Contract No DE LIFAC Sorbent Injection Desulfurization Demonstration - LIFAC Sorbent Injection Desulfurization Demonstration Project

Click to download
Contract No. DE-FC22-90PC90546 LIFAC Sorbent Injection Desulfurization ......... Demonstration Project ................................ ........ Presented By LIFAC NORTH AMERICA, INC. A Joint Venture Between /CF KAISER ENGINEERS Four Gateway Center Pittsburgh, Pennsylvania 15222 Presented To P.O. Box 626 SF-331 01 Tampere, Finland U.S. Department of Energy Pittsburgh Energy Technology Center Pittsburgh, Pennsylvania 15236 January - March 1991 LIFAC Sorbent Injection Desulfurization Demonstration Project QUARTERLY REPORT NO. 2 JANUARY-MARCH 1991 TABLE OF CONTENTS Section INTRODUCTION BACKGROUND Project Process Process Process Team Development Description Advantages Paoe No. 2 HOST SITE DESCRIPTION PROJECT SCHEDULE 6 9 9 9 13 16 17 17 18 TECHNICAL PROGRESS Project Management (WBS 1.1.1) Engineering and Design (WBS 1.1.2) Environmental Monitoring (WBS 1.1.3) Long Lead Procurement (WBS 1.2.1A) Installation and Startup (WBS 1.2.2B) FUTURE PLANS INTRODUCTION In December 1990, the U.S. funding - Department of Energy selected sponsored 13 projects for One under the Federal selected site Clean Coal Technology was the project Injection for this Program (Round III). of the projects (LIFAC NA), titled Project." Richmond Indiana. patented dioxide by LIFAC North America, Demonstration project injection of the is with sulfur 2 in Richmond, ,three-phase "LIFAC Sorbent Desulfurization Valley Unit No. The host $17 million, Power and Light's The LIFAC technology humidification (SO,) in the flue of Whitewater the flue uses upper-furnace limestone gas to remove 75-855 gas. a ten (10) month negotiation into a Cooperative Report covering engineering, of the LIFAC system. the period design contingent period, for This LIFAC NA and the report design, is the In November 1990, after the U.S. DOE entered construction, second through schedule, critical the project the Agreement and demonstration Progress end of March 1991. needed for Technical January planned 1, 1991 of Due to the power plant's outage Phase of signing and the time equipment, in August and procurement the Design upon final DOE and LIFAC NA agreed to execute 1990, with DOE funding of the Cooperative BACKGROUND ,.I Agreement. Project Team at Whitewater a joint Valley Unit No. 2 is being between: California, in Fairfax, conducted America, venture partnership The LIFAC demonstration by LIFAC North . ICF Kaiser Enoineers - A U.S. company based in Oakland, and a subsidiary of ICF International (ICF) based Virginia. . - Tamoella Power Coro. - A U.S. subsidiary of a large diversified international company, Tampella Corp., based in Tampere, Finland and the original developer for 50 of the LIFAC technology. the overall administration funds. of the project Except for and by the .- LIFAC NA is responsible for providing the administration, however, percent matching project most of the actual work is being performed 168/LIFAC/PtrlyReplOZ Page 2 two parent firms team Institute ICF ,..” firms under with Indiana including service Richmond ICF agreements Resources, for Beauty the with the Science LIFAC NA. and the Electric Both other parent project work closely members, (EPRI), Power and Light Power Research (ICS&T), of the Figure its DOE 1 Corporation manage and Technology project access Center. the three out to Peabody Coal Company, and Black Kaiser Engineers office, of the Pittsburgh representatives the project. - Coal Company. excellent LIFAC NA is having demonstration Energy Technology which provides being Pittsburgh shows the management structure used throughout phases of LIFAC NA administers decides sources, partners and procedures. Process emissions in the flue could not Therefore, Development enacted the overall invoicing, ensure that with the project through budgets, flows funding a Management and schedules. Committee All that policies, and information the project, the funding to LIFAC NA where the managing and expenditures budgets, are consistent schedules and in-line established policies, In 1983, Finland sufficient gas. be the capability acid rain that could legislation flue percent which applied limits on SO, dioxide but to require This level then gas desulfurization systems have scrubbers, to remove about eighty met by available (80%) of the sulfur injection be met by conventional sorbent an alternative technology. resulted Tampella began developing system which in the LIFAC process. Initially, Full-scale Inkeroinen sulfur 50%. Better Polish development limestone facility, coal. results included injection At Ca:S ratios could laboratory-scale tests were boiler sulfur using that to an and pilot-plant conducted using removal lime, at high-ash, was less tests. Tampella's lowthan a 160 Mwe coal-fired of 3.1, than led vertical with have been attained is much higher by Tampella but was rejected because the cost In-house involving as the 168/LlFAC/Qtrl,'Rep/QZ of lime of limestone. alternative approach investigations humidification LIFAC Process. in a separate In cooperation chamber which became known Pohjolan Voima Oy, a Finnish Page 3 .