DOE/FE-0087 CCTl87 PC 79796
Comprehensive Report Clean Coal Technology
To Congress Program
Enhancing the Use of Coals By Gas Reburning and Sorbent Injection
A Project Proposed By Energy and Environmental
Research Corporation
May 1987
U.S. Department
Office of Fossil Energy Washington, DC. 20545
of Energy
TABLE OF CONTENTS
Jl .O EXECUTIVE SUMMARY 2.0 INTRODUCTlONANDBACKGtiOUFiD 2.1 2.2 3.0
:
:
:
:
:
:, : 12
Re uirementfor Report to Congress 1 Eva uatlon and Selection Process
TECHNICAL FEATURES &)‘3.1 Project Description J3.1.1 Project Summaiy J3.1.2 Project Sponsorship and Coit : : : : 3.2 Gas Reburning-Sorbent Injection Process 3.2.1 Overview of Process Development 3.2.2 Process Descri tion : 3.2.3 Application o P Processe; in Propdsed Project 3.3 General Features 3.3.1 Evaluation of de&lo &en&l Risk : : : 3.3.1.1 Similarity of Preject to Other Demonstration/Commercial Efforts 3.3.1.2 Technical Fea$bility 3.3.1.3 Resource AvaIlability 3.3.2 Relationship Between Project Si;e and Prdjected Scale of Commercial Facility . 3.3.3 Role of the Pro’ect in Achieving commercial Feasibility oft h e Technolo 3.3.3.1 Applicabilit of the ?Y ata to be Genera Yed 3.3.3.2 Identification of Features that In&ease Potential for Commercialization. 3.3.3.3 Comparative Merits of Project and Projection of Future Commercial Economics and Market Acceptability.
37 :‘: 41 42 47 49 49 51
J4.0 J 5.0
ENVIRONMENTALCONSIDERATIONS PROJECT MANAGEMENT 5.1 5.2 5.3 5.4 5.5 Overview of Management Organization Identification of Respective Roles and Respdnsib’ilitie; Project lmplementation,and Control Procedures. Key Agreements lmpactrng Data Rights, Patent Waivkrs and InformatIon Reporting : Procedures for Commercialtzation of T&hnbiog$
J6.0
PROJECTCOST AND EVENT SCHEDULING 6.1 6.2 6.3 Project Baseline Costs Milestone Schedule Recoupment Plan . ,
:: 54
1.O
EXECUTIVE SUMMARY
The FY86 Appropriations $400 million demonstration Coal projects following to support facilities
Act, P.L. 99-190, included the construction
approximately of The Clean having the
and operation
using Clean Coal Technologies. spectrum of technologies
cover a broad in common:
things
(1) all are intended acceptable
to increase the and (2) all
use of coal in an environmentally are ready to be proven
manner; level.
at the demonstration
In response fifty-one
to the resulting
Program
Opportunity
Notice
(PON),
proposals
were received
in April
1986. After technologies,
evaluation, were
nine projects, selected
representing
seven different
in July 1986 for funding
under the Clean Coal Technology
(CCT) Program.
One of the nine projects Environmental demonstrate
selected
was the Energy and proposal Injection to process (GR-SI) combustion
Research (EER) Corporation the Gas Reburning-Sorbent boilers representing
on three different configurations.
three different
The CR-SI process has been developed coal combustion retained systems. The existing
to interface burners
with the existing are
or comoustors Control
when the GR-SI process is installed. by burning
of nitrogen of coal in the coal
oxides (NO,) is achieved boiler at a carefully
a lesser amount
controlled
air to fuel ratio.
The decreased
input to the boiler which portion nitrogen combustion natural process. is injected
is compensated downstream
for by the use of natural zone.
gas A to
of the coal combustion by the coal combustion
of the NO, formed by the reducing of natural
is converted
conditions
caused by the partial downstream combustion of the
gas. Air is then injected point to complete
gas injection
this staged
The net effect 60%
of this procedure
is to reduce NOx emissions
by approximately
Sulfur oxides, or SOx, consist primarily Emission of this pollutant injecting a sorbent is reduced
of sulfur
dioxide,
SO2.
in the CR-9 process by part of the boiler The sorbent, or into the flue in
into the upper of the boiler.
gas duct downstream the fly ash, is removed precipitator ification,
now contained electrostatic
from the flue gas in an existing
(ESP) or baghouse. which enhances
The need for flue gas humidactivity for 502captureand basis. For
both sorbent
ESP performance, this project, and sorbent cyclone boiler
will be determined
on a site specific
humidification injection
will be used at two of the three sites at the
into the flue gas duct will be tested this technology is capable
site. While
of reducing
SO2 up to 80%, one of the objectives control at approximately a higher
of this study will be to achieve burning a blend of
the 50% level while percentage technology of sulfur
coal containing provides
The GR-SI process wet Flue Gas less physical space.
an alternative
to conventional requiring
Desulfurization
(FGD) processes, while
2
This project
will use the following
as host sites:
A tangentially owned
fired,
80 megawatt
electric
(MWe)
boiler
by Illinois Illinois.
