Subtask For approval of the work completed – Conceptual Design Report &                          N/A
                 Implementation Strategy
3.3.11.3 Subtask Collect concurrence agreements from Major OIS Sections and Business.                     N/A

3.3.11.4 Subtask To authorize continued work on the project.                                              N/A
3.4 Activity Functional Design                                                                            N/A
                The purpose of this phase is to define the detailed functional and technical design
                aspects of a release. The work completed in this phase should be sufficiently
                detailed to provide the construction team with specific information for how the
                application should work. It is essential that business customers define the
                necessary detail Analysis & Design Tasks & Deliverables are used technical team’s
                Object Oriented for system functionality rather than relying on the in the rest of this
                model. Structured Analysis & Design techniques can be used in place of these, with
                minor changes to descriptions.
                Note: The use of prototyping and Joint Application Design (JAD) are recommended
                for the design of reports, screens and documents. See the RAD template to use
                activities related to prototyping.
3.4.1 Task      Plan for Implementation                                                                   Business Reengineering Plan
3.4.1.1 Subtask    Develop Business Reengineering Plan to plan for and guide the changes in               Implementation Plan
                   business processes that are necessary to implement the system/release.
3.4.1.2 Subtask    Define the Implementation Plan that specifically describe how the system/release       Security Model
                   will be transitioned into Production (i.e., training, data conversion, switchover).
3.4.1.3 Subtask    Define the post production user support (Help Desk, etc.).                             Support Plan



c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                      8
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                       Del Name & #                                          Dur. Est.   Critically   Skill
                                                                                                                                                                         Depend
3.4.1.4 Subtask    Develop the Security Model – compile all security information into a       N/A
                   comprehensive plan over the life of the development project.
3.4.2 Task        Build/acquire/ prepare the development environment (hardware and software). Installed hardware and software ready for use in
                                                                                              the development process.
3.4.2.1 Subtask     Acquire hardware and system software resources.                                  N/A
3.4.2.2 Subtask     Ensure that the development environment is ready for use.                        N/A
                Note: Hardware/software acquisition may require long lead times; therefore, initiate
                the acquisition process as early as possible.
                If there is a need to acquire hardware, system software, and/or network software,
                use the Development with Hardware and LAN Acquisition/Installation lifecycle
                activity list to identify those activities that are relevant to this project.
3.4.3 Task      Develop test strategy
                                                                                                     Test objectives
3.4.3.1 Subtask     Define the process for validation and verification for the system/release.       *Levels of testing(conceptual, functional, unit,
                                                                                                     system, integration acceptance…).
                                                                                                       *Roles and responsibilities for testing
3.4.4 Task      Identify subsystems, their data requirements and interfaces                            Systems flow diagrams
3.4.4.1 Subtask   Package the new system's functions into subsystems and map the flow of data          Updates to Use Cases
                  between them.
3.4.4.2 Subtask   Identify files and/or databases.                                                     N/A
3.4.4.3 Subtask   Identify the media (screen, paper, electronic file, document, etc.) for each data    N/A
                  flow.
3.4.5 Task      Design User Interfaces.                                                                System prototypes

3.4.5.1 Subtask      Storyboard Interfaces to describe basic flow of the screens and scenarios         Screen designs


3.4.5.2 Subtask      Create Prototypes with sample screens and basic functionality for customer input. *Form designs

                                                                                                       *Report designs
3.4.6 Task        Design Application Logic                                                             Design Model (that describes the realization of the
                                                                                                       Use Cases)

3.4.6.1 Subtask      Identify Candidate Classes with attributes, operations, methods, relationships,   UML Diagrams, Class Diagrams, Activity
                     and semantics.                                                                    Diagrams,…




c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                      9
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                       Del Name & #                                          Dur. Est.   Critically   Skill
                                                                                                                                                                         Depend
3.4.6.2 Subtask      Create Design Classes to refine the Candidate Classes with additional detail.     N/A


