					                                              ATTACHMENT 1

                                      City and County of Denver
                                     Department of Public Works
                                     Capital Project Management

         CM/GC GENERAL CONDITIONS AND OVERHEAD MINIMUM REQUIREMENTS

The following spreadsheet outlines the minimum General Conditions and Overhead requirements for the
project. If there are other items not explicitly referenced in this list, those additional items must be included in
Section O at the end of this list and budgeted for in attachment 2 . The CM/GC will be contractually obligated
to perform the services contained within this spreadsheet as part of the Project.


      Only green cells are fillable
A. PRE-CONSTRUCTION
      Constructability Review & Recommendations
      Life Cycle Costing Analysis
      Informal Value Engineering
      Material Availability Review
      Equipment Availability Review
      Construction Logistical & Execution Planning

B. PROJECT COST CONTROL
     Guaranteed Maximum Price Proposal
     Construction Cash Flow Projections (Monthly)
     Set-up Cost Accounting
     Set-up Reporting Methods
     Set-up Payment Procedure
     Set-up Change Order Procedure

C. PROJECT SCHEDULING
     Construction Activity Schedule (CPM Set-Up)
     Const Activity Schedule w/ Milestones (CPM Updates)
     Shop Drawing & Submittal Schedule / Procedure
     Mock-Up Schedule & Procedure
     Short-Interval Schedules
     Occupancy Schedules
     Client Move Coordination

D. GENERAL CONTRACTOR STAFF & SERVICES
     Project Manager(s)
     Project Superintendent(s)
     Assistant Superintendent(s) (as required)
     Project Engineer(s) (as required)
     Field Engineer(s) (as required)
     Mechanical & Electrical Coordinator(s) (as required)
     Quality Control Engineer (As Required)
     Project Assistant / Clerk / Typist (As Required)
     Project Ceritified Payroll Supervisor (As Required)
     Safety Engineer (As Required)
     Project Estimating and Scheduling (As Required)
     Accounting (as required)
     Data Processing (as required)
     Field Engineering & Layout
     Registered Surveyor (As Required)
                                            ATTACHMENT 1

                                     City and County of Denver
                                    Department of Public Works
                                    Capital Project Management

         CM/GC GENERAL CONDITIONS AND OVERHEAD MINIMUM REQUIREMENTS


E. QUALITY CONTROL / WARRANTY
     Develop & Submit Construction Quality Control Plan
     Quality Control & Inspections
     Project Progress Photographs
     Air & Water Balancing
     Operator On-Site Training
     Prepare Operation Manuals
     Prepare Maintenance Manuals
     Prepare Preventive Maintenance Manual
     Drug Testing & Screening (Field Personnel)
     Warranty Inspections Coordination
     Warranty Service
     Prepare Punch List(s)
     Manage Punch List(s)

F. TEMPORARY FACILITIES AND SERVICES
      Temporary Field Office Facility
      Field Office Furniture Equipment & Supplies
      Temporary Internet Service
      CM/GC's Storage Trailers / Sheds
      Project Sign
      Directional / Warning Signs
      Bulletin Boards
      Potable Drinking Water / Ice / Cups
      Temporary Toilets / Sanitary Sewer
      Temporary Construction Fencing
      Barricades (As Needed)
      Safety Equipment
      First Aid Station & Supplies
      Handrails / Toe Boards / Opening Protection
      Safety Nets (As Needed)
      Temporary Stairs (As Needed)
      Fire Extinguishers
      Flagman / Traffic Control (As Needed)
      Site Security (As needed for CM/GC's Operations)

G. TEMPORARY UTILITIES
     Temporary Telephone Service
     Temporary Electrical Service / Distribution
     Temporary Water Service / Distribution
     Temporary Gas Service / Distribution (As Needed)
     Temporary HVAC Services (Permanent System)

H. CLEAN-UP
      Daily Clean-Up
      Final Clean-Up
      Final Glass Cleaning
      Debris Hauling/Removal
      Trash Chutes
      Trash Dumpsters
      Dump Permits & Fees
      Dust Control
      Street Cleaning
                                            ATTACHMENT 1

                                    City and County of Denver
                                   Department of Public Works
                                   Capital Project Management