Power Company A tangentially
and located fired boiler
near has burners coal and
Hennepin, mounted air toward
at the corners
and directs the burning of the boiler.
points just off the center
A wall fired
117 MWe boiler
owned
by Central
Illinois Illinois.
Light Company
(CILCO) located has burners
near Bartonville, which
A wall fired boiler air/coal
direct the burning which is are
into the furnace
in a direction
perpendicular mounted.
to the wall in which the burners
A cyclone fired 40 MWe boiler and Power Company Illinois. which
owned
by City Water in Springfield,
Light
(CWLP) located
A cyclone fired boiler is external to the boiler
has a combustion
system
and the hot combustion is
products complete.
enter the boiler
after the combustion
The locations
of these facilities boilers
are shown
in Figure
1. All three This
units are commercial project viability is intended
that are presently the technical with different
operating.
to demonstrate boilers
and economic firing
of GR-51 on three
3
/ *
Unit No. 1 Hennepin Station Illinois Power Hennepin. IL Tangentially Fired 80 MWe I Z2G kation Central Illinois Power Bartonville, IL Wall Fired 117 MWe I %%~‘Statl0n City Water Light 8 Power Co. Springfield, Illinois Cyclone Fired
/
*-
FIGURE 1.
EER GAS REBURNING-SORBENT INJECTION PROJECT LOCATIONS OF DEMONSTRATION PLANTS IN ILLINOIS.
N0.113.941
configurations pre-NSPS boilers. fully tested performance
which
represent
the majority and sorbent
of all U.S. coal-fired, injection has been the
Gas reburning
on a pilot scale. This program of the integrated is expected technology
will demonstrate
on full scale commercial the same operating
boiler systems, which
to have about
cost as wet FGD. However, on NOx.
FGD captures
only SO2 and has no effect
This demonstration month period
project
will be performed
over a fifty-four the design and
at three test sites and includes testing,
installation and reporting scheduled months
of equipment, of results.
data analysis, site restoration as originally proposed was
This project months
for forty-eight without
with phase overlaps A fifty-four month
or sixty project period and
phase overlaps.
has since been selected eliminate phase overlaps
to accommodate
plant outage
periods
at any one test site.
The total
project
cost is $29,998,253.
The co-funders ($10,000,000)
are DOE and the
($14,998,253),
the Gas Research Institute Testing
State of Illinois ($5,000,000).
is scheduled
to begin at the and at
CILCO site in early 1989, the Illinois the CWLP site in mid-1990. to occur in late 1991. Overall
Power site in mid-1989 project completion
is scheduled
2.0-
INTRODUCTION
AND BACKGROUND
The domestic role in meeting
coal resources current
of the United energy
States play an important needs. During the past
and future effort
15 years, considerable improved provide
has been directed conversion, energy
to developing processes to
coal combustion, efficient
and utilization options.
and economic permit
These technology
developments acceptability
the attainment
of environmental utilization of coal resources.
as well as the efficient
2.1
Requirement
for Report
to Conqress
In December Technology Making Agencies Other
1985, Congress (CCT) Program
made funds available
for a Clean Coal
in Public Law No. 99-190, An Act of Interior and Related
Appropriations
for the Department September funds
for the Fiscal Year Ending This Act provided
30, 1986, and for the purpose projects of
Purposes.
“...for
conducting struction for future authorized
cost-shared and operation commercial
Clean Coal Technology of facilities applications
for the con-
to demonstrate
the feasibility and
of such technology...” Public Law available
DOE to conduct
the CCT program. to remain
No. 99-190 provided expended, of which
5400 million”... 9100,000,000
until available;
shall be immediately
(2) an additional October available
$150,000,000
shall be available
beginning shall be
1, 1986; and (3) an additional beginning October 1, 1987.”
$150,000,000 However, authority
Section 325 of the by 0.6 percent so
Act reduced
each amount
of budget
6
that these amounts $149.1 million,
became $99.4 million, for a total
5149.1 million,
and
respectively,
of $397.6 million.
In addition,
in the conference
report
accompanying a
Public Law
No. 99-190, the conferees comprehensive to be funded August Proposals report
directed
DOE to prepare received,
on the proposals
after the projects in on
had been selected.
The report
was submitted Report
1986 and was titled Received
“Comprehensive
to Congress
in Response to the Clean Coal Technology Notice,” DOE/FE-0070. Specifically,
Pro-
gram Opportunity outlines proposals
the report
the solicitation
process implemented summarizes
by DOE for receiving proposals that
for CCT projects, provides
the project
were received,
information
on the technologies specific
that were
the focus of the CCT program, related to the solicitation.
and reviews
issues and topics
Public Law No. 99-190 directed comprehensive award directive report
DOE to prepare
a full and to receive an of this
to Congress
on any project
under the CCT program. and contains
This report
is in fulfillment
a comprehensive
description
of the Energy
and Environmental Project.
