Environmental Information Volume for Illinois Power Company Hennepin Station Boiler No Enhancing the use Eastern and Midwestern Coals by Reburning Sorbent Injection

Click to download
2.0 This presents project. PROJECT DESCRIPTION section a brief describes describes technical anticipated All only the existing facility activities, EHSS areas is at defines that afforded could Hennepin project Station, resource be description project and lists data cursory of the GR-SI technology demonstration potentially factors'for tenuous. requirements impacted addressed; which 2.1 2.1.1 this and discharges, however. retrofit by the project. requested treatment in Appendix J of the DOE PON are those technology Facility demonstration makes applicability Existing Site Hennepin Description Power Station is a 533 acre 2 miles of features is facility northeast located as indicated on the Illinois Illinois 2-l of plot view River in Putnam County, 85 mil'es The layout 2-3, presented Hennepin and in Figure Station place. site. is River. River is gas. Station in place approximately of the site 2-4. is accessible line access station of Hennepin, in the aerial and about and 2-2. Figure plan west-southwest Chicago, in Figures illustrated are identified specific on the station by rail, is via truck, and barge. highway lead the north site SO/l80 from The New York to the runs 180 of the with Natural the gas from the up to 100 which Central site is to within Hennepin Mississippi Illinois service percent Railroad in about site, (Conrail) Truck 1.5 miles a major and from on site runs adjacent county which the via to the site roads forms Hennepin on-site and a siding Interstate boundary Interstate of the plant; River, for navigation groundwater and Unit to the plant The Illinois and comnerce channel connecting are taken of firing Water supplies deep wells. 1 has the capability Hennepin The GR-SI delivered has Station two coal-fired will steam electric be conducted into in generating Unit 1. pile a storage units. Coal is which technology to Hennepin demonstration by barge and unloaded 2-1 *Heyepfn Power Station, Putnam County, ~lli,, I lmx (,aNa,lpl I I ,a Figure 2-1. Locatfon 2-2 of Hennepfn Statfon. 2-3 is for maintained fifty to at a level 8 acres. sufficient The Coal rate pile to supply coal pile runoff million both is units' coal requirements surface of and has an Runoff from Unit River. is 1. ninety flow days. covers gallons a ground approximately annualired received Overflow 2.1.2 on measurements intermittent in 1986. wastes Illinois average of 0.0186 per day (MGD), based made by Hennepin Station directly personnel into the by an ash pond separate from the pond receiving from each pond is discharged Description of Existing contains generating coals Table coal Unit Process two coal-fired capacity from various for of steam electric 310 MWe. 'The fired Illinois a coal analyses rate lb/hr boiler. mines, typical generating project depending of those will units be Hennepin with ure Unit in coal a total in Unit 2-5. 1 are 1986 Unit fired conducted Station net Unit 1, an 80 MW, tangentially Coal and ash analyses as shown in Figon price fired by by 1 fires in and availability. given Testing rate Commercial firing 2-1. at These an average were done for Eased on plant lb/hr. the plant and Engineering of Co. in 1986. lb/hr. measurements, The maximum Station factor 1 fired coal of 56,164 Both units in 1986. 1 is 71,500 in 1986. at Hennepin The capacity combined of Unit at a rate of 230,909 1 was 67.6 percent An electrostatic emissions. downstream ft2/(1000 Solid the from ash coal, to to the the fly of the air ft3/min). waste precipitator a cold side preheater. (ESP) unit, is used whfch to control means that collection particulate it operates area of 223 The ESP is The ESP has specific streams from the boiler by the plant ESP. include the furnace bottom ash and ash collected for disposal. These waste streams and are sluiced rate flow rate total rate of fly are exempted to on-site of the 1 1 is RCRA Subtftle ponds ash ash lb/hr. calculations pond pond is is C Hazardous Eased that indicate Waste regulations on the Average flow flow the average The average and ash percentage of bottom station ash from Unit ash from Unit ash generation 4566 lb/hr. 1537 lb/hr. 25,285 2-6 Ffgure 2-5. Schematic of Hennepfn 2-7 Station Unft No. 1 Bofler. TABLE 2-1. COAL AND ASH ANALYSES Fuel Properties Proximate Analysis (Dry) Typical Illinois Unit 1 Coal Fixed Carbon Volatile Matter Ash Moisture Heating Ultimate (as received) Value (as fired) (Etu/lb) Analysis (as received) 48.57 38.74 12.69 13.75 10,717 Carbon Hydrogen Nitrogen Chlorine Sulfur Ash Oxygen Moisture Sulfur Forms (Dry Coal Basis) 59.69 4.11 1.07 0.12 2.89 10.95 7.42 13.75 Pyritic Sulfate Organic Ash Fusion Temp. Reducing (oFI 1.62 0.04 1.70 Initial Deformation Softening (H = W) Softening (H = l/2 Fluid Ash Density (g/cm31 W) 2075 2185 2285 2390 2.2 Coal Grindability (Hardgrove) 52 2-8 Process non-contact Boiler measured sluiced demineralizing to water cooling from the adjacent applications is provided removal Sluice sluice plant River. permit total Effluent Illinois by on-site plant. River is used for fly once-through ash. in a as and for transporting Process 2-2. ash and bottom and is treated water flow rates and bottom make-up water deep wells Fly and silica an ash pond. by the utility are suasnarized water rate average in Table ash are are is requirement is about water from the solids, are varies 1.0 MGD. the plant Unit from 0.72 MGO to These values 1 ash pond effluent year has an on for an the and estimated Discharge 1.26 MGD. Annualized approximations hours of sluicing into flow the rate, in System maximum, discharged Elimination water are for Minimum, monthly average discrepancy leaving time, depending the made by the per day. Illinois (NPDES) pH, based on sluice The plant's requires of these values 1986. rate basis. the in sluice flow rate, and rain suspended pump rating National Pollutant to monitor for from flow is and oils derived water and greases. a recent the rate done plant's and average Table of 2-3. reports values These for parameters presented value NPDES monitoring 0.353 than sluice that rather between pond fact the Effluent MGD. time water effluent Flow entering water schedule monitoring Factors instantaneous, averaged, accounting pond and discharge pump rating which patterns, varies with water time on include approximations and sluicing and the upon ash sluicing is estimated an instantaneous During was measured emissions average (lb/MEtu). hourly pounds Full hr) of load of basis. test, the Unit cubic 1 flue feet gas volumetric per minute flow rate Air the 8tu to an to 5.40 load. lb/ (53.19 a 1986 emissions at 181,036 rate dry of limit concern include standard Unit (dscfml. ,In 1986, SO2. NO,, from Btu Hennepfn of 17,050 when both and particulates. Units lb/hr, units 1 and 2 are which is are operating SO2 emission I was 5.10 pounds of SO2 per million limited at full equivalent lb/Mbtu to be 0.69 SO2 emissions SO2 mass emfssfon SD2 per particulate million emfssions were measured to be 0.062 in 1986. NO, emissions are estimated by the utility lb/MBtu. 2-9 TABLE 2-2. PROCESSWATER FLOW RATES Source Unit Plant Unit Plant 1 Circulating Cooling 1 Sluice Coal Pile Water Water Runoff Boiler Water Flow Rate (MGD) 1.68 230 0.72~1.26 0.0186 (intermittent) 2-10, TABLE 2-3. AVERAGE UNIT 1 ASH POND EFFLUENT WATER PARAMETERS Parameter Flow Rate (MGD) PH TSS (mg/l) Oils/grease(mg/l) High 0.445 8.8 15.6 2.5 LOW 0.271 8.4 6.0 1.9 Average 0.353 8.6 9.8 2.2 2-11 I I 2.2 Technical Laboratory-scale Project Description of the reburning in the early 1970's Fourteenth Pittsburgh, scale research and pilot at full M. A., Injection." Institute, "Reduction concept (e.g. were originally Wendt, J. 0. L., Trioxide and investigations United States Fuel and Matovich, conducted Sternling, Nitrogen tional) More with the oil in Oxides the C. V., of Sulfur by Secondary it has been systems. fuel circa is Symposium (Interna1973, p. 897). in Japan, but mainly work at when scale in scale on Combustion, recently fired The Combustion Recent potential natural demonstrated extensive gas. EER has demonstrated reburning in developed Tennessee with higher locations SO2 control. EER's reductions reductions sorbent those scale spectrum most of injection obtained systems. The objectives data base demonstrating and to Since population. using three applications technologies. utility the full conducted boilers of with of primary recent up to if rather of the reburning Sorbent concept, particularly was also at that full injection originally 1970's 1960 and 1970 and was demonstrated Authority's (TVA) Shawnee Power Plant Subsequently, could sorbent be achieved materials. TVA demonstrated through the potential use of Large scale Valley in the early proper poor results. levels sites and advanced significantly injection U.S. for capture work at several of this technology and Canadian has begun to confirm pilot 70 percent a hydrated optimfzed scale from typical results indicate that 60 percent Sulfur reburning for