~-- ---~.-
Dislribution
.__.~..~.-~-_.._
Category UC-101
Comprehensive Rep.ort to Congress Clean Coal Technology Program
Demonstration in an Application of Pulse Combustion for Steam Gasification
A Project Proposed By: ThermoChem, Inc.
U.S. Department of Energy Assistant Secretary For Fossil Energy Office of Clean Coal Technology Washington, D.C. 20585 October 1992
September 4,200l
The following reports were obtained from NTIS and should be added to the Compendium. There will be two or three more packages of about this size to send you all of the reports we have. I suggest that once they have all been scanned we add a single item to the What’s New portion of the Home Page that says something like “X new reports now available in electronic format”. Then on the What’s New page itself we could list each of the reports with the appropriate link. Sound reasonable? 1) Comprehensive Report to Congress, Clean Coal Technology Program, Demonstration of Pulse Combustion in an Application for Steam Gasification, Oct. 1992 (DE93000959) 2) Passamaquoddy Technology, L.P., Interim Technical Report, March 1992 (DE920 19868) 3) The Encoal Project: Initial Commercial Shipment and Utilization of Both Solid and Liquid Products. Topical Report, March 1995 (DE95009735) 4) Encoal Mild Coal Gasification Project Public Design and Construction Report, December 1994 (DE9500971 1) 5) Encoal Mild Coal Gasification Project. Annual Report, October 1990 - September 1991, February 1992 (DE92001273) 6) Encoal Mild Coal Gasification Project. Annual Report, October 1993 (DE94012274) 7) Encoal Mild Coal Gasification Demonstration Project. Annual Report, October 1993 ~ September 1994, March 1995 (DE95009710) 8) Demonstration of an Advanced Cyclone Coal Combustor with Internal Sulfur, Nitrogen, and Ash Control for the Conversion of a 23 MMBtu/Hr Oil Fired Boiler to Pulverized Coal Final Technical Report, March, 1987 -February 28, 1991, August 1991 (DE92002587) 9) Demonstration of an Advanced Cyclone Coal Combustor with Internal Sulfur, Nitrogen, and Ash Control for the Conversion of a 23 MMBtu/Hr Oil Fired Boiler to Pulverized Coal. Final Technical Report, Appendices, August 1991 (DE92002588) 10) Desulfurization of Flue Gas by the Confined Zone Dispersion Process. Final Report, October 1989 (DE90005529) 11) Environmental Monitoring Plan, LIFAC Sorbent Injection Desulfurization Demonstration Project Note that report number 8 still has the NTIS cover and back page. Please don’t scan either of these pages. All of these reports (with the exception of 11) are listed on the Compendium with the NTIS number referenced. If you have any trouble locating where to put them in the Bibliography, let me know. Thanks, Mark
TABLE OF CONTENTS
1.0 2.0
3.0
EXECUTIVE SUMMARY .............................................. INTRODUCTIONAND BACKGROUND.................................... 2.1 Requirement for a Report to Congress ...................... 2.2 Evaluation and Selection Process .......................... ...................................... 2.2.1 PON Objective 2.2.2 Qualification Review ............................... ............................. 2.2.3 Preliminary Evaluation . .......................... 2.2.4 Comprehensive Evaluation ............................. 2.2.5 Program Policy Factors ............................... Other Considerations 2.2.6 2.2.7 National Environmental Policy .............................. Act (NEPA) Compliance 2.2.8 Selection .......................................... TECHNICAL FEATURES ............................................. ....................................... 3.1 Project Description 3.1.1 Project Summary .................................... 3.1.2 Project Sponsorship and Cost ....................... 3.2 Pulse Combustion in an Application for Steam Gasification of Coal ............................ ................. 3.2.1 Overview of Technology Development ................................ 3.2.2 Process Description 3.2.3 Application of Technology in _ ................................... Proposed Project ........................... 3.3 General Features of the Project 3.3.1 Evaluation of Developmental Risk ................... 3.3.1.1 Similarity of the Project to Other .......... Demonstration/Commercial Efforts ...................... 3.3.1.2 Technical Feasibility ..................... 3.3.1.3 Resource Availability 3.3.2 Relationship Between Project Size and ............. Projected Scale of Commercial Facility 3.3.3 Role of the Project in Achieving Commercial ...................... Feasibility of the Technology 3.3.3.1 Applicability of the Data to be ................................. Generated
1 3 3 3 4 4 5 5 6 7 7 7 8 8 11 11 11 11 17 18 20 20 21 24 24 25 25 25
TABLE OF CONTENTS
4.0 5.0
6.0
Identification of Features that Increase the Potential for Commercialization ....... 3.3.3.3 Comparative Merits of the Project and Projection of Future Commercial Economics and Market Acceptability ........ ENVIRONMENTAL CONSIDERATIONS ................................... PROJECTMANAGEMENT............................................. 5.1 Overview of Management Organization ...................... 5.2 Identification of Respective Roles and Responsibilities ......................................... 5.3 Project Implementation and Control Procedures ............ 5.4 Key Agreements Impacting Data Rights, Patent Waivers, and Information Reporting ....................... 5.5 Procedures for Commercialization of the Technology ....... PROJECTCOST AND EVENT SCHEDULING .............................. 6.1 Project Baseline Costs ................................... 6.2 Milestone Schedule ....................................... 6.3 Repayment Plan ...........................................
3.3.3.2
26
26 28 30 30 30 32 35 35 37 37 38 38
1.0 Public
EXECUTIVE SUMMARY Law No. 101-121 provided (CCT) projects retrofitting, Notice 1991. to $600 million demonstrate existing to conduct technologies facilities. cost-shared that are Clean Coal capable of end, a energyThese in the to
Technology replacing, January efficient technologies emissions minimize and/or manner.
or repowering
Toward that innovative, in the 1990s. reductions facilities
Program Opportunity
(PON) was issued by the Department proposals of being nitrogen to demonstrate significant commercialized oxides
of Energy (DOE) in
This PON solicited capable
technologies of sulfur environmental (2) providing
were to be capable of (1) achieving dioxide for and/or impacts, future
from existing and interstate
such as transboundary
pollution, acceptable
energy needs in an environmentally
In response to the PON, 33 proposals evaluation, facilities also facility. One of the nine projects entitled selected nine projects control and "repowering" generating were selected technologies advanced pollution increase
were received for award. that that
by DOE in May 1991. These projects involved
After both but of the
can be "retrofitted" the operating
to existing life
technologies plant capacity
not only reduce air pollution
and extend
for
funding
is
a project will provide
proposed
by
ThermoChem. Inc. demonstration
"Demonstration
of Pulse Combustion
in an Application a commercial Inc. of coal using International,
for Steam Gasification
of Coal" (PCASGC). This project
of the Manufacturing to provide
and Technology Conversion heat of reaction.