         CM/GC GENERAL CONDITIONS AND OVERHEAD MINIMUM REQUIREMENTS


I. WEATHER PROTECTION / TEMPORARY HEATING
      Remove Snow & Ice (Site)
      Remove Snow & Ice (Buildings)
      Temporary Enclosures (Buildings)
      Temporary Weather Protection for Sub Trades
      Temporary Heating for Sub Trades
      Temporary Field Office Heating Energy Cost
      Fuel Cost for Heating (Permanent Heat System)
      Permanent Heat System Filter Replacement
      Maintenance Cost (Permanent Heat System)
      Warranty Cost

J. SMALL TOOLS & EXPENDABLE SUPPLIES
      Small Tools (CM/GC's Only)
      Expendable Supplies (CM/GC's Only)
      Rental Equipment (if neede)

K. LEED CERTIFICATION
      MRc2.1 Const Waste Management, Divert 50% from Disposal
      MRc2.2 Const Waste Management, Divert 75% from Disposal
      MRc4.1 Recycled Content, 10% (post-consumer + 1/2 pre-consumer)
      MRc4.2 Recycled Content, 20% (post-consumer + 1/2 pre-consumer)
      MRc5.1 Local/Regional Materials, 10% Extracted, Processed & Manufactured Locally
      MRc5.2 Local/Regional Materials, 20% Extracted, Processed & Manufactured Locally
      EQc3.1 Construction IAQ Management Plan, During Construction
      EQc3.2 Construction IAQ Management Plan, Before Occupancy
      EQc4.1 Low-Emitting Materials, Adhesives & Sealants
      EQc4.2 Low-Emitting Materials, Paints & Coatings
      EQc4.3 Low-Emitting Materials, Carpet Systems
      EQc4.4 Low-Emitting Materials, Composite Wood & Agrifiber Products

L. DOCUMENT REPRODUCTION / PRINTING
     Postage & Delivery Costs
     Shop Drawings
     Printing & Duplication (Miscellaneous)
     As-Built Documents (Mark-ups & Recording)
     As-Built Documents (Printing)
     Maintenance Manuals (From Subs)
     Operation Manuals (From Subs)
     Estimating Forms
     Schedule Report Forms
     Accounting Forms
     Field Reporting Forms
     Cost Reporting Forms
     Special Forms
                                           ATTACHMENT 1

                                   City and County of Denver
                                  Department of Public Works
                                  Capital Project Management

         CM/GC GENERAL CONDITIONS AND OVERHEAD MINIMUM REQUIREMENTS


M. INSURANCE & BONDS
      Builder's Risk Insurance
      Builder's Risk Deductible
      Special Insurance - Machinery & Equipment
      General Liability Insurance
      Umbrella Liability Insurance
      Excess Liability Insurance
      Completed Products Insurance
      Professional Liability Insurance
      Workman's Compensation Insurance (CM/GC's Only)
      FICA / Medicare Insurance (CM/GC's Only)
      Federal Unemployment Insurance (CM/GC's Only)
      State Unemployment Insurance (CM/GC's Only)
      Payment & Performance Bond
      Subcontractor & Supplier Bonds

N. OTHER
     Building Equipment Review (Movable)
     Building Equipment Review (Fixed)
     Coordinate Owner-Supplied Fixed Equipment
     Coordinate Owner-Supplied Movable Equipment
     Sales & Use Taxes (As Required)
     Construction Labor Costs
     Construction Material Costs
     Construction Equipment Costs
     Weekly Project Team & Subcontractor Meetings
     Weekly Project Meeting Minutes & Distribution
     CM/GC Overhead Cost
     CM/GC Profit & Margin

O. ADDITIONAL ITEMS
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
     (enter as necessary)
                                                                                          ATTACHMENT 3

                                                                                  City and County of Denver
                                                                                 Department of Public Works
                                                                                 Capital Project Management

                                                                  Guaranteed Maximum Price - Schedule of Values

The following Schedule of Values outlines the construction cost breakdown for the project. If there are other items not explicitly referenced in this list, those additional items must be included in
"Additional Items" at the bottom of the document. The CM/GC will be contractually obligated to perform the entire scope of work shown in the construction and contract documents.



