NREL Accrual System
Presentation to Oracle
User Group Meeting at
FMSIC
Kevin Novotny
April 14, 2009
NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy operated by the Alliance for Sustainable Energy, LLC
Custom Accrual System History
• Accounting Accrual Specialist maintained a manual accrual
system up until the mid 80’s
• Custom mainframe accrual system developed in 80’s for both
receiver and non-receiver required accruals.
• Custom Oracle receiver required (3-way match) system
developed in early 90s with implementation of Oracle
Purchasing, Oracle GL and Oracle Accounts Payable.
Mainframe receiver required system ended at this time.
• Custom Oracle non-receiver required (2-way match) systems
developed in the summer of 1999 to complete the replacement
of the mainframe system.
National Renewable Energy Laboratory Innovation for Our Energy Future
Monthly Accrual Transaction Volume
• Approximately 3,000 purchase order distribution lines meet
accrual criteria
• Approximately $50 million of costs are accrued
• Accruals and reversals are a standard month-end process
• Approximately 250 new and/or modified purchase orders and
subcontracts are manually reviewed for period of performance
determination
National Renewable Energy Laboratory Innovation for Our Energy Future
Oracle Accrual System Linkages
Purchasing
• Contract or purchase order period of performance
• Project number
• Expenditure type
• PO status (open, closed)
Payables
• Invoice information
Projects
• Project number validation
• Accrual costs by project and expenditure type
General Ledger
• Accrued costs by project and account
Other Systems
• Data warehouse (including commitment reporting)
National Renewable Energy Laboratory Innovation for Our Energy Future
Selection Criteria
3-way match
Receiver required
• P.O. line item(s) have been received (Oracle Receiver)
• P.O. line is open
• P.O. line is not fully invoiced
• No minimum dollar value
2-way match
Non-Receiver Action (NRA)
• P.O. header >$5,000
• P.O. is for non-capital equipment project type
National Renewable Energy Laboratory Innovation for Our Energy Future
Elements of Non- Receiver Accrual (NRA)
Program
• Collect Program
• Generate Schedule Program
• Calculate Accruals Program
• Review & Edit Accrual form
• Transfer to PA/GL Program
National Renewable Energy Laboratory Innovation for Our Energy Future
Elements of Non- Receiver Accrual (NRA)
Program
Collect Program
The program collects all POs meeting the following criteria for
subcontracts and other non-receiver POs:
• PO header total is $5,000 or more
• PO line(s) are not closed or cancelled
• PO is a 2-way match
NOTE: Start and end dates are required for calculation. POs without a
period of performance (POP) are placed on system hold for
manual input for the POP
National Renewable Energy Laboratory Innovation for Our Energy Future
Elements of Non- Receiver Accrual (NRA)
Program
Generate Schedule Program
• Generates accrual period lines for each PO line
• Updates accrual schedule for revised PO lines
• The period of performance (POP) start and end dates for the
PO lines is generated from the PO Header, contract, or
manually overridden by the Accrual Specialist
National Renewable Energy Laboratory Innovation for Our Energy Future
Elements of Non- Receiver Accrual (NRA)
Program
Calculate Accruals Program
There are four steps:
1. Calculates a preliminary straight-line accrual amount for each period of
the POP based on PO line value
2. Updates the accrual schedule for revised PO lines
3. Updates the Invoice Amount (from Accounts Payable) with any new
invoices in the current period
4. Calculates the actual accrual amount for the current period based on
prior month accrual reversal, current month schedule and current
month invoices
National Renewable Energy Laboratory Innovation for Our Energy Future
Elements of Non- Receiver Accrual (NRA)
Program
Accrual Specialist reviews and edits accrual form for:
•Subcontract and PO revisions to the standard calculation
•POP dates to subcontract and/or PO documents
•PO lines placed on “hold” by the program
•Requests from the Financial Analyst to modify the accrual schedule due to
incremental funding, variable work schedule or deliverable schedule
Accrual schedules may be adjusted at any time during the
month
Note: When accrual amounts are modified the accrual schedule must
always equal the PO line amount. PO lines are always fully accrued by
the end of the POP
National Renewable Energy Laboratory Innovation for Our Energy Future
Elements of Non- Receiver Accrual (NRA)
Program
Transfer to Projects/General Ledger
This program transfers calculated accrual amounts to Projects and
GL
• Project number(s) and expenditure type/account number are derived from PO
distribution lines
• One PO line may be split between multiple projects - accruals are prorated
based on PO line percentages – not applicable to subcontracts
• Various accrual liability accounts are used based on PO type
• Subcontract accruals
• Other non-subcontract accruals
• Reversal transactions are created with a reversal date in the following
accounting period
• The Oracle-delivered programs are run to load accruals into Projects and GL
National Renewable Energy Laboratory Innovation for Our Energy Future
Some Areas to Note
•Financial Analysts receive a preview of proposed accruals
about 5 days before each month end and after month end (data
provided via Excel)
•Period of performance changes (including contract extension)
require actual contract modification via Contracts and Business
Services
•Receipt Required accruals do not involve any manual
intervention
•Project managers or Financial Analyst review and input is
encouraged
•The accruals are run only once a month and limits NREL from
loading the data warehouse more frequently. There is a mid-
month Oracle report for accruals and invoices. NREL needs an
approach that will allow us to load our data warehouse more
frequently.
National Renewable Energy Laboratory Innovation for Our Energy Future
Conclusion
• Both the receiver required and non-receiver required accrual
systems are flexible, reliable systems
• Provides cost estimates for work performed or products received
but not yet invoiced
• Allows project manager input for service agreements and
subcontracts for better cost estimates
• Assist in management of uncosted balances
• Oracle allows view capabilities for financial analysts
• Data Warehouse allows data query and data extracts for detail
data and analysis needs
National Renewable Energy Laboratory Innovation for Our Energy Future
Custom Accrual System
Questions?
For more information about the accrual system please
Contact Phyllis Linenberger at 303-275-4525 or at
Phyllis.linenberger@nrel.gov
National Renewable Energy Laboratory Innovation for Our Energy Future
Related docs
Get documents about "