(MTCI) process for producing pulse combustion
medium-Btu gas by steam gasification the endothermic involves
The PCASGC demonstration ton/day indirect occurring the indirect product dry basis) heating
project
the construction unit. for the required
of a 428 ton/day The gasifier steam-coal bed. will
(300 use
fluidized to provide
bed, coal gasification the energy The heat will be generated
reaction
in the gasifier. heating will
be added to the gasifier
by means of of the
bundles of heat exchanger tubes submerged in the fluidized by pulse combustion gas, with the heat exchanger tubes acting 1
The hot gas for
of a portion
as the resonance tubes for the
pulse combustor. Product
Pulse combustion reducing
increases
heat transfer
rate
by a factor in the gasifier.
of
3 to 5, thus greatly gas, consisting carbon dioxide
the heat transfer
area required
predominantly
of hydrogen
(Hz), carbon monoxide (CO), to the
(CO,), and methane (CH,), is cooled and scrubbed to remove ammonia The cleaned product gas which is not sent as fuel power. and not receiving plant will any DOE costbe constructed will be byfeed be used to produce electric project
and hydrogen-sulfide. pulse combustor will Although adjacent exported product not part to the
of the demonstration MTCI gasifier. K-Fuel-
share funds,
a subbituminous
coal upgrading By-product plant, plant will
(KAFuel.)
steam from the -gasifier
for use by'the
and high-temperature, provide
high-pressure
water from the K-Fuel.
process steam and boiler
water for the gasifier. The PCASGCDemonstration Caballo Rojo Mine, located Rojo Mine will This.demonstration provide will project will be constructed Wyoming. at Caballo Rojo. Inc.'s
south of Gillette,
Coal from the Caballo
the feed coal to the gasifier. be conducted over.48 months. construction, is $37.333,474. start-up. Project activities include
design and engineering, The total project cost
and operations. is $18,666,737. The coto I
DOEIs share
funder is ThermoChem, whose share is $18.666.737. Operations are scheduled begin in 1994, and the project is scheduled for completion in 1996.
2
2.0
INTRODUCTIONAND BACKGROUND 2.1 Reouirement for a Reoort to Conaress funds for Law the fourth "An clean Act coal
On October demonstration
23. 1989, Congress made available program (CCT-IV) in Public
101-121.
Making for the "Act"). and of
Appropriations -for the Department of the Interior Fiscal Year Ending September 30. 1990. and for Among other things, operation future this Act appropriates of such 'I... . ..." "a general of cost-shared, existing effect, clean coal projects facilities requiring
and Related Agencies Other Purposes" (the
funds for the design, to demonstrate technologies request
construction, the feasibility
commercial applications
capable of retrofitting Law 101-512 for CCT-IV by projects request .for for
or repowering was signed into
On November 5, 1990, Public for proposals of make selections
no later than February 1, 1991. and to negotiations no later than eight months after proposals." Public Law 101-121 appropriates a total
the date of the general
of $600 million
for
executing
CCT-IV.
Of this total. $7.2 million are required to be reprogrammed for the Small Business Innovative Research Program (SBIR). and 625.0millfon are designated for Program Direction program. Funds for costs incurred by DOE in implementing for the CCT-IV The remaining $567.8 million was available award under the PON. which directs
The purpose of this the Department project selected
report
is to comply with Public a full and comprehensive
Law 101-512, report
to prepare
to Congress on each
for award under the CCT-IV program.
DOE issued a draft and took into received deadline.
PON for public
comment on November 20. 1990. receiving The final PON was issued on January on the draft comments received
a total 15, 1991, PON. DOE
of 19 responses from the public. consideration 33 proposals
the public
in response to the CCT-IV solicitation
by the May 17, 1991,
3
2.2.1 As stated obtain that demonstrate
PON Obiective 1.2, the objective cost-shared of the CCT-IV solicitation Clean Coal economically in the 1990s. or replacing for Technology competitive existing was to to must while the an in
in PON Section innovative,
"proposals
to conduct
projects technologies
energy efficient, repowering (2) manner." Review providing
are capable of being commercialized significant of nitrogen reductions and/or
These technologies facilities dioxide energy and/or needs
be capable of (1) retrofitting, achieving oxides
in the emissions
of sulfur future
environmentally 2.2.2
acceptable Qualification
The PON established be considered pass Qualification."
seven Qualification The Qualification
Criteria Criteria project
and provided
that.
"in order to
in the Preliminary
Evaluation
Phase, a proposal
must successfully
were as follows: or facility must be located in
(4 (b) (cl
The proposed demonstration the United States.
The proposed demonstration with coal(s)
project
must be designed for and operated in the United a cost-share at least States. of at least 50% of
from mines located
The proposer total three project
must agree to provide project phases. costs,
allowable
with
50% in each of the
(4 (e) (f)
The proposer
must have access to, and use of..the site(s) for the duration
proposed site of the project.
and
any proposed alternate The proposed project fulfilling The proposer Plan" its
team must be identified in the project. selected, 7.7. it
and firmly
committed to
proposed role agrees that, with if
will
submit a "Repayment
consistent
PON Section 4
(g)
The proposal proposing organization entirety. 2.2.3 Preliminarv that
must
be signed
by a responsible to of the Cooperative
official
of bind
the the
organization,
authorized
contractually
to the performance
Agreement in its
Evaluation Evaluation would be performed on all
The PON provided
a Preliminary
proposals that successfully passed the Qualification Review. In order to be considered in the Comprehensive Evaluation phase, a proposal must b,e consistent with the stated finance, Evaluation objectives of the PONand must contain cost, sufficient information on management. technical, described 2.2.4 The Technical Demonstration likelihood existing and other areas to permit the Comprehensive to be performed.
in the solicitation Evaluation
Comprehensive Criteria Factors
Evaluation Project
were divided
intotwomajor
categories: feasibility
(1) the and were from the the
were used to assess the technical and (2) the Commercialization meet future and the energy cost of the proposed technology as to use of coal.
of success of the project, facilities, as well acceptable
Factors through of
used to assess the potential environmentally
to reduce emissions needs effectiveness
proposed technology The Cost and Finance performance potential
in comparison Evaluation
to existing criteria
technologies. the business
were used to determine
and commitment of the proposer. the Cost Estimate proposed would cost. be of minimal project would be evaluated to determine the Proposers were advised that this to the selection..," selection. and that a Proposers were after
The PDN provided reasonableness determination detailed cautioned provide Sharing cost that of
that the
' . ..will estimate if
importance
be requested
the total
than the amount specified more funding Plan.
cost estimated after selection is greater to in the proposal, DOE would be under no obligation in the proposer's original Cost
than had been requested
5
2.2.5
Proaram Policv that Official
Factors the following to select program policy factors could be used would best
The PONadvised proposers by the Source Selection serve program objectives:
a range of projects
that
(4 0.‘)
The desirability a diversity
of selecting
projects
that
collectively
represent
of methods,
technical
approaches, projects
and applications. solicitation transport in emissions that of of
The desirability contribute pollutants sulfur
of selecting
in this
to near-ten by producing and/or
reductions an aggregate nitrogen
in transboundary net reduction
dioxide
oxides. projects that collectively conditions. that by the utilize a a
(cl
The desirability diversity
of selecting
broad range of U.S. coals
and are in locations and climatic
which represent
of EHSS. regulatory,
(4
The desirability achieve pollution a balance and
of selecting,projects between (1) reducing (2) providing for
in this ~solicitation emissions future energy needs fuels. strategic sites, total which
and transboundary
environmentally
acceptable
use of coal or coal-based projects that for form provide
(4
The desirability energy security provide multiple considerably requirements.
of selecting benefits fuel dependent
and are
for remote. resource on one
import-dependent options fuel for
or that energy
regions
The word "collectively." as used in the foregoing program policy factors, was defined to include projects selected in this solicitation and prior clean coal solicitations, as well as other ongoing demonstrations in the United States.