Research Corporation
GR-SI Demonstration
2.2
Evaluation
and Selection
Process
DOE issued a Program February
Opportunity
Notice
(PON) on cost-
17, 1986, to solicit proposals
for conducting
7
shared CCT demonstrations. proposals were required identified
Fifty-one
proposals
were received.
All
to meet preliminary
evaluation was made to evaluation
requirements determine requirements
in the PON. An evaluation met those preliminary
if each proposal
and those proposals
that did not were rejected.
Of those proposals evaluations
remaining
in the competition, Technical
separate Proposal, The PON greater and that
were made for each offeror’s Proposal, Proposal
Business and Management provided importance that the Technical
and Cost Proposal. was of significantly Proposal
than the Business and Management was minimal; however,
the Cost Proposal
everything
else being
equal, the Cost Proposal
was very important.
The Technical categories. projected different
Evaluation
Criteria
were divided
into two major addressed the
The first, “Commercialization commercialization from the proposed
Factors,”
of the proposed demonstration involved
technology. project
This was
itself and dealt
with all of the other mercialization consideration socioeconomic economics proposed
steps and factors The subcriteria
in the comallowed for
process.
in this section health,
of the projected impacts
environmental,
safety, and and the
(EHSS); the potential
marketability
of the technology; technology
and the plan to commercialize to the demonstration
subsequent
project.
The second major category, recognized
“Demonstration
Project
Factors,” project
the fact that the proposed
demonstration
8
represents operation project allowed adequacy
the critical
step between readiness,
“pre-demonstration”
scale of
and commercial itself. Subcriteria
and dealt with the proposed Project Factors” for scale- up; project; the and
in “Demonstration of technical
for consideration
readiness
and appropriateness
of the demonstration aspects;
EHSS and other site-related adequacy of the technical of Work.
and the reasonableness and quality
approach
and completeness
of the Statement
The Business and Management
Proposal
was evaluated
to deterof the under-
mine the business and management offeror, standing Proposal appropriate the proposed
performance
potential the offeror’s
and was used as an aid in determining of the technical was evaluated requirements to assess whether
of the PON. The Cost the proposed cost was cost of was
and reasonable, project
and to determine
the probable
to the Government.
The Cost Proposal approach to
also used to assess the validity completing Statement the project,
of the proposer’s
in accordance
with the proposed of the PON.
of Work and the requirements
Consideration factors:
was also given to the following
program
policy
a)
The desirability projects
of selecting
for support
a group
of technical
that represent
a diversity
of methods,
approaches,
or applications;
9
b)
The desirability projects
of selecting
for support
a group
of of
that would
ensure that a broad base is utilized,
cross section
the U.S. coal resource future; and
both now and in the
c)
The desirability projects expanding impacts.
of selecting
for support
a group
of
that represent
a balance
between
the goals of environmental
the use of coal and minimizing
An overall
strategy
for compliance consistent
with
NEPA was developed on Environmental
for
the CCT Program Quality with
with the Council
NEPA regulations
and the DOE guidelines includes impact both
for compliance and projectand
NEPA. This strategy environmental
programmatic during
specific
considerations,
subsequent
to the selection
process.
In light of the tight the confidentiality DOE established environmental decision-making Offerors specific proposal.
schedule
imposed
by Public Law No. 99-190 and PON process,
requirements alternative factors
of the competitive
procedures
to ensure that and integrated into the
were fully evaluated
process to satisfy its NEPA responsibilities. to submit both programmatic and projectpart of their
were required environmental
data and analyses as a discrete
IO
This strategy preparation
has three
major elements.
The first involves environmental and analysis impact
of a comparative
programmatic provided
analysis, based on information supplemented
by the offerors
by DOE, as necessary. environmental programmatic
This environmental consequences alternatives involves
ensures that relevant Program
of the CCT are evaluated preparation The third
and reasonable process.
in the selection of a preselection element documents the PON. provides
The second element environmental
project-specific for preparation
review.
by DOE of site-specific for financial assistance under
for each project
selected
No funds from the CCT Program design, third construction, operation,
will be provided and/or
for detailed until the completed.
dismantlement
element
of the NEPA process has been successfully each Cooperative Monitoring Agreement entered
In addition,
into will require siteand
an Environmental
Plan to ensure that significant data are collected
and technology-specific disseminated.
environmental
After factors,
considering
the evaluation
criteria,
the program submitted
policy by Energy was
and the NEPA strategy,
the proposal
and Environmental one of the proposals
Research Corporation, selected for award.
