					                                                                                                                                                  Hull City Council



                                                                         Hull City Council
                                                       Area Delivery Plan 2007-08
                                                                       Version: v01(05.03.07)


                                                                   Northern Area
                                                          Area Director: Alastair Shaw (Ext 1991)
                                                        ADP Area Contact: Alastair Shaw (Ext 1991)


  1. ADP: Executive Summary


  A summary of the broad profile of the Northern Area and the Wards it covers
  The Northern Area in the north-west of Hull covers an area of approximately 2.8 square miles. It is made up of three wards, namely Beverley, Orchard Park &
  Greenwood, and University. Within the Area there are three Secondary Schools, two have citywide catchment areas whilst the Sir Henry Cooper School is the
  designated school for the majority of young people in the Area. In addition, there are ten Primary Schools and two Special Schools.
  There are large areas that are seriously disadvantaged, mostly in the Orchard Park & Greenwood Ward where all nine super-output areas (SOA‟s) are ranked within
  the 10% most deprived areas of England overall, with three of the six SOA‟s in the University Ward also ranked within the 10% most deprived in England. This
  contrasts with other neighbourhoods throughout the Area, but particularly in the Beverley Ward, where levels of crime, disorder and deprivation are far less. The
  average IMD 2004 score for the Northern Area is 44.84 compared to an average score of 41.13 for Hull overall.
  In the 2001 Census, the total population was recorded as 32,121, with 13,062 households of which 5,824 (45%) were rented from the Council, 1,427 (11%) were
  rented from private landlords and 5,811 (44%) were owner occupied. The Census recorded 15,578 men and 16,453 women living in the Area with an average
  household size of 2.41 people. Young people under 16 accounted for 7,398 (23%) of the population whilst 4,613 residents (14%) were of retirement age. The
  number of people aged between 25 & 44 was 8,277 (26%). Of the total population, 95% stated their ethnicity as White British. Only 947 residents stated their
  ethnicity as belonging to any BME group.
  The number of people between the ages of 16 & 74 who described themselves as economically active in the 2001 Census, and said they were employed, was 10,325
  (45%) and 1,445 people (6%) stated they were unemployed. Residents between the ages of 16 and 74 who described themselves as economically inactive
  accounted for 45% (10,402) of people. In the same age range, 14,898 (65%) of residents stated they had no or only one qualification, compared to 4,586 (20%) with
  2 or more „A‟ levels or higher qualifications.




ADP Template 2007-08 (v01)
                                                                                                                                                         Hull City Council




  What does the Northern Area aspire to do?
  We will improve the quality of life in the Northern Area by:
  • working with local partners to deliver on the local priorities within the Area Community Plan which contributes to achieving the Community Strategy targets and Hull‟s
  Local Area Agreement Outcomes whilst addressing those local priorities;
  • ensuring that local services from all partners are delivered in a way that meets local needs;
  • facilitating the establishment of effective and efficient service delivery processes, initially in respect of Housing Landlord, Street Scene and Community Safety, which
  take account of core city wide standards and local needs across the Area and Neighbourhood level;
  • working in partnership with Gateway to deliver Area based regeneration in Orchard Park (Courts, Danes, Shaws and Thorpes neighbourhoods);
  • promoting existing and developing new wide ranging opportunities for the residents of the Northern Area to be involved;
  • continued engagement of local residents to increase their involvement in the design and delivery of local services, drawing on the lessons learned from the
  neighbourhood management pilots to ensure roll out through the Area Partnership mechanisms across the remainder of the area;
  • working with partners to increase and improve community cohesion across the area;
  • reducing crime and the fear of crime across the Area through partnership, working to the Common Tasking Framework;
  • working with the Orchard Park Road Customer Service Centre and proposed Information Points, as part of the Target Operating Model, to maintain and further
  develop a high quality Customer Service experience for all stakeholders in the Northern Area;
  • working with other service areas to review service migration in 2007/8 and make further recommendations for 2008/09;
  • working with partners to support the implementation of the city-wide spatial strategy, maximising all opportunities for the benefit of the Northern Area, and
  • developing local strategies for open spaces and Council owned assets in the Northern Area that compliment and contribute to the city wide strategy.



  How do we take account of the needs of our customers (especially the 3 Community Strategy Priority Audiences)?
  The Northern area is committed to providing services, which meet the needs of all our customers especially the most vulnerable.
  We will:
  • continue to identify the needs of our customers by increasing the range of activities including consultation through interest/focus groups, representation on various
  groups, and through neighbourhood and ward fora. Extending involvement in the Area Partnership structures, Neighbourhood Management Panels and the Area
  Housing Board;
  • create and implement mechanisms to ensure greater accountability of services to the Area Committee, achieving a local focus to service delivery;
  • ensure services are delivered in accordance with the Cohesion Strategy, Equalities Plan, Children‟s and Older Peoples Plan;
  • continue to develop and implement an Area based Engagement Plan;
  • through the Area Partnership mechanisms, continue to develop priority groups of residents, reflecting the three Community Strategy priority audiences, to ensure
  that the needs of those groups are identified and reflected in delivery plans as well as providing a mechanism for feedback on impact;
  • continue to develop mechanisms to ensure maximum resident involvement in determining local Community Safety priorities for action through the Community Safety
  Consultation and Tasking Groups in the Northern Area in conjunction with the Crime and Disorder Reduction Partnership and ensure feedback on progress/activity to
  date in relation to priorities set;
  • respond to customer feedback via service areas and the Customer Service Centres/Hull Connect, in terms of ethnicity, disability, age and gender to ensure parity
  across all services delivered, and
  • continue to provide relevant training to residents wishing to take a more involved role in shaping service delivery.




ADP Template 2007-08 (v01)
                                                                                                                                                                                       Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                          How will we deliver this outcome
 Service /
                                                                                                               How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                              our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...           … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                        strategy to be delivered (BC and PP)

                A1              We will continue to develop and improve the Area Community Plan Area Committee            Report to Area Committee &                             Northern Area
                                based on extensive consultation. The Plan sets out priorities for the Plan Agreed - Local Area Partnership (PP - Local                           Partnership
                                Northern Area and with appropriate partners we will continue to       Measure             Delivery)
                                address the key priorities within it. We will monitor progress
                                regularly. This will ensure that services provided in the area meet
                                local needs, involve local people in decisions about local services
                                and strengthen the accountability of partners to local people.

                Area Priority Major Milestones (Key Events)                      When            Owner        Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                    resources


                A1a             Community Conference                             May-07          Area Director LSP, Partners,         Audit of partner activity to establish what current
                                                                                                               Police, Health,        contribution can be made to the priorities within the Area
                                                                                                               Business sector,       Community Plan. Funding contribution, participation and
   e.g.                                                                                                        Voluntary and          action planning.
   xxx                                                                                                         Community sector
                A1b             Area Community Plan formally agreed              Jun-07                "       Area Partnership       Agree the Plan and contribute to implementation.
                                and launched                                                                                          Participate in formal launch.
                A1c             Performance Management Review                    Oct-07                  "    Area Partnership        Review of Implementation Plans
                A1d             Partnership Review                               Oct-07                  "    Area Partnership        Review of Governance & working arrangements to
                                                                                                                                      include strategic planning review to meet priorities for
                                                                                                                                      2008/09
                A1e             Business Audit                                   Sep-07                  "    Business                Audit of Partner activity
                                                                                                              Community




     ADP Template 2007-08 (v01)
                                                                                                                                                                                          Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:
  e.g.                          Northern
   xxx
                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                             How will we deliver this outcome
 Service /
                                                                                                                  How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                                 our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...              … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                   [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                           strategy to be delivered (BC and PP)

                A1f             We will continue to develop and improve the Area Community Plan
                                Voluntary/Community Group Audit             Sep-07              "                Voluntary/         Report to Area Committee &
                                                                                                                                    Audit of Partner activity
                                based on extensive consultation. The Plan sets out priorities for the            Community Partners Area Partnership (PP - Local
                                Northern Area and with appropriate partners we will continue to                                     Delivery)
                A1g             address the key priorities within it. We     monitor
                                Agree priorities and targets for 2008/9 willSep-07 progress "                      Area Partnership      Establish what contribution can be made to the priorities
                                regularly. This will ensure that services provided in the area meet                                      within the Area Community Plan. Funding contribution,
                                local needs, involve local people in decisions about local services                                      participation and action planning.
                A2              and strengthen the accountability of partners to local people.                   Partnership             Report to Area Committee &         Northern Area
                                We will continue to develop, support and promote the Northern
                                Area Partnership which will be responsible for ensuring that the                 established and         Area Partnership (PP - Local       Partnership
                                priority actions in the Area Community Plan are delivered. It will               operational             Delivery)
                                ensure that Elected Members and community partners are directly
                                engaged in priority setting and monitoring.
                Area Priority Major Milestones (Key Events)                      When            Owner           Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                       resources

   e.g.         A2a             Formal appointment of Partnership                Jun-07          Area Director Partners/Police/          Area Partnership Board is currently a shadow board.
   xxx                          Board members                                                                  Health/Business           • Identify and agree appropriate mechanism for
                                                                                                               Sector/Voluntary          appointment to Partnership Board
                                                                                                               and Community             • Formal adoption of the Partnership Agreement
                                                                                                               Sector                    • Training to be provided for partnership members
                A2b             Agree performance reporting schedule             Apr-07          Area Director               "                                               "

                A2c             Clarify links with LSP/Area Committee            Apr-07          Area Director               "                                               "

                A2d             Agree feedback to community                      Sep-07          Area Director               "                                               "




