                             Stage: Acceptance

                         Deployment Checklist



       Windows Web Hosting Consolidation

                          PROGRAMME NAME - Web Hosting

                                 PROJECT CODE - APS004

                            ANNUAL PLAN NUMBER - 78-503




                       Document Version: [1.0]

                                 Date: [25/08/09]


___________________________________________________________________________________

                         Information Services - Template Revised May 2009
Acceptance: Deployment Checklist                                                 Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________




Contents

1      DOCUMENT MANAGEMENT .................................................................. 3
1.1       Contributors ..................................................................................................... 3
1.2       Version Control ................................................................................................ 3

2      DEPLOYMENT ......................................................................................... 4
2.1     Deployment Strategy ....................................................................................... 4
2.2     Dependencies .................................................................................................... 4
2.3     Communication ................................................................................................ 4
2.4     Technical Issues................................................................................................ 4
2.5     Deployment Checklist ...................................................................................... 6
  2.5.1     Application Checklist................................................................................. 6
  2.5.2     Infrastructure Checklist .............................................................................. 8
  2.5.3     Support Checklist ....................................................................................... 9

3      TRAINING .............................................................................................. 11




___________________________________________________________________________________

                                                      Page 2 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

1 Document Management


1.1 Contributors
Please provide details of all contributors to this document.

Role                 Unit                     Name
Production           Application              Hugh Brown
Management           Management
Coordinator
(Owner)
Project Manager      Project Services         Nikki Stuart
Business             N/A                      N/A
Analyst
Systems Analyst      N/A                      N/A
Designer
Technical            Development              Pride Shoniwa
Architect            Technology               Iain Fiddes
Business Area        Service                  Anne-Marie Scott
Manager              Management               Jason Coleman
Other document
contributors



1.2 Version Control
Please document all changes made to this document since initial distribution.

Date        Version        Author      Section       Amendment
31/08/09    1.0            H Brown




___________________________________________________________________________________

                                             Page 3 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

2 DEPLOYMENT
The deployment of a new system or enhancement to an existing one is a significant milestone
in the delivery of the project. It is critical however that the deployment is achieved successfully
with minimal disruption to current production services. To try to ensure this it is essential that
adequate preparation take place. This Deployment Checklist highlights the key elements
that need to be in place before the project deliverables can be accepted for deployment via
the Acceptance Sign Off Review.


2.1 Deployment Strategy

        Proposed deployment date:
                               st
         Initial deployment 31 August 2009 followed by phased migration of web sites from
         existing servers.
        User groups involved:
         All web hosting customers on servers IISWEB1 and Spike
         Reasoning for selection:
         Required for decommissioning of existing servers.
        Staged rollouts:
         Initially Law websites migrated from server IISWEB1 followed by phased migration of
         web sites from servers IISWEB1 and Spike plus provisioning of new sites as required.
        Assessment of risk to existing services and measures to mitigate these:
         None – All migrated sites will be UAT tested prior to removal of existing sites.
        Post deployment actions:
         De-commissioning of servers IISWEB1 and Spike.



2.2 Dependencies
Please identify any dependencies that could impact the deployment strategy.

It has been agreed that ColdFusion sites will not be migrated or created until the outstanding
ColdFusion 8 – 8 migration utility issue has been resolved.



2.3 Communication

Scheduling of existing site migration and customer communication will be performed
by the Service Management team on a site-by-site basis.



2.4 Technical Issues

Please revisit the Implementation Plan and note any additional issues for deployment that
may need to be addresses before sign-off is possible.

Given the demand for urgent implementation required to mitigate support issues for the
current servers the following has been agreed:

Live implementation can proceed, but no ColdFusion sites will be migrated or created until the
outstanding ColdFusion 8-8 synchronisation issue is resolved.


___________________________________________________________________________________

                                             Page 4 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

All remaining activities detailed below will be completed in parallel with the initial site
migrations




___________________________________________________________________________________

                                             Page 5 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________



2.5 Deployment Checklist
Please use this checklist to ensure that required actions have been complete. Please provide
links to any relevant documentation.