Irvine, California,
11
3.0
TECHNICAL FEATURES
3.1
Project Description
The EER project Injection
will demonstrate
that Gas Reburning
and Sorbent
(GR-SI), a control
technology for retrofit
for the acid rain precursors, applications. It will be the first technology that
50x and NOx, is suitable commercial is relevant
scale demonstration to utility boilers
of this particular States.
in the United
The demonstration sites each of which configuration: relatively
will be conducted has a boiler with
at three different a different firing
utility
test
tangential,
wall and cyclone.
The boilers are all
small commercial
units sized at 80, 117, and 40 MW, represent most of the
respectively. existing
These design configurations utility boilers
pre-NSPS coal-fired
in the U.S. and successful for
demonstrations retrofit
on these units will make GR-SI attractive
applications.
The goal of this program feasibility
is to prove the technical If successful,
and economical it will achieve up
of the GR-SI technology.
to 60% NOx and 50% or more SO2 reduction as wet FGD processes which humidification enhance efficiency. capture
at about
the same cost
only SO2. GR-51 will use will ESP
in two of the three test sites. Humidification by the sorbent and aid in improving
SO2 pick-up
A summary
of the three
demonstration
projects
is shown
in Table 1.
12
Table 1. Summary of Demonstrations by EER GENERAL Utility Station, Unit Location: State Capacity (MWe) BOILER Fi;Fg ConfiguraTangential Steam Capacity 103 Ib/hr) Jl anufacturer PRECIPITATOR Location Size (Sq. Ft.) Manufacturer FUEL Coal Type Sulfur (%) Gas Availability Illinois, 3.8 Yes BIT Blend of Illinois,BIT :.ytucky, Illinois, BIT 3.6 on site, within l/2 mile BIT Front Wall 850 Riley Cyclone 320 B&W Illinois Power Hennepin, 1 Illinois 80 CILCO Edwa,rds, 1 ‘/P CWLP Lakeside, P”” 7
:8E5
Side 42”:” Side :Y;d Standard Buell American
Cold Side 333-1000 Smidth
4 miles from plant
EMISSIONS CONTROL OACH NO, Approach Control (%) SO, Aooroach
\I
$s..e&urning Uoaer Furnace lnection minimum Humidification
~;:~e&urning Duct
Control (9/o) ESP Enhancement
sd
Upper Furnace In ection minimum Humidification 503, Injection
5d
13
3.1.1
Project Summary Gas Reburning - Sorbent Injection Research Corporation
Project Title: Proposer:
Energy and Environmental (EEW
Project Locations,:
Bartonville,
Illinois (Edwards
Station)
-
Peoria County Hennepin, Putnam Illinois (Hennepin County Illinois County by gas reburning injection for NOx (Lakeside Station) Station) -
Springfield, Sangamon Technology:
Flue Gas Cleanup control
and sorbent
for SO2 control boilers
Application:
Retrofit
of coal fired utility
and industrial coals
Types of Coal Used ‘. Illinois and Kentucky (1% to 3.8% sulfur) Product: Project Size: Project Start Date: Project End Date: Environmental Control
bituminous
Technology (three sites)
80 MWe, 117 MWe, 40 MWe July, 1987 December, 1991
3.1.2
Project Sponsorship
and Cost Research
Project Sponsor:
Energy and Environmental Corporation
Proposed
Co-Funders:
U.S. Department
of Energy, State of Illinois, (GRI)
and the Gas Research Institute Proposed Project Cost: $29,998,253 Participant Share (%) 50
Proposed Cost Distribution:
DOE Share (%I 50
14
3.2
Gas Reburninq-Sorbent
Injection
Process
3.2.1 Overview
of Process Development
Sorbent
injection
Demonstrations
Sorbent
injection
has been undergoing from
development
since the mid-
1970s under funding firms.
EPA, DOE, EPRI and several commercial on identifying Work the process has focused on
Most of the work has focused which optimize sulfur injection
parameters the impacts performance impacts.
capture.
of the sorbent of a utility
process on the overall for reducing scale reactivity tests that focus on reactivity effects; large pilot those tests;
boiler
and methods laboratory
This work has included
bench scale process design development time/temperature history and sorbent
scale tests that focus on impacts mixing and combustion
of firing
system design and furnace programs. and additional directly A number efforts in
model development
of field evaluations are in progress.
have been completed either
EER has participated work.
or indirectly
most of this development
In the last !O years, a number have been carried using a variety
of test programs ranging from
for sorbent
injection
out on boilers
15 to 600 MW and ‘were carried sorbent out in
of coals. Most of these programs
Europe and Canada and they all focused injection alone without regard involve to other gas firing
on optimizing competing
technologies. for NOx
None of the programs
or have potential
15
controi
except by installation
of low NOx burners. through
This project the use of the
offers the added feature natural gas reburning
of NOx control
process.
