Conceptual Project Schedule - Excel

W
Description

Conceptual Project Schedule document sample

Document Sample
scope of work template
							                                                                                                                        Olympic Peninsula Region Projects
                                                                                                                                   Project
                                                                             Parties Impacted                                                       Scheduled    Cost       Project Need/Driver & Other                                 Plan cross
Project Name        Description                                    Sponsor                    Link to More Detail Project Stage    Commitment                                                              Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                             by Project                                                             Completion   Estimate   Notes                                                       tribal lands
                                                                                                                                   Level
Olympic Peninsula   Construct 14 miles of new double circuit 230 kV BPA      PSE                                                                    2009         $26-       Load growth and correct bus                                                Existing
Reinforcement       line from Olympia to Shelton. Loop-in the                                                                                                    million    sectionalizing breaker issue                                               Obligation
                    Olympia-Kitsap 230 kV line into Shelton.                                                                                                                                                                                           Project
                    Remove the Olympia-Shelton No.1 115 kV line.
                    The project also includes miscellaneous
                    substation work at Shelton and Olympia.


Olympia 230/115 kV Add a new 230/115 kV Transformer at Olympia BPA                                                Conceptual                        2016         $7         Load Growth                                                                Single System
Transformer Bank   substation                                                                                     Project for                                    million                                                                               Project with
No.3                                                                                                              future need                                                                                                                          possible
                                                                                                                                                                                                                                                       impacts
Shelton-Fairmount- Shelton-Fairmount 230 kV line No. 3. Construct BPA                                             Conceptual                        2016         $21.5      Load Growth                                                                Single System
Port Angeles Area  a new 230 kV line (approximately 60 miles)                                                     Project for                                    million                                                                               Project
                   between Shelton and Fairmount Substations                                                      future need
                                                                                                                                  Puget Sound Region Projects
                                                                                                                                           Project
                                                                                   Parties Impacted                                                        Scheduled      Cost                                                                          Plan cross
Project Name          Description                                       Sponsor                     Link to More Detail Project Stage      Commitment                                Project Need/Driver & Other Notes     Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                   by Project                                                              Completion     Estimate                                                                      tribal lands
                                                                                                                                           Level
North King County     This project involves looping the Monroe-          PSE                                                                               Energized                 Additional transformation                                                         Single System     Puget Sound
transformer           Sammamish 230kV line into PSE's Novelty Hill                                                                                                                   capacity for north King County to                                                 Project,          Area Study
capacity.             substation and installing a new 230/115kV                                                                                                                      meet load growth.                                                                 possible          Team
                      transformer.                                                                                                                                                                                                                                     impacts
South King County     This project involves the construction of a 2 mile PSE                                                                               Energized                 Increased reliability for Berrydale                                               Existing          Puget Sound
Capacity Increase     230kV line between Bonneville's Covington                                                                                                                      and Talbot substations and                                                        Obligation        Area Study
                      substation and PSE's Berrydale substation on                                                                                                                   capacity increase north of                                                        Project           Team
                      existing ROW. Double circuit 1590 ACSS Falcon                                                                                                                  Covington.
                      initially phased tied and operated as a single
                      line.

230 kV Line Re-       This project involves the re-termination of    Tacoma        Bonneville                           Study completed                    2011-2012      $750K to Reliability improvement                 New entry.                                  Single System     Puget Sound
termination Project   Bonneville’s South Tacoma-Cowlitz (#1) 230-kV Power                                               by Bonneville in                                  $1M                                                                                          Project,          Area Study
at and around         line from Tacoma Power's Cowlitz 230-kV Bus                                                       June 2008                                                                                                                                      possible          Team
Cowlitz Substation.   into TPWR’s Southwest (#4) line. It also                                                                                                                                                                                                         impacts
                      includes the re-termination of TPWR’s Cowlitz-
                      Southwest (#3) and Cowlitz-Tacoma (#2) 230-kV
                      lines to create a new Southwest-Tacoma 230 kV
                      line.

Pierce County         A new 230/115kV transformer at Alderton          PSE                                                                                 2011 October              Additional transformation                                                         Single System     Puget Sound
transformer           substation in central Pierce County with several                                                                                                               capacity for Pierce and south King                                                Project,          Area Study
capacity.             options being considered for the 230kV source.                                                                                                                 Counties to meet load growth.                                                     possible          Team
                                                                                                                                                                                                                                                                       impacts
Thurston County       A new 230/115kV transformer at Saint Clair or PSE                                                                                    2012 October              Additional transformation                                                         Single System     Puget Sound
transformer           Spurgen Creek substations in Southern Thurston                                                                                                                 capacity for Thurston Counties to                                                 Project,          Area Study
capacity.             County with several options being considered                                                                                                                   meet load growth.                                                                 possible          Team
                      for the 230kV source.                                                                                                                                                                                                                            impacts
North Downtown        Proposed to build a new 200 MVA substation in Seattle City                                        Conceptual         Project identified 2014 to 2018 $40 to    Load growth in North Seattle area                                                 Existing          Puget Sound
Seattle Substation    the north of downtown area to serve load       Light                                              Project for future for future need                 $200M     has slowed since late 2008. SCL is                                                Obligation        Area Study
                      growth. Install underground 230kV                                                                 need                                                         reviewing load forecasts and                                                      Project           Team
                      transmission lines from East Pine and                                                                                                                          transmission plans for the north
                      Massachusetts Substations to New Substation                                                                                                                    downtown area.
                      and add 230kV/115kV autotransformer.
                      Construct new 115kV transmission lines from
                      Canal and Broad Street Substations to New
                      Substation.


South of Sedro        Rebuild a 115kV line to become a second 230kV PSE            in parallel                                                             2010 to 2011              Increase capacity for native load                                                 Capacity         Puget Sound
Capacity Increase     line between Sedro Woolley and Horse Ranch                   w/Bonneville &                                                                                    and transmission service                                                          Increase Project Area Study
                      Substations. Includes reconductoring sections                Snohomish PUD                                                                                                                                                                                         Team
                      of the Sedro Woolley-Horse Ranch-Bothell                     w/ impacts to
                      230kV line, adding 2 breakers at Horse Ranch,                the Westside
                      and uprating the Horse Ranch-HR Tap of                       Northern
                      Monroe-Snohomish 230 kV line                                 Intertie
                                                                                                                                  Puget Sound Region Projects
                                                                                                                                            Project
                                                                                  Parties Impacted                                                        Scheduled      Cost                                                                            Plan cross
Project Name        Description                                      Sponsor                       Link to More Detail Project Stage        Commitment                              Project Need/Driver & Other Notes       Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                  by Project                                                              Completion     Estimate                                                                        tribal lands
                                                                                                                                            Level
Southwest           Modify Bus section breaker arrangement at        Tacoma                                                                               2012                      The purpose of this project is to                                                   Single System     Puget Sound
substation 230 kV   Southwest substation to eliminate single point   Power                                                                                                          improve system reliability by                                                       Project           Area Study
Bus Reliability     of failure of bus section breaker.                                                                                                                              preventing any bus fault or a                                                                         Team
Improvement                                                                                                                                                                         “stuck breaker” on one of the 230
Project                                                                                                                                                                             kV buses from resulting in total
                                                                                                                                                                                    loss of service to the substation.