     ADP Template 2007-08 (v01)
                                                                                                                                                                                       Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                          How will we deliver this outcome
 Service /
                                                                                                               How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                              our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...           … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                        strategy to be delivered (BC and PP)

                A3                       evaluate to develop and improve the Area Community Plan
                                We will continue the Neighbourhood Management pilot in Orchard                Progress against        Report to Area Committee &
                                                                                                                                      PP - Local Service Delivery                Orchard Park
                                Park rolling out good practice across the rest of out priorities for the
                                based on extensive consultation. The Plan sets the Northern Area in           Area Delivery Plan      Area Partnership (PP - Local               (Gateway) Board &
                                2007/8. Area and from the city-wide Neighbourhood Management
                                Northern Evidence with appropriate partners we will continue to               and Area                Delivery)                                  Northern Area
                                pilots will be evaluated to within it. We will monitor community
                                address the key priorities ensure effective localisedprogress                 Community Plan                                                     Neighbourhood
                                regularly. This will ensure that services provided in the area meet
                                engagement and service delivery that benefits all residents in the                                                                               Management Panel
                                local needs, involve local people in decisions about local services
                                Northern Area.
                Area Priority   and Milestones (Key Events)
                                Majorstrengthen the accountability of partners to local people.
                                                                             When         Owner               Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                    resources

                A3a             Review of Orchard Park pilot following           Apr-07          Neighbourho Housing/                 • Results of evaluation of pilots being assessed to identify
                                completion of evaluation                                         od Manager Streetscene/              good practice which can be rolled out across the whole
                                                                                                             Property/ Voluntary      area
                                                                                                             and Community            • Tasking groups to deliver on local priorities
                                                                                                             sector
                A3b             Production of detailed action plan for           Apr-07          N'bourhood               "                                               "
   e.g.                         2007/8 and agreement of local targets                            Manager
   xxx
                A3c             Agreement of monitoring/reporting                Jun-07          N'bourhood               "                                               "
                                arrangements                                                     Manager
                A3d             Support the development of the                   ongoing         N'bourhood               "                                               "
                                Northern Area Neighbourhood                                      Manager
                                Management Panel




     ADP Template 2007-08 (v01)
                                                                                                                                                                                        Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                           How will we deliver this outcome
 Service /
                                                                                                                How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                               our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...            … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                 [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                         strategy to be delivered (BC and PP)

                A4                                           the improve the Area Community and
                                We will continue to develop andWard & Neighbourhood ForumsPlan                 Formally agreed     Report to Area Committee &
                                                                                                                                   PP - Local Service Delivery                    Northern Area
                                based on extensive consultation. The Plan techniques as partfor the
                                explore new participation and engagement sets out priorities of                local engagement    Area Partnership (PP - Local                   Partnership
                                Northern Area and with appropriate partners we will continue to
                                development of the Area Partnership, and the Community                         plan                Delivery)
                                address the key priorities within greater will monitor progress
                                Engagement Plan, to promote it. We levels of community                         Co-ordinated local
                                regularly. ThisThis ensure that services provided in the area meet
                                engagement. will will focus engagement on key issues based on                  engagement activity
                                good evidence and local to the in decisions about Community
                                local needs, involvelinkedpeople themes of the Area local services
                                and strengthen the accountability of partners to local people.
                                Plan and Community Strategy.                                                   Planned, co-
                                                                                                               ordinated local
                                                                                                               engagement activity
                                                                                                               defined within
                                                                                                               Community
                                                                                                               Engagement Plan

                Area Priority   Major Milestones (Key Events)                    When      Owner               Stakeholders, other     Stakeholders Agreed Actions
   e.g.         Sub-Ref. No.
                                                                                 Completed                     resources
   xxx
                A4a             Partner Activity Audit                           Sep-07          Deputy Area   Residents/              Provide information on existing activity
                                                                                                 Director      Voluntary and
                                                                                                               Community sector/
                                                                                                               Police and Health




     ADP Template 2007-08 (v01)
                                                                                                                                                                                          Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                             How will we deliver this outcome
 Service /
                                                                                                                  How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                                 our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...              … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                   [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                           strategy to be delivered (BC and PP)

                A4b             We will continue to develop and improve the Area Community Plan
                                Northern Area Engagement Strategy           May-07       Area Director           Residents/              • Development of an engagement and participation
                                                                                                                                         Report to Area Committee &
                                based on extensive consultation. The Plan sets out priorities for the
                                formally agreed                                                                  Voluntary and           Area Partnership (PP - Local
                                                                                                                                         strategy.
                                Northern Area and with appropriate partners we will continue to                  Community sector/       • Identification of joint engagement opportunities
                                                                                                                                         Delivery)
                                address the key priorities within it. We will monitor progress                   Police and Health       • Collation and sharing of information resulting from
                                regularly. This will ensure that services provided in the area meet                                      engagement.
                                local needs, involve local people in decisions about local services                                      • IT system for data collection being developed
                A4c             and strengthen thereview
                                Joint engagement accountability of partners to local people.Director
                                                                            Oct-07       Area                                "                                               "

                A4d             Engagement priority setting 2008/09              Oct-07          Area Director               "                                               "

                A4e             Update Area Engagement Plan                      Mar-08          Area Director               "                                               "

                A5              We will develop Performance Management                                           Performance             PP - Local Service Delivery                N/A
                                processes/arrangements for local service delivery and partnership                standards agreed
   e.g.                         activity. This will ensure that progress towards agreed targets can              Reporting
   xxx                          be measured effectively and KPIs are clear and measurable.                       arrangements in
                                                                                                                 place
                Area Priority Major Milestones (Key Events)                      When            Owner           Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                       resources


                A5a             ADP targets agreed by Elected Members Apr-07                     Area            Continuous              • Discussions with Head of Improvement and Programme
                                                                                                 Director/       Improvement             Manager and Area Directors to agree performance
   e.g.
                                                                                                 Area            Service / LSP           reporting arrangements
   xxx
                                                                                                 Manager                                 • Report to be submitted to the LSP by the Partnership
                                                                                                                                         and Engagement project team




     ADP Template 2007-08 (v01)
                                                                                                                                                                                     Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                        How will we deliver this outcome
 Service /
                                                                                                             How will we measure                (and manage this)                      Partners
Corporate       Area Priority
   e.g.                                           What are we doing, why and for whom?                            our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...         … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
    xxx
   (See          (inc. CP)
                                                                                                              [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                      strategy to be delivered (BC and PP)

                A5b             We will continue to develop and improve the Area Community Plan
                                ADP review                                  Oct-07        Area Director                 "           Report to Area Committee & "
                                based on extensive consultation. The Plan sets out priorities for the                               Area Partnership (PP - Local
                A5c             Northern Area and with appropriate partners we will continueDirector
                                               Community Plan review        Oct-07        Area to                       "           Delivery)                    "
                                address the key priorities within it. We will monitor progress
                A5d             ADP revision 2008/09                        Mar-08
                                regularly. This will ensure that services provided in the Area Director
                                                                                          area meet                     "                                               "
                                local needs, involve local people in decisions about local services
                A5e             Area Community Plan revision 2008/09 Mar-08               Area
                                and strengthen the accountability of partners to local people.Director                  "                                               "

                A6              We will implement the migration of other Council services through Migration                         PP - Local Service Delivery                N/A
                                a programme of Service Level and Management Agreements which Plans/Services
                                will achieve the objectives of the Community Strategy through the migrated
                                Target Operating Model.
                Area Priority Major Milestones (Key Events)                      When            Owner      Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                  resources
   e.g.
   xxx          A6a             Development and implementation of                Mar-08          Area       Other services/         Area Directors and Area Managers to develop processes
                                either Management or Service Level                               Managers   property/ C&YP          specific to each service to ensure the smooth migration of
                                Agreements - Highways and Park                                              services/ adult         those services throughout 2008/09.
                                Rangers priority areas                                                      services/ highways/     Area Directors/Area Managers to develop Warden role to
                                                                                                            economic                underpin delivery of migrating services at a local level.
                                                                                                            development/
                                                                                                            enforcement/ waste
                                                                                                            management/
                                                                                                            finance




     ADP Template 2007-08 (v01)
                                                                                                                                                                                     Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                        How will we deliver this outcome
 Service /
                                                                                                             How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                            our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...         … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                              [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                      strategy to be delivered (BC and PP)

                A6b             We will continue to develop and improve the Area Community Plan
                                Ongoing development of migration of         Mar-08        Area                          "           Report to Area Committee & "
                                appropriate elements of Children The
                                based on extensive consultation. and Plan sets out priorities for the
                                                                                          Managers                                  Area Partnership (PP - Local
                                Young People‟s Services
                                Northern Area and with appropriate partners we will continue to                                     Delivery)
                A6c             address the key(CSC) information We willOngoing progress
                                Identification of priorities within it.      monitor      Area                          "                                               "
                                                                                          area meet
                                regularly. This will ensure that services provided in the Managers
                                points across the Northern Area
                                local needs, involve local people in decisions about local services
                A6d             Rationalisation of Wardens Service in       Mar-08        Area
                                and strengthen the accountability of partners to local people.                          "                                               "
                                the Northern Area in relation to location                 Managers

                A6e             Identification and implementation of    Apr-07                   Area                   "                                               "
                                scheme of work for wardens that                                  Managers
                                supports the work of other service
                                providers to meet the needs of Northern
                                residents.
   e.g.         A7              We will develop and implement local strategies that contribute to     Strategies produced Project plan through Area                            Northern Area
   xxx                          the overarching strategies for the city. This will contribute to                          Partnership                                          Partnership
                                corporate objectives in a way that reflects and meets need at a local
                                level.
                Area Priority Major Milestones (Key Events)                      When            Owner      Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                  resources