Reburninq
Demonstrations
Compared
to sorbent effort
injectio.n,
considerably
less development on gas reburning
and for NOx
demonstration control.
has been expended work
The original
was done in the United
States in the
early 1970s with subsequent commercial scale tests where
work done in Japan, including NOx emission During reductions of greater
than 50 percent
were achieved. (mostly
these tests coal and oil fuel was
were fired simultaneously
oil) and the reburning
oil. Hence, the results are not representative boiler practice.
of recent U.S. utility
Since 1981, EER has continued United focused States under on defining support
the development
of reburning has
in the
from EPA and GRI. This work and included
the key process variables IO million Btu/hr
tests up to about
to large pilot scale: 1 MWe.
which corresponds
These tests have demonstrated The EPA program
that gas is the optimum has focused on gas reburning with
fuel for reburning.
only; the work for GRI includes sorbent injection.
integration
of gas reburning to co-fund of reburning and operation
GRI and EPA have agreed This EPA/CR1 demonstration data on the design
a reburning will of full scale
demonstration. provide
considerable
gas reburning
systems.
However,
this reburning
demonstration sorbent
will be technology injection
specific
in that it will not include
for 502 control.
3.2.2
Process Description
Gas Reburning-Sorbent combustion staging
Injection
is a two part process in which NOx while sorbent injection
is used to control
is used to control
SO2.
Gas Reburninq
Nitrogen
oxides, or NOx, are formed or when nitrogen
when
nitrogen
included
in the air is
fuel oxidizes oxidized. nitrogen combustion
contained
in the combustion
The formation content
of NOx depends
on flame temperature, for
of the fuel, quantity
of excess air available
and residence
time at high temperature. the greater is the tendency
The greater to form NO,.
any of these parameters,
Reducing
any of these parameters lower
will reduce NOx formation. short residence time and
Unfortunately oxygen other
flame temperature, sufficient to greatly
deprivation, problems
reduce NO,, result in of carbon monoxide, soot, may
such as high emissions organic effects. boiler contained
and partially produce practices portion
oxidized
compounds, In addition, efficiency
some of which
adverse health result in loher of the energy
these NOx avoidance waste a the
and thereby Therefore,
in the fuel.
??
problem
has been to reduce side effects.
NOx formation
and emissions
without are (GR),
these undesirable required
Special combustion
techniques
and one that has been developed
is gas reburning
part of the GR-SI process. combustors reburning, currently
This process is applicable pulverized nitrogen
to all types of
used for firing
coal. In gas (N2).
NOx is reduced
to molecular
For NOx control, stages. reburning
the combustion
process is divided
into three
These are the primary, zone and the burnout fuel is natural fuel in earlier to the extent
or main heat release zone, the zone. The primary fuel is coal and
the reburning the reburning not decreased
gas. Others experiments, achieved with
have used oil or coal as however natural NOx levels were gas.
Figure 2 depicts pertaining sorbent
a boiler schematic
which
indicates
the key areas A-E at which
to gas reburning may be injected.
and identifies
the points
The primary
zone is the main heat release 80 to 85 percent with sufficient of the total air for its Sufficient reactions
zone and accounts heat release. combustion. residence before
for approximately
In this zone, coal is burned
Very little excess air is used in this zone. time is provided to complete the combustion
the combustion
products,
including
some NOx, enter the
next zone.
In the next zone, the reburning produce an oxygen deficient
zone, natural condition.
gas is injected
to
This converts zone to nitrogen.
some of the The use of
NOx which
was formed
in the primary
18
W d 0 ai a* E
d
i s? ;r z 3 z
$j --.\ ~.ulcn ‘\ 0 ---. y-0 1 II G4 I
n
t-g, i:
in,
19
natural
gas instead
of a coal or oil as the reburning fuel bound nitrogen cyanide
fuel avoids
introduction
of additional
into the process. (HCN) are also formed This mixture
Some ammonia
(NH3) and hydrogen
in this zone as well as fragments then enters the next zone.
of the fuel molecules.
In the burnout fragments
zone, additional
air is injected water
to burn the fuel dioxide. In
and this produces
vapor and carbon cyanide
this zone the ammonia converted to molecular
(NH3) and hydrogen nitrogen
(HCN) are also NO.
and to some residual
The net effect reduction other
of this combustion
technique
is up to a 60% of
in NOx formation chemical
without compounds no sulfur,
increases in the emission or a waste of fuel. there is a reduction of gas fired. In
undesirable
addition, emissions
since gas contains commensurate
in SO2
with the fraction
Sorbent
Injection
Sulfur oxides, predominantly of sulfur controlled, flue gas. compounds
502, are formed
from the oxidation
in the coal and its ash. The SO2, if not to the atmosphere with the balance of the
is discharged
One method
of removing
the SO2 is by dry sorbent
injection
as
used in this and several other
processes that are in approximately
20
the same state of development sorbent can be injected,
as GR-9.
Locations
A-E, where
the
are shown
in Figure 2.