Beverly Park 230-   Expand the existing 115 kV switching station    Snohomish     Additional                           Project is in the                  2012                      Load Growth and expected local          In service date is delayed                  Single System     Puget Sound
115 kV Capacity     and add two 230-115 kV 300 MVA transformers. PUD No. 1        Bonneville                           design and                         November                  reliability deficiency in Paine Field   from 2011 to 2012 and                       Project,          Area Study
Addition            The 230 kV source will be from the BPA                        Snohomish                            construction                                                 and Everett areas requires              second transformer                          possible          Team
                    Snohomish Substation. An existing 115 kV line                 230kV bus                            Phase                                                        capacity increases to meet District     included at Beverly Park.                   impacts
                    from BPA Snohomish to the Glenwood Tap will                   positions are                                                                                     level of service guidelines
                    be converted to 230 kV. The 115 kV line serving               required
                    the Glenwood Tap will then be configured to be
                    served from the Beverly Park 115 kV bus.



Canyon substation   Canyon is a 230/110 kV substation to be located Tacoma        BPA                                  Study completed High               2011-12                   The addition of this substation is                                                  Single System     Puget Sound
                    in the southern part of Tacoma Power’s service Power                                               by BPA in 2008                                               intended to improve system                                                          Project,          Area Study
                    territory. Tacoma Power proposed to                                                                                                                             reliability, operational flexibility,                                               possible          Team
                    interconnect this new substation to Bonneville’s                                                                                                                and at the same time, provide                                                       impacts
                    South Tacoma Substation. A single 230/110 kV                                                                                                                    more system capacity to
                    step down transformer will be installed at this                                                                                                                 accommodate load growth in the
                    substation in the near term with provisions                                                                                                                     area.
                    made for a future second transformer.



IP line conversion to Convert PSE's 115kV "IP" line to 230kV between PSE          Puget Sound                          Conceptual                         2013 to 2015              Load growth in Puget Sound and                                                      Single System     Puget Sound
230 kV                Kittitas substation and Lake Tradition substation           Utilities                            Project for future                                           generation integration, related to                                                  Project,          Area Study
                      in King County to increase cross-Cascade                                                         need                                                         North Cross Cascades                                                                possible          Team
                      capacity and interconnect Kittitas County wind                                                                                                                Improvements                                                                        impacts
                      projects


North Cross         Alternatives include 500 kV series capacitors to Bonneville   Puget Sound                                                             2014-2016                 Load growth in Puget Sound and                                                      Existing          Puget Sound
Cascades            the Schultz-Raver 500 kV lines No.3 & 4,                      Utilities                                                                                         Transmission Service Requests                                                       Obligation        Area Study
Reinforcement       additional 500 kV shunt capacitors in the area,                                                                                                                                                                                                     Project           Team
                    construction of a new 500 kV line across the
                    Northern Cascades to serve loads in the Puget
                    Sound area


Seattle Area        Add a new 500/230 kV transformer bank in the Bonneville       PSE - Covington                                                         2016                      Load growth in Puget Sound area                                                     Existing          Puget Sound
500/230 kV          Seattle vicinity to serve loads in the Puget                  - Berrydale                                                                                                                                                                           Obligation        Area Study
Transformer Bank    Sound area.                                                   230kV line                                                                                                                                                                            Project           Team
                                                                                                                                 Puget Sound Region Projects
                                                                                                                                          Project
                                                                                  Parties Impacted                                                            Scheduled      Cost                                                                          Plan cross
Project Name         Description                                     Sponsor                       Link to More Detail Project Stage      Commitment                                    Project Need/Driver & Other Notes     Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                  by Project                                                                  Completion     Estimate                                                                      tribal lands
                                                                                                                                          Level
North King County    A 230kV line between Sammamish Substation PSE                In parallel w/                                                              2015 to 2017              Increased capacity across the                                                     Existing          Puget Sound
Capacity Increase    in North King County to Talbot substation in                 Bonneville &                                                                                          Monroe-Echo Lake cutplane for                                                     Obligation        Area Study
                     central King County. The project would involve               SCL w/impacts                                                                                         native load and transmission                                                      Project           Team
                     rebuilding an existing 115kV line to 230kV.                  to the Westside                                                                                       service.
                                                                                  Northern
                                                                                  Intertie

South Everett Area   Reconductoring Bonneville Snohomish to           Snohomish   The Bonneville                                          Project no longer                             Load Growth and expected local        The Beverly Park and                        Single System     Puget Sound
115 kV Expansion     Pinehurst 115 kV line (2019). This line is owned PUD No. 1   portion of this                                         in Shohomish                                  reliability deficiency requires       South Snohomish County                      Project,          Area Study
                     by Bonneville and Snohomish PUD                              line requires                                           PUD plan                                      capacity increases to meet District   115 kV Expansion Projects                   possible          Team
                                                                                  increase                                                                                              level of service guidelines           have replaced the South                     impacts
                                                                                  capacity                                                                                                                                    Everett Area Expansion
                                                                                                                                                                                                                              Project
115kV North Seattle Uprate 115kV transmission lines in the north Seattle City     BPA, NI                              Plan of Service    Included in SCL     2009                      Increase North Seattle 115kV                                                      Single System
Transmission Lines end of Seattle to 100 degree C conductor      Light                                                 determined         budget                                        Transmission line capacity and to                                                 Project
upgrade             temperature. Remaining tasks include                                                                                                                                improve transmission reliability.
                    completion of the Bothell-Shoreline #1 by
                    summer 2009 and removing obstructions below
                    the Bothell-Canal 115 kV lines.

Cowlitz substation   Modify Bus section breaker arrangement at         Tacoma                                          Preliminary                            2012                      The purpose of this project is to     Reclassified as single                      Single System
230 kV Bus           Cowlitz substation to eliminate single point of Power                                             study                                                            increase system reliability           system project                              Project
Reliability          failure of bus section breaker. This project will                                                 completed. Final
Improvement          be implemented at the same time as the 230 kV                                                     study will be
Project.             Transformer Replacement project at Cowlitz.                                                       performed in the
                                                                                                                       near future in
                                                                                                                       anticipation of
                                                                                                                       budget approval
                                                                                                                       in 2011-2012.



Cowlitz 230 kV       Replace the two 250 MVA transformers at         Tacoma                                            Study                                  2010                      The two 250 MVA transformers at The size of the new                               Single System
Transformer          Cowlitz with two 400 MVA, 230/115 kV,           Power                                             completed. 1st                                                   Cowlitz were installed in the mid- transformers changed                           Project
Replacement          autotransformers. instead of 500 MVA as                                                           transformer                                                      60s. The new transformers will     from 500 to 400 MVA
                     previously reported.)                                                                             purchased in                                                     provide more capacity to
                                                                                                                       2008 and 2nd                                                     accommodate system load
                                                                                                                       transformer will                                                 growth. They will also provide
                                                                                                                       be purchased in                                                  better operational flexibility and
                                                                                                                       2009.                                                            higher reliability by allowing N-1
                                                                                                                                                                                        operation when one of them is
                                                                                                                                                                                        taken out of service for
                                                                                                                                                                                        maintenance.
                                                                                                                                    Puget Sound Region Projects
                                                                                                                                            Project
                                                                                     Parties Impacted                                                       Scheduled    Cost                                                                          Plan cross
Project Name         Description                                      Sponsor                         Link to More Detail Project Stage     Commitment                              Project Need/Driver & Other Notes     Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                     by Project                                                             Completion   Estimate                                                                      tribal lands
                                                                                                                                            Level
Swamp Creek 115      Construct a six 115 kV breaker switching station Snohomish                                           Project under                     2021                    South County area load growth       In service date is delayed                    Single System
kV switching station with a ring bus arrangement using GIS               PUD No. 1                                        study                             November                and expected reliability            from 2017 to 2021                             Project
                     technology (four breakers only needed for                                                                                                                      deficiencies will require capacity
                     phase one work). Future construction will                                                                                                                      increases to meet District level of
                     include one 115 kV line position will terminate a                                                                                                              service guidelines. This
                     new 115 kV line from the Paine Field Area and                                                                                                                  construction work is also part of a
                     one new 115 kV termination of a 230kV / 115 kV                                                                                                                 multi-project effort to provide
                     transformer. This switching station will                                                                                                                       three 115 kV ties between
                     terminate 115 kV lines from SnoKing (2 Lines),                                                                                                                 Bonneville SnoKing and Bonneville
                     Halls Lake (1 line) and from Beverly Park (1 line).                                                                                                            Snohomish substations.