,
2.2.6 The PDN stated to projects treat technologies. application projects value. geographic of received
Other Considerations that, in making selections, in states DOEwould consider bodies giving preference projects if, factors, or after two
located This
for which the rate-making the same as pollution could criteria
of those states
the Clean Coal Technologies consideration the evaluation identical
control breaker policy
be used as a tie and the program if,
evaluation
scores and remained essentially by so doing. selected Policv would be significantly Act (NEPA) Comoliance
equal in altered.
This consideration distribution 2.2.7 National evaluation
would not be applied
the regional
of the projects Environmental
As part Policy
of
the
and selection for
process, with
the Clean Coal Technology the National Quality Environmental NEPA regulations were This in
Program developed (40 CFR 1500-1508). December 15, 1987). published procedure Final in the included
a procedure
compliance
Act of 1969 (NEPA). the Council DOE final Federal
on Environmental replacing 24.
and the DOE guidelines Register
for compliance with NEPA (52 FR 47662, the DOEguidelines of a publicly (DOE/EIS-0146). publicly 1992 (57 FR 15122). issued available
NEPA regulations on April Impact DOEuse.
the publication Environmental
and consideration Statement of confidential
available
Programmatic
November 1989. and the preparation environmental site-specific under NEPA. 2.2.8 After considering Selection the evaluation reviews for internal
preselection project
project-specific as appropriate
DOEalso prepares demonstration
documents for each selected
criteria,
the program policy
factors,
and the
NEPA strategy as stated in the PON, the Source Selection Official selected nine projects as best furthering the objectives of the CCT-IV PON. These selections were announced on September 12, 1991, during a press conference.
3.0
TECHNICAL FEATURES 3.1 Project Descriotion demonstrate the production of medium-Btu fuel gas by the MTCI
ThermoChem will
Feed to the gasifier will be Powder River PCASGCprocess. coal from the Caballo Rojo Mine, which has almost 450 million reserves. The,site
Basin subbituminous tons of recoverable
for the demonstration is the Caballo Rojo Mine near Gillette, plant Wyoming, as shown in Figure 1. The product fuel gas from the gasification will be utilized to generate electric or in anon-site Power & Light (K-Fuel.) power, either gas turbine (WPL), using facility as a supplemental private funding. will fuel in a nearby power plant subsidiary product system constructed by Enserv, a The bybe consumed by adjacent
of Wisconsin
steam produced from the waste heat of the gasifier coal upgrading which will
a subbituminous
be located
to the gasifier. The K-Fuel. plant will be constructed and operated by Enserv strictly with private funding; no DOE cost-share funds will be used. Locating the water the K-Fuel. process plant next to the MTCI gasifier feed enhances the environmental project, water because water from for process steam a sources. Since this
performance K-Fuel. is generation, significant by flashing the fluidized gasifier, process.
and economics of the PCASGC demonstration can be used as boiler to the gasifier of the gasifier's at ,elevated recovered thus eliminating
the need for water from other
delivered portion this
temperature from this to
and pressure, can be provided
process steam requirement In addition providing facility
water.
Any hydrocarbons
water are sent to steam to will the produce upgrading Figure 2 is with
bed to be gasified. high-pressure
the heat recovery system within Thus. the gasifier and K-Fuel.
the gasification processes integrate
enough export
steam to supply the needs of the K-Fuel. well. project
a block diagram other facilities.
showing how the PCASGCdemonstration
interfaces
8
Caballo Cabello Gillette,
Rojo Mine * Rojo .Incorporated WY
/
WYOMING
FIGURE 1. PCASGC DEMONSTRATION PROJECT LOCATION.
9
.~. E a
W 5
f
i
m 00
W
C r-
r
5 3
E - .2°C 02
L: ! 5: Y a,0
10
3.1.1 Project Proposer: Project Location: Title:
Project
Summary Demonstration of Pulse Combustion in Application for Steam Gasification of Coal ThenaoChem. Inc. Cabal10 Rojo Mine Gillette, Wyoming Campbell County an
Technology: Application: Type of Coal Used: Product: Project Project Project Size: Start Date: End Date: 3.1.2 Project Estimated Estimated Distribution: Sponsor: Project Cost Cost: Project
Indirectly Production steam
heated coal gasification as the heat source of medium-Btu fuel
process using
pulse combustion
gas and by-product coal
Powder River Low-sulfur. 428 ton/day August 1996 Sponsorshio
Basin subbituminous medium-Btu fuel (300 ton/day gas
on a dry basis)
September 1992
and Cost
ThermoChem, Inc. $37,333,474 Participant Share I%) 50 DOE gwLp3.l 50
3.2
Pulse Combustion in an Aoolication for Steam Gasification 3.2.1 of Coal Develoament this demonstration pulse The development of project:
Overview of Technoloov are incorporated into
Two technologies
combustion and indirectly heated steam gasification of coal. these technologies and their integration is described below. 11
Pulse include transfer
combustion
involves
combustion-induced
flow
oscillations
produced heat
intentionally rates
by the design of the equipment. in the resonance tubes. can be divided naturally, device, into
The benefits
of pulse combustion
enhanced heat release
rates in the combustion chamber and increased
Pulse combustors pulsations maintain belongs referred further occur the to into which require
two general
classes:
those in which the and those
due to combustion-induced
instability,
an external pulse
combustion
such as a spark plug or a flapper valve, to The combustor used in this project process. ,This class Schmidt, of combustors, combustors, and Rijke which can be can be divided of the
to the first three
of these classes. types, Helmholtz,
as self-induced
or resonating-pulse
tube type combustors,
depending upon the configuration oscillations.
of the combustor and the characteristics
The pulse combustor type employed by the MTCI and ThermoChem equipment design is the Helmholtz consists (or because it resonance configuration tube). This (see Figure air inlet combustor (flapper 3). The basic Helmholtz is configuration reliable, suitable for erode of an aerodynamic valve, a combustion chamber, and a tailpipe inherently It is especially
configuration valves). fuels,
has no moving parts
the combustion valve surfaces. The efficiency diffuses of combustion particles concentration as the burning oscillatory
of coal and other solid
since these fuels
can quickly
of a coal-burning (water and
furnace
depends upon the rate at which 'oxygen a boundary layer important and of products and oxygen of the motion as the coal the builds more up around the particle
to the coal surface.