NOx with of can be achieved pre-NSPS NOx levels. by combining is used. dioxide can be achieved sorbent gas These data are typical injection achievable reburning-sorbent to be generally a wide in full fuels and they appear the current project are to provide of this a comprehensive boiler of combination the performance promote the design of GR-SI in pre-NSPS utility characteristics could with commercialfzatfon and operating demonstration a total utility 2-12 of pre-NSPS address will varying be vary widely, no single pre-NSPS adequately widely Consequently, of three boilers demonstrations characteristics. as applied Figure boiler. NO that (CH) with percent emission the plant nitrogen is is The GR-SI systems will to each specific 2-6 illustrates in that host unit. be designed for optimum performance the application zone. the reaction NO is of of GR-SI in a tangentially release NH via reduced of NO with by a hydrocarbon NCO. N at high does fired radical Molecular and 60 to Natural producing NH2 at gas is injected HCN which allows above the main heat formation zone to reburn produced produced lower by the temperature provide have be useful not temperatures Thus, to future four (t22OOoF). this The GR-SI system will unit reduction could NOx control. constraint. in response 2-6 The pre-NSPS Hennepin an NOx NO, emission NO, regulations. are shown for to sulfur hydroxide. sulfur 1 boiler, firing upper capture. capture furnace an injection sorbent temperature Injection is injection; three of In Figure these injection for For duct the (A. is locations because B, and C) correspond necessary to maximize of calcium can help fired This plan is both Unit while emission to inject will injection. location also will Upper furnace of approximately D provides since performance. be to reduce sulfur by existing furnace material upgrades on this in the will included 2250°F is required injection tangentially coals. humidification SO2 emissions Illinois regulations unit. flue during A humidifier and precipitator the SO2 strategy the existing is with into not by 50 percent but could medium and high required reduction compliance the sorbent increase design startup be used for any future the upper SO2 regulations. The preliminary Sorbent gas. the injection several the amount of solid and performance phase. Among phase of the project and SO3 injection. the plant's current Therefore, during are flue waste The solid will ESP modifications and be assessed modifications Solid system. ash which, to lime/fly from product the detailed and implemented these possible construction gas humidification be managed using wet sorbent handling with fly waste from GR-SI is a blend of unreacted prepared dryer lime, for sludge spray of a calcium has similar sludge This due to the presence ash/scrubber lime-based characteristics or the solid hardens after disposal waste systems. 2-13 I I SH ____' I C- - -. B -’ - -, :I PNI)(ARV SH A -’ w -c - - REBlJRlW6 ZOIIE MAIN HEAT RELEASE ZONE -.---------em_ FUMACE COM- Ffgure 2-6. Applicatfon for NO,/SO, of gas reburning control. sorbent Injection 2-14 placement commercial 2.3 2.3.1 and value produces for stable landfills. applications. Such a blend may also have construction of Activities of Project will take Description Description The GR-SI project Phases 53 months in three to complete. phases: This initial phase plan will testing. transfer. will begin Follo~wing equipment panel. and Disposition. of Phase 2 and unit will will be data and test be made to the will The process after DOE be and will culminate injection for An industry EER will conduct the technology a demonstration Phase l--Design in the panel the detailed for the systems project and Permitting. design Hennepin construction of site. gas reburning A program and demonstration and sorbent be prepared equipment will be established to initiate and Startup. and will out at last technology This a Phase Z--Construction Phase approval, installed engineering 1 is completed and checked will phase 16 months. injection site. industry the gas reburning designs and sorbent Hennepin be presented Collection, with to the 0 Phase 3--Operation, Phase will tested results available industry 3 will last for will panel. of GR-SI is rather it will begin one year to industry. 