Doka Formwork Systems - PDF

W
Description

Doka Formwork Systems document sample

Document Sample
scope of work template
							                                                                                                      US Site Review
                                                                                                              1/2004




Conesco Doka takes formwork technology
          and customer service to new levels in the US.
The Heritage at Millennium
Park, Chicago




 37th Street Theatre, New York              World of Concrete                       Metro tunnel extension in Largo, MD

 Conesco Doka helps concrete                Conesco Doka to prove its superb        Doka systems keep Maryland
 contractor in a tight situation   Page 2   formwork technology capability Page 4   metro project on track       Page 7
                        37th Street Theatre, New York


                        Conesco Doka helps concrete                                                         All of the Top 50 gangs and
                                                                                                         MF 240 platforms were pre assem-
                                                                                                         bled in Conesco Doka’s Ready-to-
                          contractor in a tight situation                                                Use pre-assembly service in Little
                                                                                                         Ferry, New Jersey and shipped to
                                                                                                         the site. At various stages of the
                        An intricate architectural concrete theatre is being constructed                 project, entire sections of form-
                        on a tight New York City site only 75 feet wide by 100 feet deep,                work were replaced with new
                        using pre assembled Top 50 gangs with MF 240 climbing brack-                     ones to accommodate the varying
                        ets, telescopic shaft beam platforms, custom steel forming                       changes in the building plan from
                        plates and both Dokaflex and 10 Kip shoring.                                     floor to floor.
                                                                                                            Accuracy in both the engineer-
                                                                                                         ing drawings and in the pre-assem-
                                                                                                         bled gangs together with perfect
                                                                                                         timing of deliveries was critical to
                                                                                                         ensure a continuous work cycle.
                                                                                                         The Theatre is 8 stories high with
                                                                                                         various openings in all of the
                                                                                                         walls. Each of the floors has a dif-
                                                                                                         ferent height. The structure is be-
                                                                                                         ing built in 18 lifts to accommodate
                                                                                                         the varying floor levels within the
                                                                                                         structure.
                                                                                                              Two of the exterior walls are
                                                                                                         being built adjacent to the existing
                                                                                                         structures with only 3” of clearance
                                                                                                         between the theatre walls and
                                                                                                         these structures. Conesco Doka fur-
                                                                                                         nished custom steel forming plates
                                                                                                         with captured tie nuts as an outside
                                                                                                         form to fit into the 3” space. Since
                                                                                                         the beginning of the project there
                                                                                                         have been numerous changes in
                                                                                                         the shape and quantity of walls.
                                                                                                            According to Peter Ruttura, Vice
                                                                                                         President of Ruttura and Sons
                                                                                                         “Being able to rely on a formwork
                                                                                                         partner with the strength, expertise
                                                                                                         and commitment to service that is a
                        The Top 50 gangs and MF 240 platforms were pre-assembled in Conesco              trademark of Conesco Doka has
                        Doka's ready-to-use service in Little Ferry, New Jersey.                         enabled us to undertake this most
                                                                                                         difficult project. We couldn’t have

                        R   uttura and Sons Construction
                            Corp of Farmingdale, New York
                        is the concrete contractor chosen
                                                                  tectural patterns were achieved in
                                                                  both placement of the plywood
                                                                  forming sheets and tie locations.
                                                                                                         done it without them.”


                        to build this complicated structure
                        known as the 37th Street Theatre,          Accuracy in the engineering draw-
                        with no room for storage.                 ings and the pre-assembled gangs,
                           Ruttura decided to use Conesco             and perfect timing of deliveries
                        Doka for this project because of our      were critical to ensure a continuous
                        engineering expertise, our knowl-            work cycle. And that work cycle
                        edge of limited clearance forming,          was carried out to perfection by a
                        our ability to provide just in time de-    highly committed formwork gang.
Formwork News 1| 2004




                        liveries of pre assembled equip-
                        ment and our expert field service.            From left to right: Tom Bruno,
                           Conesco Doka worked closely             Conesco Doka Account Manager -
                        with both the contractor and the           Paul Pereira, Carpenter Foreman -
                        architect to ensure that the final            Peter Ruttura, Vice President -
                        concrete structure met with every-         Bobby Leonard, Superintendant -
   2                    one’s expectations. Special archi-           Dave Marques, Superintendant.
                                                                                  The Heritage at Millennium Park,
                                                                                  Chicago: Conesco Doka’s Midwest
                                                                                  Branch developed a tailor-made
                                                                                  formwork concept for Walsh Con-
                                                                                  struction based on SKE automatic
                                                                                  climbers.