During combustion. barrier.
vapor and carbon oxides) become smaller and
acts as an oxygen diffusion burn
T~his is particularly
ash-laden, In a Helmholtz relative
in the surrounding coal particles increases velocity
gas decreases.
pulse combustor,
flow down the resonance tube. and causes vigorous
the amplitude oscillatory
between the burning particle and the surrounding gas. This causes the diffusion barrier around the burning particle to be swept away, thus permitting access of oxygen to the particle release rate. and resulting in high carbon burnout and a high heat
12
0” ZW =ei 3 OtVW is h az
In 1982, DOE's Pittsburgh the development commercial, The initial the development and industrial
Energy Technology Center (PETC) began actively coal-fired market sectors. Under a DOEcontract, program was conducted
pursuing
andtesting,of
combustion systems for the residential. MTCI initiated in three phases. of pulse combustion.
of a new combustor,
based on the principle
pulse combustor development
Phase I included a review of the prior art on pulse combustion and the This work indicated potentially development of pulse combustor design concepts. favorable fired coal economics for replacement combustors. should of oiltype and gas-fired indicated rather rate) that equipment with pulse combustors tube) coalfor and pulse Work in Phase II be Helmholtz air inlet Btu/hr valves firing
applications
(chamber and resonance and testing burning
should employ aerodynamic Phase III involved valves. pulse combustor (1 million (CWM). The Phase III at heat release burners. rates
than the more common flapper of a laboratory-scale a coal-water mixture
the fabrication
results up,to
showed that coal can be burned in a pulse combustor 10 times higher than those achieved in conventional
Based on the success of the initial initiated the development
pulse combustor development pulse coal combustor Btu/hr) (100,000 for
program, for
MTCI
of a slagging
industrial residential industrial
retrofit applications and a smaller unit applications, both under DOE sponsorship.
Under the program for
retrofit applications, a slagging tandem pulse coal combustor system with dry coal fuel was developed and optimized at the laboratory scale (2 million Btu/hr). This unit was subsequently tested million scaled up to a 3.5 to 5 million Btu/hr firing rate and extensively with CWM. Recently, the design and construction of a 15 Btu/hr system was completed. In 1989, MTCI was awarded a DOE contract operate, Btu/hr and demonstrate a completely integrated and automated 5 system for market evaluation. is providing heat for the steam
to fabricate, to 6 million One application gasification oxygen into the process.
for the use of pulse combustion
of coal. Most commercial processes for coal gasification introduce the gasifier and burn part of the coal to provide the heat needed by The attractiveness of the in-situ heat transfer aspect of these
partial-oxidation gasification processes has been their relative simplicity compared to the complexity and high cost of indirectly heated systems. Some 14
indirectly other
heated systems require large heat transfer
two vessels
and complex solids
circulation; coefficients. heat on the
require
areas due to poor heat transfer
The low heat transfer fluidized-bed reactors flue
rate of conventional fire tubes used to indirectly is a result of the low heat transfer coefficient tube; the heat transfer is reasonably coefficient coefficient high. material
gas side of the fire
between the fire resulting
tube and the fluidized-bed in an increase In conventional in overall
In a pulse combustor, significantly, of 3 to 5. all the heat
the flue gas side heat transfer
is increased
heat transfer
rate by a factor
combustor and fire
tube arrangements.
essentially
the highest temperature is at is released in the combustion chamber. Therefore, the inlet to the fire tubes. The temperature of the flue gas monotonically decreases combustion along the length In pulse tubes) duty, of the tube, as heat is transferred combustion. however, for not all persists flue a significant from the flue length gas to the reactor. the fuel environment. burns in the down the Thus. for
chamber, and combustion
resonance tubes (fire the same heat transfer
in an oscillating the inlet
flow field
gas temperature
to the resonance
tubes is lower than in conventional fire tube 'systems. However, the continued heat release from burning fuel in the resonance tubes maintains a higher bulk flue gas temperature than in the conventional in an appreciably case. Thus. the use of a Helmholtz heat transfer area requirement. rate is the ability of the and the in very in the High in an pulse coal combustor results coefficient. An important reactor a high heat flux, benefit enhanced convective
and a reduced surface
of an enhanced heat transfer
to support highly
carbon-steam reaction. high rates of devolatilization formation of char particles rates viable reactor heat transfer economically Several are:
endothermic reactions, such as devolatilization Rapid heat transfer in the fluidized bed results and pyrolysis. that are extremely to support with a reasonable This, in turn, results reactions porous with high reactivity. such endothermic throughput.
are essential
carbon consuming reactions
occur in the gasifier.
the two most important
15
c + H,O = CO + H, c + co, = 2co A third reaction of importance is the water-gas-shift reaction:
CO + H,O = CO, + H, Generally, the steam-carbon gas. pulse-enhanced, indirect, steam gasification technology during was to an reaction controls the rate at which carbon is
consumed (gasified), of the product
and the water-gas-shift
reaction
determines
the composition
MTCI's proprietary first investigated
under Phase I and Phase II DOE/SBIR grants
1984-1986.
Under Phase II of this DOE/SBIR grant. testing of the gasifier was limited biomass feedstocks. In early 1987, Weyerhaeuser Paper Company expressed interest Preliminary gasifier further liquor, California in testing tests the MTCI gasifier were conducted technology funding using black liquor verified the feedstocks.
which
feasibility
of the MTCI In order to including black
to process black liquor develop this MTCI secured
feedstocks'safely from DOE, the
and effectively. Weyerhaeuser
for biomass waste gasification, Energy Technologies included technology,
Company, and the and verification of ofgasifier in early the for confined technology
Energy Commission's of these projects liquor
Advancement Program (ETAP). of a broad spectrum were completed
The objectives
process development testing
of the MTCI black biomass feedstocks scaleup
recovery
under varying
process conditions.
and verification
to feed rates
of 100-200 lb/hr.
