Ministry Finance and Economic Development (MOFED) Expenditure Management and control Reform Program Consultancy Procurement Plan for 2007/08
Country/Organisation:ETHIOPIA Project/Programme:EMCP
S/NO Description* Package Number
In 000 USD
Selection Method
Lumpsum or Time-Based Estimated Amount in US$ '000 Prior/Post Review
Plan vs. Actual
Prep & Submission by Exec Agency
No-objection Date
Date Published
Lead-time before shortlist
Submission Date
No-objection Date
Invitation Date
Submission/ Opening Date
Submission Evaluation Report (T)
No-objection Evaluation Report (T)
Opening Financial Proposals
Preparation Eval Report (T) (F)
Negotiations No-objection Submission Date (N) Date
Contract Amount in US$ '000
Prepare manual & training module on program budgeting, engage consultant 1 Prepare TOR and engage consultant to study the Stock management system. 2 Impact Assessment of EMCP's different activities at Federal, Regional, Zone & Woreda level Coverage of assessment 20%by local consultant Consultant to EMCP coordinating Office to help the office in different coordinating activities for one Year Per month birr 20,000.00 Consultancy Service To Develop Procurement Manual,traning module, Conduct training of trainers & provide trainings all federal & regional procurement staff EMCP/G-02/08 IC EMCP/G-01/08 LC
Lumpsum 54.23 Post Plan ######## 18-Dec-07 28-Dec-07 12-Jan-08 22-Jan-08 21-Feb-08 2-Mar-08 9-Mar-08 24-Mar-08 31-Mar-08 15-Apr-08 NA
Lumpsum 43.1 Post Plan 8-Dec-07 28-Dec-07 7-Jan-08 22-Jan-08 1-Feb-08 2-Mar-08 12-Mar-08 20-Apr-08 5-May-08
Lumpsum EMCP/G-03/8 LC 54.23 Post Plan 18-Dec-07 7-Jan-08 17-Jan-08 1-Feb-08 11-Feb-08 12-Mar-08 22-Mar-08 29-Mar-08 13-Apr-08 20-Apr-08 5-May-08
3
4
EMCP/G-04/8
IC
Time Based
19.52 Post
Plan
28-Dec-07
17-Jan-08 27-Jan-08 11-Feb-08
21-Feb-08 22-Mar-08
1-Apr-08
15-Apr-08
30-Apr-08
5
**
Lump sum EMCP/G-01/07 QCBS 119.85 Prior Plan ######## 25-Nov-07 5-Dec-07 15-Dec-07 25-Dec-07 1-Jan-08 15-Feb-08 31-Mar-08 15-May-08 25-May-08 4-Jun-08 14-Jun-08 24-Jun-08 4-Jul-08 19-Jul-08 NA
NB-Consultency activity marked with
**was incorporated in 2006/07Procurement Plan and
approved by the WB.
Contract Award
Contract Signature
Beneficeries
25-Apr-08
10-May-08 Budget Reform
15-May-08
30-May-08 Property reform
15-May-08
30-May-08
EMCP
10-May-08
25-May-08
EMCP
3-Aug-08
18-Aug-08 Legal Reform
Ministry Finance and Economic Development (MOFED) Project/Program Expenditure Management and control Reform Program(EMCP) Goods Procurement Plan for 2007/08
In 000 USD
Loan #:CR.3899-ET Quantity Estimated Amount in US $
BASIC DATA
Lot Number Procurement Pre-or Post Prior or Post Method Qualification Review Plan vs. Actual
Draft Bid Documents, including specs and quantities, draft SPN
Prep & Submission by Ex Agency No-objection Date
SPN Advert
On-line UNDB Nat Press
Bidding Period
Bid Invitation Date Bid ClosingOpening
Bid Evaluation
Submission Bid Eval Rpt Noobjection
Contract Finalization
Contract Amount in US$'000 Date Contract Award Date Contract Signature
S/NO
Description*
Package Number
IT Equipement
1 Lap top computer 19
MoFED G-01/08
44.82 1
NCB
post
post
Plan Actual
02/Oct./07
NA
8-Oct-07 12/oct./06
12/Nov./06
27/11/200 7 NA
########
24-Dec-07
SOFTWARE & HARDWARE
Procurement IFMS Softwaer & Hardwaer # #
MoFED G-06/07
10000.00
ICB
prior
prior
Plan
Accomplished
Accomplished
Accomplished
Accomplished
Accomplished
15-Nov-07 10-Dec-07
24-Jan-08
30-Jan-07
2 NB
1
Actual
## - An item which was incorported in 2006/07 Procurement plan , approved by World Bank and under process of action. - An amount USD 3,255,040.00 budgeted for 2007/08 fiscal year
Beneficeries
IFMS Project & all regions
MOFd,NBE,NBE ...
Ministry Finance and Economic Development (MoFED/AA/) Expenditure Management and control Reform Program Training Procurement Plan for 2007/08
LOAN NO. 3899 ET 1USD = 9:22 BIRR
Ser. Package No. No.
Activities
Type of Trainin Organizer g
In house
Legal Dep.