29 months. Data Reporting, the final stages concurrent Following over into DOE approval, of conditions. results will a guideline the host All a range be compiled manual which The project be presented The demonstration technology technology but not intended conducted as a first generation of several of specific individual build upon the results demonstrations now being by the EPA and others. F-15 I 2.3.2 Description The following of Installation section as part personnel describes of the Activities the GR-SI specific technology Worker to ensure this installation demonstration safety that program has not only occupational tasks that by EER will be undertaken plant but to rules of injury will personnel, concern liability, subjected safety risk and local project. risks. enforced since All responsibility labor. is a primary a financial are not and the health workers in any industrial an ethical be fully unreasonable to workers. an employer appropriate throughout to minimize The GR-SI equipment in a series of five steps: installation work at Hennepin site will be conducted 1. 2. 3. 4. 5. Step outage at the Procurement Initial Final Checkout Correction three, of deficiencies final is the installation, key element will schedule power in time must correspond determining to a normally load if scheduled schedule. requirements outage until in this to of is and installation installation (normal (outage) unit operation) and this time are the installation a fall The specific scheduled there the regard. procure the final Most silos. items etc., will low but load long outage the period lead depend on the utility's For example. than anticipated to delay request may elect The program EER will greater and the condition no major problems, the items schedule of the unit. the utility spring. flexibility, demand is in the fall the outage authoriration the completion must be flexible To maximire design of the need as soon as possible following specifications. equipment will be standard directly items such as piping, A limited specific valves, number of and will be obtained from vendors. to meet site to be custom-fabricated 2-16 requirements. , These include general conduct possible. and fitting The initial operation following 1. 2. 3. 4. 5. A plot silo is the the gas and sorbent to will the limit during installation step will installation be installed equipment fabrication/assembly This required injectors, work outage will work step during windbox off site modifications, to the etc. will The be to approach procurement and installation maximum extent the amount of time-consuming the short work where all periods. be divided is conducted requires unit which custom installation on-site installation into two during steps: normal outage. an unit The and the final equipment Sorbent Sorbent Sorbent Sorbent a unit operation: normal unloading feeding piping injection and storage and transport equipment. equipment. equipment assembly. final connections. of the sorbent storage and injection control installation Station 2-7. complete the assembly. except showing for Instrumentation plan of Hennepin the location shown in Figure is to The intent flexibility The following 1. 2. 3. 4. 5. 6. Boiler handling initial installation installation during an outage: during in time to provide outage. on completing equipment the final a scheduled must be installed Windbox modifications. Furnace Final Final Final or duct connections gas plumbing. instrumentation connections. penetrations for control for gas injectors, overfire air ports or sorbent injectors. equipment. ESP upgrades. tubes will are lined licensed with asbestos All boiler to minimize modification asbestos 2-17 heat loss, and some asbestos be conducted include by in EER will be required. work will a contractor to work with materials. I I q -w-e z .z y the contractor's specifications be satisfied, and proper that all a requirement including disposal final the the prior that all applicable DSHA and air EPA regulations monitoring It single will is asbestos removal guidelines, requirements, not necessary outage to items considerations. work be completed penetrations, completion available. outage. of the at a installation initial to during the scheduled be given following installation. Consideration windbox initial would This installing if furnace/duct outage becomes modifications installation reduce 2.4 This technology categories 2.4.1 and ESP upgrades a scheduled of effort Source Terms characterizes project. requirements the intensity Project section of resource Project required the final all of the source can discharges. terms of the GR-SI the demonstration Source and project terms be divided into Resource resource Requirements requirements include Figure requirements energy, land, water, with labor, important the GR-SI Project materials, process technology