                                                                                  re-erection cycle down to just 1.5
                                                                                  hours - a record for any highrise
                                                                                  project Doka has been involved
                                                                                  with in the U.S.
                                                                                     Dokaflex 20 is used for all typical
                                                                                  floor slabs applications. Walsh also
                                                                                  chose 10 Kip/Leg shoring for sup-
                                                                                  port of beams, ramps, high floors
                                                                                  and the helix at the parking struc-
                                                                                  ture, and Framax framed panel
                                                                                  formwork for all retaining walls and
                                                                                  shear walls, the columns in the
                                                                                  basement level and the entire park-
                                                                                  ing structure below level 9.

                                                                                     Concrete work started on 2 Janu-

Heritage climbs                                                                   ary 2003. By year-end, the high-rise
                                                                                  tower was up to level 37 and the

         ahead of schedule
                                                                                  low-rise was almost complete.
                                                                                     Mike Hoge is the Superintendent
                                                                                  for Walsh Construction. He says,
                                                                                  "Maintaining our 3-day-cycle per
Contractors working on a 92,889m2 (1m ft2) residential develop-                   floor and considering some addi-
ment in downtown Chicago are set to complete concrete pouring                     tional time for changes in the top
operations almost three months ahead of schedule, thanks large-                   floor layouts and various heights
ly to a tailor-made formwork system supplied by Conesco Doka.                     within the upper levels of the tower
The Heritage at Millennium Park is a 190m (625 ft) tall landmark                  we should top out at this building
along the Michigan Avenue skyline. Comprising the 28-storey                       by May 2004."
Park Plaza and the 57-storey Skyline Tower, it combines a curved
glass façade and detailed exterior concrete architecture with four
existing six-storey façades built during the 1920s.


T   he structural design calls for the
    shaft walls, the floor slabs with
upturned and downturned span-
                                            The cores at the center of the
                                         structure are formed one level
                                         ahead of the slab using Doka Top50
drel beams and exterior columns to       large-area wall formwork gangs
be poured monolithically to mini-        and Doka SKE100 self-climbing
mize construction joints. In addi-       platforms. A concrete placing boom
tion, a combination of concave and       climbs together with the core
convex shapes and straight transi-       forms, delivering an uninterrupted
tion zones demands extremely ac-         supply of concrete. The four-man
curate planning.                         crew has gotten the stripping and

   To accommodate these require-         "The key to the success is the use of
ments and avoid the need to set in-       steel forms for the entire outside of
side panels by hand, Conesco Doka         the building with all reveals and de-
and the main contractor, Walsh              tails welded to the formwork pan-
Construction, together have devel-           els," says Mike Hoge, Superinten-
oped a climbing formwork system          dent (left), with Karen Latus, Project
with steel panels that open on one,       Engineer (center) and Roy Eikeland,
two and, in some places, three            General Superintendent. According
hinges. This allows the entire form-       to Roy, "We felt confident working
work unit to be rolled back and            with Conesco Doka as our forming
climb vertically without disturbing           partner that, together, we would
the freshly poured concrete.               solve all of our forming problems."
                        Conesco Doka to prove its superb formwork technology
                        capability yet again – at "World of Concrete".
                                                                                                         Equipped with the new Xlife sheet
                                                                                                         plus accessories for simple shaft
                                                                                                         formwork and extra-large panels
                                                                                                         for faster forming, Framax Xlife
                                                                                                         system provides the perfect
                                                                                                         framed-formwork solution.


                                                                                                         cause no extra fillers are needed to
                                                                                                         aid stripping. This reduces the
                                                                                                         number of wall-ties that are need-
                                                                                                         ed, and improves the quality of the
                                                                                                         concrete surface. The shaft form-
                                                                                                         work can then be repositioned as a
                                                                                                         complete system, thereby also sav-
                                                                                                         ing valuable hours of labor.

