Dear Market Participants and Interested Parties:

Re:    Letter of Notice – Proposed Level II Changes to Existing OPP 003.2, OPP
       301, OPP 310, OPP 312, OPP 702, OPP 704 and Proposed LIII Changes to
       Existing OPP 302

Pursuant to Section 2(1) of the Alberta Utilities Commission (“Commission”) Rule 017,
the Alberta Electric System Operator (AESO) is providing notice and seeking feedback
on OPP Rule changes that are being considered for recommendation to the AESO
Executive Rules Committee (“ERC”) in April 2009.

For your consideration, attached are the proposed OPP Rule changes. If you are
interested in a particular OPP Rule, the following grid is hyperlinked to provide
assistance in directing you to the OPP Rule of interest.

 Rule Number Description                           Level   Most relevant stakeholder
                                                           interest
 OPP 003.2         Automated Dispatch and            II    All Market Participants
                   Messaging System
                   (ADAMS)
 OPP 301           Alberta-BC Interconnection        II    GFOs, TFOs, PPA Buyers, Wire
                   Scheduling                              Owners, load customers and
                                                           Market Participants on the
                                                           Alberta-BC Interconnection
 OPP 310           Alberta-Saskatchewan              II    GFOs, TFOs, PPA Buyers, Wire
                   Interchange Verifications               Owners, load customers and
                                                           Market Participants on the
                                                           Alberta-Saskatchewan
                                                           Interconnection
 OPP 312           Import Load Remedial              II    TFOs, ILRAS Service Provider,
                   Action Scheme (ILRAS) and               LSS Service Provider, load
                   Load Shed Service (LSS)                 customers and Market Participants
                                                           on the Alberta-BC Interconnection
 OPP 702           Voltage Control                   II    GFOs, TFOs and PPA Buyers
 OPP 704           Remedial Action Scheme            II    AESO - Confidential
 OPP 302           Alberta-Saskatchewan             III    GFOs, TFOs, PPA Buyers, Wire
                   Interconnection Scheduling              Owners, load customers and
                                                           Market Participants on the
                                                           Alberta-Saskatchewan
                                                           Interconnection
Please see the attached summaries for more information on these proposed OPP Rule
changes, including a brief explanation of the reason for the change.

Comments and suggestions on the OPP Rule changes being proposed are encouraged.
Please use the comment matrix provided when submitting comments to the AESO on the
proposed OPP Rule changes. Click here to access the comment matrix for the proposed
OPP Rule changes. Only written comments will be considered in finalizing the OPP Rule
changes.

Please provide feedback or questions by Friday, February 27, 2009 to the individual
specified within the OPP Rule change description below.

The AESO will be publishing all stakeholder comments received for industry review
shortly after the comment deadline. Stakeholder comments received along with AESO
responses will be published with the final proposed OPP Rule changes being submitted to
the ERC for approval in April 2009.

Yours sincerely,

Original Signed By

Paul Glatthor
Senior Coordinator, Rules
Ph: (403) 539-2464
E-mail: paul.glatthor@aeso.ca
                                       Proposed LEVEL II ISO Rule Changes
Level II changes are changes that are expected to have a moderate or low impact on the industry or the ISO, and generally require
little or no effort by stakeholders for implementing a solution. They are provided to stakeholders to review to ensure that the expected
impact is reasonable, to identify unrealized impacts and/or to provide notice of the potential change in administrative processes.

                    OPP 003.2 Automated Dispatch and Messaging System (ADAMS)

Rule Section/Number                                                  Part 3, OPP 003.2 Automated Dispatch and Messaging System
                                                                     (ADAMS)
Summary of ISO Rule                                                  OPP 003.2 specifies the automated dispatch and messaging
                                                                     system standards for pool participants who receive energy market
                                                                     dispatches, ancillary services dispatches and/or ancillary services
                                                                     directives. Additionally, the automated dispatch and messaging
                                                                     system will be used to notify participants of firm load alerts and
                                                                     energy market suspensions.

Summary of Amendment                                                 Proposed amendments to OPP 003.2 are required to delete the
                                                                     ADAMS workstation requirements in Table 2.