In the GR-SI process, sorbent conveyed to a storage
(lime) is unloaded
from trucks and to a feed silo. or
silo and then transported is conveyed
From the feed silo, the sorbent injection system to the point
to a distribution
that it is injected
into the flue gas. It part of the boiler of the boiler is removed in an
can be injected combustion (D, E). After
with the burnout
air, in the upper
zone (A, B, C) or in the duct downstream absorbing the SO2, the spent sorbent to be inadequate
ESP. If an existing
ESP is considered
for the job, it to
may have to be upgraded enhance benefits, its performance. is accomplished the boiler
or humidification Humidification, by the injection
may be required which has several
of a water
spray into the and to and
duct between humidification
and the ESP. Moisture controlled
additions
will be carefully
in these operations improvements
meet the requirements SO2 capture.
of particulate
control
For all three test sites, the nominal percent firing. of the heat input The sorbent
test design
basis is for 15 and 85 percent by coal
to be by gas firing rate is projected
utilization
to be 25 percent, of bottom ash is
Due to the lower reduced
coal consumption, injection,
the quantity the amount
and due to sorbent
of precipitator
solid waste is increased. waste.
The net impact
is an Increase in solid
21
3.2.3 Application
of Processes in Proposed
Project
The three specific sites involved the activities planned
in this project
and a description
of
for each site are as follows.
Hennepin
Station
Unit No. 1
This unit is a tangentially at the corners. and air toward such a manner particles.
fired boiler
which
has burners
mounted coal in
The burners points which
at each corner
direct the burning
are just off the center of the boiler a swirling motion to the gas and coal
as to impart
The installation
of the GR-SI system on the boiler and windbox the tangential modifications firing system.
requires be
that the furnace redesigned
penetrations
to accommodate
Figure 3 is an overall installation.
process flow diagram
for a typical
GR-SI
The specific objectives are to: (1) reduce emissions particulate approach
of the demonstration by 60 percent,
at Hennepin
Station
NOx emissions
(2) reduce SO2 or improve
by 50 percent emissions to applying
or more and (3) maintain operability.
and general
The preliminary station with is the use of upper furnace and
GR-SI at the Hennepin integrated
gas reburning sorbent
in the upper furnace and humidification
injection
to improve
SO2 removal
ESP performance.
22
23
Edwards
Station
Unit No. 1
The Edwards
unit is front air/coal
wall fired.
In a wall fired unit the burners with their direction the burners are mounted. objectives NOx
direct the burning being perpendicular The front
into the furnace
to the wall in which
wall is opposite
the exit ductwork. Station
The specific
of the demonstration emissions equivalent
at Edwards
are to: (1) reduce levels
by 60 percent,
(2) maintain
SO2 emission firing
to those of a 1% sulfur coal while sulfur level, and (3) maintain a solid sorbent
a coal blend emissions at
with a higher current
particulate is being
levels even though
used.
The planned
approach
used to apply the GR-SI process to this unit is system in the upper furnace, injection of hydrated lime with integrate the
to install the gas reburning the upper reburning performance furnace sorbent
system and improve via humidification.
electrostatic
precipitator
GR-SI will allow coal which percent
a significant
increase in the fraction
of high sulfur
can be fired.
The fuel distribution
on a heat input
basis is as follows: Present, Baseline Heat Input ?/o GR-SI
&eJ High Sulfur Coal Low Sulfur Coal Gas TOTAL
24
Natural
gas is presently
not available
at Edwards
Station.
A new to supply through
line will be run approximately this fuel. multiple
four miles to the station into the upper furnace system will be added The water precipitator will be injected performance.
The gas will be injected nozzles. A humidification
downstream
of the air heater.
through Bench capture
an array of nozzles to improve scale tests suggest considerably
that this process may increase sulfur the sorbent requirement.
thus reducing
City Water
Liqht & Power (CWLP) Lakeside
Unit No. 7
This boiler combustor products
uses a cyclone combustor is external to the boiler
system.
In this system the
and the hot combustion is complete. The
enter the boiler
after combustion into which
cyclone combustor of air are injected
is a cylinder
coal and a small amount
from the end while the bulk of the combustion at a very high velocity. motion This imparts an
air enters tangentially intense swirling
or cyclonic
to the coal and gases.
The specific
objectives
of the demonstration Station: (1) reduce
at Lakeside
Station
are
the same as at Hennepin percent,
NOx emissions
by 60
(2) reduce SO2 emissions or improve However, an alternate and corrosion particulate
by 50 percent emissions
or more, and and general at this plant pass
(3) maintain operability. requires erosion
the cyclone firing sorbent injection
configuration approach.