                        "Leadership in formwork technology" – this is the motto under                       Complete "all-in-one" reposition-
                        which Conesco Doka will be presenting several major innova-                      ing of large deck units is also revo-
                        tions, all aimed at making formwork assignments on the site                      lutionizing the field of floor-slab
                        even more efficient and at giving construction firms a sharper                   formwork. With its new Dokamatic
                        competitive edge.                                                                table, Conesco Doka offers a sys-
                                                                                                         tem of preassembled and standard-
                            "Increasing the durability of the      When it comes to stripping form-      ized formwork units for all areas of
                        formwork, minimizing damage to          work inside shafts, the new Framax       slab. Tableform units of up to 300
                        the form-facing, reducing the           bias cut corner I is a tremendous        sq. ft can be repositioned "in one
                        amount of cleaning needed - and         practical help. The stripping mech-      piece". The "Dokamatic" makes a
                        improving the quality of the con-       anism can be operated effortlessly       quick and easy job of adapting to
                        crete surface at the same time". It     and without any special tools. The       widely varying slab thicknesses.
                        was to satisfy exactly these require-   new shaft formwork is easy to strip      Because it can be repositioned so
                        ments from actual practice that the     from the concrete, simply by turn-       quickly and effortlessly using the
                        Doka Formwork Experts developed         ing spindles – and without having        Doka shifting appliances, with only
                        a new system: The Xlife Framax          to use the crane to break the forms      a minimum of labor, it makes
                        gang form system. The new sys-          free from the concrete. The system       work go ahead very efficiently. For
                        tem comes with a package of out-        also offers a further very significant   slabs at heights of over 23 ft, the
                        standing product advantages: By         advantage, however: The inside           table superstructure can readily be
                        combining the twin materials of         formwork can be assembled from           combined with Conesco Doka’s
                        wood and plastic, a completely          the widest possible panels – be-         shoring. The integral table plat-
                        new form-facing came into being –                                                forms make it unnecessary to
                        the Xlife sheet. As its name implies,                                            mount work and safety scaffolds,
                        it makes for a significantly longer                                              and provide a high level of safety
                        lifespan, while drastically reducing                                             for users. Thanks to the easily
                        its tendency to damage. Whereas                                                  transferable swivel-heads, chang-
                        on plywood with a thin film coat-                                                ing geometrical and structural-
                        ing, chips tend to break away when                                               design requirements can be ac-
                        nails are hammered into the sur-                                                 commodated very quickly. The new
                        face, the tough, elastic plastic sur-                                            Dokamatic table fits seamlessly
                        face of the Framax Xlife sheet with-                                             into the existing Dokaflex 1-2-4
                        stands very much greater stresses.                                               floor-slab product line.
Formwork News 1| 2004




                        The result: No damage to the form-
                        facing, and no imprints on the con-                                              With the Framax Bias Cut Corner
                        crete surface. Another advantage is                                              shaft formwork can be stripped
                        the minimal amount of cleaning                                                   and repositioned as a single unit in
                        needed after pouring, as the con-                                                as little as a quarter of the time it
                        crete is so easy to remove from the                                              takes using conventional formwork
 4                      special smooth coating.                                                          stripping systems.
    The new Dokamatic table makes
 it possible to reposition large-area
   slab formwork units in one piece.
  Its integral platforms and connec-
     tors, and compatibility with the
      flexible Dokaflex 1-2-4 system,
make Dokamatic a highly-economi-
               cal formwork solution.

   At many jobsites, the quality and
durability of system components -
like formwork beams, for example -
have a critical influence on costs.
The new Doka beam H20 top has
a novel end-reinforcement that
multiplies the lifespan of the
beam several times over. Investi-
gations into different types of
damage, and the frequency with
which they occur, pointed clearly
to this area as one where damage
could be minimized. The new
beam will be used with the
Dokaflex 1-2-4 floor-slab systems,
the new Dokamatic table and Doka
timber-beam formwork.

   Another highlight at this year's
show is the use of the Doka Top 50
system for bridge construction.
A full size mock up of a box
girder bridge form will be dis-
played, showing the versatility of
the Top 50 system.

                                                                                                        In addition, the booth will
                                                                                                     feature Conesco Doka's "Ready-
                                                                                                     to-Use" pre-assembly service. Pho-
                                                                                                     tos will be available of formwork
                                                                                                     that has been pre-assembled at
                                                                                                     our warehouse and delivered to
                                                                                                     the site, saving the contractor
                                                                                                     weeks on his schedule and on site
                                                                                                     labor costs.