     ADP Template 2007-08 (v01)
                                                                                                                                                                                      Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                         How will we deliver this outcome
 Service /
                                                                                                              How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                             our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...          … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                               [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                       strategy to be delivered (BC and PP)

                A7a             We will continue to develop and improve the Area Community Plan
                                Agree strategy needs for Northern Area ongoing           Area Director       Partners/ police/       • Northern Local Area Transport Plan – City Transport
                                                                                                                                     Report to Area Committee &
                                based on extensive consultation. The Plan sets out priorities for the        Health/ Business        Area Partnership (PP - Local
                                                                                                                                     Plan
                                Northern Area and with appropriate partners we will continue to              sector/ Voluntary       • Northern
                                                                                                                                     Delivery) Play Strategy- City Play Strategy
                                address the key priorities within it. We will monitor progress               and Community           • Northern Area Sports Strategy- City Sports Strategy
                                regularly. This will ensure that services provided in the area meet          sector. HCC Link        • Northern Shopping Strategy- Spatial Strategy
                                local needs, involve local people in decisions about local services          Officers
                A7b             Produce open the accountability of partners to local people.Director
                                and strengthenspace strategy                ongoing      Area                HCC Link                Northern Green Space Strategy, Northern Tree Strategy -
                                                                                                             Officers/Area           City Greenspace Strategy
                                                                                                             Partnership
                A8              We will provide support to and work with voluntary/ community                Audits produced         Project plan through Area                  Northern Area
                                sector groups and local businesses to establish and achieve                                          Partnership                                Partnership, Hull
                                clear outcomes that contribute to greater wellbeing for residents in                                                                            Community Network,
                                the Northern Area. This will contribute to the priorities within the                                                                            Northern Hull Alliance
                                Area Community Plan and Community Strategy.
   e.g.
   xxx          Area Priority   Major Milestones (Key Events)                    When      Owner             Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.
                                                                                 Completed                   resources

                A8a             Business Audit                                   Sep-07          PACT Co-    Business sector/        Northern Business Audit
                                                                                                 ordinator   Voluntary and
                                                                                                             Community sector
                A8b             Voluntary Community Sector Audit                 Jun-07          PACT Co-              "             Northern Voluntary/Community Sector Audit
                                                                                                 ordinator




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A9              We will continue toWe will meet or better the core minimum
                                STREETSCENE: develop and improve               Area Community Plan         Monthly                 Report to Area Committee &
                                                                                                                                   PP - Local Service Delivery,               N/A
                                based on extensivedelivered Streetscene Services and seek for the
                                standards for area consultation. The Plan sets out priorities              performance             Streetscene Migration Local
                                                                                                                                   Area Partnership (PP -Plan
                                Northern Area and with appropriate partners we This will (i)improve
                                improvement & efficiencies in Service Delivery. will continue to           statistics              Delivery)
                                cleanliness key priorities within it. We core Council and locally
                                address thestandards to meet national, will monitor progress               Quarterly
                                agreed targets will ensure that services provided consistency
                                regularly. This for BVPI 199; (ii) maintain service in the area meet       performance report
                                local needs, involve local people in decisions about local services
                                across the city to minimum baseline standards, and (iii) allow areas       to Area Committee
                                to determine resource according of partners to local people.
                                and strengthen the accountabilityto local need for delivery beyond
                                the minimum standards.
                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
   e.g.         Sub-Ref. No.                                                     Completed                 resources

   xxx
                A9a             Review of performance and trend                  Monthly         Area      Streetscene Area  Core standards to be agreed citywide. Each Area Team
                                analysis                                                         Manager   Team, Streetscene responsible for maintaining standards. Provide local
                                                                                                           Corporate         intelligence on service standards.
                                                                                                           Performance Team,
   e.g.                                                                                                    Community
   xxx                                                                                                     Surveyors

                A9b             Performance report to Area Committee             Quarterly       Area                  "                                               "
                                                                                                 Manager
                A10             STREETSCENE: We will promote and develop the community                     Number of               PP - Local Service Delivery,               N/A
                                surveyor role within our neighbourhoods to increase the number of          Community               Streetscene migration plan
                                community surveyors and increase community involvement in                  Surveyors
                                assessing and recommending delivery in their neighbourhoods.




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                              We Milestones (Key Events)
                Area Priority Majorwill continue to develop and improve the Area Community Plan Stakeholders, other
                                                                         When       Owner                                          Report to Area Committee
                                                                                                                                   Stakeholders Agreed Actions&
                                                                         Completed
                Sub-Ref. No. based on extensive consultation. The Plan sets out priorities for the resources                       Area Partnership (PP - Local
                                Northern Area and with appropriate partners we will continue to                                    Delivery)
                A10a            address recruitment literature explaining monitor        Area
                                Develop the key priorities within it. We willMay-07 progress                                       Schedule of training for Community Surveyors to be
                                regularly. This will ensure for services provided in the Manager
                                the role and opportunities that                          area meet         Community               developed and further recruitment activity.
                                involvement
                                local needs, involve local people in decisions about local services        Surveyors,
                                and strengthen the accountability of partners to local people.             Communications &
                                                                                                           Marketing, CPO's,
                                                                                                           Area Streetscene
                                                                                                           Co-ordinator
                A10b            Develop annual schedule of training for          May-07          Area                "                                                 "
                                new surveyors                                                    Manager
                A11             STREETSCENE: We will investigate new technology and assess its             Production of           PP - Local Service Delivery,               N/A
                                impact in creating efficiencies and adding value. This will generate       cashable and non-       Streetscene migration plan
   e.g.                         'smarter' working arrangements between Area services generating            cashable efficiency
   xxx                          budgetary and resource flexibilities in order to address local needs.      savings to be
                                                                                                           reinvested into
                                                                                                           service delivery
                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources


                A11a            Investigate key processes for each area Apr/May 07 Area          Area Managers,    Discussions to take place once technological
                                delivered service and identify any                 Manager/      Area based Teams, development have been identified
                                possible streamlining opportunities                Area Director ICT Services




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A12             We will continue towe will, inand improve with Area Community Plan
                                STREET SCENE: develop conjunction the the Head of                          Response time of        Report to Area Committee &
                                                                                                                                   PP - Local Service Delivery,               N/A
                                based on extensive consultation. The Plan sets out priorities for the
                                Streetscene, aim to restructure the way services are delivered             service requests        Streetscene migration Local
                                                                                                                                   Area Partnership (PP -plan
                                locally, taking and with appropriate This will ensure that services
                                Northern Areaaccount of local need.partners we will continue to                                    Delivery)
                                address the key priorities within it. We will monitor progress
                                meet local need and efficiencies are gained, including the feasibility
                                regularly. This will ensure that services provided in the area meet
                                of introducing a seven day working week.
                                local needs, involve local people in decisions about local services
                Area Priority                                               When         Owner
                                Major Milestones (Key Events) of partners to local people.                 Stakeholders, other     Stakeholders Agreed Actions
                                and strengthen the accountability
                Sub-Ref. No.
                                                                            Completed                      resources

                A12a            Establish business reasons and                   Apr-08          Area      H of Streetscene, Draw up business reasons, efficeincies and outputs
                                expected gains                                                   Manager   Area based Teams,
                                                                                                           Human Resources,
                                                                                                           Trade Unions

                A12b            Be actively involved with negotiations           ongoing         Area                              Negotiation with Unions will start once proposals have
   e.g.                         between unions and personnel                                     Manager                           been drawn up.
   xxx          A12c            Restructure services delivered locally,     Mar-08          Area                                   Area Team involvemnt in mew working arrangements
                                including investigation of a seven day                      Manager
                                working week
                A13             STREETSCENE: We will deliver the area based Streetscene                    Documented            PP - Local Service Delivery,                 N/A
                                Services within the budget allocated to the Northern Area and              efficiencies          Migration plan
                                generate service efficiencies to increase flexibilities in funding.        generated and re-
                                                                                                           invested into service
                                                                                                           delivery


   e.g.
   xxx

     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                              We Milestones (Key Events)
                Area Priority Majorwill continue to develop and improve the Area Community Plan Stakeholders, other
                                                                         When       Owner                                          Report to Area Committee  &
                                                                                                                                   Stakeholders Agreed Actions
                                                                         Completed
                Sub-Ref. No. based on extensive consultation. The Plan sets out priorities for the resources                       Area Partnership (PP - Local
   e.g.
                                Northern Area and with appropriate partners we will continue to                                    Delivery)
   xxx          A13a            Create athe key priorities within it. We willApr-07 progress
                                address budget profile for the year           monitor     Area             Streetscene             Discussions with Finance taking place around budget
                                regularly. This will ensure that services provided in the Manager
                                                                                          area meet        Services, Area          dissagregation and funding limitations.
                                local needs, involve local people in decisions about local services        Manager, Finance
                A13b            Establish monthly monitoring schedule        ongoing      Area
                                and strengthen the accountability of partners to local people.                         "                                               "
                                                                                          Manager
                A13c            Mid year financial review                        Oct-07          Area                  "                                               "
                                                                                                 Manager
                A14             COMMUNITY SAFETY: We will continue to develop the Community                Police data and         Agree local targets through the Northern Area
                                Safety Tasking Group in line with the Common Tasking Framework             Home Office             Area Tasking arrangements (PP Community Safety
                                as part of the Area Partnership, in order to contribute to a reduction     IQUANTA website,        - Local Service Delivery)       Partnership, Police,
                                in the total British Crime Survey (BCS) comparator crimes recorded         Common Tasking                                          Humberside Fire and
   e.g.                                                                                                    meetings, number                                        Rescue, CDRP,
                                within Hull from a baseline of 35788 in 2003/4 to 25052 by the end
   xxx                          of March 2008. This will improve the quality of life in the Northern       of SARA packages                                        Northern Area
                                area through addressing both actual crime and perceptions of crime         developed                                               Partnership
                                in all neighbourhoods.