Paine Field 115 kV   This capital expansion includes design and       Snohomish                                           Project under                     2021                    South County area load growth       In service date is delayed                    Single System
Switching Station    construction of a six 115 kV breaker ring bus    PUD No. 1                                           study                             November                and expected reliability            from 2020 to 2021                             Project
                     adjacent to the existing Paine Field Substation.                                                                                                               deficiencies will require capacity
                     The existing Paine Field Substation will have a                                                                                                                increases to meet District level of
                     station bus looped through from the new                                                                                                                        service guidelines. This
                     adjacent ring bus and the Paine Field to Boeing                                                                                                                construction work is also part of a
                     115 kV Line. When completed, the switching                                                                                                                     multi-project effort to provide
                     station will terminate lines from Mukilteo,                                                                                                                    three 115 kV ties between BPA
                     Olivia Park, Boeing, Gibson, Beverly Park via                                                                                                                  SnoKing and BPA Snohomish
                     Casino (new), and Swamp Creek via Picnic Point                                                                                                                 Substations.
                     tap (new).


Swamp Creek to       This capital expansion includes design and       Snohomish                                           Project under                     November                South County area load growth                                                     Single System
Picnic Point Tap 115 construction of a 115 kV line (2.9 miles) with   PUD No. 1                                           study                             2020                    and expected reliability                                                          Project
kV Line              1272 kCM conductor from Swamp Creek to the                                                                                                                     deficiencies will require capacity
                     Picnic Point tap. A new 115 kV line position and                                                                                                               increases to meet District level of
                     breaker will be added to the Swamp Creek 115                                                                                                                   service guidelines. This
                     kV Switching Station. This new 115 kV line will                                                                                                                construction work is also part of a
                     be configured (closed loop network connection)                                                                                                                 multi-project effort to provide
                     with the Paine Field 115 kV Switching Station.                                                                                                                 three 115 kV ties between BPA
                     The Picnic Point Tap to the Picnic Point                                                                                                                       SnoKing and BPA Snohomish
                     Substation 115 kV Line will be operated                                                                                                                        Substations.
                     normally opened.

Marysville 230-      Construct a new 230 – 115 kV 300 MVA              Snohomish     BPA                                  Project under                     November                Marysville area load growth and                                                   Single System
115kV Substation     Transformation Substation in the Marysville,      PUD No. 1                                          study                             2025                    expected North County reliability                                                 Project,
                     Washington area. This new transmission                                                                                                                         deficiencies will require capacity                                                possible
                     substation will be connected (looped) to the                                                                                                                   increases to meet District level of                                               impacts
                     existing BPA Murray to BPA Snohomish 230 kV                                                                                                                    service guidelines
                     line. The new substation will consist of four 115
                     kV line positions and connect to the existing
                     area 115 kV network and the Stimson Crossing
                     115 kV Switching Station.


Beverly Park and     Addition of several 115 kV line capacity          Snohomish                                          Projects are in                   November                Beverly Park and South Everett       Revised Project scope and                    Single System
South Snohomish      additions in the South Everett Area: Beverly      PUD No. 1                                          the design and                    2012                    area load growth and expected        dates advanced to 2012                       Project
County 115 kV        Park to Everett 115 kV Line (2012) , Beverly Park                                                    construction                                              local reliability deficiencies will
Expansion            to Boeing (reconductor) 115 kV line (2012).                                                          phase                                                     require capacity increases to meet
                                                                                                                                                                                    District level of service guidelines
                                                                                                                               Puget Sound Region Projects
                                                                                                                                      Project
                                                                                Parties Impacted                                                       Scheduled    Cost                                                                         Plan cross
Project Name         Description                                      Sponsor                    Link to More Detail Project Stage    Commitment                               Project Need/Driver & Other Notes    Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                by Project                                                             Completion   Estimate                                                                     tribal lands
                                                                                                                                      Level
Chehalis-Centralia   Rebuild both of the Chehalis-Centralia 69 kV    BPA                                                                                                       Load growth in Chehalis and                                                      Single System
Rebuild              lines No.1 and 2 with higher capacity conductor                                                                                                           Centralia areas                                                                  Project
                     using H-frame structures, and 115 kV spacing
                     and insulation. The lines will be operated
                     initially at 69 kV.


East King County     This project involves looping the Maple Valley- PSE                                                                               2012                    Additional transformation                                                        Single System     Puget Sound
transformer          Sammamish #1 230kV line into PSE's Lake                                                                                                                   capacity for east King County to                                                 Project,          and Northern
capacity             Tradition Substation and installing a new                                                                                                                 meet load growth.                                                                possible          Mid-C Area
                     230/115kV transformer. A future connection to                                                                                                                                                                                              impacts           Study Teams
                     the west end of the IP line is also planned.


Skagit County        This project involves installing an additional   PSE                                                                              2013                    Additional transformation                                                        Single System     Puget Sound
transformer          230/115kV transformer into PSE's Sedro                                                                                                                    capacity for Skagit County to meet                                               Project,          Area Study
capacity             Woolley Substation.                                                                                                                                       load growth.                                                                     possible          Team
                                                                                                                                                                                                                                                                impacts
                                                                                                                            Central Washington Region Projects
                                                                                                                                          Project
                                                                                   Parties Impacted                                                         Scheduled                    Project Need/Driver & Other                                Plan cross
Project Name          Description                                        Sponsor                    Link to More Detail Project Stage     Commitment                     Cost Estimate                                 Changes from Previous Plan                  Type of Project    Study Team(s)
                                                                                   by Project                                                               Completion                   Notes                                                      tribal lands
                                                                                                                                          Level
Mid-Columbia Area     Rebuild 9 miles of the Vantage-Midway 230 kV line BPA        PAC & Grant                          Plan of Service   Funding            2011        $14 million     Load growth in Mid C area                                                 Existing           NTAC
Reinforcement         (about 10 miles is already rebuilt) in Central WA.                                                Determined        approved by                                    and transfers of generation                                               Obligation
                      Add sectionalizing breaker at Vantage substation.                                                                   sponsor                                        out of the area                                                           Project

Mid-Columbia Area     Wanapum-Pomona Heights 230-kV #2 Line in the       PAC       BPA, Grant                                                               2012                         Load growth in Yakima area                                                External Project NTAC
Reinforcement         Yakima area.