      Only green cells are fillable. Column widths are adjustable
                                    DESCRIPTION                                                           PRICE               %                                  COMMENTS

DIVISION 03        CONCRETE (INCLUDING STEEL REINFORCEMENT)                                                        $0.00        0.00%
                      CAST IN PLACE CONCRETE                                                                                    0.00%

DIVISION 04        MASONRY                                                                                         $0.00        0.00%
                      UNIT MASONRY                                                                                              0.00%

DIVISION 05        METALS                                                                                          $0.00        0.00%
                      STRUCTURAL STEEL FRAMING                                                                                  0.00%
                      ARCHITECTURALLY EXPOSED STRUCTURAL STEEL FRAMING                                                          0.00%
                      STEEL JOIST FRAMING                                                                                       0.00%
                      STEEL DECKING                                                                                             0.00%
                      COLD-FORMED METAL FRAMING                                                                                 0.00%
                      METAL FABRICATIONS                                                                                        0.00%
                      METAL STAIRS                                                                                              0.00%
                      PIPE RAILINGS                                                                                             0.00%
                      DECORATIVE FORMED METAL                                                                                   0.00%

DIVISION 06        WOOD, PLASTICS AND COMPOSITES                                                                   $0.00        0.00%
                      MISCELLANEOUS ROUGH CARPENTRY                                                                             0.00%
                      SHEATHING                                                                                                 0.00%
                      ARCHITECTURAL WOODWORK                                                                                    0.00%
                      GLASS-FIBER-REINFORCED PLASTIC PANELING                                                                   0.00%

DIVISION 07        THERMAL AND MOISTURE PROTECTION                                                                 $0.00        0.00%
                      BITUMINOUS DAMPPROOFING                                                                                   0.00%
                      SINGLE-COMPONENT POLYURETHANE WATERPROOFING                                                               0.00%
                      THERMAL INSULATION                                                                                        0.00%
                      WEATHER BARRIERS                                                                                          0.00%
                      METAL PLATE WALL PANELS                                                                                   0.00%
                      COMPOSITE WALL PANELS                                                                                     0.00%
                      THERMOPLASTIC MEMBRANE ROOFING                                                                            0.00%
                      STANDING SEAM STEEL SHEET METAL ROOFING                                                                   0.00%
                      SHEET METAL FLASHING AND TRIM                                                                             0.00%
                      ROOF HATCHES                                                                                              0.00%
                      PENETRATION FIRESTOPPING                                                                                  0.00%
                      JOINT SEALANTS                                                                                            0.00%

DIVISION 08        OPENINGS                                                                                        $0.00        0.00%
                      HOLLOW METAL DOORS AND FRAMES                                                                             0.00%
                      FLUSH WOOD DOORS                                                                                          0.00%
                      ACCESS DOORS AND PANELS                                                                                   0.00%
                      OVERHEAD COILING DOORS                                                                                    0.00%
                      ALUMINUM ENTRANCES AND STOREFRONTS                                                                        0.00%
                      STRUCTURAL SEALANT GLAZED CURTAIN WALLS                                                                   0.00%
                      DOOR HARDWARE                                                                                             0.00%
                      GLAZING                                                                                                   0.00%
                      MIRRORS                                                                                                   0.00%
                      GLAZING SURFACE FILMS                                                                                     0.00%
                                                                                          ATTACHMENT 3

                                                                                  City and County of Denver
                                                                                 Department of Public Works
                                                                                 Capital Project Management

                                                                  Guaranteed Maximum Price - Schedule of Values

The following Schedule of Values outlines the construction cost breakdown for the project. If there are other items not explicitly referenced in this list, those additional items must be included in
"Additional Items" at the bottom of the document. The CM/GC will be contractually obligated to perform the entire scope of work shown in the construction and contract documents.