flow and other rates. demonstration resources. project 2-8 is a diagram below. detailing The resource associated are identified Energy Requirements Additional demonstration gas required consumption 1877 standard flow. 45,713 Coal lb/hr. for energy include the rate ft3/min. feed rate as reburning site for requirements electrical fuel. is about the host associated The estimated 800 kW. site It at full decrease with increase is estimated operating the GR-SI technology and natural power will be gas to the natural power to run sorbent equipment that in electrical capacity gas consumption Coal usage will is expected due to the added natural by approximately 19 percent to decrease 2-19 I I . Ir iI # b il 1 z E a 5 z tl j , Land Requirements The GR-SI technology control is associated requirement been insiallation is available examined for procedures within with to implemented demonstration utility boiler relatively the existing that location storage adequate of all involves boilers. structure compact, plant space required the retrofit Since there is of two emission itself systems site has for space on existing the existing are GR-SI the technology is and the ancillary The host Sufficient no anticipated on site of land outside ensure of the sorbent convenient boundaries. equipment. available hardware. and feeding Water Requirements The GR-SI However, process Hennepin requirement MGD. Based the MGD. Labor Requirements Labor operation performance. labor skills. requirement, locally A breakdown Dperation additional existing labor; plant by EER using will be required of the is still available of labor for the equipment a relatively labor requirements of the that installation hardware. small installation effort both to provide of the GR-SI equipment, of system the largest can be managed and specialized 2-4. very little by the program. more will Station will process sluice generate does water not will require the of utilization because fly that value that is ash. of of water, the sorbent Calculations sluice per se. injection by water 2.45. be required amount indicate current also an increased from will water its and EER personnel increase water the average 1.0 MGD to about Humidification on calculations gas flue be needed to enhance ESP performance. the gas will expected be saturated, 0.15 to be about made by EER assuming requirement humidification and maintenance Although it and verification represents which general is presented GR-SI these systems tasks in Table requires and maintenance it is anticipated staff operations may be conducted training upon completion 2-21 of a brief TABLE 2-4. PROJECT LABOR REDUIREMENTS Task I Duration (months1 Comnunity-Supplied Labor (hrs) Phase 1: Phase 2: Phase 3: Baseline Testing Construction GR-SI Testing 1 16 12 240 8,310 2,000 10,550 2-22 During oversee test periods, EER test crew personnel will also be available to operation and maintenance verification will procedures. will be conducted tests. by EER test crews. No Performance additional Materials labor tasks for be required these Requirements material sorbent. the course requirement During of silo. the for the GR-SI technology 6093 lb/hr 15,000 150 tons for producer. tons sorbent process. generate River demonstration will will be are be of sorbent The primary is a calcium required. expected stored for tested Illinois quantities Illinois access which will During in the site's the lime of lime based operation program, of CalOH) of sorbent The sorbent to be used state at the site. sorbent of Illinois as part hydrate plant. will Sulfuric vulcan are Approximately The raw material is a major is limestone to be two However, sufficient The two with easy be selected producers, calcium manufacturers of the demonstration and Marblehead, supply on the located to easily the demonstration. Illinois to the Hennepin Construction Construction and small will also hardware materials materials include items. locally. be purchased sorbent acid silo from local for distributors. equipment, piping pH adjustment and handling and CO2 required be purchased Transoortation Reouirements impacting usage. trucks transportation The sorbent per day for barge. will delivery. are decrease be trucked in coal in and will usage and require delivered entering deliveries the is The main factors increase to in sorbent two coal approximately Hennepin for plant Coal is currently no trucks in barge change by means of delivery. There are currently No substantive expected. 