3.4.6.3 Subtask   Refactor Design Classes to identify commonality in the system to achieve             N/A
                  maximum reuse and a consistent design.
3.4.7 Task      Design External Interfaces                                                             N/A
3.4.7.1 Subtask   Design the Functions of the External Interfaces                                      N/A
3.4.8 Task        Develop System Test Plan                                                             Test Cases


3.4.8.1 Subtask      Define test cases (started early so that during the development of the use case   Installed hardware and software ready for use in
                     the each test case is being defined).                                             the test process.
3.4.8.2 Subtask      Ensure that the test environment is ready for use                                 N/A

3.4.9 Task        Refine the Conceptual Data Model into a logical, application data model              Logical Data Model fully attributed with
                                                                                                       relationships, roles, cardinality, and optionality.

3.4.9.1 Subtask      Identify the data required to support the system functionality.                   N/A
3.4.9.2 Subtask      Normalize the data model.                                                         N/A


3.4.9.3 Subtask     Identify data segments or records based on the way data will be used in the        N/A
                    system.
3.4.10 Task       Design physical data base and/or files                                               Physical data base design


3.4.10.1 Subtask Map the logical data base design to the specific data base or file management         N/A
                 system(s) to be used.
3.4.10.2 Subtask Describe the data as it will be stored on the physical media.                         N/A
3.4.11 Task       Update previous work                                                                 Documented Changes, Issues, Risks
3.4.11.1 Task     Update Conceptual Design – data, process, and technology                             Updates to Requirements Traceability Matrix

3.4.11.2 Task     Update Project Plan, Schedule, Budget                                                N/A




c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                      10
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                         Del Name & #                                       Dur. Est.   Critically   Skill
                                                                                                                                                                        Depend
3.4.11.3 Task     Reevaluate technical infrastructure – storage utilization, capacity estimates,         N/A
                  hardware acquisition
3.4.12 Task       Prepare for Implementation                                                             Updates to Implementation Plan - data conversion
                                                                                                         plan and schedule, training plan and schedule

3.4.12.1 Subtask Plan for file/database conversions – identify conversion requirements and the           N/A
                 programs and controls required for conversion.

3.4.12.2 Subtask Identify required user, support staff and/or operator documentation and training.       N/A
3.4.13 Task       Conduct walkthrough                                                                    Issues, Risks, Defects, Change Requests


3.4.13.1 Subtask Validate the designs (logical and physical) to ensure that they adequately fulfill      N/A
                 requirements.
3.4.13.2 Subtask Validate that all requirements have been addressed                                      N/A
3.4.14 Task       Obtain formal user, technical, and sponsor concurrence                                 Formal acceptance of the System Design and
                                                                                                         Implementation Plan
3.4.14.1 Subtask Decision point for the Steering Committee:                                              N/A
3.4.14.2 Subtask For approval of the work completed.                                                     N/A
3.4.14.3 Subtask To authorize continued work on the project.                                             N/A

3.4.14.4 Subtask To confirm commitment of the implementation plan by all effected groups.                N/A
3.5 Activity System Construction                                                                         N/A
                  The purpose of this phase is to build and unit test the system components –
                  application code, database definition language (DDL), user procedures, and test
                  plans.
3.5.1 Task        Build Test Environment                                                                 System Test Plans


3.5.1.1 Subtask    Define test cases, create test data, identify test criteria – include platforms and   N/A
                   data validation.
3.5.2 Task        Write System Documentation                                                             Operator Manual
3.5.2.1 Subtask      Write on-line help files                                                            Administrator Manual




c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                     11
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                       Del Name & #                                  Dur. Est.   Critically   Skill
                                                                                                                                                                 Depend
3.5.2.2 Subtask      Write user procedures, compile into user manual                                   N/A