- _. - . . : : .* .* .* .* .. .* .. . .. .. .. .. .. .. .. . .. .. :: L 0 :: ‘= ‘i: :: a :: &ta z .2 ::. g ii::. E e,** Q) :: 0 P ij :: 2 .gii k 2 :: J ::* l l * l . l * l * *a l * :: :: :: :: :: :: l . l * l * -0 l * fj s-; r--l-. 18 1 If-i 1 1 l- 1 I ;% 5’ i 3W-E 1 nuz L.Ya 1 oh? LI -r-J .--?! sl Ewa caut 5iL$ ii0 -i a3 a Ii ,--ls it ktj 6 0 g sl* 0 ii i: .---- -l utility, facility, Tampella installed boiler a full-scale located activation residence times at limestone the (2.5 injection calcined facility At limestone the resulted laboratory on this was gas in SO, to a 220 Mwe coal-fired a slipstream Reactor of 84%. relationships Polish full-scale a flue used to test was humidified. removal develop rates the Kristiinankaupunki. MW) in which tests operating (5000 SCFM) containing reactor a small-scale of 3 to 12 seconds Additional level between LIFAC pilot-scale the important were conducted and design at the 8 Mwe (thermal) parameters. In built the 1986, at the Neste Ku1100 combustion coal was burned to achieve of LIFAC was conducted boiler. representing about represented at low-sulfur testing 84% SO, removal. Imatran Voima's Inkoo power plant to treat on a 250 Mwe utility gas stream An activation 70 Mwe. about coal rates chamber was Even though one-half of boiler was 250 Mwe, the gas feeding This 61%. a LIFAC i.e., 70 Mwe stream boiler By late activation an entire This the flue removal to 76%. additional one of the plant's two EPSs (i.e., used a 1.5% sulfur 1987, SO, removal reactor flue gas/ESP and 2.5:1. at the each ESP receives and sulfur had improved to treat an 75the 3% of flue a 125 Mwe gas stream). was initially In 1988, 125 Mwe -with was added reactor pilot stream-worth gas from this 80% SO, removal tests sulfur. This of the Process using same boiler. high-sulfur rates newer activation between 2:l were run a Pittsburgh is achieving scale at of 2:l. Ca:S ratios U.S. Center, In 1988, the first containing coals using Neste Ku1100 Research SO, removal No. 8 coal of 77% were achieved project coals will at a Ca:S ratio LIFAC demonstration high-sulfur LIFAC process Description upper-furnace U.S. be conducted on a 60 Mwe boiler application burning to demonstrate utilities. the commercial to U.S. LIFAC combines humidification and the ESP. partially removed at the limestone reactor produces injection located followed waste reactor by post-furnace preheater that is product in an activation The process ESP. between the air a dry and stable removed from the bottom of the activation and partially Finely the injection pulverized part are of in limestone the the lime boiler. range is pneumatically Since of As the the lime 1800-2000" take place. (CaSO,), Essentially conveyed temperatures F, the passes part all and injected at the the then point limestone into of (CaCO,) upper decomposes initial with to form (CaO). reactions through of which furnace, oxidizes trioxide desulfurization sulfate A portion of the of the SO, reacts sulfur the CaO to form calcium with sulfite to form calcium (SO,) reacts The flue preheater. patented dioxide spray. enhances time before reactor build-up ratio flue gas. for (CaSO,). the CaO to form CaSO,. lime exit the boiler In the flue gas and pass through mixture additional with lime, Ca(OH),, reactor, is the air the gas and unreacted On leaving capture further effective the flue occurs LIFAC activation Humidification the air after converts preheater, the lime the gas/lime enters reactor. sulfur a water which to allow evaporate for solids humidified (CaO) to hydrated reactor gas, the water reactor. effect SO, removal. humidification gas leaves of the The activation of the flue All the activation the sorbent. is designed droplets activation of the lime, The activation and reaction of the SO, with is also designed on the walls in the range of 2:l specifically chamber. to 2.5:1, to minimize The net the potential is that at a Ca:S 70-80X of the SO, is removed from the The flue to the of fly