These projects
1989 and yielded extremely successful commercialization potential of the indirectly biomass and waste gasification. A series 1030°F to feedstock. of process Gasifier characterization performance included tests, using
results which heated gasifier
covering
the temperature black during
range of liquor the test
1160°F. was conducted
a 67% solids-containing test 16 run.
met or exceeded expectations
program which also
a 40-hour
ThetmoChem, MTCI, 75 ton/day mill. tubes, black supported
ESI, liquor
and Weyerhaeuser gasifier by a DOE cooperative
are
fabricating
and
installing
a
for Weyerhaeuser's exchanger module. project:
New Bern, except for
North Carolina, the number of of the number
in part
agreement. however,
The New Bern project scaleup
uses the same pulse combustor/heat of tubes is a critical Over the indirectly feedstock. element
being used in the demonstration
in the demonstration. for the biomass
last two years. MTCI has been testing various feedstocks heated gasification reactor. In addition to the early MTCI has now tested a wide variety of materials, including
wastewater
refuse derived fuel (RDF), lignite. subbituminous coal, and mild sludge, gasification char. All these tests were conducted using the gasification system located rated at MTCI's Santa Fe Springs, at a nominal low-rank coal 40 lb/hr for other California, laboratory. of 15-30 lb/hr The gasifier bed. The gasifier (as received) is and the gas throughput feedstocks. combustor.
approximately heat exchanger resonance fuel. The discussion
is heated by means of using natural
tubes immersed in the fluidized
These tubes comprise
component of the pulse
which is fired
above shows that gasifier
both the pulse
combustor
and the
indirectly
heated fluidized-bed for demonstration. 3.2.2 This project an innovative, will
have undergone extensive
development and are ready
Process Descriotion demonstratetheMTC1 fluidized-bed clean, gasifier, fuel which incorporates steam gasification gas without the need the by the MTCI multiple
indirect-heating The indirect
process forthethennochemical medium-8tu heat transfer is provided reactor.
of coal to produce a hydrogen-rich, for an oxygen plant. heat exchanger
resonance tube pulse combustortechnology
with the resonance tubes comprising
immersed in the fluidized-bed
The high heat transfer
coefficient (3 to 5 times greater than for indirectly heated gasifiers not using pulse combustion) exhibited by the MTCI multiple resonance tube pulse combustor minimizes the required heat transfer surface.
17
A simplified Appropriately fluidized bundles, hot flue bed.
flow
diagram
of
the
MTCI' gasifier provides
is
shown
in
Figure
4.
sized coal and steam are fed to the fluidized-bed from waste heat recovery, Immersed in the fluidized gas from the gasifier through flue the the endothermic gas flows bed are a series
gasifier.
Steam,
which is supplied
the fluidization
gas for the Part of the and the the leaving heat the
of heat exchange tube
which serve as resonance tubes for the pulse combustors. gas passing to sustain the heat exchange bundles reactions. provides After
cleaned product necessary generated,
is burned in the pulse combustors. gasification
heat exchangers,
to a waste heat boiler.
where steam is
and then to a stack. gas from the gasifier goes first to a heat exchanger. where it
The hot product
superheats the gasifier process steam. It then passes through a cyclone for char removal and a waste heat boiler for steam generation. The cooled gas is then scrubbed SulFerox elemental with water process sulfur in a venturi scrubber to remove ammonia. Company. This Finally, process the gas produces as a to power goes to a desulfuri.zer for removal of hydrogen sulfide. by Dow Chemical from hydrogen sulfide. of the product It is planned to use the is discharged
developed directly
The sulfur
cake containing production
10% to 15% moisture. The remainder uses.
Part of the clean gas is sent as fuel gas is sent to electric
the pulse combustor. or other 3.2.3 ThermoChem will demonstrate Inc.'s with producing Caballo recoverable
Aoolication construct
of Technoloqv a 300 ton/day
in ProDosed Project coal gasification be located This is at Caballo a surface the project will unit to
(dry basis) will Wyoming.
the PCASGCprocess. 12-14millionton/yr reserves
The gasifier ofsubbituminous
Rojo, mine, will be
Rojo Mine near Gillette,
Wyodak (Powder River Basin) coal, Feed coal for coal handling facilities
of 448,600,OOO tons.
come from the mine, and some of the existing used to transport coal to the project site. Enserv will construct a coal upgrading
(K-Fuel.)
plant
at the same site,
but
using private funds with no DOE cost share. The steam requirements of the K-fuel plant will be supplied by by-product steam from the gasifier, and high18
4.Y 3 ‘-L. ;c,I-+~ -D ! 0 = 1 m 50 .g L CT ;;=I 0.N 25 ni r_, I /--. )A-7
temperature. gasifier.
high-pressure Also, coal fines
process water from, the K-Fuel. from the K-Fuel.
plant
will unit
be flashed will be fed
to supply the boiler to the gasifier. The net electricity product
feed water (BFW) and some of the process steam needs of the coal preparation
gas from will build
the
gasifier
will
either with
be burned private
to
produce gas.
at an existing
power station, a gas turbine of the Project
or Enserv, generator
funds and no
DOE cost share, 3.3
to burn the product
General 3.3.1
Features Evaluation
of Develoomental
Risk project recovery. since pulse gasifier tested, is a factor and installed of 6 at
Although greater
the throughput than the unit
for the demonstration now being for black duties require liquor
fabricated,
Weyerhaeuser's of the pulse fabricated project.
New Bern mill combustors
the size and heat load combustors have been
no scaleup.
and tested
at higher
than will
be used in the demonstration
The resonance tubes that from 72 tubes scaled
also act as the heat exchanger will The heater bundles
require
a scaleup been They have
to 252 tubes per bundle.
have already
up from 1 to 2, 2 to 8, 2 to 12. 8 to 61, and 8 to 72 tubes.
been fabricated and tested in these sizes for many gasification applications. Pulse tubes have also been scaled up from 3/8-inch to 1 5/8-inch inside diameter; an increase factor by a factor of almost 20 in flow area. extremely Pulse combustor firing Btu/hr, sufficient that rates scaleup, to ensure have been scaled of 1,500. development, up and tested ThermoChem feels level from 10,000 to 15.000.000 confident experience an overall
testing.
and hardware fabrication
is available
success at the operational
of 300 ton/day.
Although heat exchanger (resonance) tube fouling is a potential problem, this has Therefore, fouling is not not been a problem in the units tested to date. anticipated to be a problem in the demonstration plant.
20
3.3.1.1
Similaritv
of the Project
to Othw Efforts in commercial operation or in
Demonstration/Commercial A number of coal gasification processes are either
These processes are generally divided into three major the development stage. classes: fixed-bed processes, fluidized-bed processes. and entrained-flow processes. each type. Fixed-bed The Lurgi grate processes process have been used extensively uses a stirred, the coal. fixed-bed in coal gasification. units gasifier equipped with The Lurgi a rotating with The following discussion is limited to representative examples of
process is in commercial to support
use, and a large number of Lurgi Gasification of coal
have been built. by reaction
takes place
steam and oxygen~ under high pressure, and coals of all In addition to the synthesis gas product..tars and light products. The Mineraloeltechnik preparation, treatment. discharging million ft'/min Lurgi process Gmbtl. Frankfurt,
ranks can be gasified. oil are produced as'by-
gasification, The reactor ash. for earlier
was developed by the Lurgi Kohle and Germany. Major process steps are coal gas purification, by-product recovery, and liquor is provided with lock-hoppers for feeding coal and capacity per unit ft'/min. is typical of entrained-flow slurry. gas without The any has increased from 0.3 units to 3.5 million Inc.,
The gas production
The Texaco process, gasifiers. liquid process Texaco process gasifies by-product. gasification,
developed
by Texaco,
Coal is fed to the gasifier coals of all
in the form of a coal-water slurry
ranks and produces synthesis
Major process steps are coal preparation, at commercial scale. coal gasification
preparation, The Texaco
water quench, gas purification,
and waste disposal.