2.5.1 Application Checklist

       Area                        Description                  Mandatory        Reviewed           Actions
                                                                  [Y/N]         (Date/Pers        (What/Who)
                                                                                    on)
Implementation         Feedback from previous test                    Y         31/08/09
Plan                   implementations completed and                            H Brown
                       successful full implementation
                       undertaken for UAT

                       ColdFusion Synchronisation:
                       http://www.projects.ed.ac.uk/area
                       s/itservices/integrated/APS004/se
                       cure/Implementation_Plan.doc

                       IIS
                       K:\mis\dsg\Projects\APS004\Proc                                         Documents
                       edures\Migrating IIS sites                                              require details of
                       procedures.doc                                                          actual MSDeploy
                                                                                               and Robotcopy
                       K:\mis\dsg\Projects\APS004\Proc                                         command lines,
                       edures\Synchronising the IIS                                            paths to calling
                       webservers.doc                                                          batch files and
                                                                                               frequency of
                                                                                               execution

System Support         Ensure SSD completed and                       Y         27/08/09       An additional
Document(SSD)          accurate.                                                H Brown        support
                                                                                               requirement is
                       http://www.projects.ed.ac.uk/area                                       the provision of
                       s/itservices/integrated/APS004/se                                       automated
                       cure/APS004_Service_document                                            reporting of
                       ation.doc                                                               failure of
                                                                                               Robocopy or IIS
                                                                                               Synchronisation.

Technical              Appropriate documentation has                  Y         31/08/09
Documentation          been produced for use by staff                           H Brown
                       providing technical support for the
                       new application.
                       Detailed in TAD
                       http://www.projects.ed.ac.uk/area
                       s/itservices/integrated/APS004/se
                       cure/APS004%20Technical_Archi
                       tecture%20v1.1.doc


Scalability/Load       Adequate load testing has taken                Y                        Pending
Testing                place and results recorded.                                             completion of
                                                                                               UAT
                                                                                               documentation

___________________________________________________________________________________

                                             Page 6 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

       Area                        Description                  Mandatory        Reviewed           Actions
                                                                  [Y/N]         (Date/Pers        (What/Who)
                                                                                   on)
Performance            The application has been tested                Y                        Pending
                       against stated performance                                              completion of
                       criteria. Performance has been                                          UAT
                       assured by user and support staff                                       documentation
                       testing.
Source Code            Source code has been secured                   Y         N/A
                       with VSS or other SCM

                       CFSynchronisation source code
                       in VSS under “ColdFusion
                       ServerSynchronisation”
Configuration          The relevant details regarding                 Y
Management             new or changed infrastructure
Database               components have been added to
                       the configuration management
                       database ( Change Control
                       System)

Change Control         A change control entry has been                Y         Agreed as
                       created for the LIVE                                     N/A for this
                       implementation. The person who                           project by
                       reviews this Deployment                                  project
                       Checklist will approve the change                        team
                       control request.
Test Log Review        A review of the test log has taken             Y                        Pending
                       place to ensure all required                                            completion of
                       actions have been completed. If                                         UAT
                       this is not the case, then                                              documentation
                       confirmation on criticality of
                       outstanding issues and action
                       plan for resolution is required.

Production             Handover to Production                         Y         28/08/09
Management             Management is completed and                              Confirmed
Handover               the team are in are in position to                       by J
                       support the application post                             McFarlane
                       deployment.

Implementation         A risk assessment has been                     Y         N/A as new
Risk Assessment        undertaken for the                                       server is
                       Implementation Plan and selected                         overlay.
                       deployment dates. (e.g. roll back)

Accounts               Setup Read access accounts or                  Y         N/A
                       update current read access
                       accounts
                       (May requires business owner
                       approval)
InfoKeep               InfoKeep has been updated with                 Y         28/08/09
                       all relevant account details                             Confirmed
                       including external supplier                              at project
                       accounts                                                 meeting.
Environment            Database comparison between                   N          N/A
comparison             TEST and LIVE (might be
                       required before and after go-live)


___________________________________________________________________________________

                                             Page 7 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

       Area                        Description                  Mandatory        Reviewed           Actions
                                                                  [Y/N]         (Date/Pers        (What/Who)
                                                                                    on)
Client                 Does the application have                      Y         N/A
requirements           specific client requirements, such
                       as JVM/JRE versions, JInitiator?




2.5.2 Infrastructure Checklist

       Area                        Description                  Mandatory        Reviewed           Actions
                                                                  [Y/N]         (Date/Pers        (What/Who)
                                                                                    on)
Technical              Documentation complete and                     Y         31/08/09
Architecture           accurately reflects the                                  H Brown
Document(TAD)          environment subjected to UAT.