of - gas leaving disposal the activation and fly flue gas. reactor then enters is collected also the existing ESP by the where the spent humidification of the calcium, the spent and/or the sorbent facilities. of the ash are removed from the flue ESP effectiveness The solids by the gas and sent ESP consist utilization reactor ahead of enhanced ash, CaCO,, Ca(OH),, and increase sorbent reactor. CaO, CaSO,, and CaSO,. SO, reduction in the bottom of To improve the activation to between 75 and 85%, a portion the ductwork just collected in the ESP hoppers is recycled back into activation Process The Advantages technology using chamber attached has to similarities the to other a unique sections sorbent patented of the injection vertical boiler to Page 5 LIFAC technologies reaction 168,L1FAC,PtrlyRep,O2 humidification, but employs down-stream facilitate This lime and control the sulfur rather capture reaction and other efficiency chemical reactions. the such as sorbent chamber improves which are often the overall used to enough to allow reagents of other use of pulverized injection Sorbent wet lime test dioxide systems, processes. injection limestone than more expensive the efficiency increase is a potentially scrubbing, injection recirculation material. these sorbent with important and this of the alternative project sorbent, for if is In to conventional another comparison removes less effort to to wet is and limestone LIFAC, alternative approaches. sulfur - 75-85% relative more reagent LIFAC will offer to 90% or greater important conventional the scrubbers and requires successful, systems: . However, demonstration over wet scrubbing advantages LIFAC is relatively easy to retrofit requires less area than conventional LIFAC is processes. LIFAC's are less, of emission less expensive to install to an existing wet FGO systems. than conventional boiler and . wet FGD . overall costs measured on a dollar-per-ton advantage in a regulatory SO, removed basis regime with trading an important allocations. a dry, . LIFAC produces wet product. readily disposable waste by-product versus a . LIFAC is relatively simple to operate. HOST SITE DESCRIPTION The site for the Indiana. coal LIFAC demonstration coal-fired Valley tangentially-fired Western Indiana. units in 65 megawatts. is Richmond Power and Light's in 1971, uses highgeneration The Page 6 Whitewater in Richmond, is sulfur produced smallest 168/LIFRC/PtrlyRep/O2 Valley 2 pulverized Engineering from power station 2, which boiler Actual As such, the (60 MWe), located which power it Whitewater began service a Combustion bituminous by the unit existing, approaches tangentially-fired is one of the States. United furnace primary to loss is potential 540,000 is 26-feet, and secondary the for lbs/hr. are air while gas-side 11-inches highest deep and 24-feet, Tube sizes heat-transfer The unit of the lack also of 8-inches rates gas turns. outlet the wide. with At at rated It the full has a least load and shaft is superheater. possible fouling. because hour. at and spacings has an inherent are designed low draftcapacity achieve characteristic 651 x lo6 Btu per of steam are generated. The design 955°F. 1320 psi preheater. the flue The heat input superheater The unit has leaving pressure economizer temperature basket-type about 645"F, draft unit a horizontal The temperature gas temperature is about 316°F. The balanced- has 12 burners. unit was fitted Firing and fully NO, emissions optimized with a state-of-the-art a very cost retrofit secondary zone in the with other In 1980 the effective possibilities. air along Low-NO, Concentric System (LNCFS). The LNCFS represents in comparison a fuel air reduces of directing rich means of reducing the sides furnace. walls The system works of the furnace on the principal and creating center of the With the LNCFS, the excess the installation heat absorption coal with all compartments three increasing can be maintained ash accumulation attemperation auxiliary air of the 52 grind has a tangential operating, with below 20 percent. on the furnace requirements. windbox primary total coal compartments. transport combustion Additionally, and reducing and four With the LNCFS, each corner of air air. three load from the Pulverizer At full of the furnace consisting 593 RB pulverizers is 26,400 lbs/hr. pulverizers capacity amounts to 23 percent and 70 percent Unit with the minus 200 mesh. cold 45,000 (from in 1985. efficiency of 87.47 percent at full heat Page 7 Whitewater erected feet area. achieves ..