has been demonstrated process is
The Winkler
a fluidized-bed
process
that
has
achieved commercial acceptance. All types of coal can be gasified using the Winkler process, but caking coals require pretreatment. Crushed coal (3/8" x 0) is fed into the fluidized bed where carbon reacts with steam and oxygen to produce a gas containing hydrogen. carbon monoxide. carbon dioxide, and methane. A gas with a heating value of 275 Btu/SCF can be produced if the gasifier is 21
oxygen blown. a temperature essentially
The Winkle gasifier of no tars or hydrocarbons.
operates
at near atmospheric upon the feedstock.
pressure It
and at produces
1500°F to 1850°F depending
The KRWprocess is typical dried reactor air coal and limestone through vessel
of pressurized are introduced the
fluidized-bed into
gasifiers.
Crushed and fluidized bed by injecting nozzles. water quench. The KRWprocess
the pressurized, The bed is fluidized zone through
a lock hopper system. combustion
or oxygen and steam into
special
Process steps include coal and limestone preparation, gasification, calcium sulfite oxidation. gas purification, and waste disposal. is being demonstrated Indirectly gasifiers heated for by a CCT-IV project. have a major applications, air separation advantage over
gasifiers in order
partial-oxidation gasifiers For a typical Most gas they air-blown gas.
industrial-scale operation, simple utility.
since partial-oxidation is usually gas. uneconomic. Although the fuel
must be oxygen-blown industrial-scale industrial systems produce gasifiers requiring is gasifiers are relatively of limited
to produce a medium-Btu fuel
are air blown and produce a low-8tu and reliable Several ~.indirectly
gas producers,
heated.
fluidized-bed Ash
were under development in the 1970s to produce a medium-Btu gas without an oxygen plant. process. These systems, steam-carbon the gasifier. circulation such as Battelle's process. reaction Agglomerating Conoco's CO,-Acceptor and the COGASprocess, a hot solids two vessels cost of the heat, the and cost,
Coal Gasification
supply heat for the endothermic stream from a combustor and a fairly into complex hot solids
by circulating
These processes require system, and the capital
plants is fairly.high. Also, since process char is burned to provide flue gas may have to be desulfurized. Because of their complexity these systems have not yet achieved commercialization.
The MTCI Pulse Coal Gasification process. which is designed mainly low-rank coals. uses an alternative approach to heat a fluidized-bed heat transfer tubes immersed in the fluidized bed. simplifies the process configuration, since it requires and no complex solids circulation such as that other gasifiers,
to process reactor-greatly vessel.
This approach only one reactor
system is involved. However, as employed in developed by the University of Missouri for 22
gasification of reactive biomass feedstocks. the heat transfer coefficient inside the tubes is so low that a very large surface area is required. The use of pulse combustion coefficient, relatively in the MTCI process significantly enhances the heat transfer which enables high temperatures. pressurized generation the technology to be applied to systems requiring
such as coal gasification. have merit for synthesis gas or combined-
Oxygen-blown, cycle power
gasifiers at
large scale: but, for smaller applications not requiring high-pressure gas, the cost of an oxygen plant and the complexity of feeding solid fuel into a pressure vessel are major deterrents to industrial acceptance. systems also have a disadvantage product, gasifiers since by-product typically entrained-flow in any application hydrocarbon liquids hydrocarbons in which fuel are produced. areproduced; liquids unless
a sufficiently
The fixed-bed
gas is the desired In high-temperature, and fluidized-bed operated
systems, no liquid
do not produce hydrocarbon (around 12OO'F).
at mild gasification
temperatures
A major drawback of entrained-flow the gasifier. not stopped the gasifier, reliable disruption entrained with combustion developed. required. slurry immediately, possibly
systems is the very low carbon inventory even temporarily, with and oxidant
in
If coal feed is disrupted, oxygen can react resulting
flow is
hydrogen and carbon monoxide in Due to the use of a fairly is not prone to this beds are inherently carbon inventory interrupted. problem; safer than to react major damage duetothe
in an explosion.
feed system,
the Texaco gasifier gasifiers
however, other entrained-flow of coal feed. in the beds, because there event gasifier
have experienced
Fixed beds and fluidized is always a sufficient coal feed is risk. that
oxygen
The MTCI pulse processes have been gas is
(PCG) does not have this Thus, although many coal
because no oxygen is supplied medium-Btu
to the gasifier.
gasification
the MTCI PCG has advantages
when low-pressure,
23
3.3.1.2 The project technology; integrated section liquor size
Technical
Feasibilitv on the basis of the ~maturity of the
has been established
15 million Btu/hr pulse combustors have already been fabricated, into fire-tube boilers, and tested successfully. The major facet of that requires
the technology than four
scaleup is the number of tubes in the resonance Although the required number of tubes is less of the pulse combustor. times the number already gasifier this risk scaleup liquor. fabricated and field tested for the black Also, to be installed is a critical Gasifier is involved at a Weyerhaeuser mill factor throughput in New Bern,
recovery
North Carolina, a greater gasification of 10.
in the demonstration. will
technical of black
in the gasification
of coal than in the be scaled up by a factor
There do not appear to be any critical addressed mitigated combustor, is expected start-up in the design by the fact and testing that
design issues that of the 30 ton/day is limited unit.
have not already Technical risk to
been is in It the
new technology plant
the gasifier/pulse items available prototype. during
with the balance of plant The demonstration it will,~with be replicated 3.3.1.3 that
equipment being standard is a commercial-scale modifications market sale.
the marketplace. period,
whatever
are required
for the first
Resource Availability for this project over the 4bmonth dedicated demonstration the personnel
Adequate resources period. necessary
are available in Section cost. this
As discussed to conduct
6.'1, ThermoChem has committed ThermoChem has also program.
funds adequate to
cover the proposed project
demonstration
Sufficient space is available at the Caballo Rojo Mine site for installation of the equipment required for the demonstration. Arrangements have been made to provide project the necessary needs. quantity and quality of coal from the Caballo Rojo Mine. to meet Adequate utilities (water and electric power) are available at the site
24
3.3.2
Relationshio and Projected
Between Project
Size
Scale of Commercial Facility a plant rated at 300 ton/day range, to involve (dry basis). rather
The demonstrationproject This plant than utility, 3.3.3 size is well version market for this
involves within
the commercial
facility
since
the major
of the technology
is likely
industrial.