Northern Mid-C Area   Douglas-Rapids 230 kV line, Douglas 230/115 kV     Douglas   Douglas,                             Plan of Service   sponsor           2012                         Project needed to meet load New Project                                   Existing           Northern Mid-
Support               transformer, Rapids 115 substation with                      Chelan, BPA,                         Determined        committed                                      growth                                                                    Obligation         C Study
                      terminations for Pangborn, South Nile and Hanna              Grant, PSE                                                                                                                                                                      Project            Group
                      115 kV lines
Northern Mid-C Area   Andrew York 115kV Bus Arrangement: change the      Chelan    Douglas,                             Plan of Service   Included in     Fall 2010      $750k           Project needed to match       New Project                                 Single System      Northern Mid-
Support               line termination bus arrangement at Andrew York    County    Chelan, BPA,                         Determined        Sponsers Budget                                line capacities for bus                                                   Project            C Study
                      Switchyard                                         PUD       Grant, PSE                                                                                            segment outage                                                                               Group

Northern Mid-C Area   Rebuild McKenzie to Wenatchee Tap 115 kV line      Chelan    Douglas,                             Plan of Service   Project identified Fall 2012   $6M             This project is needed to     New Project                                 Single System      Northern Mid-
Support                                                                  County    Chelan, BPA,                         Determined        as future need -                               provide a higher rating and                                               Project            C Study
                                                                         PUD       Grant, PSE                                                                                            mitigate reliability criteria                                                                Group
                                                                                                                                                                                         violations.
Northern Mid-C Area   Build new Rapids-Columbia 230 kV line              unknown Douglas,                               Plan of Service   Project identified 2013                        Project needed to meet load New Project                                   Existing           Northern Mid-
Support                                                                          Chelan, BPA,                           under Study       as need                                        growth and transfers                                                      Obligation         C Study
                                                                                 Grant, PSE                                                                                                                                                                        Project            Group

Northern Mid-C Area   Add 230kV bus section breaker at Columbia          BPA       Douglas,                             Plan of Service   Project identified 2013                        Project needed to meet load New Project                                   Existing           Northern Mid-
Support                                                                            Chelan, BPA,                         under Study       as need                                        growth and transfers                                                      Obligation         C Study
                                                                                   Grant, PSE                                                                                                                                                                      Project            Group

Mid-Columbia Area    Upgrade Wanapum-Midway 230-kV line in central       Grant                                                            Project identified 2015                        Load growth in Yakima area, Project schedule                              Existing
Reinforcement, Phase WA,                                                 County                                                           as future need -                               new wind generation plants identified                                     Obligation
2                                                                        PUD                                                                                                             and transfers of generation                                               Project
                                                                                                                                                                                         out of the area


Columbia - Larson 230 Construct a new 230 kV line from Rocky Ford to     Grant     Interconnect                                                             2012         $30 million Meet load growth, increase Changed from Columbia-                             Single System
kV Line               Columbia, connect to existing Rocky Ford-Larson    County    w/BPA at                                                                                          transmission system        Rocky Ford to Columbia-                            Project with
                      230 kV line to form Columbia-Rocky Ford line.      PUD       Columbia Sub                                                                                      reliability and improve    Larson.                                            possible
                                                                                                                                                                                     voltage stability                                                             parallel impacts
                                                                                                                                                                                     performance.

Andrew York - Rocky   Construct 8.5-mile 230kV transmission line from     Chelan                                                          Complete          Complete     $14 million Provide adequate capacity                                                     Single System
Reach 230 kV Line     Rocky Reach Switchyard to Andrew York               County                                                                                                     to Chelan’s 115kV                                                             Project
                      Switchyard. Construction includes 230kV ring bus at PUD                                                                                                        transmission system to meet
                      Andrew York with 250MVA 230-115kV                                                                                                                              reliability and operational
                      autotransformer. Improvements at Rocky Reach                                                                                                                   standards with expected
                      Switchyard includes addition of one 230kV breaker                                                                                                              load growth.
                      and main transfer bus extension.
                                                                                                                              Central Washington Region Projects
                                                                                                                                            Project
                                                                                     Parties Impacted                                                         Scheduled                    Project Need/Driver & Other                                     Plan cross
Project Name           Description                                         Sponsor                    Link to More Detail Project Stage     Commitment                     Cost Estimate                                      Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                     by Project                                                               Completion                   Notes                                                           tribal lands
                                                                                                                                            Level
Columbia - Ancient     13.13 miles of the Columbia – Quincy 115 kV line    Grant     Mid-C Joint                          Complete                            Complete                     To provide capacity to meet                                                    Single System
Lake 115 kV            will be reconductored from 556 ACSR to 795 ACSS     County    Study Group                                                                                           load growth in northwest                                                       Project
Reconductor            to increase the rating of the line.                 PUD       effort                                                                                                Grant County and
                                                                                                                                                                                           surrounding areas, this
                                                                                                                                                                                           project will obtain a higher
                                                                                                                                                                                           rating and mitigate
                                                                                                                                                                                           reliability criteria violations.


Entiat 115kV Switching Construct 3 breaker ring style 115kV switching      Chelan                                         Conceptual        Project identified Fall 2014   $2-3 million Load Growth                           Project delayed                             Single System
Station                station near Entiat. The existing Rocky Reach to    County                                         Project for       as future need -                                                                                                              Project
                       Chelan Falls 115kV transmission line will be tapped PUD                                            Future Need
                       with a new 115kV transmission line to serve Entiat
                       Valley load area.

Larson - Stratford 115 Upgrade 16.14 miles of the Larson – Stratford 115   Grant                                                                              Nov 2010                     This project is needed to          New Project                                 Single System
kV Line                kV line.                                            County                                                                                                          provide a higher rating and                                                    Project
                                                                           PUD                                                                                                             mitigate reliability criteria
                                                                                                                                                                                           violations with the
                                                                                                                                                                                           increasing load in the area.


Anderson Canyon        Installation of thermal relay on Anderson Canyon - Chelan                                          Complete          Included in     Spring 2009    $100k           Protects line from numerous New Project                                        Single System
Thermal Relay          Beverly 115kV line                                 County                                                            Sponsers Budget                                overloads that occur for                                                       Project
                                                                          PUD                                                                                                              contingencies. Opens the
                                                                                                                                                                                           line at Summit.