Level                                                                II

Explanation of Confidentiality                                       None

Proposed Effective Date                                              May 21, 2009

AESO Contact                                                         Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
                                                                     (403) 539-2497



                                                                                                                                 3
Attachments   See attached – blacklined version.
              OPP003.2DRAFT2 - blacklined

              See attached – clean version.
              OPP003.2DRAFT2 - clean




                                                   4
                                 OPP 301 Alberta-BC Interconnection Scheduling

Rule Section/Number                                     Part 3, OPP 301 Alberta-BC Interconnection Scheduling
Summary of ISO Rule                                     OPP 301 defines define the policies and procedures to be
                                                        followed by the system controller (SC) when scheduling
                                                        interchange transactions on the Alberta-BC interconnection.

Summary of Amendment                                    Proposed amendments to OPP 301 are required to change the cut
                                                        off time for British Columbia Transmission Corporation (BCTC)
                                                        to apply their cut order, from the current hh:40 to hh:45, to allow
                                                        more time for the SC to apply the Alberta cut order if required.

Level                                                   II

Explanation of Confidentiality                          None

Proposed Effective Date                                 May 21, 2009

AESO Contact                                            Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
                                                        (403) 539-2497
Attachments                                             See attached – blacklined version.
                                                        OPP301DRAFT2 - blacklined

                                                        See attached – clean version.
                                                        OPP301DRAFT2 - clean




                                                                                                                    5
                          OPP 310 Alberta-Saskatchewan Interchange Verifications

Rule Section/Number                                  Part 3, OPP 310 Alberta-Saskatchewan Interchange Verifications
Summary of ISO Rule                                  OPP 310 defines the policies and procedures for the system
                                                     controller (SC) in verifying scheduled interchange and actual
                                                     interchange with the Saskatchewan control area. The verifications
                                                     apply to previous hours when interchange has taken place. The
                                                     real time interchange scheduling procedure is covered in OPP
                                                     302.

Summary of Amendment                                 Proposed amendments to OPP 310 are required to update the
                                                     verification process in accordance with the current practice with
                                                     SaskPower.

Level                                                II
Explanation of Confidentiality                       None

Proposed Effective Date                              May 21, 2009

AESO Contact                                         Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
                                                     (403) 539-2497
Attachments                                          See attached – blacklined version.
                                                     OPP310DRAFT2 - blacklined

                                                     See attached – clean version.
                                                     OPP310DRAFT2 - clean




                                                                                                                6
     OPP 312 Import Load Remedial Action Scheme (ILRAS) and Load Shed Service (LSS)

Rule Section/Number                         Part 3, OPP 312 Import Load Remedial Action Scheme (ILRAS)
                                            and Load Shed Service (LSS)
Summary of ISO Rule                         OPP 312 defines the policies and procedures for the system
                                            controller (SC) in the application of ILRAS and the LSS, in order
                                            to facilitate increased import capability on the Alberta-BC
                                            interconnection for energy and reserve services.

Summary of Amendment                        Proposed amendments to OPP 312 are required to change
                                            Canexus LSS volume reduced from 31 MW to 20 MW and
                                            ERCO to zero MW.

Level                                       II

Explanation of Confidentiality              OPP 312 has a confidential appendix that contains LSS providers
                                            contact information (i.e. telephone numbers). No change is
                                            proposed to the confidential appendix.

                                            The AESO will not be requesting the Commission confirm that
                                            disclosure of confidential appendix to the OPP Rule would not be
                                            in the public interest as this has previously been confirmed by the
                                            Commission.
Proposed Effective Date                     May 21, 2009




                                                                                                        7
AESO Contact   Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
               (403) 539-2497
Attachments    See attached – blacklined version.
               OPP312DRAFT2 - blacklined

               See attached – clean version.
               OPP312DRAFT2 - clean




                                                                        8
                                 OPP 702 Voltage Control

Rule Section/Number                          Part 3, OPP 702 Voltage Control
Summary of ISO Rule                          OPP 702 provide consistent voltage control guidelines for the
                                             Alberta Interconnected Electric System (AIES) and operating
                                             policy for all parties concerned with voltage control, including the
                                             transmission facility owners (TFOs), generation facility owners
                                             (GFOs) and the system controller (SC).