applications. Role of the Project Feasibilitv in Achievinq Commercial
of the Technoloqv is crucial to achieving commercialization of the
The demonstration
project
technology, as it will demonstrate, at full commercial scale, the integrated operation of the pulse combustor and the indirectly heated coal gasifier. This project providing will confirm plant that operability, is vital Aoolicabilitv will will test all will product quality, and process effort. costs, information to the commercialization
3.3.3.1 The demonstration scale, and will collection, performance. applicable fired scale project
of the Data to be Generated aspects of the technology for electric be performed during thermal will Although be directly the data will at commercial Data phase to the so that
and the product analysis, include
be burned reliability,
power production. the operations applicable efficiencies,
and reporting
on-stream gas-fired data will
and equipment not be directly
The data that will to coal-fired
be generated
design of other the performance of
facilities. combustors,
there are enough design similarities
pulse combustors. operation, efforts
be useful in providing guidance in the scaleup of coalFurthermore, demonstration of pulse combustion at this regardless of all of fuel, will greatly facilitate the pulse combustors.
commercialization
25
3.3.3.2
Identification the Potential
of Features
that
Increase
for Commercialization furnaces it to reduce SO, emissions. is combusted. One
The CAAA require option gasifiers, requiring large efficient technology applications. gasifiers. essentially product heat for
existing
coal-burning this
accomplishing whether either
is to produce a clean gaseous fuel gas before in order fluid-bed or under development,
by gasifying of
coal and desulfurizing
the product commercial solids area
Other available fuel gas, a
have the disadvantage vessels,
an oxygen plant in the
to produce a medium-Btu two reaction gasifier. coal gasifier
complex circulating transfer
flow scheme involving
or a very MTCI PCG costs, for the ~many
Because the using air capital of that. choice unlike
produces medium-Btu gas in a single-vessel pulse combustor/heat being demonstrated advantage Another no tars should
and a highly
exchangersystemthatminimizes be the process of the MTCI PCG is of. Also.
fixed-bed
very few hydrocarbons or oils steam is produced,
heavier than methane are produced. a considerable well
and there are amount of bywith processes
to dispose
so the MTCI PCG should integrate
which use large
amounts of steam. 3.3.3.3 Comparative and Proiection [conomics Merits of the Proiect Commercial
of Future
and Market Acceotability medium-Btu fuel gas by gasifying coal in an reactor. By-product steam will also be the process has advantages over competing make it economically advantageous in many
This project will produce a clean, indirectly heated. fluidized-bed produced. processes applications. The MTCI pulse combustion technology As discussed that are above. to expected
has a.wide range of potential
applications,
including utility steam and power generation. use of pulse combustion for steam gasification gas and by-product steam in conjunction with that will utilize the by-product steam.
This project will demonstrate the of coal to produce medium-Btu fuel a low-rank coal upgrading process
26
Other provide'
potential fuel
applications gas for
include
producing applications.
medium-Btu gasification
fuel
gas
as a
substitute
for natural
gas in industrial gas turbines As fuel cells
The process the
could also MTCI pulse
in integrated
combined cycle
(IGCC) power generation. combustion application fuel gas. hydrogen rich In addition related mills results
become commercial,
for steam gasification
of coal could be used to provide
to these applications,
there is a substantial alone.
potential
in a closely of pulp liquor,
application
in the pulp and paper industry in the United States of about 88 million produced practice ton/yr
which has more than 350 pulp The processing black of by-product
and 600 paper mills in the production
the dark-colored liquid The current processes. produce steam and electricity gasifiers would significantly market for MTCI gasifiers Thus, because of its PCG technology industrial applications.
when pulp is made by the sulfate and soda of using black liquor recovery boilers to Replacing these boilers with MTCI efficiency. The estimated annually. the MTCI for
is inefficient. in this application
improve the conversion
alone is 28 units and high quality acceptance,
simplicity achieve
of operation ready
product, particularly
should
market
27
4.0
ENVIRONMENTAL CONSIDERATIONS procedure, cited analysis; in Section 2.2, contains (PEIS); three major
The NEPA compliance elements: . project-specific environmental
a Programmatic analysis.
Environmental
Impact Statement
a preselection. site-specific in November 1989
environmental
and a post-selection, PEIS to the public
DOE issued the final
derived from the Regional Emissions (DOE/EIS-0146). In the PEIS, results Database and Evaluation System (REDES) were used to estimate the environmental impacts compared conventional flue The expected with the to occur no-action in 2010 if each technology were to reach full commercialization and capture 100% of its applicable which alternative. through 2010 with market. These impacts were assumed continued use of using conventional Standards. review, focusing on
coal technologies
new plants
gas desulfurization preselection,
to meet New Source Performance project-specific environmental
environmental issues pertinent to decision-making, was completed for internal DOE use. This review summarized the strengths and weaknesses of each proposal in compliance to the reasonably of required with the environmental possible, available permits. to the offeror, This analysis evaluation of practical criteria alternative mitigating for in the PON. It included, sites land processes and a list of the measures, extent a discussion
was provided
the consideration
Source Selection
Official
in the selection
of proposals. the Participant Volume specified will prepared (ThermoChem) will in the PON. This for the NEPA with the
As the final element of the NEPA strategy, submit to DOE the Environmental Information detailed siteand project-specific by DOE. documents prepared
information
form the basis
These documents,
in compliance
Council on Environmental Quality regulations for implementation of NEPA and the DOE regulations for NEPA compliance, must be approved before Federal funds can be provided In addition of the for detailed design, construction, outlined sufficient and operation activities. must prepare The purpose and site
to the NEPArequirements to ensure that
above, the Participant technology, project,
and submit an Environmental EMP is
Monitoring
Plan (EMP) for the project.
28
environmental information Air pollutants
data are collected for use in subsequent resulting project are gas in
to provide commercial
health,
safety,
and environmental of the technology.
applications
from burning expected the venturi to
the medium-Btu be low. scrubber,
gas produced about
in matter
this is of
demonstration scrubbed particulates desulfurization SO,/million Gasifier permitted will site. stripped
Most particulate and only
from the
1 ton/yr
is expected system. Btu. ash is classified landfill.
to be emitted. and sulfur
Most of the sulfur are expected
is removed in the to be about 0.07 lb
emissions
as nonhazardous sulfur will
waste and will be sold,
be disposed
of in a it
By-product
if possible;
otherwise.
be landfilled. from this
Wastewater will water before
be discharged determine
to an evaporation
pond at the
Test work planned for Phase I will disposal.
whether ammonia needs to be
29
5.0
PROJECTMANAGEMENT 5.1 Overview will of Management Oroanization be managed by a ThermoChem Project contact with DOE for matters Manager. regarding This individual
The project will
be the principal
the administration The DOE Contracting
of the Cooperative Officer Officer's
Agreement between ThenaoChem and DOE.
is responsible for all contract matters, and the DOE Contracting Technical Project Officer (TPO) is responsible for technical liaison of the project. of Resoective Roles and Resoonsibilities
and monitoring 5.2
Identification
DOE shall be responsible for monitoring all aspects of the project and granting or denying approvals required by the Cooperative Agreement. The DOE Contracting, Officer is DOE's authorized Agreement. Officer all which may: of the Cooperative which assist Agreement effort, recommend a will appoint matters a TPO who will and will be the authorized to issue representative for all matters related to the Cooperative
The DOE Contracting representative "Technical for Advice"
technical
have the authority
Suggest ' shifting of certain Work.
redirection lines
of work emphasis between work areas or tasks, of inquiry in accomplishing
or suggest pursuit the Statement of
Approve all
technical
reports,
plans, by the
and items of technical Participant to the
information the
required to be delivered Cooperative Agreement.