- 2 has a Lodge Cottrell boiler. of 316°F The precipitator flue gas with fields efficiency side treats precipitator 227,000 feet electrical which actual fields of collection was cubic and Power per minute The unit square 3.9 gr/ft3 has two mechanical removal was optimized new controllers Unit 2's overall and four 99 percent purchased Valley to 0.04 gr/ft3). The ESP performance and Light Whitewater load by Lodge Cottrell when Richmond has shown little variation over the years. The unit's average 168/LIFAC/PtrLyi?eplO2 rate coal is 10,280 Btu/Kwh. At 60 percent The unit 8.51 of full load, the unit's 0.935 efficiency pounds of increases to 88.17 percent. uses approximately per Kwh and generates emissions are calculated Btu. Opacity limited Opacity the test pounds of steam per Kwh. at the station using an in-situ Current opacity while in are SO, and opacity. and are limited for ranges SO, to 6 The primary emissions lbs/106 monitored is monitored Btu, based on the coal to 40 percent. at work low load indicated analysis meter at the ESP outlet SO, emissions the unit from 15 load from and is currently are approximately to 20 percent. Limited Results lbs/106 testing from Btu. 4 lbs/106 at full (40MW) ranges that 3 to 5 percent. 0.65 was conducted November of 1986 for NO, emissions. averaged NO, emissions Whitewater demonstration of will retrofit typical application relative to other points 2 will of U.S. U.S. a prior technology. of the site of Valley site. joint 2 has several important of if qualities Valley LIMB sorbent remains as a LIFAC One of these EPA/EPRI is that injection Whitewater equipment possible. site. are 2 was the site injection on site for is sites is thus for small and a advantage demonstration Much of the sorbent is that many Whitewater U.S. power hence, situation in order times performance a logical LIFAC's be used in the due to the LIFAC demonstration, Valley plants it cramped conditions Another The plant potential 2 boiler profiles injection of the 2 is a challenging at the which Whitewater candidate of LIFAC. to its boilers. capacity; This furnace residence In addition, will Valley sorbent removal. has high-temperature require sulfur deadburning relative at higher reagent and Valley in the to prevent may decrease needed for will Whitewater show LIFAC's power plants. and is for coals under operational demonstrate of the success conditions Finnish most typical work The project commercial LIFAC on high-sulfur demonstration extension and important in the U.S. 168/LIFAC/C!trLyRep/OZ G I n : I I I I I I % 3 3 % co r CD ld P 04 P 0 'c I II II I I : I I I m I . I I I I m I I co In * :: l l l :: l 0 g 4. 0 i; ;’ . . * * I I I I 01 I I I I I I II II II I I I I I I I I I 2 hia, 5' n 6 rti gg a m@Eg -.‘p”gs $ .E g&g aO.iiw 5 $ n CEO 5 F.P 8 .c v) 'iii - 5 .3 w L 2 0 E Q) P f : : . .*. .* .* .* .*. .. . .. .. .. .. .. .. .. .. .. .. .. s :: s :: a:: 0:: l * . $ii . 2 -4.. g*. a :: 2 k i jii ‘E 8 :: ii 0. 0. 0. 0. 0. :: :: :: .- :: :: :: :: 0. l * l * 1: .0 s -0 4. 0 ii i: the Deslgn Phase construction (Project and activities Management, the Long Engineering Lead Procurement and Phase. Design, task and Following Environmental preliminary is Monitoring) in the Construction under these tasks. a summary of the work performed Management (WBS 1.1.1) the January related to several through to other Project During March period, the areas including: - management efforts Agreement shifted and from related negotiations documents . DOE Cooperative Finalizing Partnership Engineers of Agreements resolved all nearly Tampella all is Power Corporation issues during related the licensing and to next ICF Kaiser the Final reporting . remaining expected marketing, execution period. partnership and technology agreements agreements. Joint full LIFAC NA/DOE Cooperation implementation Conducted Pittsburgh Provided reports Prepared establish requirements Worked to resolve Presented for Engineers, Tampella Tampella the - LIFAC NA took many steps Agreement project of two including: review towards of the Cooperative first quarterly 14 drafts first meeting in on February preliminary and sent key DOE administrative to DOE, and began with to DOE - Cost Plan and Cost Management Report invoices LIFAC NA accounting procedures invoicing tier consistent problem LIFAC NA subcontracts ICF Kaiser ICF Resources, DOE drafts of the first Power Corporation, and Richmond Power and Light implementation of all remaining period. all necessary state accounting, Anticipate invoicing, . full and reporting Continued requirements efforts to in next obtain Regulatory permits and approvals: 168/LIFACIPtrlyReplO2 Page 10 Filed testimony for obtaining Utility a Certificate Regulatory law. of Need and under the the with Necessity the state's Commission Power and certificate Set ,_- from the Indiana staff, Light. legal Commission Clean Coal Project experts Anticipate Worked closely in and the host utility, success Richmond obtaining or a waiver with of the requirement. Indiana Department steps related discussion to negotiate of of Environmental waste elsewhere). and finalize other project up meetings permit - Management officials disposal to outline to a solid (see environmental Continued efforts -_ . __ Funding Agreements for arrangements participants: “.