                                                                                                         With these highlights, Conesco
                                                                                                     Doka is looking forward to drawing
                                                                                                     a capable and informed trade pub-
                                                                                                     lic coming to meet its system sup-
                                                                                                     plier, Conesco Doka, with a healthy
                                                                                                     mixture of curiosity, requests and
                                                                                                     suggestions from actual practice.

The novel end-reinforcement of the new Doka beam H20 top increases
the lifespan of the beam several times over. The beam will be used with
                                                                                                                                                      Formwork News 1| 2004




Dokaflex 1-2-4 floor-slab systems, the new Dokamatic table and Doka
timber-beam formwork.

Imprint:
“Formwork News” is a publication of the International Doka Group. Publisher: International Doka Group, Reichsstrasse 23, A 3300 Amstetten, Austria.
Editor-in-chief: A. Zehetner, Layout design: COMO Werbe & PR GmbH, A 4020 Linz, Reprography: Nureg Reproduktionen, Nuremberg, Germany. Printers:
Fr. Ant. Niedermayr, Grafische Kunstanstalt, Regensburg, Germany. In some cases the site photos show the situation during formwork assembly and are
therefore not always complete from the point of view of safety.                                                                                          5
Scott Candler filtration project, Atlanta

                                                                               Covering a site of 60 acres (24.3 ha)
                                                                               the Scott Candler filtration con-
                                                                               tract includes updating existing
                                                                               plant and facilities, new structures,
                                                                               raw water and fresh water piping
                                                                               and installation of plant in the filter
                                                                               and ozone buildings.


                                                                                  Archer Western is also using
                                                                               extensive quantities of Doka’s Alu-
                                                                               Framax system, particularly for the
                                                                               sedimentation beams, columns
                                                                               and edge forms because its light
                                                                               weight allows ‘hand-set’ installa-
                                                                               tion and positioning, eliminating
                                                                               the need for a crane.

Efficient four-day cycle                                                          “The main advantage of the
                                                                               Framax system is the minimum use
                                                                               of walers and stiffeners as we just

       for wall construction                                                   clamp the panels together,” said
                                                                               Lynn.
                                                                                  On a project where construction
Extensive water penetrations on the Scott Candler filtration project           joints are not typical and ever
in Atlanta, Georgia where, according to the Project’s Superinten-              changing, Lynn highlighted a fur-
dent, there is not a wall without a pipe penetration, led the main             ther benefit of the clamping sys-
contractor Archer Western Contractors Ltd. to use Doka Framax                  tem, allowing simple reconfigura-
formwork system to ensure versatility.                                         tion.
                                                                                  Use of the Framax system en-
                                                                               sured an efficient four-day cycle for
“A serious consideration through-       system that allowed versatility to     wall construction. Typically, a non-
out construction of the new plant       meet the ever-changing shapes.”        stop pour could comprise 50-60 ft
and upgrading of the existing facili-       Forming the ‘backbone’ of the      (15.2-18.1 m) long walls with three
ties is that it must remain opera-      formwork system according to           40 ft (12.2 m) long ‘T’ intersection
tional throughout all phases of con-    Lynn Walker, the contractor is rely-   walls up to 30 ft (9.1 m) high.
struction,” said Senior Project Su-     ing on the Framax 135 cm x 270 cm         “Time is money,” he said, “And
perintendent Lynn Walker.               (4.43 ft x 8.9 ft) panels to cover     though it’s difficult to compare
                                        large areas, particularly in the       one framed gangform system to
   He continued, “Another problem       filter building. Here for example,     another, one thing is for sure - the
is that throughout construction of      the larger panels are being used       Framax system is so much quicker
the new facility there are so many      to cover areas of up to 1680 ft2       and easier to erect compared to
water penetrations in virtually         (156 m2) and for the 30 ft (9.14 m)    other systems. And that’s what it
every wall, we needed a formwork        tall columns in a single form.         takes to work efficiently.”


                                        Archer Western Contractors Ltd,
                                        is constructing more than
                                        1 million ft2 (92,900 m2) of walls
                                        and columns, using almost 62,000 ft2
                                        (5760 m2) of Doka Framax form-
                                        work system.