DOE under
The DOE TPO does not have the authority
to issue technical
advice which:
30
Constitutes Work.
an assignment
of additional
work outside
the Statement
of
In any manner causes an increase or the time required
or decrease in the total of the Cooperative or specifications
estimated Agreement.
cost
for performance conditions,
Changes any of the terms, Agreement. Interferes conditions All technical with the
of the Cooperative
Participant's
right
to
perform
the
terms
and
of the Cooperative advice shall
Agreement. by the DOE TPO.
be issued in writing
Particioant The following from conceptual organizations will interact effectively to meet the intent of the
PONand to assure timely
and cost-effective
implementation
of the PCASGC project
design to start-up
and operation:
ThermoChem. Inc. Manufacturing Enserv, RMT, Inc. Weyerhaeuser Paper Company ThermoChem will be primarily responsible for the for reporting all to and interfacing with Inc. and Technology Conversion International, Inc. (MTCI)
DOE. ThermoChem will The overall necessarily project be limited project
be responsible approach to, of
phases of the project. will include, but not
Participants
the following: be responsible phases. to DOE and all project
A single Participants
manager will three project
for all
31
ThennoChem will other
be the primary
liaison
between the Government and all 5. Project pulse Organization. system. technical
organizations. design during
,as shown in Figure and fabricate the
MTCI will conduct support
combustor/gasifier and provide
the system startup the project.
and shakedown testing,
Enserv will demonstration demonstration RMT. together engineering
obtain plant plant. with
the necessary with other
permits, facilities,
handle the interfacing and operate
of the the
and maintain
an A&E firm plant, serve
to be selected, technical advisory
will service.
handle
design
and of
of the balance
of the plant,
procurement
and construction
the demonstration Weyerhaeuser will evaluate 5.3 All
and provide in a technical
and review
capacity
and
the technology
for pulp and paper industry and Control Procedures
applications.
Proiect
Imolementation
work to be performed These phases are:
under the Cooperative
Agreement is divided
into
three
phases.
Phase I: Phase II: Phase III: As shown in Figure
Design and Engineering Construction Operations (14 months) (24 months) project
(10 months)
6, the total
encompasses 48 months. Consistent reports with P.L. dealing aspects with 101-512. the DOE will technical, will be
Two budget periods will obligate funds sufficient Throughout the course
be established. to cover its of this project,
share of the cost for each budget period. of the project
management, cost. and environmental prepared by ThenaoChem and provided
monitoring to DOE.
32
_’
I
I : n
1 I 1
I j I
!
ZGI i ’ g ,
~--
I r-
i =kz / 5
33
L
1.
34
5.4
y Ke A r ement Im act'n Information Reoortinq respect to patents are included, unlimited and data are: giving rights, the Government the right all technical data first to
The key agreements with Standard produced Proprietary
data provisions
have delivered
and use, with
in the performance data, with certain
of the Agreement. exclusions, may be required to be delivered
to the Government. and non-proprietary the project Rights its if
The Government~has obtained rights to proprietary data data sufficient to allow the Government to complete withdraws. and background data of ThermoChem and all to assure commercialization of of the
the Participant
in background patents are
subcontractors
included
technology. ThermoChem will make such data, as is applicable interested and non-proprietary, and the public. available
to the U.S. DOE, U.S. EPA, other 5.5 The Procedures
agencies,
for Commercialization strategy
of the Technology is based however, on control of the
ThermoChem connnercialization applications,
manufacturing industrial
of the pulse combustor equipment; ThennoChem will license
for utility
and large
the balance of the plant.
ThermoChem will retain the right to design. manufacture, and sell industrial and commercial coal-fired retrofit systems both in the U.S. and overseas. ThermoChem will also retain plants the right to manufacture gasifiers liquor for moderate size gasification etc. (up to 1000 ton/day) low-rank for black recovery, paper mill
sludge gasification,
coal steam reforming,
sewage sludge gasification,
35
In addition
to this that
direct within
utility
and industrial K-Fuel.
market for PCASGC, a potential such as K-Fuel.. of could achieve a 5% penetration
market also exists Enserv believes
in conjunction
with coal upgrading processes,
20 years,
the U.S. coal market. ThermoChem's strategy for penetrating this potential market is to grant to Enserv an exclusive license for the MTCI PCG used in conjunction by identifying warrant with beneficiation the utility technology. and industrial and obtaining Enserv plans to market aggressively coal consumers whose immediate commitments for long-term needs purchases.
the use of K-Fuel.
36
6.0
PROJECTCOST AND EVENT SCHEDULING 6.1 Project estimated Baseline cost Costs for thi,s project is $37,333,474. The Participant's project are as follows: Percent % 50 50 Share
The total
share and the Government's
share in the costs of this Dollar Share I$)
Pre-Award Government Participant Phase Government Participant Phase II Government Participant Phase III Government Participant Total Project 18.666.737 18,666.737 50 50 5,771.475 5,771,475 :: 11.388.685 113388,685 :i 1,258.287 I,2589287 50 50 248,290 248,290
Government Participant
Budget Period 1 will Phase II obligate
include
Pre-Award and Phase I; Budget Period 2 will At the beginning of each budget period, share of expenses for that
include DOE will
and Phase III. funds sufficient
to pay its
budget period.
37
The project
will
be co-funded
by DOE and ThermoChem, as follows: BP2 $17.160.160 $17.160.160 $34.320.320 Total $18.666.737 $18.666.737 437.3X.474
DOE ThenoChem TOTAL 6.2 The overall Milestone project
BP1 %1,506.577 $1.506.577 $3.013.154 Schedule will be completed
in 48 months. 6. will of
The project
schedule,
by
phase and activity, Phase I, Phase II, operations, 6.3 which will
ReDaVment
is shown in Figure design will 24 months. Plan policy
involves last
and engineering, last a total
continue
for
10 months.
construction,
14 months,
and Phase III,
In response to DOE's stated contribution in accordance to the project, with
to recover
an amount up to the Government's has agreed to repay the Government which is consistent with the model
the Participant
the Repayment Agreement, in the CCT-IV PON.
repayment agreement
38