Venue (Town & Country)
MoFED/AA/
Duration
Period
Number Estimated of Cost in Beneficiary Participa USD'000' nts
180 4.88 Federal Budgetary Institution
1
EMCP/T-01/08
2
EMCP/T-02/08
Provide work shops for federal to discusses on financial laws, regulation and directive. Provide work shops for regions & city administration to discusses on financial laws, regulation and directive. Train federal and regional staff in procurement Provide Training procurement For trainers selected from regions Prepared prototype Procurement Guideline in a pool system environment at region zone or woreda levels & give training. Strength Budget Reform in Somali Region and provide Training. Select Training Institution & Provide Training for Regional/urban administrations budget Staff on budget Conduct work shop on revised Budget Manual
2 Days
Dec.15-20/07
In house
Legal Dep.
MoFED/AA/
2 Days
Dec.10-20/07
60
5.69
Federal Budgetary Institution Federal & all regions Federal & all regions Federal & all regions
3
EMCP/T-03/08
In house In house
Procurement
EMI
10 Days
May10-25/08
900
50.60
4
EMCP/T-04/08
Procurement
EMI
10 Days
Feb.05-25/08
90
5.53
5
EMCP/T-05/08
In house
Procurement
EMI
5 Days
Nov.20-30/07
45
11.88
6
EMCP/T-06/08
In house
Budget
Somali region
5 Days
Dec.15-28/07
600
21.69
Somali region
7
EMCP/T-07/08
Generic
Budget
EMI
1 month
Dec.10-31/07, Feb05-25/08
1200
54.23
All regions
8
EMCP/T-08/08
In house
Budget
MoFED/AA/
3 Days
Dec10-15/07
140
7.78
Federal Budgetary Institution
9
EMCP/T-09/08
Provide staff training to 30 federal & 70 regional staff on program budgeting Select Training Institution and Provide Training on cash management for federal & regional staff on Cash management reform provide training for regions on zero drawing account system & give continuous support strengthen Account Reform in Afar, Gambella & Somali. on modified cash base Conduct workshop on revised manual account manual Select Training Institution & Provide Training Regional/urban administrations Account Staff on modified cash based system
Give support on the internal Audit Manual and training module to Oromiya & Afar regions.
Train 1500 (of which 500 are federal & 1000 regional Staff) users and & IT professionals to enable them operate and implement the system
In house
Budget
MoFED/AA/
5 Days
Dec15-25/07
100
18.14
Federal & all regions
10
EMCP/T-10/08
In house
Cash management
EMI
5 Days
May10-20/08
500
99.08
Federal & all regions
11
EMCP/T-11/08
In house
Cash management
MoFED/AA/
5 Days
Apr15-25/08
60
10.30
All regions
12
EMCP/T-12/08
In house In house
Account
Afar, Gambella & Somali MoFED/AA/
10 Days
Dec05-25/07
1200
156.48
Afar, Gambella & Somali Regions Federal Budgetary Institution Federal & all regions
13
EMCP/T-13/08
Account
3 Days
Dec10-25/07
140
7.87
14
EMCP/T-14/08
Generic
Account
EMI
1 month
Dec01-25/07, Jan 05-30/08
1000
87.10
15
EMCP/T-15/08
In house
Internal Audit
Oromiya and Afar regions
10 Days
Dec05-21/07
15
1.63
Oromiya Afar regions
16
EMCP/T-16/08
In house
IFMS
MoFED/AA/
15 Days
Dec01-25/07, Jan 10-31/08
1500
61.93
Federal & all regions
17
EMCP/T-17/08
Training of trainers (high level technical training on IFMS to be provide abroad) Training on IBEX & BDA system & Install the system at federal & regional levels
Generic
IFMS
Selecting country
5 Days
May 05-15/08
3
17.35
IFMS
18
EMCP/T-18/08
In house
IFMS
MoFED/AA/
5 Days
Jan.10-25/08
60
10.63
Federal & all regions
19
EMCP/T-19/08
20
EMCP/T-20/08
Training staff at federal budgetary institutions on property management manual & prepare training module. Apply property management system on selected pilots regions for Tigray,Deradewa & Addis Ababa. Awareness creation on property management for regions Awareness creation for somale Region on account reform Give Coordination Support and Supervision to all regions
In house
Property
MoFED/AA/
10 Days
Jun10-30/08
180
12.38
Federal Budgetary Institution
In house
Property
Tigray,Deradewa & Addis Ababa
3 Months
Dec.01/07 up to Mar 31/08
50
6.51
Tigray,Deradewa & Addis Ababa
21
EMCP/T-21/08
In house In house In house
Property
MoFED/AA/
1 Days
Nov.25-30/07
60
4.89
All regions
22
EMCP/T-22/08
EMCP
Somali region
2 Days
Dec.25-31/07 Dec.01/07 up to Jun 30/08
250
10.85
Somali region
23
EMCP/T-23/08
EMCP
All regions
30 Days
50
21.69
All regions
TOTAL TRAINING PLAN FOR 2007/08
689.11