                                        “The formwork and service provid-
                                        ed by Conesco Doka has helped us
                                             to achieve our goal of pouring
                                          80,000 cubic yards (61,200 m3) of
                                         concrete in one year,” says Senior
                                           Project Supervisor Lynn Walker.
Metro tunnel extension project in Largo, Maryland


Conesco Doka systems keep
Maryland metro project on track
A formwork system supplied by Conesco Doka has reduced
pouring cycle times by a third on the $ 215 million WMATA
(Washington Metropolitan Area Transit Authority) Metro tunnel
extension project in Largo, Maryland.
                                                                                                  With around 300 pours to complete
                                                                                                  and an aggressive construction
                                                                                                  schedule to keep, the LGS Joint
                                                                                                  Venture needed a forming system
                                                                                                  that could accommodate the wide
                                                                                                  range of tunnel heights and widths
                                                                                                  as well as the radius sections.

                                                                                                  dule of a pour every three days.
                                                                                                  Greg Johannes, Project Manager
                                                                                                  for LGS JV, was pleased with the
                                                                                                  results, stating that “ the com-
                                                                                                  pletely hydraulic system really sim-
                                                                                                  plified the stripping, driving, and
                                                                                                  setting operation throughout the
                                                                                                  constantly changing tunnel align-
                                                                                                  ment. It was well worth the addi-
                                                                                                  tional cost to fully automate the
                                                                                                  system. It was the only way we
                                                                                                  could pick up time on the sched-
                                                                                                  ule.”
The project includes the cut and cover construction of 4.83km (3 miles) of                           Elsewhere on the project, the
double tunnel box, with straight sections poured in 15.24m segments and                           LGS JV used the Doka Framax
curves in 7.62m chords.                                                                           gang forming system backed with
                                                                                                  Doka Support “A” frames to form

T   he design build project in-
    cludes the cut and cover con-
struction of 3 miles of double 12 ft.
                                        commodate the wide range of tun-
                                        nel heights and widths as well as
                                        the radius sections.
                                                                                                  the 18 ft. high walls of the West
                                                                                                  Service Room and double cross-
                                                                                                  over areas; and Framax with D-22
high x 14-15 ft. wide tunnel box,           The system supplied by Conesco                        support frames for the 12 ft. high
with the straight and curved sec-       Doka comprised a traveller sys-                           walls of the Triple Box area.
tions poured in 50 ft. segments.        tem, with independently-control-                             LGS decided to gang-form the
There is also a series of flared sec-   led front and rear wheel drive and                        continuous column footings for
tions, triple box sections, service     braking systems, front and rear                           Triple Box, and Conesco Doka sup-
and operations buildings, plus an       steering, and vertical height and                         plied a Quad-8 forming system
aerial structure and freeway cross-     width adjustment.                                         with custom support brackets and
ing. With approximately 300 pours           The 50 ft. long roof and side                         8” steel channels. The system was
to complete and an aggressive con-      forms could be “crabbed” in two 25                        hung from the 24” diameter sup-
struction schedule to keep, the LGS     ft. sections as needed in the curved                      port struts spanning the tunnel
(Lane Construction Corp., Granite       sections. This allowed the LGS JV                         width. With this system the LGS
Construction Co. and Slattery-          to pour two 25 ft. chords at a time                       JV were able to strip and set an en-
Skanska Inc.) Joint Venture need-       using one 50 ft. traveller, thereby                       tire 50 ft. long footing in just two
ed a forming system that could ac-      saving a day on the original sche-                        25ft. gangs.
                                                                                                                                                              Formwork News 1| 2004




                                          Conesco Doka Ltd.                       Little Ferry Branch      Atlanta Branch              California Office
                                          Little Ferry Headquarters               208 Gates Road,          105A Boulderbrook Circle,   6901 Central Avenue,
                                                                                  Little Ferry, NJ 07643   Lawrenceville, GA 30045     Riverside, CA 92504
                                          214 Gates Road,
                                                                                  Tel: (800) 631-1978      Tel: (888) 618-4700         Tel: (909) 509-0023
                                          Little Ferry,                           Fax: (201) 329-6229      Fax: (770) 962-5238         Fax: (909) 509-0024
                                          NJ 07643
                                          Tel: (800) 631-1978                     Chicago Branch           Maryland Office
                                          Fax: (201) 641-6254                     1032 Moen Avenue,        6537 Mid Cities Ave.,
                                          E-Mail: dest@conescodoka.com            Rockdale, IL 60436       Unit 11,
                                                                                  Tel: (815) 730-6700      Beltsville, MD 20705
                                                                                  Fax: (815) 730-8178      Tel: (301) 595-1808                                   7
                                                                                                           Fax: (301) 595-7395