                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                             P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                 What are we doing, why and for whom?                            our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                          …we will do this….in order to achieve…for this audience...         … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A14a            We will continue to develop and improve the Area Community Plan Area Partnership
                                Establsih Area & Ward Tasking               Apr-07       Area Director                             Report to Area Committee &
                                                                                                                                   Provision of intelligence, resources and expertise in
                                based on extensive consultation. The Plan sets out priorities for the
                                arrangements                                                                                       addressing Area (PP - Local
                                                                                                                                   Area Partnership priorities/targets
                                Northern Area and with appropriate partners we will continue to                                    Delivery)
                                address the key priorities within it. We will monitor progress
                A14b            regularly. & develop Ward and Area                        area meet
                                Establish This will ensure that services provided in the Deputy Area Area Partnership
                                                                            Apr-07                                                 Residents identify priorities. Partners tasked to address
                                local needs, involve local people in decisions about local services
                                Consultation arrangements                                Director/     and Residents               priorities
                                and strengthen the accountability of partners to local people.
                                                                                         Tasking
                                                                                                Officer

                A14c            Community Safety updates to be                  ongoing         Area       Area Partnership        Implement effective common monitoring and recording
                                reported to Area Committees, Area                               Manager/                           system
                                Partnership and Community Safety                                Tasking
                                Forums.                                                         Officer
   e.g.
   xxx




     ADP Template 2007-08 (v01)
                                                                                                                                                                                        Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                           How will we deliver this outcome
 Service /
                                                                                                                How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                               our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...            … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                 [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                         strategy to be delivered (BC and PP)

                A15             We will continue to develop and improve thepromote greater levels
                                COMMUNITY SAFETY: We will continue to Area Community Plan                      Number of Area      Report to Area Committee &
                                                                                                                                   PP - Local Service Delivery                    Northern Area
                                based on extensive consultation. Common Tasking approach for the
                                of community engagement in the The Plan sets out priorities to                 Community Safety    Area Partnership (PP - Local                   Common Tasking
                                Northern Area and with appropriate partnersthe area.
                                tackling Crime       Anti-Social Behaviour in we will continue to              Consultation events Delivery)                                      Partnerships, Police,
                                address (i) establish formal community will monitor progress
                                This will the key priorities within it. We consultation & engagement           held                                                               Humberside Fire and
                                mechanisms in response that Police & Justice in 2006 and the
                                regularly. This will ensureto theservices providedBill the area meet                                                                              Rescue, CDRP,
                                local needs, involve local Crime &in decisionsPartnership;services
                                statutory functions of the people Reduction about local (ii) create                                                                               Northern Area
                                multi-agency working in the Area of partners to local people.
                                and strengthen the accountability with a Common Tasking approach                                                                                  Partnership
                                to problem solving that addresses local priorities; (iii) integrate the
                                combined Area Anti-Social Behaviour Enforcement Officers and
                                also the mainstreamed Neighbourhood Warden Service into the
                                Area structures; (iv) provide residents with a single Area resource
                                for raising local community safety issues, and (v) strengthen the
                                accountability of partners to local communities

   e.g.
                Area Priority Major Milestones (Key Events)                      When            Owner         Stakeholders, other     Stakeholders Agreed Actions
   xxx          Sub-Ref. No.                                                     Completed                     resources


                A15a            Establish formal community consultation Apr-07                   Area          Citysafe                Agreement of new consultation arrangements
                                and engagement mechanisms – themed                               Director/
                                events to address local priorities                               Deputy Area
                                                                                                 Director




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A15b            We will continue multi-agency working at the Area Community Plan
                                Development of to develop and improve Apr-07              Area                         "           Report to Area Committee & "
                                the Area extensive consultation. The Plan
                                based on& Neighbourhood level through sets out priorities for the
                                                                                          Director/                                Area Partnership (PP - Local
                                Northern Area and with appropriate partners we will continue toArea
                                a Common Tasking approach accepted                        Deputy                                   Delivery)
                                address the key priorities within it. and will monitor progress
                                by all Partners – agreeing reactive We                    Director
                                regularly. responses to Area priorities provided in the area meet
                                proactive This will ensure that services
                                local needs, involve local people in decisions about local services
                                and strengthen the accountability of partners to local people.
                A15c            Neighbourhood Warden priorities              Apr-07       Area                         "                                               "
                                reviewed and aligned to the priorities of                 Director/
                                the Area – working with partners to                       Deputy Area
                                ensure best use of all available                          Director
                                resources
                A16             COMMUNITY SAFETY: We will increase the number of people                    Number of residents PP - Local Service Delivery                    Northern Area
                                who consider their neighbourhood a safe place to live in line with         feeling their                                                      Community Safety
                                priorities set out in the Community Strategy and the Northern Area         neighbourhood is a                                                 Partnership, Police,
   e.g.
                                Community Plan                                                             safe place to live                                                 Humberside Fire and
   xxx                                                                                                                                                                        Rescue, CDRP,
                                                                                                                                                                              Northern Area
                                                                                                                                                                              Partnership
                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources




     ADP Template 2007-08 (v01)
                                                                                                                                                                                        Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                           How will we deliver this outcome
 Service /
                                                                                                                How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                               our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...            … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                 [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                         strategy to be delivered (BC and PP)

                A16a            We will continue to develop and improve the Area Community Plan Citysafe
                                Baseline to be determined                   Apr-07       Area                                          Report to new Common Tasking arrangements and agree
                                                                                                                                       Consider Area Committee &
                                based on extensive consultation. The Plan sets out priorities for the
                                                                                         Director/                                     what Partnership (PP - Local
                                                                                                                                       Area further action is required. Obtain feedback from
                                Northern Area and with appropriate partners we will continue toArea
                                                                                         Deputy                                        Delivery)
                                                                                                                                       residents
                                address the key priorities within it. We will monitor progress
                                                                                         Director
                                regularly. This will ensure that services provided in the area meet
                A16b            Agree Performance local people &
                                local needs, involve Managementin decisions about local services
                                                                            Apr-07       Area            "                                                                 "
                                and strengthen the accountability of partners to local people.
                                reporting framework                                      Director/
                                                                                         Deputy Area
                                                                                         Director

                A16c            Develop community safety report for              Apr-07          Area                      "                                               "
                                submission to Area Committee                                     Director/
                                                                                                 Deputy Area
                                                                                                 Director
   e.g.
   xxx          A17             HOUSING: We will fully integrate the Housing Landlord function into Core minimum                       PP - Local Service Delivery,               N/A
                                the Northern Area Team and provide a customer focussed service      standards                          Migration Plan
                                which meets or exceeds our targets set by the Area Housing Board,
                                Area Committee and Director of Housing with the aim of embedding
                                the new structure to deliver high quality, good value service,
                                delivering improvements via the Target Operating Model

                Area Priority Major Milestones (Key Events)                      When            Owner         Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                     resources




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A17a            We will continue to develop and improve the Area Community Plan
                                Monthly performance reporting                Apr-07       Area             Housing Service,   Report to Area Committee & Area Housing Landlord
                                                                                                                              Management Agreement and
                                based on extensive consultation. The Plan sets out priorities for the
                                framework established                                     Manager/         Area Housing Board Area Partnership (PP - Local plan
                                                                                                                              Team implementing migration
                                Northern Area and with appropriate partners we will continue to
                                                                                          AHB              Governance Team Delivery)
                                address the key priorities within it. We will monitor progress
                                                                                          Governance
                                                                                          area meet
                                regularly. This will ensure that services provided in the Officer
                A17b                                  local people in decisions about
                                local needs, involveand amend policies Ongoing local services
                                Adopt joint working                                       Area             Northern Area Team Clear lines of communition, best use of available
                                     procedures to accountability of partners to local people.
                                and strengthen thereflect this                            Manager/                            resources
                                                                                          Housing
                                                                                          Manager
                                Ensure PPD's reflect new roles and           Ongoing      Area Director    Area Manager/                                               "
                A17c            linkages                                                                   Housing Manager
                A18             HOUSING: We will work with and fully support the Area Housing
                                Board to engage tenants in decisions about the delivery of Housing
                                Services in the Northern Area in order to give tenants direct
   e.g.                         involvement in the delivery of the Housing Landlord function
   xxx
                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources


                A18a            Monthly performance reporting                    Apr-07          Area      Housing                 To provide performance reports
                                framework established                                            Manager

                A18b            Relocation of the Area Housing Board             Apr-07          Area      Housing                 Access to local intitiatives/Area working practices
                                Governance Officer to the Area Team                              Manager




     ADP Template 2007-08 (v01)
                                                                                                                                                                                       Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                          How will we deliver this outcome
 Service /
                                                                                                               How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                              our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...           … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                                [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                        strategy to be delivered (BC and PP)