      Only green cells are fillable. Column widths are adjustable
                                    DESCRIPTION                                                           PRICE               %                                  COMMENTS

DIVISION 09        FINISHES                                                                                        $0.00        0.00%
                      NON-STRUCTURAL METAL (STUD FRAMING)                                                                       0.00%
                      GYPSUM BOARD                                                                                              0.00%
                      TILING                                                                                                    0.00%
                      ACOUSTICAL CEILINGS                                                                                       0.00%
                      RESILIENT FLOORING                                                                                        0.00%
                      RESILIENT BASE AND ACCESSORIES                                                                            0.00%
                      STATIC-DISSIPATIVE RESILIENT FLOORING                                                                     0.00%
                      FLUID-APPLIED FLOORING                                                                                    0.00%
                      TILE CARPETING                                                                                            0.00%
                      ACCESS FLOORING                                                                                           0.00%
                      EXTERIOR PAINTING                                                                                         0.00%
                      INTERIOR PAINTING                                                                                         0.00%
                      DRY ERASE COATINGS                                                                                        0.00%

DIVISION 10        SPECIALTIES                                                                                     $0.00        0.00%
                      INTERIOR BUILDING SIGNAGE                                                                                 0.00%
                      SOLID-POLYMER TOILET COMPARTMENTS                                                                         0.00%
                      OPERABLE PARTITIONS                                                                                       0.00%
                      CORNER GUARDS                                                                                             0.00%
                      TOILET BATH AND SHOWER ACCESSORIES                                                                        0.00%
                      FIRE DEPARTMENT KEY BOX                                                                                   0.00%
                      FIRE-PROTECTION SPECIALTIES                                                                               0.00%
                      STANDARD METAL LOCKERS                                                                                    0.00%
                      FIXED SUNSCREENS                                                                                          0.00%

DIVISION 11        EQUIPMENT                                                                                       $0.00        0.00%
                      RESIDENTIAL APPLIANCES                                                                                    0.00%
                      PROJECTION SCREENS                                                                                        0.00%

DIVISION 12        FURNISHINGS                                                                                     $0.00        0.00%
                      WINDOW BLINDS                                                                                             0.00%
                      ROLLER WINDOW SHADES                                                                                      0.00%
                      ENTRANCE FLOOR GRILLES                                                                                    0.00%
                      BOLLARDS                                                                                                  0.00%
                      WEATHER PROTECTED ASH URN                                                                                 0.00%
                      SITE TRASH AND LITTER RECEPTORS                                                                           0.00%
                      R.O.W. TRASH AND LITTER RECEPTORS                                                                         0.00%
                      SITE SEATING AND TABLES                                                                                   0.00%
                      R.O.W. SEATING                                                                                            0.00%

DIVISION 14        CONVEYING EQUIPMENT                                                                             $0.00        0.00%
                      HYDRAULIC ELEVATORS                                                                                       0.00%
                                                                                          ATTACHMENT 3

                                                                                  City and County of Denver
                                                                                 Department of Public Works
                                                                                 Capital Project Management

                                                                  Guaranteed Maximum Price - Schedule of Values

The following Schedule of Values outlines the construction cost breakdown for the project. If there are other items not explicitly referenced in this list, those additional items must be included in
"Additional Items" at the bottom of the document. The CM/GC will be contractually obligated to perform the entire scope of work shown in the construction and contract documents.



      Only green cells are fillable. Column widths are adjustable
                                    DESCRIPTION                                                           PRICE               %                                  COMMENTS

DIVISION 21        FIRE SUPPRESSION                                                                                $0.00        0.00%
                      COMMON WORK RESULTS FOR FIRE SUPPRESSION                                                                  0.00%
                      FACILITY FIRE-SUPPRESSION WATER-SERVICE PIPING                                                            0.00%
                      WET PIPE SPRINKLER SYSTEMS                                                                                0.00%