2-23 2.4.2 Project Significant Discharaes waste discharge stack streams from the boilers site, decrease employing emission to 0.28 the GR-SI of fly have ash been coal dry reduction lb/MBtu. emissions technology and spent targets established. Emissions quality. are standard Solid to hr. greater natural will not the expected This of include sorbent. emissions for are and a solid demonstration ND, and 502, expected to waste consisting respectively, At the technology 60 and 50 percent NOx emissions of SO2 would Flue decrease gas flow No changes to 2.55 lb/MBtu, hydrocarbons. will rate based on 1986 average or particulate slightly to 181,515 in CO, unburned anticipated. ft3/min. waste increase is.expected of sorbent. from its would amount of to change in both Flow current fly ash occur rate level the from of fly flow rate and composition to about rate being rate, 11,000 would coal which due lb/ be by ash, GR-SI addition increase than gas. affect coal the ash collected injection is by the ESP is to increase of 4566 lb/hr sorbent coal that ash will decrease since displaced The new composition CaSO4. and 41 percent per se, is consumption. are also of anticipated will solid waste. of the fly Ca(DHl2. to be 34 percent to 1248 lb/hr 25 percent reduced Bottom ash flow expected because of Changes pond. increased water increase of become permit Possible include the in liquid be required Based show that to the fly of effluent because on the average ash will discharge GR-SI will flow expected effluent from the ash generate rate will to an More sluice amount by about more limit increase, water calculations amount of sluice 1.45 MGD. thus making sorbent Monitoring measures with sulfuric In both of the new value 1.80 MGD. The addition stream be adjusted in acid to meet the the dioxide addition ash pond through (CO2 unreacted and spent alkaline. of 9. cause the waste The pH of the ash pond will pH will to acid these lower the be done during pH level of carbon the GR-SI operation. neutralization injection water. or bubbling processes, alkaline 2-24 reacts limit in water of 9. Oil to form carbonic acid1 will lower the pH to within the permit and grease will residence reacts loadings time of are not anticipated below the regulatory the water in the concentration pile runoff to change. limit of pond or using is expected sulfate. Total chemical suspended by increasmeans to because is not solids ing the the be maintained rate. with 15 mg/l enhance settling sorbent expected Coal result contributions In addition, slightly. increasing Canadian 'leachability increase in Sulfate coal to increase Coal pile size SO2 to form calcium to change and thus usage will from pH is Studies pH (e.g. will of not change. the GR-SI than levels of metals T. W., Technical there is project, those or to and as a metals from coal. increase with of 805, and be no of decrease metals sorbent expected have Cote, 1984, as a result loading to remain that will at coal-based decrease. to be smaller current In general, are expected shown leachability and Constable, Special Since decrease, effluent decreases Publication P. L. p. in 53). to either "Development loading to Data Base on Waste Leachability, are metals both expected ASTM, Philadelphia, coal-based metals expected levels or groundwater as a result the GR-SI project. 2.5 Potential A number proposed groundwater focuses probable EHSS Receptors features include use, the labor air force, could potentially surface with and energy environment be impacted water respect impact resources. by the 3 of environmental These land quality, action. quality, quality, Section of to these on characterizing impact receptors. receptors. existing Section 4 evaluates the probable GR-SI one these 2-25 3.0 This Hennepin were EXISTING ENVIRONMENT section site, action. in in this Atmospheric The area provides focusing Section section. Resources: Illinois Meteorology, in which climate average Peoria west annual Air Quality, and Noise site Peoria south is located cold a description on environmental is 2.5. Each of of divided these the into environmental that might the six setting be impacted categories is characterized at by that features the proposed individually 3.1 The environment mentioned categories of central 3-l is the demonstration with wind roses of the for site. provides winters. for station Illinois inches. a typical Figure and Moline State The climate continental the year. about warm summers and fairly 50 miles shows BO-year and Moline of Hennepin to the is 34.9 4 months throughout is about 60 miles average According in Peoria states climatologist, is typical of a local precipitation midwestern