- participation/funding Electric several parameters, version funding, members. a report report Power Research representatives (2) and (4) estimates the Institute of the potential additional - Met costs for in of Palo the Alto with of EPRI to discuss: (1) LIFAC process commercial (3) EPRI including I_ of LIFAC developed Agreed to provide on LIFAC market answering this during by an EPRI subcontractor, information market LIFAC among EPRI prospects among EPRI members; a draft and is anticipated request the next for was written period. to be provided Indiana awarded period. for contract arranged Expect period. Corporation Science million steps and Technology dollars to sign Provided in during (CST) - CST the previous with CST and next LIFAC NA 0.8 LIFAC NA undertook outlining meeting full their with their of a contract the in the provision of the funding. CST a new proposed project Indianapolis. in participation representatives all resolution outstanding issues Peabody Coal Company on contracts program. 168/LIFAC/PtrIyReplO2 - Scheduled provision negotiations of coals with during Peabody the test for the Page 11 Black Beauty Coal Company - Scheduled for the provision that LIFAC NA is optimistic negotiations of coals contract during with Black Beauty on contracts program. will be successful. the test negotiations Lafarge/Limestone due to recent indicate project's characterization regrettable, partners arranged discuss Rodgers, and materials their but Company - Lafarge financial in of difficulties. potentially uses for informed LIFAC NA that of the project however, in and decision since it did the would not be able to participate interest tests in the funding Lafarge, participating the waste This the project Subsequently, limestone study was the LIFAC to (2) We of the waste by-product. in no way jeopardizes and committed with three was to provide. other in the project: for are capable Lafarge meetings and (3) to purchasing the services companies participation that (1) Mulzer, Corporation. will Kosmos Cement - Southdown a replacement Lafarge are optimistic . be found. transfer technical Technology activities ceremony, questions, Transfer including participation protecting Activities preliminary in several patent Undertook planning conferences, etc. copy of for technology answering a ground-breaking rights, . Test Plan - An internal was prepared Valley This ports Plan. Oversight the during the Unit for 2. working a sampling the identified the proper the requirements for be that where samples should so document Whitewater will installed. use in designing The document was in used preparing by LIFAC system be collected and where analyzers document were engineers installed and instrumentation designers locations draft in the test/sampling the Monitoring . and by environmental Environmental Management design conducted Valley and LIFAC NA maintained preliminary maintenance outage close oversight activities Whitewater of successful planned construction at the 2 site. Engineering During outage reactor layout removal piping, this tie-in and Design period, activities. mass balance concept. reheat (WBS 1.1.2) was placed on the completion of the March a the slag and Tampella flowsheet, Other system, delivered updated storage during area, system, to ICF KE in mid January P&ID and proposed this period activation humidification activation included reactor, system, emphasis preliminary design system, electrical activities recycle and design of the limestone and instrumentation requirements. Engineering and design activities included: . March tie-in activities including boiler Completion of modifications; water, steam and condensate pipe tie-ins; supply and return ductwork design; ductwork hanger and support and walkway emphasis storage building. System. and penthouse. of powerhouse. and steel. limestone reactor fan floor design; design. damper design/selection; . and access platform Design limestone drive