                A19             We will continue to develop and improve the and partners to Plan
                                HOUSING: We will work with the community Area Community                       Record of               Report to Area Committee &
                                                                                                                                      PP - Local Service Delivery,               Gateway, Ings
                                regenerate our neighbourhoods The Plan sets out priorities for
                                based on extensive consultation.offering a choice of tenures to the           identification of       Area Partnership (PP - Local
                                                                                                                                      Neighbourhood Management                   Neighbourhood
                                Northern the qualitywith appropriate partners we will continue to
                                increase Area and of life for our residents.                                  regeneration            Delivery)Plan
                                                                                                                                      Delivery                                   Management
                                address the key priorities within it. We will monitor progress                activities needed                                                  Partnership Board
                                regularly. This will ensure that services provided in the area meet           and update on
                                local needs, involve local people in decisions about local services           progress
                Area Priority   and Milestones (Key Events)
                                Majorstrengthen the accountability of partners to local people.
                                                                            When          Owner              Stakeholders, other      Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                   resources


                A19a            Develop local intiatives in preparation of Apr-07                Area        Housing Services,        Gateway Board established and working relationships
                                planned Gateway interventions                                    Manager/Nei Gateway                  being developed with Housing Services and Gateway
                                                                                                 ghbourhood
                                                                                                 Manager
                A19b            Action Plan developed and agreed                 Sep-07          Area                 "
   e.g.                                                                                          Manager/Nei
   xxx                                                                                           ghbourhood
                                                                                                 Manager
                A19c            Establish Partnership working practices Oct-07                   Area                 "
                                with RSL's & privae landlords in the Area                        Manager/Nei
                                                                                                 ghbourhood
                                                                                                 Manager
                A19d            Update of Neighbourhood Management               Jul-07          Area                 "
                                Delivery Plan                                                    Manager/Nei
                                                                                                 ghbourhood
                                                                                                 Manager




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A20             We will continue to develop and improve the Area Community Plan Decrease in repair
                                HOUSING: We will              effective links with Connaught                                       Report to Area Committee &
                                                                                                                                   PP - Local Service Delivery,               Area Housing Board,
                                based on extensive consultation. The provide a proactive approach requests
                                Partnership Ltd and other investors to Plan sets out priorities for the                            Area Partnership (PP - Local
                                                                                                                                   Migration Plan                             Canought Ltd
                                to home Area and with reducing the need for responsive repairs
                                Northernimprovements, appropriate partners we will continue to                                     Delivery)
                                and improving the quality within it. to will monitor
                                address the key priorities of serviceWeour tenants. progress
                                regularly. This will ensure that services provided in the area meet
                                local needs, involve local people in decisions about local services
                Area Priority   and Milestones (Key Events)
                                Majorstrengthen the accountability of partners to local people.
                                                                             When         Owner         Stakeholders, other        Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources


                A20a            Formal working arrangements             Apr/May-07 Area                    Connaught               Contract starts in April 2007
                                developed between Connaught                           Manager              Partnership Ltd,
                                Partnership Ltd and the Northern Area                                      Housing Manager
                                Team
                A20b            Structure of regular partnership        Apr/May-07 Area                                "                                               "
   e.g.                         meetings established.                                 Manager
   xxx          A21             HOUSING: We will promote opportunities for resident involvement            Increase in number PP - Local Service Delivery ,                   Area Houing Board
                                in service improvement through the Northern Area Housing Board,            of Northern          Migration Plan
                                service improvement groups, mystery shopping exercises and                 residents on service
                                patchwalks ensuring all customer groups are able to be represented.        improvement groups


                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A21a            We will continue to develop and improve the Area Community Plan
                                Promote opportunities for membership        Jun-07       Area              Housing Service,     Report toservice improvement groups in operation
                                                                                                                                Citywide Area Committee &
                                of city on extensive consultation. The Plan sets out priorities for the
                                based wide service improvement groups                    Manager           Tenant Participation Area Partnership (PP - Local
                                Northern Area and with appropriate partners we will continue to
                                to local residents                                                         Team. AHB            Delivery)
                                address the key priorities within it. We will monitor progress             Governance Officer
                                regularly. This will ensure that services provided in the area meet
                A21b            local needs, involve local people in decisions about local services
                                Propose establishment of an Area            Jun-07       Area                          "                                               "
                                and strengthen the accountability of partners to local people.
                                service improvement group to the Area                    Manager
                                Housing Boards
                A21c            Develop programme of patch walks to         Apr-07       Area              Tenants/Residents       Best use of available resources. Issues fed into the Area
                                cover whole of Northern Area                             Manager                                   Neighbourhood Panel
                A22             HOUSING: We will reduce the number of empty properties within              Average relet times     PP - Local Service Delivery,      Area Housing Board,
                                our communities and increase the speed in which properties are let         (days)                  Migration Plan                    Northern Area
                                with the aim of reducing voids by 2009 and reducing turnaround                                                                       Neighbourhood Panel
                                time to upper quartile levels by the end of 2008.
   e.g.
   xxx          Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources


                A22a            Identification of further proposals to  Apr-07                   Area      Housing Manager,        Review procedures and implement best practice
                                demolish or bring back into use long                             Manager   Estate Manager,
                                term voids                                                                 HomeSearch
                A22b            Investigate further opportunities for   Jul-07                   Area               "                                                  "
                                promoting the standard in which tenants                          Manager
                                should leave their property




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                A22c            We will continue to develop and improve the Area Community Plan
                                Identify efficiencies, in conjunction with Jul-07         Area                 "                   Report to Area Committee & "
                                based on extensive consultation. The Plan sets out priorities for the
                                Homesearch, to increase the speed of                      Manager                                  Area Partnership (PP - Local
                                Northern Area and with appropriate partners we will continue to
                                advertising properties for let.                                                                    Delivery)
                A22d            Promote 'back to back' lettings it.          monitor
                                address the key priorities withinand We willJul-07 progress
                                                                                          Area                 "                                                "
                                                                                          area meet
                                regularly. This will ensure that services provided in the Manager
                                ensure these happen wherever feasible
                                local needs, involve local people in decisions about local services
                A23             and strengthen the accountability homelessnesslocal people.
                                HOUSING: We will work with the of partners to section to ensure       Reduction of use of          Housing Service Delivery Plan              Area Housing Board
                                all residents are offered effective advice and support in order to    bed and breakfast
                                prevent/respond to homelessness                                       accommodation

                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources


                A23a            Establish links with homeless section     Sep-07       Area                Homelessness            Homesearch remit established and operational
   e.g.                         and Homesearch                                         Manager             section
   xxx          A23b            Work with partner agencies to identify    Sep-07       Area                Area Partnership        Preventative policies and working practices to be
                                key issues in prevention of                            Manager                                     established/reviewed
                                homelessness
                A23c            Provide training on homelessness          Sep-07       Area                Homelessness            Training packages to be developed
                                advice for area based staff                            Manager             section
                A23d            Identify long term empty properties       Jun-07       Area                Housing Manager,        All Area properties to be available for let at the earliest
                                suitable for bringing back into use                    Manager             Contractor              possible date.
                A24             HOUSING: We will use customer feedback and analysis of the                 Customer feedback       PP - Local Service Delivery,        Area Housing Board
                                demographics of the Northern area to tailor our services to local                                  Migration Plan
                                need and and improve customer access.




     ADP Template 2007-08 (v01)
                                                                                                                                                                                    Hull City Council




2a. ADP: SERVICE/CORPORATE PRIORITIES: What is Our Area's Contribution to the Service/Corporate Priorities for serving our residents?

Area Name:                      Northern

                                SERVICE / CORPORATE                                              P R I O R I T I E S (Area's Specific Contribution)
                                                                                                                                       How will we deliver this outcome
 Service /
                                                                                                            How will we measure                (and manage this)                      Partners
Corporate       Area Priority
                                                  What are we doing, why and for whom?                           our success       Please state if you have a Business Case (Name of formal Partnerships
Priority Ref.     Ref. No.
                                           …we will do this….in order to achieve…for this audience...        … what will Change     and/or Programme Plan* for the priority   or Partner Organisations
   (See          (inc. CP)
                                                                                                             [outcome + KPI Ref]      (e.g. Enable the Customer Services    helping us deliver this priority)
Guidance)
                                                                                                                                     strategy to be delivered (BC and PP)

                              We Milestones (Key Events)
                Area Priority Majorwill continue to develop and improve the Area Community Plan Stakeholders, other
                                                                         When       Owner                                          Report to Area Committee  &
                                                                                                                                   Stakeholders Agreed Actions
                                                                         Completed
                Sub-Ref. No. based on extensive consultation. The Plan sets out priorities for the resources                       Area Partnership (PP - Local
                                Northern Area and with appropriate partners we will continue to                                    Delivery)
                A24a                                                                      Area
                                Statistical analysis of the demographicswillJul-07 progress
                                address the key priorities within it. We     monitor                       Equalities Officer,     Information being gathered.
                                of each neighbourhood (sex, race,
                                regularly. This will ensure that services provided in the Manager
                                                                                          area meet        CSC's, Housing
                                religion, language). local people in decisions about local services
                                local needs, involve                                                       Manager
                A24b            and strengthen thefor collection and partners to local people.
                                Establish systems accountability of         Jul-07        Area                         "                                               "
                                analysis of local customer feedback.                      Manager
                A25             HOUSING: We will work with the Area Housing Board and                Financial analysis            PP - Local Service Delivery,               Area Housing Board,
                                Connaught Partenrship Ltd to ensure value for money is maximised                                   Migration Plan                             Kingstown Works Ltd
                                through identifying area priorities and reduced maintenance costs to
                                the benefit or local tenants.
                Area Priority Major Milestones (Key Events)                      When            Owner     Stakeholders, other     Stakeholders Agreed Actions
                Sub-Ref. No.                                                     Completed                 resources
   e.g.
                A25a            Formal working arrangements                      Apr/May 07 Area           Area Housing            Clear lines of commuication established, performance
   xxx
                                developed between Conaught Ltd and                          Manager        Board, Contractor       management info presented on time, planned programme
                                the Northern Area Team                                                                             of all works agreed
                A25b            Structure of regular partnership                 Apr/May 07 Area           Area Housing            Attendance - contribution to the meetings
                                meetings established                                        Manager        Board, Contractor
                A25c            Programme plan and budget projection             Apr/May 07 Area           Area Housing            Performance information - identification of
                                developed in conjunction with the Area                      Manager        Board, Contractor,      efficiencies/slippages - action agreed
                                Housing Board                                                              Housing Services,
                                                                                                           Finance