Convective
are serious problems
for cyclone
units that
25
may be worsened Consequently, downstream Gas reburning a commensurate this station the existing approaches, alternative
by sorbent
injection approach
into the upper furnace. involves sorbent injection
the planned
of the air heater
but upstream loading
of the precipitator. and should result in
r,educes the particulate reduction of erosion
and corrosion. are required For SO2 control,
The ESP at to maintain various
is large and no enhancements particulate including sorbents, emission rates.
the use of sorbent will be assessed.
slurry systems and
Due to the design of the air supply system to the cyclone combustors, the preheated it will be most convenient combustion to run a lateral duct from
air duct around
the side of the unit to This plant will require air injection Alternate the
the space above the cyclone combustors. addition
of a short gas supply line. Gas and overfire on the front wail are planned.
into the upper furnace locations considered.
on the rear wall and closer to the cyclone exit will also be
3.3
General
Features
of the Project
3.3.1
Evaluation
of Developmental
Risk
As with any new technology, described sorbent earlier, injection.
there is some risk. However
as
much prior work
has been done in the area of amount of work has
A lesser, but still significant
26
also been done with the reburning as the reburning obtained probability fuel. It is through
technology,
especially
with
oil
the data and experience retains a high
from this earlier work that this project of success.
After
reviewing
the results
of the developmental
work at the
0.1 MW and 1.O MW levels for the GR-SI process and information supplied process. by EER, a low to moderate It will result in increased equipment. risk has been assigned solids loading, Upper furnace fouling affecting sorbent to this both the injection of
ESP and ash handling
may increase the potential boiler tubes. Duct injection
for slagging, of sorbent
and erosion
may lead to a build may result in
up of
solids in the duct work and humidification condensation in the ESP and/or
stack. These are considered
to be and
low or moderate controls Further,
risks because there will be instrumentation and mitigate potential problems.
that will identify the regular
plant operating
staff will be in full charge
of
the boilers that will be involved
in this test program.
3.3.1.1
Similarity Commercial
of the Project to Other Efforts
Demonstration/
Gas reburning-sorbent aimed at reducing chemicals sorbent between
injection emissions
is a combination
of processes
of undesirable To capture
acid rain precursor based zone or
from combustors. is injected the boiler
SO2, a calcium
into the boiler
above the reburning
and the ESP. This process is similar to the
Babcock the upper proceeding sorbent
&Wilcox
LIMB process, where zone.
the sorbent
is injected
into
part of the combustion to near term commercial
Both processes are If the then the dry sorbent at Low
scale demonstrations. of the boiler
injection
takes place downstream
GR-51 process is similar to two other injection processes, Coolside (HALT).
low temperature, Addition
and Hydrate
Temperature
The distinguishing injection preheater
characteristics (hydrated
of the Coolside
process are the of the air
of a dry sorbent followed
lime) downstream for SO;! capture. by lowering
by humidification
Humidification and thereby
decreases improves
flue gas volume
temperature
ESP efficiency.
The Coolside
process has
been demonstrated
at the 0.1 and 1 .O MW levels.
In the Dravo HALT process, the flue gas stream humidification, capture then the hydrated lime sorbent
is cooled is injected
through to
SO2. The HALT process is now undergoing
demonstration
at the 5 MW level.
The gas reburning of converting technologies
aspect of the GR-SI process is a unique to nitrogen. that permit Low NOx burner staged a portion combustion
method control without
NOx mainly use burners
the later injection was formed
of fuel to destroy
of the NOx which to this point and
in the burner.
Work done on reburning with
has been accomplished reburning fuel.
largely
oil as both a primary
28
3.3.1.2
Technical
Feasibility
The concept
of reburning
has been recognized that significant
for over a decade. flue gas NOx that carboncan react
Early research demonstrated reductions hydrogen with can be achieved (CH) fragments
based on the principle of larger organic
fuel molecules converted
NO. When this happens,
NOx is mainly
to molecular
nitrogen
(Nz), and the CH fragments has recently been applied
are oxidized at a foreign
to CO2 and H20. commercial in the United
This concept
scale but it has not been demonstrated States. EER has conducted extensive
commercially
bench and pilot scale testing a scale-up domestic
to characterize methodology fuels.
the fundamental appropriate
processes and develop burning
for use in U.S. boilers
The results of EER bench and pilot scale research have been recently now available. impact completed under funding
programs
which
from
EPA and GRI are the effecfor conditions. in a 25 kW to control burners pulverized fuels. In
These studies were undertaken
to quantify on reburning required industrial
of fuel type and process parameters scale-up information under
tiveness and to provide commercial applications
of reburning
Initial parametric refractory
screening
studies were conducted which allowed
lined tunnel
furnace profile.
workers
the time temperature
Premixed
and diffusion liquids,
were used to study gaseous fuels, petroleum coals, and coal water slurries as primary
and reburning
29
subsequent develop
tests, a 3.0 MW, downfired The work
furnace
was used to on the the to
scaling criteria.
at both scales focused nitrogen species within
importance reburning directly
and fate of reacting zone. ‘The experimental
conditions
were designed
simulate
a practical
boiler.