Civil/Structural/Architectural Layout and design center/variable Design Design Layout Supply storage Layout Layout of duct of activation and design and return design building. and design and design of included: area/motor control frequency support/stair reactor of reactor ductwork for stair Support tower. platforms design tower, air outside Foundation of secondary of electrical equipment room. . Mechanical design emphasis included: Process flow diagrams Mechanical arrangement silo of limestone injection port storage building. New Limestone Design/Analysis Finalization installation Design Layout Layout of the expansion of modifications discharge sorbent of reactor of spent joints. to existing equipment. system. Page 13 arrangement injection and details system locations and seal box of limestone of boiler Completion flue gas ductwork. recirculation lc%/LIFAC/PTr.LyRepIO2 Calculated Calculated equipment. Determined Calculated air requirements. of silo existing pneumatic capacities. specifications. transport capacities limestone flue and bin vent thermal equipment/system gas duct mechanical expansions. Wrote various . HVAC design emphasis included: Determination of heating, requirements center, equipment Sized of the limestone frequency room. variable the appropriate design design ventilation storage drive for and air building, room, and conditioning motor control electrical equipment the above requirements. . Piping/Vessel Started Layout Layout transport Layout emphasis included: of activation reactor pipe supports storage air service air piping pneumatic slag recycle and limestone air, balance piping of various of limestone of secondary systems of spray water, recycle and design P&ID of steam flow diagram system existing diagram compressed Engineering of standard and design and design piping and design sorbent layout and spent Completed Completed Layout Completed P&ID steam/condensate ESP tie-in piping and systems and design of steam and condensate relocation specifications miscellaneous Wrote various . piping/vessel emphasis included: began on single conduit of Electrical design Engineering lighting plan. Layout Layout Layout line diagrams, schedules conduit plans, schedules, and design and design and design and cable and grounding general lighting plan P&x 14 activation reactor reactor electrical platform arrangement of activation and grounding of spend sorbent area conduit 168/LIFAC/QtrlyRep/O2 General plant lighting electrical design specifications. Wrote various . Instrumentation design emphasis included: Development of P&ID's, legends and general Wrote various equipment/instrumentation for by the notes specifications and and the .. - Specifications systems were instrumentation specifications required written groups. written Motor purchase of various equipment the mechanical, electrical following during is this a list of period: Panels The and completed Control Center additions - Power Transformers 480 volt 4160 volt Primary Duplex Reactor Conveyor . and Distribution Pump Splitter Switchgear and Secondary Humidification Basket Air Water Booster Sorbent Strainer Fan Flight Secondary Discharge Conveyor/Crushers and Flight Transfer and Accessories is a list of this period: Hangers Storage Ductwork Vibrators Recycle Equipment Silo Expansion Joints of Activation Reactor specifications which were reissued or The following started during Ductwork Limestone Reactor Pneumatic Fabrication and Supports -. and Erection Flue Gas Reheater .- Sorbent Pressure Indicators Elements Transmitters Temperature Temperature Flow Elements Level Control Ultrasonic Pressure 168/LlFAC/atrlyRep/O2 Switches Valves (Manual Level and Motor) System Analog Transmitters me 15 .- Weigh Cells Pilot In January, the project Tube Flow Element design to observe had design for the potential team leaders units visited the existing LIFAC installations Power Plant Tampella materials also held generated in Finland and operations also of construction to review waste. engineers construction meetings of the new reactor at the Inkoo Plant. equipment project. to discuss at the Vantaa ICF KE and selection Meetings of and were LIFAC- of the existing the Richmond Power & Light problems/benefits/marketability ICF KE also engineers began to develop in providing the process control logic system for LIFAC. Tampella assisted the control and interlocking description. Environmental Environmental site permitting Monitoring activity issues, (WBS 1.1.3) during this quarter involved on the effects issues maintaining/tracking related EMP. of unresolved involved involving