Anderson Canyon        Installation of undervoltage relay at Anderson      Chelan                                         Plan of Service   Included in     Fall 2009      $100k           Safety net for BSBF        New Project                                         Single System
Undervoltage Relay     Canyon                                              County                                         Determined        Sponsers Budget                                contingency at Andrew York                                                     Project
                                                                           PUD
Wine Country 230/115 Add substation and 230/115 kV Transformer             PAC                                                                                2008-09                      Load Growth                                                                    Single System
kV Transformer       tapping Midway-Mabton 230 line and serving the                                                                                                                                                                                                       Project
                     Sunnyside and Grandview areas
                                                                                                                                      Northeastern Region Projects
                                                                                                                                                    Project
                                                                                          Parties Impacted                                                         Scheduled      Cost                                                                      Plan cross
Project Name        Description                                             Sponsor                        Link to More Detail Project Stage        Commitment                               Project Need/Driver & Other Notes Changes from Previous Plan                  Type of Project    Study Team(s)
                                                                                          by Project                                                               Completion     Estimate                                                                  tribal lands
                                                                                                                                                    Level
Benewah – Shawnee This 230 kV line is part of the comprehensive West of    Avista                                                                   Complete          Complete               The line will add a second 230 kV                                             Capacity
230 kV Line       Hatwai (WOH) transmission project. This project                                                                                                                            source between Avista’s northern                                              Increase Project
                  involves the construction of a new 230 kV line from                                                                                                                        and southern transmission
                  Avista’s Benewah substation to Avista’s Shawnee                                                                                                                            systems. Additionally Benewah
                  substation. The line will be approximately 60 miles long                                                                                                                   230 kV substation will have 3
                  and will be constructed with double circuit towers along                                                                                                                   capacitor banks of 67.1 MVAR
                  an existing 115 kV line right of way for 40 miles. The                                                                                                                     each
                  remaining 20 miles will be constructed along new right
                  of way. One circuit will be constructed as 230 kV, while
                  the other circuit will be constructed as 115 kV. The new
                  230 kV line will be 1590 ACSS conductor.



Benewah 230 kV      This 230 kV capacitor bank is part of the comprehensive Avista                                                                  Complete       Complete                  Load growth and transfers                                                     Capacity
Capacitor Bank      West of Hatwai (WOH) transmission project. Benewah                                                                                                                                                                                                     Increase Project
                    230 kV substation will have three capacitor banks of
                    67.1 Mvar each to be energized in October of 2008.



Boundary            Installation of a 230/115KV autotransformer in the      Seattle                                                                 under                  2009              BPA, SCL and Pend Oreille PUD                                                 Existing
Transformer         Boundary Switchyard to interconnect to SCL's 115KV      City Light,                                                             construction                             have negotiated the Boundary                                                  Obligation
replacement with    Boundary transmission tap line will also enhanced       BPA,                                                                                                             Transformer Agreement to allow                                                Project
connection to       electric grid reliability.                              Pend                                                                                                             for the cost-effective delivery of
existing 115kV                                                              Oreille                                                                                                          Article 49 Power and tailwater
transmission line                                                           PUD                                                                                                              encroachment compensation
                                                                                                                                                                                             from the Boundary Project to the
                                                                                                                                                                                             POPUD via SCL’s Boundary Tap
                                                                                                                                                                                             Line and BPA’s Box Canyon Tap
                                                                                                                                                                                             Line.


Dry Creek – North   This project involves resagging the existing line from   Avista                                                                 Complete       Complete                  The line was resagged to meet a                                               Single System
Lewiston 230 kV     Avista’s Dry Creek substation to Avista’s North Lewiston                                                                                                                 498 MVA (in place of the 684                                                  Project
Reconductor         substation. The line is approximately 8 miles in length.                                                                                                                 MVA) requirement needed to
                                                                                                                                                                                             serve load in the
                                                                                                                                                                                             Lewiston/Clarkston area.

Libby (FEC)-Troy 115 Rebuild the Libby (FEC)-Troy 115 kV line (approximately BPA                                                                    under                  2009 $19          Replacement of aging line                                                     Single System
kV Line Rebuild      17 miles) with new single circuit 115 kV conductor.                                                                            construction                million                                                                                    Project



Spokane Area 230    Add a 230/115 kV autotransformer in the Sunset          Avista                                             Project identified                          2015              To provide capacity to meet load                                              Single System
kV Reinforcement    substation area with 230-kV lines to Westside and                                                          as future need -                                              growth in the south Spokane area                                              Project with
                    either Beacon/Boulder 230 kV switching stations                                                                                                                                                                                                        possible
                                                                                                                                                                                                                                                                           impacts


Planned Capacitors 13.42 MVARs @ Grangeville, 13.42 MVARs @ Nez             Avista                                                                                 2008, 2009,                                                                                             Single System
                   Perce, 6.7 MVARs X 3 @ Lind,                                                                                                                    2010                                                                                                    Project
                                                                                                                                 Northeastern Region Projects
                                                                                                                                               Project
                                                                                     Parties Impacted                                                         Scheduled    Cost                                                                      Plan cross
Project Name        Description                                            Sponsor                    Link to More Detail Project Stage        Commitment                             Project Need/Driver & Other Notes Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                     by Project                                                               Completion   Estimate                                                                  tribal lands
                                                                                                                                               Level
Proposed Capacitors 15 MVARs @Coeur d'Alene, Post Falls, Kettle Falls; 20 Avista                                          Projects                            1-5 years                                                 new                                         Single System
                    MVARs in Pullman area (Shawnee); 30 MVARs @ Airway                                                    identified as                                                                                                                             Project
                    Heights, Hallet and White; 50 MVARs @ Francis and                                                     short term need
                    Cedar

Moscow 230/115-kV Increase Moscow transformer capacity to 250 MVA          Avista                                         Project identified                  6-10 years                                                new                                         Single System
Upgrade                                                                                                                   as long term                                                                                                                              Project
                                                                                                                          need



Lewiston 10 Year    Second Hatwai-Lolo 230 kV line is one solution, Long   Avista    BPA, IPCO, PAC                       Project identified                  10 years                Loss of Hatwai-Lolo and Hatwai-   new                                                           Needed
Plan                range study needed                                                                                    as long term                                                North Lewiston 230 kV lines for
                                                                                                                          need                                                        heavy flows to Walla Walla and
                                                                                                                                                                                      Idaho

Tri-Cities          Add a 115 kV bus sectionalizing breaker at White Bluffs BPA                                           Plan of service      Included in     2010        $1.4       Load Growth and operational                                                   Single System
Reinforcements      Substation and reterminate the Richland and DOE B3-                                                   determined           sponsors budget             million    flexibility                                                                   Project
                    S4 lines.

Tucannon-Walla     Rebuild the Tucannon-Walla Walla 115 kV line section    BPA                                                                                                        Repair aging line                                                             Single System
Walla Line Upgrade with new structures and higher capacity conductor.                                                                                                                                                                                               Project


Little Goose Area   Add 40 mile 500 kV line from new wind collection       BPA                                            Project              Depends upon   September    $99        To serve requests made under      New                                         Requested
Reinforcement       station to Lower Monumental Substation                                                                Committed            NEPA           2013         million    2008 Network Open Season                                                      Service Project
                                                                                                                          under Network
                                                                                                                          Open Season



Walla Walla-McNary PacifiCorp is proposing to build a 230-kV line from     PAC and BPA                                    In WECC Phase 1                     2012                    Transmission Service Requests                                                 Requested       TCWG
230 kV line        Walla Walla to Wallula to McNary/Boardman/Echo          Avista                                         Rating process in                                                                                                                         Service Project
                   area. Avista is looking to expand this project to                                                      TCWG
                   accommodate requests they have received.
                                                                                                                                        Western Region Projects
                                                                                 Sponsor                                                          Project
                                                                                           Parties Impacted                                                         Scheduled                    Project Need/Driver & Other                                Plan cross
Project Name             Description                                                                        Link to More Detail Project Stage     Commitment                     Cost Estimate                                 Changes from Previous Plan                  Type of Project    Study Team(s)
                                                                                           by Project                                                               Completion                   Notes                                                      tribal lands
                                                                                                                                                  Level
Lebanon Area             Add a 19.6 MVAR, 115 kV shunt capacitor bank at         BPA                                            Plan of service   Funding           2010         $3 million      Load Growth                   Changed plan from                           Single System
Reinforcement            Lebanon Substation                                                                                     determined        approved by                                                                  230/115 Transformer
                                                                                                                                                  sponsor
I-5 Corridor (SW      Construct a new 500 kV line (approx. 70 miles) from        BPA       PAC Swift                            Project           Depends upon      2015         $300 million    Transmission Service                                                      Requested       I-5 Corridor
Washington - NW       Troutdale Substation to the new Castle Rock                          Troutdale                            Committed         NEPA                                           Requests                                                                  Service Project Regional
Oregon Reinforcement) substation located approximately 12 miles north of                   project                              under Network                                                                                                                                              Planning
                      Allston Substation on the Paul-Allston No.1 500 kV                                                        Open Season                                                                                                                                                Study Team
                      line.