     ADP Template 2007-08 (v01)
                                                                                                                                              Hull City Council




3. ADP: OUR BUDGET OVERVIEW

Area Name
                                              B U D G E T // F I N A N C E
                                          2006-07                                                                              2007-08
                                                     Gross Initial                  Net Original                                                    Net
                                                                         Target                                                      Target
                                                 Expenditure                        Expenditure    Projected  Gross Expenditure                  Estimated
                                                                       Income (£)                                                  Income
                    Division of Service         Estimate (£)                        Estimate (£)    Out-turn Estimate          (£)              Expenditure
                                                                            B                                                          (£)
                                                             A                           C                                                            (£)
                                                    Pay      Non-Pay                                            Pay      Non-Pay
Cemeteries                                      000,000     000,000    000,000      Sum of A - B 000,000     000,000    000,000    000,000      000,000




PLEASE DO NOT COMPLETE - WILL BE POPULATED BY FINANCE WHEN FIGURES ARE FINALISED




   ADP Template 2007-08 (v01)
4. ADP: OUR CUSTOMER RESPONSIVENESS
Area Name:                Northern

                                      A)       CUSTOMER                 SERVICE               STANDARDS
                                                      What standard of service do our customers want?
                    (This will be informed by the outcome of the needs analysis (B below) and also our Corporate Service standards)
          This is our Service Standard              We will work with the following                   This is how we will measure it
• Respond to telephone calls within 15 seconds         • Call Centre                • Telephone statistics
• All staff representing the Area Team will portray    • All services               • Citizen feedback
a professional image at all consultation and
engagement
• We will arrange three Area Community Safety          • All partners               • Citizen/partner feedback
Consultation events in each calendar year
• The Area Anti-Social Behaviour Enforcement                                        • ASB IT Software packages
Team will respond to all queries and/or service
requests within 48 hours of receipt




                                                      B)      OUR       RESPONSIVENESS
                                                How will we find out the needs of ALL our customers?
                 (List all the proposed activities taking into account the 3 Priority Audiences in the Community Strategy (see Guidance)
             This is what we will do                            Frequency                    We will work with the following      This is who will lead




ADP Template 2007-08 (v01)
             This is what we will do                              Frequency                       We will work with the following           This is who will lead
• The Northern Area Team will continue to play a      A full schedule of Neighbourhood/     Public, private, voluntary and Community      Elected Members
key role in ensuring that the Council moves           Ward Forums, average                  Sectors, Police, Primary Care Trusts, faith   Area Team
forward with plans to completely transform service    bi-monthly                            Communities and communities of interest       Delivery Group Lead
delivery, ensuring that services are customer-                                                                                            Community representatives
focused and responsive to the needs of local          Area Partnership meetings quarterly
communities through the roll out of
Neighbourhood Management across the area              Area Partnership Community
based on the results from the evaluation of           Conferences
Neighbourhood Management pilots across the city       Bi-annually
but specifically the lessons learned from the
Newland and Sculcoates Area.                          Publicly accessible Area Committee
                                                      Meetings - monthly

                                                      Community Safety taking events

• Through the continuing development of Area          Distribution of the Area Community    Public, private, voluntary and Community      Elected Members
Plans (underpinned by Engagement Plans), we           Plan for comment annually             Sectors, Police, Primary Care Trusts, faith   Area Team
will endeavour to work with increasing numbers                                              Communities and communities of interest       Delivery Group Lead
within our communities and with our partners to       Web site, Quality of Life surveys,                                                  Community representatives
make sure that local priorities are informed at the   focus groups, delivery
local level, and that all communities across the
Northern Area benefit from the delivery of the
Community Strategy translated to address local
need
• We will assist with, contribute to and learn from                                         Public, private, voluntary and Community      Elected Members
surveys carried out at a citywide level                                                     Sectors, Police, Primary Care Trusts, faith   Area Team
                                                                                            Communities and communities of interest       Delivery Group Lead
                                                                                                                                          Community representatives

                                                      Citywide surveys
• We will work with partners to create an equitable   All of the above and additional       Public, private, voluntary and Community      Elected Members
environment where, Older People, Vulnerable           targeted activity to respond to the   Sectors, Police, Primary Care Trusts, faith   Area Team
People and their carers have the opportunity to       specific engagement needs of the      Communities and communities of interest       Delivery Group Lead
help shape the Area Community Plan and the            priority groups.                                                                    Community representatives
services required to deliver on the priorities w




ADP Template 2007-08 (v01)
             This is what we will do                                Frequency                      We will work with the following           This is who will lead
• We will engage with Black and minority ethnic        All of the above and additional       Public, private, voluntary and Community      Elected Members
people, disabled people and their carers, and          targeted activity to respond to the   Sectors, Police, Primary Care Trusts, faith   Area Team
other traditionally marginalised and excluded          specific engagement needs of the      Communities and communities of interest       Delivery Group Lead
groups, by working with and through existing           priority groups.                                                                    Community representatives
organisations and by tailoring activity to promote
inclusivity and accessibility.
• We will engage with Black and minority ethnic        All of the above and additional       Public, private, voluntary and Community      Elected Members
people, disabled people and their carers, and          targeted activity to respond to the   Sectors, Police, Primary Care Trusts, faith   Area Team
other traditionally marginalised and excluded          specific engagement needs of the      Communities and communities of interest       Delivery Group Lead
groups, by working with and through existing           priority groups.                                                                    Community representatives
organisations and by tailoring activity to promote
inclusivity and accessibility.
                                                       To be developed                       All services and appropriate partners         Customer Service Manager
• The Call Centre and Customer Service Centre
provide a wealth of information with regard to the
needs of our customers. A detailed work
programme will be implemented in 2007/8 to
ensure that this information can be translated into




                                                       C)      OUR           COMMUNICATION
                     How will we give feedback to our customers and also inform them of new or modified services?
                                                     (i.e. feedback to customers from surveys, focus groups etc.)
             This is what we will do                                Frequency                   We will work with the following              This is who will lead
• The Area Community Engagement Plan will lay        Annually                                Organisations across the public, private,     Area Directors
out partner engagement activity for 2007/08. It will                                         voluntary and community sectors that serve
seek where possible to ensure there is a co-                                                 the Northern Area
ordinated approach to community engagement.

• We will ascertain local priorities with regard to    Bi-Monthly                            Organisations across the public, private,     Area Managers
service delivery at ward fora and report back on                                             voluntary and community sectors that serve
action taken in response on a rolling programme.                                             the Northern Area




ADP Template 2007-08 (v01)
             This is what we will do                              Frequency        We will work with the following           This is who will lead
• We will use Community Conferences to explore      Annually                  Organisations across the public, private,    Area Team
the long term aspirations for Northern and report                             voluntary and community sectors that serve
back to the Community regarding action and                                    the Northern Area
future strategy at the following conference

• We will seek to produce a generic newsletter                                Organisations across the public, private,    Partnership
advising the community about activity across the                              voluntary and community sectors that serve
whole of the Partnershio and area                   Bi-Annually               the Northern Area
• Hull in Print provides a resource that is often   Fortnightly               Communications Team                          Head of Area and
under utilised. Current proposals to develop an                                                                            Neighbourhood
“area page” for each of the seven areas to be                                                                              Management
developed for 2007




ADP Template 2007-08 (v01)
                                                                                                                                                                 Hull City Council




5a. ADP: MEASURING SUCCESS (Service/Corporate Priorities)
Area Name:            Northern

                                                               MEASURING                    SUCCESS
      *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local             Using: LAA // Customer Promises (CuP) // Partnership // Statutory
  Area            Our Priority or Activity    Type of Performance Indicator        Method of Measuring    Benchmark    Annual     Latest         Target       Target       Target
 Priority                                       PI*   Description                    e.g. calculation,                 2005/06   Forecast        2006/7       2007/8       2008/9
 Ref. No.                                             (include core minimum         survey, feedback,                            2006/07
                                                      standard, if applicable)      external inspection


                                   Our Area's Performance Measures that contribute to the Service/Corporate Priorities
Jobs & Prosperity


Education, Learning & Skills


Quality of Life

A1          Development of Area               Local    Production of plan          Plan                   N/A         N/A        1           1            1            1
            Community Plan                             document
A2          Development of Area               Local    Partnership Board meeting   Meeting minutes        N/A         N/A        2           2            4            4
            Partnership
A3          Roll out of Neighbourhood         Local    Progress against Area       Ward priorities        N/A         NA/        75% of      100% of      100% of      100% of
            Management pilot                           Delivery Plan and Area      established and                               agreed      agreed       agreed       agreed
                                                       Community Plan              performance                                   priorites   priorities   priorities   priorities
                                                                                   reports to Area                               actioned    actioned     actioned     actioned
                                                                                   Committees,
                                                                                   surveys
A4          Community Engagement              Local    Production of plan          Agreed Area            N/A         N/A        1           1            1            1
                                                       document.                   Engagement Plan,
                                                       Generic engagement          survey, feedback
                                                       activity across the area
A5          Performance Management            Local    Performance standards       Framework and          N/A         N/A        1           1            1            1
                                                       agreed, reporting           reporting
                                                       arrangements in place       arranegments in
                                                                                   place
A6          Migration of all other Services   Local    Migration plans/Services    Plans                  N/A         N/A        3           3            8            8
                                                       migrated