air the permit status waste to the of host initiation addressing permitting issues of Phase I construction, ICF KE continued issues of air streams emissions evaluation limits and a renewed focus of the potential EIV. on the analyses and the future support presented and solid in the These issues waste disposal streams. site no-action in existing LIFAC waste to the ICF KE provided related, and EPA. no-action The host addressing Act should assurance whether would a researchwith IDEM that insure assurance under the Clean Air be pursued research-related modifications demonstration The planned triggered Contact a permit prepared with project initiation would not trigger activities permitting for a new source during early designation. of Phase I construction address construction the March outage in the quarter. that to ICF KE for waiving indicated be required the need to IDEM regarding and obtained a construction the scope of the Phase I activities, Phase I but would before permit Phase II construction for application a letter would not be required to IDEM on January be submitted the need for was initiated. the basis 24, 1991 documenting application Phase I activities. 16!3/LIFAC/atrlyRep/OZ Page 16 In conjunction monitoring draft EMP., monitoring intersection requirements. At the February request with the development activities were to plan, held of the LIFAC system design refocused to discuss control, availability on revising process and of monitoring control and control and finalizing monitoring locations system the and and the requirements, Meetings locations of test clarify process environmental monitoring of DOE, ICF KE prepared IDEM issues project on the environment (WBS 1.2.1A) bid specifications a draft letter to potential to Jerry effects Hebb of DOE on of the LIFAC of the host site. 18th addressing related demonstration at or in the vicinity Long Lead Procurement During items. . this period, were issued for most remaining long lead These included: Limestone storage bin 4160 volt switchgear Reactor slag discharge Transformers this period, . . . During system purchase orders/subcontracts were issued for these items/activities: . . . During will March outage construction ID fan variable frequency 4160 volt switchgear the next reporting be completed. and Startup and March, period, controller all remaining long lead procurement activities Installation During were completed. . (WBS 1.2.28) all tie-in requirements at Whitewater Valley Unit 2 February These include: . . Adding five additional injection ports into the boiler at a higher elevation than the existing ports. Installing bypass ductwork and dampers. Installing tie-in pipes and valves on the ESP hoppers for future recycling of spent sorbent. 168lLlFAClPtrlyReplO2 Page 17 . . . Installation return. Installing Rerouting dampers. during use during this of tie-ins for water supply, steam supply the of and condensate additional of existing catwalks and landings around pipes due to installation boiler. new ductwork and Also, for period LIFAC NA set up a field and operations. office at the Whitewater site construction FUTURE PLANS During funding LaFarge. Meetings the will be held with permits or various variances regulatory needed agencies to install in hopes of obtaining and operate LIFAC all at the next period, LIFAC NA hopes co-funders. to This conclude includes negotiations finding and secure for from the identified a replacement necessary Richmond Power & Light. Complete all complete Complete Submit detailed all design and procurement purchase of equipment orders needed for installation needed to of LIFAC and issue construction the required and startup and subcontracts by the end of October it 1991. review the and comment. Cooperative the next draft all past of the EMP and submit deliverables to DOE for due project as required under Agreement. Page 18

Related docs
Other docs by EIA
Standard Sample of Net Office or Industrial Lease
Views: 645  |  Downloads: 30
Shareholders Resolution Appointing Directors
Views: 250  |  Downloads: 4
Application to Extend Time
Views: 187  |  Downloads: 0
Deere and Co Ammendments and By laws
Views: 243  |  Downloads: 1
Barr Laboratories Inc Ammendments and By laws
Views: 214  |  Downloads: 0
Batmobile Side
Views: 616  |  Downloads: 6
Final Demand For Payment
Views: 517  |  Downloads: 24
CorpDocs-Articles of Incorporation California
Views: 355  |  Downloads: 22
Criminal Psychology
Views: 600  |  Downloads: 61
CONTRACT FOR SALE OF GOODS
Views: 402  |  Downloads: 6
BILL OF SALE WITH WARRANTY OF TITLE
Views: 263  |  Downloads: 1