Summary of Amendment                         Proposed amendments to OPP 702 are required to reflect SVC
                                             additions, and revised voltage limits in the northwest area.

Level                                        II

Explanation of Confidentiality               None

Proposed Effective Date                      May 21, 2009

AESO Contact                                 Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
                                             (403) 539-2497
Attachments                                  See attached – blacklined version.
                                             OPP702DRAFT2 - blacklined

                                             See attached – clean version.
                                             OPP702DRAFT2 - clean




                                                                                                         9
                      OPP 704 Remedial Action Scheme

Rule Section/Number                  Part 3, OPP 704 Remedial Action Scheme
Summary of ISO Rule                  OPP 704 identifies the remedial action schemes (“RAS”) that are
                                     installed on the Alberta Interconnected Electric System (“AIES”).
                                     RAS are defined in the ISO Rules as “protection schemes
                                     designed to perform pre-planned corrective measures following a
                                     disturbance to provide for acceptable AIES performance or
                                     equipment protection”. OPP 704 identifies and provides
                                     documentation on RAS that have significant effects on the AIES.

                                     OPP 704 is specific to the RAS that apply to all transmission
                                     facility owners (TFOs), all generation facility owners (GFOs),
                                     and BCTC and the City of Medicine Hat (the “Affected
                                     Stakeholders”). The Affected Stakeholders own and operate the
                                     RAS identified in OPP 704. OPP 704 includes requirements with
                                     regard to the review, testing, monitoring and maintenance of each
                                     RAS. Further, OPP 704 also prescribes actions required by
                                     system controller (SC), if RAS are out of service, unavailable or
                                     fail to operate.

                                     As part of the OPP 002: OPP Change Management Process, all
                                     Affected Stakeholders have received those amendments to OPP
                                     704 that are applicable to them, and have been provided the
                                     opportunity to verify and comment on those part(s). Further, once
                                     the amendments to OPP 704 are in effect, these stakeholders will
                                     receive those parts of OPP 704 applicable to them and now in
                                     effect.



                                                                                               10
Summary of Amendment             Proposed amendments to OPP 704 are required to update an
                                 Alberta system RAS.

Level                            II

Explanation of Confidentiality   The RAS descriptions contained in the confidential OPP 704
                                 expose the vulnerabilities in the AIES, which, if made public,
                                 could put AIES security and reliability at risk.

                                 The AESO will be requesting that the Commission confirm that
                                 disclosure of this OPP Rule would not be in the public interest.

Proposed Effective Date          May 21, 2009

AESO Contact                     Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
                                 (403) 539-2497
Attachments                      No attachment




                                                                                            11
                                 Final Proposed LEVEL III ISO Rule Changes
        Level III changes are administrative changes that do not impact the meaning and/or implementation of the ISO Rules.

                          OPP 302 Alberta-Saskatchewan Interconnection Scheduling

Rule Section/Number                                               Part 3, OPP 302 Alberta-Saskatchewan Interconnection
                                                                  Scheduling
Summary of ISO Rule                                               OPP 302 defines the policies and procedures for the system
                                                                  controller (SC) and the policies for market participants when
                                                                  scheduling interchange transactions on the Alberta-Saskatchewan
                                                                  interconnection.

Summary of Amendment                                              Proposed amendments to OPP 302 are required to add back the
                                                                  operating policies and procedures regarding the AB-SK
                                                                  interconnection scheduling limits due to the McNeill Converter
                                                                  operating constraints. These were inadvertent left out of the
                                                                  November 13, 2008 version of OPP 302.

Level                                                             III

Explanation of Confidentiality                                    None

Proposed Effective Date                                           May 21, 2009

AESO Contact                                                      Operating Policy and Procedures, Anita Lee, anita.lee@aeso.ca,
                                                                  (403) 539-2497
Attachments                                                       See attached – blacklined version.



                                                                                                                              12
OPP302FINAL - blacklined

See attached – clean version.
OPP302FINAL - clean




                                13

								