     ADP Template 2007-08 (v01)
                                                                                                                                                               Hull City Council




5a. ADP: MEASURING SUCCESS (Service/Corporate Priorities)
Area Name:            Northern

                                                              MEASURING                    SUCCESS
       *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local         Using: LAA // Customer Promises (CuP) // Partnership // Statutory
  Area            Our Priority or Activity   Type of Performance Indicator        Method of Measuring    Benchmark    Annual     Latest        Target       Target          Target
 Priority                                      PI*   Description                    e.g. calculation,                 2005/06   Forecast       2006/7       2007/8          2008/9
 Ref. No.                                            (include core minimum         survey, feedback,                            2006/07
                                                     standard, if applicable)      external inspection


                                   Our Area's Performance Measures that contribute to the Service/Corporate Priorities
A7          Identification and development Local      Strategies produced         Implementation of      N/A         N/A        0          0            2               2
            of local strategies                                                   Area specific
                                                                                  initiatives
A8          Support to voluntary and         Local    Audits produced/Networks    No. of Voluntary/      N/A         N/A        0          0            2               0
            community sector                          established                 Community groups
                                                                                  and Businesses
                                                                                  engaged - survey
                                                                                  network
A9          STREETSCENE: Maintain      Local • Litter                             Local grades A - D - N/A           N/A        N/A        N/A                 90% of
                                                                                                                                                        85% of the
            core minimum standards     (Grade • Detritus                           measured by                                                          area   the area
                                       s A - D) • Graffiti                        survey/inspection                                                     meetingmeeting
                                                • Flyposting                                                                                                   the
                                                                                                                                                        the agreed
                                                • Grass                                                                                                 core   agreed
                                                • Shrub / Flower beds                                                                                   minimumcore
                                                • Trees                                                                                                        minimum
                                                                                                                                                        standard
                                                • Sport grounds                                                                                                standard
A10         STREETSCENE: Promote and Local Number of Community                    No's trained,          N/A         N/A        25        50        75 trained 80
            develop Community Surveyor          Surveyors identified and          survey returns                                trained   trained   70%        trained
            role                                trained                                                                         70%       70%       conducting 70%
                                                                                                                                conductin conductin surveys    conductin
                                                                                                                                g surveys g surveys            g surveys

A11         STREETSCENE: Create              Local    Production of cashable and Efficiency returns      N/A         N/A        N/A        N/A          Identificatio   Identificati
            efficiencies                              non-cashable efficiency                                                                           n of 2%         on of 2%
                                                      savings to be reinvested                                                                          efficiency      efficiency
                                                      into service delivery                                                                             saving          saving




      ADP Template 2007-08 (v01)
                                                                                                                                                                  Hull City Council




5a. ADP: MEASURING SUCCESS (Service/Corporate Priorities)
Area Name:            Northern

                                                             MEASURING                       SUCCESS
       *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local           Using: LAA // Customer Promises (CuP) // Partnership // Statutory
  Area           Our Priority or Activity   Type of Performance Indicator           Method of Measuring    Benchmark    Annual     Latest        Target        Target     Target
 Priority                                     PI*   Description                       e.g. calculation,                 2005/06   Forecast       2006/7        2007/8     2008/9
 Ref. No.                                           (include core minimum            survey, feedback,                            2006/07
                                                    standard, if applicable)         external inspection


                                  Our Area's Performance Measures that contribute to the Service/Corporate Priorities
A12         STREETSCENE: Restructure Local           Response time to service       CSC/customer           N/A         N/A        N/A        N/A          Decrease      Decrease
            local service delivery                   requests                       feedback                                                              by 2%         by 2%
A13         STREETSCENE: Deliver within Local        Documented efficiencies        Efficiency returns,    N/A         N/A        N/A        N/A          Annual        Annual
            budget                                   generated and re-invested      end of year budget                                                    spend         spend
                                                     into service delivery          figures                                                               within        within
                                                                                                                                                          budget        budget
A14         COMMUNITY SAFETY:               PSA      Overall reduction of 30%       Police data and        N/A         3,928                 3,800        2,914
            Common Tasking and                       across the ten comparator      Home Office
            Reduction in BCS Comparator              crimes within three years      IQUANTA website
            crimes                                   using 2003/4 baseline
                                                     (4,612), finishing 2007/8
                                            PSA      Reduction of 30% in cases      Police data and        N/A         1,388                 1,300        991
                                                     of criminal damage from        Home Office
                                                     2003/4 baseline                IQUANTA website
                                            PSA      Reduction of 40% in cases      Police data and        N/A         654                   580          333
                                                     of theft from a vehicle from   Home Office
                                                     2003/4 baseline (555)          IQUANTA website
                                            PSA      Reduction of 35% in cases      Police data and        N/A         415                   530          380
                                                     of domestic burglary from      Home Office
                                                     2003/4 baseline (585)          IQUANTA website
                                            PSA      Reduction of 30% in cases      Police data and        N/A         629                   600          382
                                                     of wounding from 2003/4        Home Office
                                                     baseline                       IQUANTA website
                                            Local    Area Tasking meetings          Minutes of Tasking     N/A         N/A        5          5            20            20
                                                                                    meetings
                                            Local    Ward Tasking meetings          Minutes of Tasking     N/A         N/A        5          5            25            25
                                                                                    meetings




      ADP Template 2007-08 (v01)
            Reduction in BCS Comparator
            crimes

                                                                                                                                                                Hull City Council




5a. ADP: MEASURING SUCCESS (Service/Corporate Priorities)
Area Name:            Northern

                                                             MEASURING                     SUCCESS
       *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local         Using: LAA // Customer Promises (CuP) // Partnership // Statutory
  Area           Our Priority or Activity   Type of Performance Indicator         Method of Measuring    Benchmark    Annual     Latest        Target        Target     Target
 Priority                                     PI*   Description                     e.g. calculation,                 2005/06   Forecast       2006/7        2007/8     2008/9
 Ref. No.                                           (include core minimum          survey, feedback,                            2006/07
                                                    standard, if applicable)       external inspection


                                  Our Area's Performance Measures that contribute to the Service/Corporate Priorities
                                            Local    Number of SARA packages Calculation                 N/A         N/A        9          9            20            20
                                                     developed
A15         COMMUNITY SAFETY:               Local    Number of Area & Ward    Calculation                N/A         N/A        3          3            15            15
            Establish Area Community                 Community Safety
            Safety Consultation                      Consultation events held
            arrangements
A16         COMMUNITY SAFETY:               Local    Number of residents feeling Survey                  N/A         N/A        N/A        N/A          N/A           N/A
            Increase number of people                their neighbourhood is a
            considering neighbourhood                safe place to live
            safe
A17         HOUSING: Integrated service,    CPA   Proportion of local authority   Calculation                        N/A        97.84%     98.20%       98.30%        98.45%
            compliance with management      H6    rent collected
            agreement                       Local Current rent arrears as a       Calculation                        N/A
                                                  proportion of rent roll
                                            BV66b % tenants with over 7           Calculation                        N/A        3.98%      4.10%        3.90%         3.80%
                                                  weeks rent arrears
                                            BV66c % tenants in arrears who        Calculation                        N/A        33.66%     37%          31%           29.00%
                                                  have had Notices Seeking
                                                  Possession served
                                            BV66d % tenants evicted as a          Calculation                        N/A        0.78%      0.90%        0.58%         0.48%
                                                  result of rent arrears
A18         HOUSING: Area Housing           Local Record of informed              Board minutes                      N/A        N/A        N/A          100% of all 100.00%
            Boards                                decisions based on                                                                                    decisions
                                                  professional and accurate                                                                             made in
                                                  reports                                                                                               receipt of
                                                                                                                                                        all
                                                                                                                                                        requested
                                                                                                                                                        information




      ADP Template 2007-08 (v01)
                                                                                                                                                                Hull City Council




5a. ADP: MEASURING SUCCESS (Service/Corporate Priorities)
Area Name:            Northern

                                                             MEASURING                      SUCCESS
       *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local          Using: LAA // Customer Promises (CuP) // Partnership // Statutory
  Area           Our Priority or Activity   Type of Performance Indicator          Method of Measuring    Benchmark    Annual     Latest        Target       Target        Target
 Priority                                     PI*   Description                      e.g. calculation,                 2005/06   Forecast       2006/7       2007/8        2008/9
 Ref. No.                                           (include core minimum           survey, feedback,                            2006/07
                                                    standard, if applicable)        external inspection