DIVISION 22        PLUMBING                                                                                        $0.00        0.00%
                      COMMON WORK RESULTS FOR PLUMBING                                                                          0.00%
                      COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT                                                          0.00%
                      EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING                                                          0.00%
                      METERS AND GAGES FOR PLUMBING PIPING                                                                      0.00%
                      GENERAL-DUTY VALVES FOR PLUMBING PIPING                                                                   0.00%
                      HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT                                                    0.00%
                      HEAT TRACING FOR PLUMBING PIPING                                                                          0.00%
                      IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT                                                          0.00%
                      PLUMBING INSULATION                                                                                       0.00%
                      DOMESTIC WATER PIPING                                                                                     0.00%
                      DOMESTIC WATER PIPING SPECIALTIES                                                                         0.00%
                      DOMESTIC WATER PACKAGED BOOSTER PUMPS                                                                     0.00%
                      FACILITY SANITARY SEWERS                                                                                  0.00%
                      SANITARY WASTE AND VENT PIPING                                                                            0.00%
                      SANITARY WASTE PIPING SPECIALTIES                                                                         0.00%
                      SANITARY WASTE INTERCEPTORS                                                                               0.00%
                      FACILITY STORM DRAINAGE PIPING                                                                            0.00%
                      STORM DRAINAGE PIPING SPECIALTIES                                                                         0.00%
                      SUMP PUMPS                                                                                                0.00%
                      FUEL-FIRED DOMESTIC WATER HEATERS                                                                         0.00%
                      PLUMBING FIXTURES                                                                                         0.00%
                      WATER COOLERS                                                                                             0.00%

DIVISION 23        HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)                                               $0.00        0.00%
                      COMMON WORK RESULTS FOR HVAC                                                                              0.00%
                      COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT                                                              0.00%
                      HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT                                                        0.00%
                      IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT                                                              0.00%
                      TESTING, ADJUSTING, AND BALANCING FOR HVAC                                                                0.00%
                      DUCT INSULATION                                                                                           0.00%
                      HVAC PIPING INSULATION                                                                                    0.00%
                      INSTRUMENTATION AND CONTROL FOR HVAC                                                                      0.00%
                      FACILITY NATURAL-GAS PIPING                                                                               0.00%
                      METAL DUCTS                                                                                               0.00%
                      NONMETAL DUCTS                                                                                            0.00%
                      AIR DUCT ACCESSORIES                                                                                      0.00%
                      HVAC POWER VENTILATORS                                                                                    0.00%
                      DIFFUSERS, REGISTERS, AND GRILLES                                                                         0.00%
                      PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS                                                     0.00%
                      SPLIT-SYSTEM AIR-CONDITIONERS                                                                             0.00%
                                                                                          ATTACHMENT 3

                                                                                  City and County of Denver
                                                                                 Department of Public Works
                                                                                 Capital Project Management

                                                                  Guaranteed Maximum Price - Schedule of Values

The following Schedule of Values outlines the construction cost breakdown for the project. If there are other items not explicitly referenced in this list, those additional items must be included in
"Additional Items" at the bottom of the document. The CM/GC will be contractually obligated to perform the entire scope of work shown in the construction and contract documents.



      Only green cells are fillable. Column widths are adjustable
                                    DESCRIPTION                                                           PRICE               %                                  COMMENTS

DIVISION 26           ELECTRICAL                                                                                   $0.00        0.00%
                      LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES                                                        0.00%
                      GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS                                                              0.00%
                      HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS                                                               0.00%
                      CONDUIT                                                                                                   0.00%
                      SURFACE RACEWAYS                                                                                          0.00%
                      BOXES                                                                                                     0.00%
                      UNDERFLOOR DUCTS                                                                                          0.00%
                      IDENTIFICATION FOR ELECTRICAL SYSTEMS                                                                     0.00%
                      ELECTRICAL POWER MONITORING                                                                               0.00%
                      ENCLOSED CONTACTORS                                                                                       0.00%
                      LOW-VOLTAGE TRANSFORMERS                                                                                  0.00%
                      SWITCHBOARDS                                                                                              0.00%
                      PANELBOARDS                                                                                               0.00%
                      MOTOR-CONTROL CENTERS                                                                                     0.00%
                      ELECTRICAL SERVICE ENTRANCE                                                                               0.00%
                      WIRING DEVICES                                                                                            0.00%
                      FUSES                                                                                                     0.00%
                      ENCLOSED CIRCUIT BREAKERS                                                                                 0.00%
                      ENCLOSED SWITCHES                                                                                         0.00%
                      INTERIOR LIGHTING                                                                                         0.00%
                      EXTERIOR LIGHTING                                                                                         0.00%