of the entire area and not representative The air County including Geographic in February Emissions businesses particulates, The River. ongoing shaping area Current is in total Intrastate), specialized environment. site is generally 71 (North EPA criteria Pollutants of Illinois good. Central Putnam Illinois to EPA's there the Air quality federal in the area of Hennepin air quality control area for Status EPA. that emit NO,. the all region 502, and is an attainment suspended 1985 by the Inventory 10 emit revealed and industrial Designations of Attainment Illinois that plants U.S. pollutants, published are 95 56 emit particulates, and NO2, according of Criteria A survey air in Putnam and Bureau Counties pollutants, of which SD2. and 17 emit surrounding are other at the immediately but noise feeding). there levels activities Hennepin plants plant site are is not the highly Illinois to pile industrialized, industrial Hennepin plant along attributable (e.g. coal construction and coal and normal operation 3-l JANUARY a. 80-YEAR TOTAL (1901-80) NT b. APRIL BO-YEAR TOTALl1901-80) NT Figure 3-1. Wind roses for Moline and Peoria, Illinois. 3-2 JULY~~-YEARTOTAL(~QO~-~~) C. NT OCTOBER QC-YEARTOTAl.(lQOl-801 d. NT For each concentric circle, the Key: wind blows 1 percent of the time from the direction of the line. Thus, a line directed vertically downward from the city that passed through 10 circles would indicate that the wlnd blew from the south 10 percent of the time Figure 3-1. Wind roses for Moline 3-3 and Peoria. Illinois, (Concl.) 3.2 Land Resources Hennepin Power Station along There near Lowland are Spring of of been is the located upper in Putnam County, Illinois hills loess River Province. in the The powerplant alluvian Hennepin which by the immediately Station areas this within is Illinois. The power Ridged country Illinois outwash within which the flood of plant Plain is terrain River iS situated of the Central level. is found in the Bloomington The surrounding vicinity, lies Station a village surrounding the,IOO-year Hennepin and glacial is for in the Physiographic no large Creek. thick Hennepin, created areas Hennepin which are of nearly but rolling floodplain of the zone for to lie of the of River. the composed Village yet underlain boundaries zone maps However, Hennepin by flood Therefore, considered by Pennsylvania have not age bedrock. National Insurance on the east flood Station Agency. and west plain. will be unincorporated A13.areas, the fn a flood the proximity the Village have been mapped. is enclosed purposes volume, zone Al3 area. of the plant to the 3-2. between the bed. While Illinois River. by the there Illinois with as a deal are Because wetlands Department the Illinois in area. code This flooded A wetlands map as constructed site that area, Conservation code is shown in Figure PAB4FX on the indicates There is a wetland is classified is a great classification the ash ponds and the there wetland semipermanently of agricultural Soil site and Water is classified Palustrine District are aquatic activity in the Hennepin according clay loam, to the Putnam County surrounding which Hennepin is of marginal immediately Conservation use. There site. most of the soil silty or unique as moundprairie agricultural surrounding 3.3 no prime farmlands the Hennepin Water Resources Hennepin Ambient water in summarized contaminants. plant quality Table intakes data 3-1, 3-l water for it from and discharges the Illinois flow River rates to the Illinois River. site are of and near Hennepin and concentrations fron. including From Table can be seen that 3-4 copper. mercury. I I U! TABLE 3-1. WATER QUALITY DATA FOR ILLINOIS HENNEPIN (1985) RIVER AT *Flow Rate (ft3/s) Oxygen (mg/l) Dissolved Barium Boron (mg/l) Cadmium (mg/l) Chromium (mg/l) Copper (mg/l) Manganese (mg/l) Mercury Nickel (mg/l) (mg/l) (mg/l) 0.024 D.36* 0.15 0.005 0.13** 0.05 0.010 0.26** 0.10
Related docs
Other docs by EIA
nc320
Views: 53  |  Downloads: 0
How do CFO's decide on Capital Stucture
Views: 884  |  Downloads: 39
tr130
Views: 53  |  Downloads: 0
Glossary of Financial Valuation and Accounting terms
Views: 5881  |  Downloads: 391
tfintelements[1]
Views: 64  |  Downloads: 1
sc130_002
Views: 36  |  Downloads: 0
ud105_001
Views: 47  |  Downloads: 0
Music Facts Band
Views: 1716  |  Downloads: 33
wg002
Views: 76  |  Downloads: 0
mc956_003
Views: 46  |  Downloads: 0
Gatsby Quotes
Views: 1165  |  Downloads: 8
anderson[1]
Views: 67  |  Downloads: 2
pldc0012
Views: 37  |  Downloads: 1
dinner invite
Views: 1084  |  Downloads: 30