Demolition Cost Estimate Template

W
Description

Demolition Cost Estimate Template document sample

Document Sample
scope of work template
							                          UNIVERSITY OF MICHIGAN HOSPITALS AND HEALTH CARE CENTERS
                                    FACILITIES PLANNING AND DEVELOPMENT
                                                                      2101 Commonwealth, Suite B
                                                                      Ann Arbor, MI 48105-5759

RTN NUMBER & PROJECT NAME HERE                                                                                              Date:
CONSTRUCTION COST OPINION SUMMARY                                                                                    Prepared by:                             -



                                                             CONSTRUCTION SPECIFICATION INSTITUTE (CSI)
                                                                                                                                    COST PER      % OF 0-16
                                             ESTIMATE SUMMARY                                                       TOTAL $         BLDG. SF       TOTAL
   01    GENERAL REQUIREMENTS
                                                                                    TOTAL GENERAL REQUIREMENTS        $0
   02    DEMOLITION/SITE WORK
                                                                                     TOTAL DEMOLITION/SITE WORK       $0
   03    CONCRETE
                                                                                                 TOTAL CONCRETE       $0
   04    MASONRY
                                                                                                  TOTAL MASONRY       $0
   05    METALS
                                                                                                    TOTAL METALS      $0
   06    WOOD & PLASTICS
                                                                                           TOTAL WOOD & PLASTICS      $0
   07    THERMAL & MOISTURE PROTECTION
                                                                      TOTAL THERMAL & MOISTURE PROTECTION             $0
   08    DOORS & WINDOWS
                                                                                           TOTAL DOORS & WINDOWS      $0
   09    FINISHES
                                                                                                   TOTAL FINISHES     $0
   10    SPECIALTIES
                                                                                                TOTAL SPECIALTIES     $0
   11    EQUIPMENT
                                                                                                 TOTAL EQUIPMENT      $0
   12    FURNISHINGS
                                                                                               TOTAL FURNISHINGS      $0
   13    SPECIAL CONSTRUCTION
                                                                                    TOTAL SPECIAL CONSTRUCTION        $0
   14    CONVEYING SYSTEMS
                                                                                       TOTAL CONVEYING SYSTEMS        $0
   15    MECHANICAL
                                                                                                TOTAL MECHANICAL      $0
   16    ELECTRICAL
                                                                                                TOTAL ELECTRICAL      $0
                                                                     PROJECT SUBTOTAL CONSTRUCTION                    $0

                                FOR INFORMATION ONLY, AMOUNT OF ABOVE SUBTOTAL FACTORED FOR PREMIUM TIME              $0
   99    99010 - DESIGN CONTINGENCY AND
         ESCALATION
                                                                                             TOTAL CONTINGENCIES      $0
                                                                                            PROJECT SUBTOTAL          $0
         99030 - CONSTRUCTION MANAGER/              99033 - CM FEE/GC PROFIT                                          $0                       7.5%
         GENERAL CONTRACTOR                                        TOTAL AE FIXED LIMITS OF CONSTRUCTION              $0
                                                                                            PROJECT SUBTOTAL          $0
         99040 - CONSTRUCTION MANAGER


                                                                     TOTAL CM FIXED LIMITS OF CONSTRUCTION            $0
                                                                                            PROJECT SUBTOTAL          $0
         99050 - ALLOWANCES


                                                                                               TOTAL ALLOWANCES       $0
                                                                                            PROJECT SUBTOTAL          $0
         99090 - ALTERNATES                         99091 - ALTERNATE #1

                                                    99091A - DESCRIPTION #1
                                                    99091B - DESCRIPTION #2
                                                    99091C - CONTINGENCY                                              $0                       0.0%
                                                                                               TOTAL ALTERNATE #1     $0
                                                    99092 - ALTERNATE #2
                                                    99092A - DESCRIPTION #1
                                                    99092B - DESCRIPTION #2
                                                    99092C - CONTINGENCY                                              $0                       0.0%
                                                                                               TOTAL ALTERNATE #2     $0

                                                                                            TOTAL ALL ALTERNATES      $0

                                                                                                PROJECT TOTAL         $0




D:\Docstoc\Working\pdf\1a5271ea-8ddc-4fa0-bb3a-cf8090a260bf.xls (UPDATED 8/11/08)      1                                                       1/18/201111:23 AM
                                                     UNIVERSITY OF MICHIGAN HOSPITALS AND HEALTH CARE CENTERS
                                                               FACILITIES PLANNING AND DEVELOPMENT
                                                                        2101 Commonwealth, Suite B
                                                                         Ann Arbor, MI 48105-5759


RTN NUMBER & PROJECT NAME HERE                                                                                                                                                Date:
CONSTRUCTION COST OPINION BREAKDOWN                                                                                                                                   Prepared By: -

       ASSUMPTIONS:
       PHASE:
       Costs are estimated assuming that project will be competively bid by General Contractors.
       Estimated costs are in year 2011 dollars based on industry averages and are for budgeting purposes only
       Estimated labor costs are estimated to be performed during normal working hours unless noted with "Y" under premium time column. Average
                                       Standard time average hourly rate: $80.00 per hour                                                         YES
                                      Premium time average hourly rate: $112.00 per hour
       Estimated construction costs DO NOT include owner provided equipment, furniture, window coverings, furnishings, hazardous material
       Estimated construction costs DO NOT include allowances for escalation or contingencies
                                               Approximate area of work:               GSF

                                                                                   QUANTITY           MATERIAL                              LABOR
                                                                                                                                                                     SUBTOTAL
DIV                               WORK ITEM                                      # OF    UNIT      $ PER                 $ PER             HOURLY         LABOR
                                                                                                           TOTAL                                                       COST
                                                                                UNITS   MEAS.       UNIT                  UNIT     HRS PER TOTAL PREMIU   TOTAL
       Infection Control Measures                                                                                                    UNIT
                                                                                                                   of Total Labor Cost     LABOR M TIME
                                                                                                             $0.00                           0.0          $0.00
                                                                                      DIVISION 01 TOTALS:     $0                              0            $0             $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 2 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 2 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 2 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 3 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 3 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 3 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 4 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 4 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 4 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 5 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 5 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 5 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 6 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 6 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 6 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 7 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 7 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 7 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 8 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 8 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 8 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                    DIVISION 9 SUBTOTALS:     $0                              0            $0             $0
                                                                         DIVISION 9 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                         DIVISION 9 TOTAL:                                                                $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 10 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 10 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                       DIVISION 10 TOTAL:                                                                 $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 11 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 11 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                       DIVISION 11 TOTAL:                                                                 $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 12 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 12 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                       DIVISION 12 TOTAL:                                                                 $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 13 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 13 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                       DIVISION 13 TOTAL:                                                                 $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 14 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 14 SUBCONTRACTOR OH&P:                                                   0.0%            $0
                                                                                       DIVISION 14 TOTAL:                                                                 $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 15 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 15 SUBCONTRACTOR OH&P:                                                   7.5%            $0
                                                                                       DIVISION 15 TOTAL:                                                                 $0
                                                                                                             $0.00                           0.0          $0.00
                                                                                  DIVISION 16 SUBTOTALS:      $0                              0            $0             $0
                                                                        DIVISION 16 SUBCONTRACTOR OH&P:                                                   7.5%            $0
                                                                                       DIVISION 16 TOTAL:                                                                 $0




      D:\Docstoc\Working\pdf\1a5271ea-8ddc-4fa0-bb3a-cf8090a260bf.xls (UPDATED 8/11/08)              2                                                        1/18/201111:23 AM

						