DIVISION 27        COMMUNICATIONS                                                                                  $0.00        0.00%
                      OPERATIONS AND MAINTENANCE OF COMMUNICATIONS SYSTEMS                                                      0.00%
                      STRUCTURED CABLING GENERAL REQUIREMENTS                                                                   0.00%
                      COMMUNICATIONS EQUIPMENT ROOM FITTINGS                                                                    0.00%
                      COMMUNICATIONS BACKBONE CABLING                                                                           0.00%
                      COMMUNICATIONS HORIZONTAL CABLING                                                                         0.00%
                      COMMUNICATIONS CONNECTING CORDS, DEVICES AND ADAPTERS                                                     0.00%
                      AUDIO-VIDEO SYSTEMS                                                                                       0.00%

DIVISION 28        ELECTRONIC SAFETY AND SECURITY                                                                  $0.00        0.00%
                      ACCESS CONTROL SYSTEM                                                                                     0.00%
                      VIDEO SURVEILLANCE SYSTEM                                                                                 0.00%
                      ELECTRONIC PERSONAL PROTECTION SYSTEMS                                                                    0.00%
                      DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM                                                                    0.00%

DIVISION 31        EARTHWORK                                                                                       $0.00        0.00%
                      SITE CLEARING / DEMOLITION                                                                                0.00%
                      EARTH MOVING                                                                                              0.00%

DIVISION 32        EXTERIOR IMPROVEMENTS                                                                           $0.00        0.00%
                      ASPHALT PAVING                                                                                            0.00%
                      CONCRETE PAVING                                                                                           0.00%
                      CONCRETE PAVING JOINT SEALANTS                                                                            0.00%
                      TURF AND GRASSES                                                                                          0.00%
                      PLANTS                                                                                                    0.00%

DIVISION 33        UTILITIES                                                                                       $0.00        0.00%
                      STORM UTILITY DRAINAGE PIPING                                                                             0.00%
                                                                                          ATTACHMENT 3

                                                                                  City and County of Denver
                                                                                 Department of Public Works
                                                                                 Capital Project Management

                                                                  Guaranteed Maximum Price - Schedule of Values

The following Schedule of Values outlines the construction cost breakdown for the project. If there are other items not explicitly referenced in this list, those additional items must be included in
"Additional Items" at the bottom of the document. The CM/GC will be contractually obligated to perform the entire scope of work shown in the construction and contract documents.



      Only green cells are fillable. Column widths are adjustable
                                    DESCRIPTION                                                           PRICE               %                                   COMMENTS

                   ADDITIONAL ITEMS                                                                                $0.00        0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
                                                                                                                                0.00%
TOTAL HARD CONSTRUCTION COST                                                                                      $0.00        0.00%

1. CM/GC Overhead and Profit (Reference Attachment 1)                                                                           0.0%
2. Construction Services General Conditions (Reference Attachment 1)                                                            0.0%
3. Construction Services Fixed Fee: Total of CM/GC OH&P and General
Conditions (1 + 2 above)                                                                                          $0.00         0.0%
3.1 CM/GC Contingency                                                                                                                   % of Hard Construction Cost
4. Guaranteed Maximum Price - Total Hard Construction Cost +
Construction Services Fixed Fee + CM/GC Contingency)                                                             $0.00

ALTERNATES: Refer to Project Manual section 01 23 00. Amounts must include
all general conditions and general requirements, surety, insurances, overhead and
profit, permits and fees.

Add Alternate No. 01 - Add Data Outlets:

Alternate No. 02: Parking Area Paving

Alternate No. 03: Add flat-screen television monitors

Alternate No. 04: Steele Street Right of Way Improvements

5. Construction Change Order Mark-Up “Free Zone”* ($ amount of changes
allowable without any CM/GC markup whether self-performed or subcontractor
performed)
6. Self-Performed Construction Change Order Mark-Up (inclusive of all mark-ups
including surety, insurances, OH&P and GC's)

7. Subcontractor-Performed Construction Change Order Mark-Up (inclusive of all
mark-ups including surety, insurances, OH&P and GC's)
Self-Performed Work (CM/GC to list all scopes of work (in whole or part) that are
intended to be self-performed, in YELLOW cells below)

				