3.5.2.3 Subtask      Create the training material, curriculum                                          N/A

3.5.3 Task        Build Application                                                                    Application Module
3.5.3.1 Subtask      Develop program code and perform unit tests.                                      Physical Database
3.5.3.2 Subtask      Build user interfaces                                                             N/A


3.5.3.3 Subtask      Create database to implement the schema, triggers, and stored procedures          N/A

3.5.4 Task      Conduct walkthrough                                                                    Issues, Risks, Change Requests
3.5.4.1 Subtask  Code Review                                                                           N/A
3.5.4.2 Subtask  Test Plan Review                                                                      N/A
3.6               <Activity Title, i.e Test> – <activity description>                                  N/A
Activity

3.6.1 Task        <Task title> – Task Description                                                      N/A
3.6.1.1           <Milestone Title>                                                                    N/A
Milestone

3.7 Activity Implementation                                                                            N/A

                The purpose of this phase is to validate the system, train the users, and transition
                the system/release into production.
3.7.1 Task      Validate the System                                                                    Test Report
3.7.1.1 Subtask   Conduct Functional Tests (black box) to ensure system performs desired               Change Requests, Issues, Risks
                  functionality.
3.7.1.2 Subtask   Once each Function is tested then assemble into a build.                             N/A


3.7.1.3 Subtask      Conduct System Tests to ensure the system performs as expected under volume N/A
                     and exception conditions
3.7.1.4 Subtask      Conduct Acceptance Tests to validate the system meets the customers’              Trained users, operators, and support staff
                     expectations.


c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                              12
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                                                                           Del Name & #                                        Dur. Est.   Critically   Skill
                                                                                                                                                                           Depend
                  Note: Testing may include parallel test, usability test, Beta Test, or other tests. It
                  may be performed in a special test environment.
3.7.2 Task        Train users, operators, and support staff                                                Formal acceptance of the system release

3.7.2.1 Subtask      Ensure that all users, operators and support staff are able to use the system.        N/A
3.7.3 Task        Obtain formal user and sponsor concurrence                                               N/A

3.7.3.1 Subtask      Decision point for the Steering Committee:                                            N/A

3.7.3.2 Subtask      For approval of the work completed                                                    N/A

3.7.3.3 Subtask      To authorize continued work on the project.                                           N/A

3.7.4 Task        Prepare for transition to production                                                     Operations schedules (batch schedule and on-line
                                                                                                           availability)
3.7.4.1 Subtask      Ensure that the production environment (including users, operations personnel,        Programs transferred to production libraries
                     and support staff) is prepared for the start of production.
3.7.4.2 Subtask      Install required new hardware, system software, and communications systems.           Production job control or command lists available
3.7.4.3 Subtask      Perform data conversions                                                              New or changed security data (passwords, etc.) in
                                                                                                           the proper tables

3.7.4.4 Subtask      Perform environment tests                                                             Users and support staff of systems that may be
                                                                                                           effected by the new system advised of the
                                                                                                           transition
                Note: For applications to be run by computer operations all forms must be filled out
                and submitted, as required by current procedures.
3.7.5 Task      Deploy System                                                                              System in Production
3.7.5.1 Subtask   Move system into production use                                                          N/A
3.7.5.2 Subtask   Performance tune application/database as necessary.                                      N/A
3.7.6 Task      Evaluate System/Release                                                                    Updates to Project Plan, Schedule, and all
                                                                                                           previous work
3.7.6.1 Subtask      Evaluate project performance                                                          Lessons Learned
3.7.6.2 Subtask      Evaluate system performance to measure how well it meets user expectations.           N/A




c59c63f7-10e5-4788-be63-64151b53e3fb.xls                                                                                                                                                        13
Incremental Development Work Breakdown Structure Dictionary

#                 WBS Dictionary                              Del Name & #   Dur. Est.   Critically   Skill
                                                                                         Depend

4.0 Phase Controls – Administer and manage work controls to   N/A

          ensure project performance.