                                  Our Area's Performance Measures that contribute to the Service/Corporate Priorities
A19         HOUSING: Regeneration           Local    Record of identification of   Area Housing           N/A         N/A        0          0            8             8
                                                     regeneration activities       Board minutes,
                                                     needed and update on          reports to Area
                                                     progress                      Housing Board
A20         HOUSING: Home                   Local    Decrease in repair requests   Calculation            N/A         N/A        N/A        N/A          2%            2%
            improvements                                                                                                                                 decrease      decrease
                                                                                                                                                         in repair     in repair
                                                                                                                                                         requests      requests
A21         HOUSING: Resident               Local    Increase in number of      Survey                    N/A         N/A        N/A        N/A          5%            5%
            Involvement                              Northern residents on                                                                               increase in   increase
                                                     service improvement groups                                                                          no. of        in no. of
                                                                                                                                                         Northern      Northern
                                                                                                                                                         Area          Area
                                                                                                                                                         residents     residents
                                                                                                                                                         involved      involved
A22         HOUSING: Voids and relets       BV212 Average relet times (days)       Calculation                                   47         49           33            31
A23         HOUSING: Preventing /           Local Zero use of bed and              Calculation            N/A         N/A        N/A        N/A          10%           10%
            responding to homelessness            breakfast and 10%                                                                                      decrease      decrease
                                                  decrease of Northern Area                                                                              in            in
                                                  residents presenting as                                                                                homelessn     homeless
                                                  Homeless                                                                                               ess           ness
                                                                                                                                                         presentatio   presentati
                                                                                                                                                         ns            ons
A24         HOUSING: Customer               Local    Service improvements          Customer feedback N/A              N/A        N/A        N/A          5 Service     7 Service
            involvement                              evidenced by analysis of                                                                            improveme     improvem
                                                     local need                                                                                          nts           ents
                                                                                                                                                         proposed      proposed
                                                                                                                                                         by AHB        by AHB




      ADP Template 2007-08 (v01)
                                                                                                                                                        Hull City Council




5a. ADP: MEASURING SUCCESS (Service/Corporate Priorities)
Area Name:            Northern

                                                             MEASURING                     SUCCESS
       *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local         Using: LAA // Customer Promises (CuP) // Partnership // Statutory
  Area           Our Priority or Activity   Type of Performance Indicator         Method of Measuring    Benchmark    Annual     Latest     Target   Target     Target
 Priority                                     PI*   Description                     e.g. calculation,                 2005/06   Forecast    2006/7   2007/8     2008/9
 Ref. No.                                           (include core minimum          survey, feedback,                            2006/07
                                                    standard, if applicable)       external inspection


                                  Our Area's Performance Measures that contribute to the Service/Corporate Priorities
A25         HOUSING: Value for Money        Local    Cost per property analysis   Financial analysis     N/A         N/A        N/A        N/A




      ADP Template 2007-08 (v01)
                                                                                                                                                        Hull City Council




5c. ADP: MEASURING SUCCESS (Other Statutory Measures)

Area Name
                                                             MEASURING                       SUCCESS
       *Type of PI (multiple coding allowed):- CPA // BV // Corporate // Local           Using: LAA // Customer Promises (CuP) // Partnership // Statutory

                                                        Performance Indicator      Method of Measuring
 Area                                        Type     Description                    e.g. calculation,                           Latest
Priority                                        of      (include core minimum       survey, feedback,                 Annual    Forecast   Target   Target     Target
Ref. No.        Our Priority or Activity        PI*     standard, if applicable)    external inspection   Benchmark   2005/06   2006/07    2006/7   2007/8     2008/9
                                           Our Area's Performance Measures relating to Other Statutory Measures
OS-1                                         BV199
OS-2
OS-3
OS-4
OS-5
OS-6
OS-7




    ADP Template 2007-08 (v01)
                                                                                                                                                          Hull City Council




6. ADP: OUR AREA RISKS

Area Name: Northern

                                                             RISK              MANAGEMENT
                                    (For each priority, describe your major risks and how they are being managed)
Service /   Area    Risk   Risk Description (People, Assets, IT etc.)      Impact x                        Mitigating Action                           Risk Owner
Corporat Priority   No.                                                    Likelihood
e Priority Ref. No.
Ref.

          A1      1        LSP do not support the format/content        3x1             Template for ACPs agreed with LSP Working group           Area Director
                           within the Area Plan                                         created including LSP representatives to oversee
                                                                                        development of Area Plan
          A1      2        ACP is not used to inform partner activity   3x1             Partnership agreement being developed.                    Deputy Area Director
                                                                                        Engagement strategy and plan in development
          A2      3        Partners do not commit to delivering on       2x2            Partnership agreement being developed                     Deputy Area Director
                           priorities within the ACP
          A3      4        Evaluation identifies issues with delivery at 2x3            Further development of delivery plans based on input      Neighbourhood
                           the local level                                              from Northern Area Neighbourhood Management               Manager
                                                                                        Panel and resident survey
          A3      5        Timescales for roll out lead to reduced      2x3             Roll out is phased by service, Environmental issues
                           standard of service                                          and Community Safety first
          A4      5        Community do not engage in the Area          2x1             Partners to carry out joint engagement activity in line   Deputy Area Director
                           Partnership Mechanism                                        with the priorities agreed within the Area Engagement
                                                                                        Strategy.
          A5      6        Contribution to Community Stategy targets 2x3                Project team working to establish area contribution to    Area Director
                           unclear                                                      Community Strategy targets
          A5      7        Baseline data is unavailable/incorrect    2x3                Project team currently assessing appropriate IT           Area Director
                           leading to difficulty assessing actual                       systems for collection and collation of data
                           performance at an area level




    ADP Template 2007-08 (v01)
                                                                                                                                            Hull City Council




     A6      8      Timescales for migrating additional             4x3   Assessment of lessons learned from current                Area Director
                    services cannot be met                                migration. Development of migration checklist.
                                                                          Appointment of leads from within area teams on each
                                                                          service area. Support from LSD project team.
     A6      9      Level of service drops during migration         4x3   Transitional arrangements implemented to ensure           Area Manager
                    period                                                effective handover of arrangements
     A7      10     Local strategies do not reflect/contribute to   1x3   All local strategies to benefit from input from the       Area Director
                    citywide stategies                                    department responsible for the citywide stategy
     A8      11     Audits highlights support needs we are          1x2   Partners to reassess the support they are able to offer   Area Director
                    unable to meet                                        in line with audit results
     A9      12     Core minimum service standards not met          3x2   Regular review of performance against standards and       Area Manager
                                                                          implementation of any remedial action necessary

     A10     13     Lack of resident interest in Community          3x2   Quality marketing and promotion of the role and           Area Manager
                    Surveyor opportunities                                provision of regular training programmes
     A11     14     Long term efficiences overshadowed by           2x3   Short term expense recorded against long term             Area Manager
                    short term expense                                    benefits. Regular communication with Finance and
                                                                          Members
     A12     15     Union disagreement to seven day working 4x4           Early negotiations and regular communications with        Area Manager
                    week                                                  Union officials and Personnel
     A13     17     Area budget not sufficient for delivery of 4x2        Core standards costed to identify local budgetary         Area Manager
                    core minimum standards                                constraints. Budget profile for the year to be
                                                                          developed.
     A14     18     Community Safety:                               2x3

                    *Failure to obtain the commitment of                  Area Partnership arrangements supported by the Area Area Manager
                    Partners to work in partnership with the              Committee and local partners.
                    Area Community Safety Team.
                    *Failure to agree a formal process for
                    linking with the Area Partnership
                                                                          Multi agency working at the Area level has resulted in
                    structures/mechanisms.
                                                                          positive actions in addressing local priorities. The
                    *Lack of resources to support the
                                                                          same partners will play a key role in the proposed
                    Community Safety Engagement &
                                                                          Common Tasking arrangements.
                    Participation events and poor engagement
                    by Partners.




ADP Template 2007-08 (v01)
                                                                                                                                      Hull City Council




                    *Partners failing to accept ownership of
                    issues raised through the Area Common
                    Tasking arranagements.
                    *Partners, including the Area ASB                 Tasking actions arising from the Area multi-agency
                    Enforcement Team and the                          meetings are monitored by the Area Director.
                    Neighbourhood Wardens, not directing
                    resources to address identified Area
                    priorities.
     A15     19     As A14
     A16     20     Residents' perceptions reduce               3X2   Delivery of P14/15 above, positive publicity campaign   Deputy Area Director
     A17     21     Landlord Service not fully integrated       4X1   Locate Area Manager with Area Team. Joint events        Area Manager
                                                                      with migrated staff training
     A18     22     Area Housing Board makes unreasonable       3x2   Regular communication of resource pressures to the      Area Manager
                    requests on resource                              Board
     A19     23     Funding not available to regenerate areas   4x4   Alternative external funding options to be identified   Area Manager
                    once identified as in need
     A20     24     Contractor unwilling to engage or work to   4x1   Check contract specifications and requirements          Area Manager
                    a proactive approach
     A21     25     Residents unwilling to engage in service    4x2   Promote wider ownership and empowerment of              Area Manager
                    improvement                                       residents and market opportunities
     A22     26     Homesearch and Voids Team unable to         4x3   Raise with Housing Services and Performance             Area Manager
                    complete activities on time                       Manager
     A23     27     Homelessness Section unable to              4x3   Raise with Housing Services and Performance             Area Manager
                    complete activities on time                       Manager
     A24     28     Customer feedback does not highlight        2x2   Use of service improvement groups, Ward Forums,         Area Manager
                    improvements to benefit local need                CSC to generate targeted feedback
     A25     29     Cost of Area delivery increases in the      4x3   Budget pressures raised with Housing Services and       Area Manager
                    short term following migration                    Performance Manager




ADP Template 2007-08 (v01)
                                                                                                           Hull City Council



  7. ADP: Sign-Off Proforma

                                                        Hull City Council
                                          Area Delivery Plan 2007-08
                                                    Version: v01 (05 March 2006)


                                                    Northern Area

                                        Read, Approved and Signed By:-

  Area Director: Alastair Shaw


  Signed:                                                                          Date: xxxxxxxxxxxxxxx




  Head of Service: Stuart Davy


  Signed:                                                                          Date: xxxxxxxxxxxxxxx




  Area Committee Chair: Councillor Korczak Fields


  Signed:                                                                          Date: xxxxxxxxxxxxxxx




ADP Template 2007-08 (v01)

				