Pearl – Sherwood 230     PGE and BPA plan to re-terminate the existing double PGE and W ith BPA                                                   Project identified 2017                        Reliability and Load growth   Delay from 2015                             Multi-system
kV                       circuit operating in parallel between BPA’s Pearl     BPA                                                                as future need - November                                                                                                EOP with only
                         Substation and PGE’s Sherwood Substation. This will                                                                                                                                                                                               one ColGrid
                         require two new circuit breakers. When the project is                                                                                                                                                                                             participant
                         completed, there will be a Pearl-Sherwood #1 230-kV
                         circuit and a Pearl-Sherwood #2 230-kV circuit.



Chemawa 230/115 kV       Add a new 230/115 kV Transformer at Chemawa             BPA                                                              Project identified 2016        $5 million      Load Growth                                                               Single System
Transformer Bank         Substation                                                                                                               as future need -

Cross-Cascades South     Station K development connecting Ashe-Marion,           BPA       PGE, PAC                                               Conceptual                                     Load Growth                                                               Multi-system
                         Buckley-Marion and both John Day-Grizzly lines                                                                           project for                                                                                                              EOP with only
                         together at a new station where the lines cross is                                                                       future need                                                                                                              one ColGrid
                         proposed.                                                                                                                                                                                                                                         participant

Carver-McLoughlin 230- PGE plans to construct a second transmission line      PGE                                                                                   Completed                                                                                              External Project
kV #2 line             from Carver Substation (Carver, Oregon) to their
                       McLoughlin Substation (Oregon City, Oregon). This
                       project requires five miles of new 230-kV transmission
                       line.

Horizon 230/115-kV       PGE plans to install a 230/115-kV, 320 MVA auto-        PGE       Connection to                                                            2010                                                       Project modified to add                     External Project
transformer              transformers at Horizon Substation, located in                    BPA via Keeler                                                                                                                      transformer at new
                         Hillsboro, Oregon. This project requires construction                                                                                                                                                 Horizon Substation
                         of a new 230-kV transmission line from Sunset                                                                                                                                                         instead of Sunset
                         Substation to Horizon (approximately 1 mile).


Blue Lake-Gresham 230- PGE plans to construct a transmission line from Blue      PGE                                                                                Jun 2015                                                                                               External Project
kV Line                Lake Substation (Troutdale, Oregon) to Gresham
                       Substation (Gresham, Oregon). This project requires
                       4.2 miles of new 230-kV transmission line.


Swift-Troutdale 230-kV   PacifiCorp is proposing to build a new 230-kV line      PAC       BPA                                  Re-evaluating                       2014                                                                                                   External Project
line                     from Swift Reservoir to Troutdale Substation east of                                                   need
                         Portland.
                                                                                                                                       Western Region Projects
                                                                                Sponsor                                                         Project
                                                                                          Parties Impacted                                                        Scheduled                    Project Need/Driver & Other                                Plan cross
Project Name             Description                                                                       Link to More Detail Project Stage    Commitment                     Cost Estimate                                 Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                          by Project                                                              Completion                   Notes                                                      tribal lands
                                                                                                                                                Level
Longview-Cowlitz 115kv Create second 115kv connection between BPA            Cowlitz      BPA                                                   Project under     2011         $5 million      Reliability and Load growth   Updated schedule                            Single System
#2                     Longview and BPA Cowlitz. This will be done by using                                                                     Construction                                                                                                             Project
                       existing Cowlitz 69kv circuit and converting to 115kv
                       from BPA Longview through Washington Way and 7th
                       ave substations and adding tap from 7th Ave to BPA
                       Cowlitz.


Bakers Corner            Create looped feed for Bakers Corner sub by tapping Cowlitz      BPA                                                   Project under     2010         $150,000        Reliability and Load growth   Updated schedule                            Single System
                         to BPA Longview to Lexington 115kv. Bakers Corner is                                                                   study                                                                                                                    Project
                         currently radial from BPA Longview


Rogue SVC (South         Add a -45 to +50 MVAR, Static VAR Compensator (SVC) BPA                                                                under             2009         $9 million      Southern Oregon Load                                                      Single System
Oregon Coast)            at Rogue Substation connected to the 115 kV bus                                                                        construction                                   growth - needs dynamic SVC                                                Project
                                                                                                                                                                                               control v. static caps.
South Oregon Coast       Construct a new 115 kV transmission line to provide a BPA                                                              Project under     2015         $30 million     Load growth along                                                         Single System
Transmission             new source to the South Oregon Coast load area                                                                         study                                          southern Oregon coast                                                     Project
Reinforcement



Kalama Energy            Construct new 230kv line from BPA Longview to          Cowlitz                                        Project under    Conceptual        2012-2018    $20 million                                                                               Single System
                         Kalama. Line will be needed for either connection of                                                  study            project for                                                                                                              Project
                         the new Kalama Energy 680 MW gas turbine project                                                                       future need
                         and/or to provide for load growth in area.

Allston Shunt Capacitors Add 500-kV shunt capacitor at Allston Substation       BPA                                                             Not needed with                                To meet load growth          Cancelled from plan
                                                                                                                                                I-5 project                                    projections in greater
                                                                                                                                                                                               Portland load area
Eugene-Albany Rebuild Rebuild a section of the Albany-Eugene 115 kV line        BPA                                                             Plan of service   2011                         To meet load growth                                                       Single System
                      with new structures and higher capacity conductor                                                                         determined                                     projections and repair aging                                              Project
                                                                                                                                                                                               line
Longiew-Lexington 115    Create a connection between BPA Longview and         Cowlitz                                                           Under             2013                         Reliability and Load growth Addition to Plan                              Single System
kV line #2               Lexington Stubstations through Cowlitz substations                                                                     Construction                                                                                                             Project
                         (Mint Farm, Olive Way, 20th and Ocean Beach and
                         West Kelso).
Longview-Lexington-      Create a connection between BPA Longview,            Cowlitz                                                           Funding           2014                         Reliability and Load growth   Addition to Plan                            Single System
Cardwell 115 kv line     Lexington, East Kelso and Cardwell substations                                                                         apporved by                                                                                                              Project
                         through Cowlitz substations with a 115 kV connection                                                                   sponsor
                         between East and West Kelso.