                                          For the Doka address nearest you, please see our web-site: http://www.conescodoka.com
                        Mesa Performing Arts Center, Mesa, Arizona


                        Conesco Doka delivers fine performance
                        at Arizona´s largest arts center
                        Doka Top 50 formwork has provided the ideal solution to a tough             not a concern. All forms above
                        architectural challenge at the new $ 94m Mesa Arts Center in the            grade level were climbed on Doka
                        state of Arizona. Located on a 2.83ha site in downtown Mesa, the            MF240 rollback units. These pro-
                        62,640m2 development includes four theatres, five galleries, 14             vided a safe working platform for
                        studios and classrooms, meeting spaces, a lecture hall, internal            carpenters and reinforcing steel in-
                        performance spaces and administrative offices.                              stallers, as well as a trailing work
                                                                                                    level for finishing and patching op-
                                                                                                    erations.
                                                                                                       According to Peter Franceschina,
                                                                                                    Western Regional Manager for
                                                                                                    Conesco Doka, “The biggest chal-
                                                                                                    lenge was coping with the pre-
                                                                                                    determined sizes of the form liner
                                                                                                    sheets and handling the reduction
                                                                                                    in wall lengths due to the sloping
                                                                                                    walls. Furthermore, the horizontal
                                                                                                    construction joints were not level
                                                                                                    but perpendicular to the sloped end
                                                                                                    walls. This meant that the rollback
                                                                                                    platforms also had to be sloped.”
                                                                                                       Scheduled to open in spring
                                                                                                    2005, the Mesa Arts Center will be
                                                                                                    the largest arts centre in the State
                                                                                                    of Arizona.




                        Layton Company of Arizona used Top 50 with articulated steel walers to
                        achieve outer radii of 21.63m, 29.55m and 31.69m on the curved,
                        battered walls.


                        T   he largest three theatres are a
                            complex design that combines
                        canted, curved and conventional
                                                              sloped inwards at either 4, 5 or 6
                                                              degrees. For the curved, battered
                                                              wall at the opposite end to the
                        cast-in-situ concrete walls with      flytowers, Layton Company of          In total, Conesco Doka supplied
                        sloping flat roofs and stringent      Arizona used Top 50 with articulat-   approximately 1400m2 of formwork
                        finishing requirements.               ed steel walers to achieve outer      to the project, including some
                           To meet the demands, general       radii of 21.63m, 29.55m and           Framax for the foundation and
                        contractor Layton Company of          31.69m. The two remaining walls       straight theatre walls.
                        Arizona opted for Doka equipment.     were also formed with Top 50,
                        Each theatre has a back-of-stage      with one wall inclined at 4, 5 or 6
Formwork News 1| 2004




                        scenery “flytower” formed using       degrees to match the flytower.
                        Doka Top 50 gangs, with an elas-         In total, Conesco Doka supplied
                        tomeric form liner moulded onto       approximately 1400m2 of form-
                        the plywood facing providing the      work to the project, including
                        woodgrained exterior finish. The      some quantities of Framax for the
                        towers range from 34m to 54m high     foundation and straight theatre
 8                      and each incorporates one wall        walls where concrete finish was

						
Other docs by kzn42472
Domestic Partner Health Insurance Agreement
Views: 22  |  Downloads: 0
Domestic Discipline Contract
Views: 1351  |  Downloads: 1
Dog Pedigree Template - PowerPoint
Views: 948  |  Downloads: 1
Domain Leasing Agreement - Excel
Views: 9  |  Downloads: 0
Dog Boarding Agreement and Liability Release
Views: 59  |  Downloads: 0
Donor Contracts
Views: 8  |  Downloads: 0
Domain Purchase Trademark
Views: 6  |  Downloads: 0