Security               All security requirements, e.g.                Y         28/08/09
                       SSL encryption, IP based                                 SSL
                       restrictions firewall requirements                       certificates
                       have been specified, tested and                          and Cosign
                       implemented in LIVE                                      Installation
                                                                                confirmed
                                                                                at project
                                                                                meeting.
SSL Certificates       All changes to certificates or new             Y
                       certificates for this service have to
                       be added to the certificate master
                       list. The certificate master list is
                       being managed by Applications
                       Management This includes TEST
                       and LIVE certificates.
Asset Register         Details of any new hardware                    Y
                       acquired as part of the project
                       have been recorded in the Asset
                       Register




___________________________________________________________________________________

                                             Page 8 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________



2.5.3 Support Checklist

       Area                        Description                  Mandatory        Reviewed           Actions
                                                                  [Y/N]         (Date/Pers        (What/Who)
                                                                                    on)
Support                A support agreement is in place                Y         Existing
Agreement              for any new applications –                               OLE
(including any         including any hosting or support
charging               charges.
arrangements)

Time Recording         A Time Recording code for the                  Y         N/A
Code                   application, if required, has been                       Code
                       confirmed and set up.                                    exists.

Backup and             All backups as noted in the TAD                Y         Standard       Ongoing query
Recovery               need to be confirmed operational.                        IS-            regarding system
                       A test recovery of user data                             Architect-     state pending.
                       needs to be done to validate the                         ure team
                       integrity of the recovery                                backup.
                       mechanism and process.
Disaster Recovery      Appropriate DR/BC provision is in              Y         DR/BC          Pending
and Business           place and has been fully tested.                         covered by     completion of
Continuity             Application DR/BC details have                           server         UAT
                       been transferred to the DR                               resience
                       Portfolio.

Hardware and           All required licensing is in place             Y         Standard
Software Licensing     including maintenance/support                            IS-
                       arrangements with external                               Architect-
                       suppliers.                                               ure team
                                                                                support
Browser                Browser compatibility has been                 Y         N/A
Compatibility          tested and compatibility
                       information updated
                       See
                       http://www.ucs.ed.ac.uk/ucsinfo/b
                       rowsercompat.html for details
Portal                 Portal compatibility, where                    Y         N/A
Compatibility          required, has been confirmed the
                       Portals Service Owner.

Help Desk              The new application is recognised              Y         Existing
                       with the CMS Help Desk (A                                service
                       business contact queue is defined
                       where initial calls are raised with)

PICCL Review           Review of the PICCL has taken                  Y
                       place to ensure that there are no
                       outstanding issues that would
                       affect deployment

User Guide             Appropriate documentation has                  Y         Existing
Documentation          been produced for users of the                           hosting
                       new application.                                         documenta
                                                                                -ion



___________________________________________________________________________________

                                             Page 9 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

       Area                        Description                  Mandatory        Reviewed           Actions
                                                                  [Y/N]         (Date/Pers        (What/Who)
                                                                                    on)
Training Material      Training material, if required, has           N          N/A
                       been produced and is of an
                       appropriate standard.

Demonstration or       Demonstration or walkthrough of               N          N/A
Walkthrough            the new application has taken
                       place for other stakeholder.

Deployment Date        Agreed date has been confirmed                 Y         31/08/09       Date agreed with
                       that allows adequate time for                            H Brown        Production
                       completion of Acceptance Sign                                           management
                       Off Review.                                                             subject to parallel
                                                                                               completion of
                                                                                               outstanding
                                                                                               activities.
Deployment             IS and business area resources                 Y         Dev-Tech
Resources              required for deployment, including                       resources
                       those needed for post                                    arranged
                       implementation checking and sign                         for
                       off have been secured.                                   deployment
                                                                                and site
                                                                                migration
Service                Draft service announcements                    Y         Agreed N/A
Announcement           have been created with the                               by project
                       agreed deployment dates.                                 team

Web Sites and          External and internal web site                 Y         N/A
Other Document         have been reviewed to ensure
Sources                that all application references are
                       present, correct and up to date.
Deployment             Setup Read access accounts or                  Y         N/A
Resources              update current read access
                       accounts
                       (requires business owner
                       approval)




___________________________________________________________________________________

                                             Page 10 of 11
Acceptance: Deployment Checklist                                   Windows Web Hosting Consolidation
[Version: 1.0]
_______________________________________________________________________________________________________

3 TRAINING

Please detail how the training will be delivered, including the following:

Project involves replacement/upgrade of existing servers. No specific training is required.
Familiarisation of Technology Management representatives has occurred by involvement in
the initial testing and example site migration.




___________________________________________________________________________________

                                             Page 11 of 11

								