Trojan-Horizon 230 kV    Provide additional capacity to move Port Westward      PGE       Impacts to                           Project under                                                   Transmission Service          Addition to Plan
line                     and Beaver generation to Portland load area.                     South of Allston                     study                                                           Request

Parish Gap Substation    Construct a new 230/69 kV substation connected to      PAC                                                                               2011                         Reliability and Load growth   Addition to Plan
                         the Bethel-Fry 230 kV line in the Albany area
Medford 230/115 kV       Add a 230/115 kV substation in the White City area     PAC                                            Project under                                                   Reliability and Load growth                                               Single System
Transformer addition     fed from the Grants Pass-Meridian 230 kV line                                                         study                                                                                                                                     Project
                                                                                                                                         Eastern Region Projects
                                                                                                                                                      Project
                                                                                               Parties Impacted                                                         Scheduled    Cost       Project Need/Driver & Other                                Plan cross
Project Name             Description                                               Sponsor                      Link to More Detail Project Stage     Commitment                                                              Changes from Previous Plan                  Type of Project    Study Team(s)
                                                                                               by Project                                                               Completion   Estimate   Notes                                                      tribal lands
                                                                                                                                                      Level
Lower Valley             This is a joint project with BPA, PacifiCorp, and Lower   BPA/ PAC/                                                          construction on   2011          $16       Load Growth in Eastern        Project delayed from 2010                   Multi-system
Reinforcement (Hooper    Valley Energy. PacifiCorp will construct Three Mile       Lower                                                              hold pending                   million    Idaho                         to 2011                                     EOP with only
Springs)                 Knoll - a new 345/138 kV substation. The Goshen-          Valley                                                             agreement                      for BPA                                                                              one ColGrid
                         Bridger 345 kV line will be looped-into the new           Electric                                                                                          portion                                                                              participant
                         substation. BPA will construct Hooper Springs - a new
                         138/115 kV substation. Lower Valley Energy will
                         construct a new double circuit 115 kV line
                         (approximately 20 miles) from Hooper Springs to
                         Lanes Creek/Valley Substations.



COI Reinforcement (4800 This project includes 2-500 kV series capacitor groups BPA                                                  Plan of service   Funding           2012         $63        Remove nomogram                                                           Capacity
MW)                     added at Bakeoven; 2-500 kV shunt capacitor groups                                                          determined        approved by                    million    limitations on COI                                                        Increase Project
                        added at Captain Jack; and a 500 kV shunt capacitor                                                                           sponsor
                        group added at Slatt substation. This project also
                        includes upgrading the John Day-Grizzly 500 kV lines
                        No.1 & 2, and control and communications.




Redmond 230/115 kV       Add a second 230/115 kV transformer bank at               BPA                                              Plan of service   Funding           2011         $12        Load growth in the area                                                   Single System      Joint studies
Transformer Bank No.2    Redmond substation.                                                                                        determined        approved by                    million                                                                                                 w/PAC, BPA
                                                                                                                                                      sponsor                                                                                                                                and Central
                                                                                                                                                                                                                                                                                             Electric Coop




Celilo Upgrades          Replace the Celilo controls.                              BPA                                              Project under     Included in       2012         $35        Replace aging control                                                     Capacity
                                                                                                                                    study             sonsors budget                 million    equipment on DC terminal                                                  Increase Project


McNary - John Day         Construct a new 500 kV line (approximately 79 miles) BPA                                                  Project           In permitting     December     $175       Transmission Service                                                      Requested       West of
                         from McNary to John Day Substation                                                                         Committed         process           2012         million    Requests                                                                  Service Project McNary
                                                                                                                                    under Network                                                                                                                                         Regional
                                                                                                                                    Open Season                                                                                                                                           Planning
                                                                                                                                                                                                                                                                                          Study Team


Big Eddy - Knight        Construct a new 500 kV line (approximately 29 miles) BPA                                                   Project           In permitting     February     $66        Transmission Service          Knight Substation was                       Requested       West of
                         from Big Eddy to a new Knight Station, which                                                               Committed         process           2013         million    Requests                      formerly called Station Z.                  Service Project McNary
                         connects to the Wautoma-Ostrander 500 kV line. (3                                                          under Network                                                                                                                                         Regional
                         breaker ring bus)                                                                                          Open Season                                                                                                                                           Planning
                                                                                                                                                                                                                                                                                          Study Team


Pilot Butte 500/230 kV   Add a 500/230 kV transformer at Pilot Butte or in the BPA             PAC                                  Preliminary     Project identified 2014                     Load growth and loss of the Changed transformer                           Multi-system
Transformer Bank         vicinity.                                                                                                  engineering and as future need -                            existing transformer        location from Ponderosa                       EOP with only
                                                                                                                                    NEPA                                                                                    to Pilot Butte                                one ColGrid
                                                                                                                                                                                                                                                                          participant
                                                                                                                           Eastern Region Projects
                                                                                                                                       Project
                                                                                 Parties Impacted                                                      Scheduled    Cost       Project Need/Driver & Other                                Plan cross
Project Name           Description                                     Sponsor                    Link to More Detail Project Stage    Commitment                                                            Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                 by Project                                                            Completion   Estimate   Notes                                                      tribal lands
                                                                                                                                       Level
Sandpiper Substation   Add 500 kV Switchyard on the new John Day McNary BPA                                           Project          In permitting   2012                    Integrate wind generation     new project                                 Requested
                       500 kV line where Ashe-Marion lines cross to                                                   Committed        process                                                                                                           Service Project
                       integrate wind genertion; also called Mercer Ranch                                             under Network
                                                                                                                      Open Season
                                                                                                                                                   Regional Projects
Project Name                                                                                                                       Project Stage        Project            Scheduled
                                                                                            Parties Impacted                                                                                          Project Need/Driver & Other                                Plan cross
                         Description                                              Sponsor                    Link to More Detail                        Commitment         Completion Cost Estimate                                 Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                            by Project                                                                                                Notes                                                      tribal lands
                                                                                                                                                        Level
West of McNary Area      This project consists of a new 500 kV line               BPA                                              Completed            Project           M-JD:        $241 million   Transmission Service          Knight Substation was                                         ColGrid West
Reinforcement Project    (approximately 79 miles) from McNary to John Day                                                          WECC Regional        Committed         December                    Requests                      formerly called Station Z.                                    of McNary
                         Substation and a new 500 kV line (approximately 29                                                        Planning through     under Network     2012,    BE-                                                                                                            Regional
                         miles) from Big Eddy to a tap point (3 breaker Ring at a                                                  ColumbiaGrid         Open Season. In   Knight:                                                                                                                 Planning
                         new station called Knight) along the Wautoma-                                                             Study Team, now      permitting        February                                                                                                                Study Team
                         Ostrander 500 kV line.                                                                                    in Technical         process.          2013                                                                                                                    and TCWG
                                                                                                                                   Coordination
                                                                                                                                   Work Group
                                                                                                                                   (TCWG)




I-5 Corridor Project (SW This project consists of a new 500 kV line (approx. 70   BPA       PAC (Swift                             Completed            Project         2015           $300 million   Transmission Service                                                                        ColGrid I-5
Washington - NW          miles) from Troutdale Substation to a Castle Rock                  Troutdale                              WECC Regional        Committed                                     Requests                                                                                    Corridor
Oregon Reinforcement) Substation located approximately 12 miles north of                    project, PGE                           Planning through     under Network                                                                                                                             Regional
                         Allston Substation on the Paul-Allston No.1 500 kV                 Trojan-Horizon                         ColumbiaGrid         Open Season. In                                                                                                                           Planning
                         line.                                                              230 line                               Study Team, now      permitting                                                                                                                                Study Team
                                                                                            project)                               in Technical         process.                                                                                                                                  and TCWG
                                                                                                                                   Coordination
                                                                                                                                   Work Group
                                                                                                                                   (TCWG)




Cascade Crossing         The Cascade Crossing Project is a 200 mile line from    PGE        BPA                                    In WECC Rating                         2015                        Transmission Service          Formerly called the                                           TCWG
Project                  PGE’s Coyote Springs generation plant in the town of                                                      process in TCWG                                                    Requests                      Southern Crossing Project.
                         Boardman, Oregon west to PGE’s Bethel substation in                                                                                                                                                        Inservice date delayed
                         Salem, Oregon where the line will be terminated into a                                                                                                                                                     from 2013 to 2015.
                         new 500/230 kV transformer bank. The new line will
                         also interconnect with a new substation 72 miles east
                         of Salem called Juniper Flat which will be the point of
                         interconnection for new wind generation projects.
                         The project will also interconnect at the existing
                         Boardman substation. The proposed rating of the
                         single circuit 500 kV transmission line is 1500 MW.




Gateway West Project     Idaho Power and PacifiCorp are proposing a joint       Idaho                                              In WECC Rating                         2013                        Transmission Service                                                                        TCWG
                         project with a double circuit 500-kV line from Jim     and PAC                                            process in TCWG                                                    Requests
                         Bridger (Wyoming) to Hemingway substation in the
                         Boise area. This project is being planned with a 3,000
                         MW capacity.
                                                                                                                                                  Regional Projects
Project Name                                                                                                                      Project Stage        Project         Scheduled
                                                                                           Parties Impacted                                                                                       Project Need/Driver & Other                                Plan cross
                          Description                                            Sponsor                    Link to More Detail                        Commitment      Completion Cost Estimate                                 Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                           by Project                                                                                             Notes                                                      tribal lands
                                                                                                                                                       Level
Hemingway-Captain         In conjunction with the Gateway West project,            PAC     BPA                                    In WECC Rating                      2014                        Transmission Service                                                                        TCWG
Jack Project              PacifiCorp is proposing to extend this project from                                                     process in TCWG                                                 Requests
                          Hemmingway into southern Oregon with a new 375
                          mile, 500-kV line to Captain Jack. This line is expected
                          to add 1,500 MW of capacity to support westside load
                          growth and increase east to west path capability.




Hemingway - Boardman In conjunction with the Gateway West project, Idaho Idaho             BPA, Avista,                           In WECC Rating                      2012                        Transmission Service                                                                        TCWG
Project              Power is looking to extend this project from                          PAC                                    process in TCWG                                                 Requests
                     Hemingway further to the north and west with
                     possible western terminals at NEO, Boardman or
                     McNary. The project is intended to provide 1,500 MW
                     of capacity in both directions.



PG&E Canada - Pacific     PG&E is proposing an AC line from Selkirk substation PG&E        BPA, PSE, PGE,                         In WECC Rating                      2015                                                                                                                    TCWG
Northwest – Northern      in SE British Columbia to the Boardman/NEO area,                 PAC                                    process in TCWG
California Transmission   along with an High Voltage DC line from the Boardman
Line Project              area to the Tesla/Tracy area in the San Francisco Bay
                          area. The bi-directional capacity of this line is planned
                          to be 3,000 MW. Interconnections to this project
                          have been proposed at Devil's Gap, McNary and
                          Round Mountain in Northern California.




Devil's Gap               In conjunction with the PG&E Canada-NW-Northern        Avista    BPA                                    In WECC Rating                      2015                                                                                                                    TCWG
Interconnection to        California Project, Avista is proposing an                                                              process in TCWG
Canada - PNW –            interconnection at Devil’s Gap west of Spokane.
Northern California
Transmission Line
Project

Northern Lights Project Northern Lights Transmission is proposing a High       Northern BPA                                       In WECC Rating                      2014                                                                                                                    TCWG
                        Voltage Direct Current line beginning at Edmonton,     Lights                                             process in TCWG
                        Alberta and ending near Maupin, Oregon. At least
                        one intermediate terminal is planned in a location
                        south of Calgary, near Alberta’s largest wind
                        development region. The project is planned to be a bi-
                        directional line with an expected capacity of up to
                        3,000 MW. This project takes advantage of the
                        diversities in load and generation between the two
                        areas.



Juan de Fuca Cable        SeaBreeze Pacific is proposing an underwater 550 MW SeaBreez BPA, PSE                                   In WECC Rating                                                                                                                                              TCWG
Project #1                HVDC Light cable from Vancouver Island in BC to the e                                                   process
                          Port Angeles WA area across the Strait of Juan de
                          Fuca. This project rating is planned to be bi-
                          directional.
                                                                                                                                             Regional Projects
Project Name                                                                                                                 Project Stage        Project         Scheduled
                                                                                      Parties Impacted                                                                                       Project Need/Driver & Other                                Plan cross
                      Description                                           Sponsor                    Link to More Detail                        Commitment      Completion Cost Estimate                                 Changes from Previous Plan                  Type of Project   Study Team(s)
                                                                                      by Project                                                                                             Notes                                                      tribal lands
                                                                                                                                                  Level
Juan de Fuca Cable    SeaBreeze Pacific is proposing an underwater HVDC   SeaBreez BPA                                       In WECC Rating                                                                                                                                              TCWG
Project #2            cable from Prince Rupert (Northern BC) to Vancouver e                                                  process
                      Island (SW BC) to Allston substation in NW Oregon
                      near Ranier to San Francisco Bay area. This project
                      has a planned capacity of 1600 MW.


Walla Walla-McNary    PacifiCorp is proposing to build a 230-kV line from   PAC and BPA                                      In WECC Phase 1                     2012                        Transmission Service                                                                        TCWG
230-kV line Project   Walla Walla to Wallula to McNary area.                Avista                                           Rating process in                                               Requests
                                                                                                                             TCWG
Project Stage         ProjectCommitment         Tribal Type of Project
                                                       Existing Obligation
Conceptual Project    Project identified as            Project
for future need       future need -             Yes
                                                       Capacity Increase
Project under                                          Project
study; needed this    Included in sponsors
planning cycle        budget                    No
Project under         Funding approved by              Service Request Project
study                 sponsor
Plan of service                                        Existing Obligation
determined                                             Project with Expanded
                      siting permits obtained          Scope
Agreement by                                           Single System Project
responsible parties
(what to build,
who builds,
schedule, who
pays)                 under construction
approved by                                            Multi-system EOP with
ColumbiaGrid                                           only one ColGrid
Planning process                                       participant

						
Other docs by lpm55956
Concierge Company Sales Letter - Excel
Views: 32  |  Downloads: 0
Conceptual Physics Worksheet - PowerPoint
Views: 177  |  Downloads: 0
Concert Tour Contract - PowerPoint
Views: 64  |  Downloads: 0
Conditional Offer to Buy Realestate
Views: 39  |  Downloads: 0
Concert Event Planner Worksheet - Excel
Views: 156  |  Downloads: 0
Conclusion on Start Small Business
Views: 347  |  Downloads: 0
Concrete Business Forms
Views: 7  |  Downloads: 0