There is, therefore, reburning
a sound basis of data existing NOx emissions.
for the concept has
of
as a way to reduce
This technology
been practiced capable
on the commercial
scale in Japan in installations States. This
of coal firing experience
and in pilot scale in the United provides
background probability reduction
the basis for believing achieving
that a high a 60%
of success exists for this technology in NOx emissions.
The sorbent amount
injection
technology
is based on an even greater to enhance its chances for success. for similar and
of data and experience
Demonstrations technologies Conoco. technology
at the commercial developed
scale are scheduled &Wilcox,
by the EPA, Babcock
A smaller
scale (5 MW) demonstration by Dravo. laboratory
on a similar are all
is also planned of extensive
These demonstrations and pilot work which the proper conditions
the culmination enabled successful commercial been carried
these companies operation. applications out.
to establish
for
In addition,
a significant injection
number
of foreign have
of the sorbent
technology
30
EER has participated injection
in a number
of field evaluations project
of sorbent for process of EER
and is scheduled of a sorbent
to carry out another injection system.The
optimization
experience injection
plus the wide spread interest indicate project that sorbent injection
and work on sorbent is technically
viable and that this reduction in SO2
will achieve its goal of a 50% or greater
emissions.
3.3.1.3
Resource Availability
Adequate present personnel
resources members
are available
for this program.
EER will use Additional
of its staff to fill key positions.
will be hired as needed.
This project
will not increase the host boilers’ will use approximately amount compared
requirements
for
coal. The project which
45,000 tons of sorbent to the total U.S. annual for
is a very minor
production natural surpluses
of 700 million
tons of limestone. current supplies
The requirement using available
gas can be met from in the natural is expected
gas market.
The availability
of these major
raw materials stration
to be adequate
not only for the demonwhen this
program
but also to meet the demands
technology
has been commercialized.
This program separate generating
involves
pre-NSPS boiler
installations
at three power
sites, each being station,
a fully operational facilities
electrical
with appropriate
and scheduling
31
flexibility
to accommodate
this project.
These three sites, selected an excellent all of the
for the proposed opportunity situations
demonstration
of GR-SI, will provide in essentially
to evaluate
the technology
that will likely be encountered All appropriate
in the commercialization can be made available The installation, will be handled themselves. to cover by
of the technology.
resources
to the site such as coal, natural construction personnel Adequate and restoration available funds
gas, and sorbent. of GR-SI hardware
at EER and at the utilities
have been committed project
by the co-funders costs.
their share of the estimated
These sites are likely to be required rain legislation is enacted.
to lower
their emissions
if acid
Two of the sites are burning of GR-SI will lower a lower sulfur region.
medium SOx and NOx blend in
sulfur coals for which emissions.
application
The Edwards
unit is burning
order to meet compliance
in a non-attainment
At this site the sulfur SOx NOx
the use of CR-SI will be evaluated content emissions emissions.
as a means whereby while
of the blend can be increased at compliance The furnaces
still maintaining
levels and at the same time lowering are large enough to provide
a full scale
test of the technology. demonstrated
Finally, the suitability
of the process will be wall fired, and for ail
for three distinct
systems, tangential,
cyclone fired units, which will prove the technology commonly used firing systems.
32
3.3.2
Relationship Commercial
Between Facility
Project Size and Projected
Scale of
As mentioned commercial multiple injection Therefore the number
previously, units ranging
all three test boilers from 40 to 117 MWe.
are operating, However,
small they use gas
burners nozzles,
and the test will require air injection
the use of multiple injection
ports and sorbent utility boilers
nozzles. increasing
scale up to larger of injection
only involves points
points
and distribution
representing will on many
only the most minimal prove the applicability pre-NSPS boilers without
risk. The net effect
is that this project for retrofit
of the CR-SI technology further demonstration.
3.3.3
Role of the Project in Achievinq the Technoloqy
Commercial
Feasibility
of
The combination medium
of CR-SI has the potential coals under
to enhance requiring
the use of
and high sulfur
conditions
compliance
with environmental requires
control.
The commercialization data base enhancement needs and directly to and
of
the GR-SI technology demonstrating cost effectiveness means whereby industry.
a comprehensive performance
emission applied
control,
to meet specific
industry
the technology
can be transferred
33
3.3.3.1
Applicability
of the Data to be Generated
In order to produce demonstrations collection
accurate
and reliable
performance
data, the data system
wiil be fully instrumented A new computerized plant
and use automated data acquisition
techniques.
will interface
with the existing the following:
instrumentation
to gather
data to monitor
0 0 0 0 0 0 0 0 0 0 0 0 0
Furnace absorptionicleanliness Convective surface cleanliness rates
Slag deposition Sootblower
effectiveness
Gas temperatures Effectiveness of SOx and NOx reduction
ESP performance Combustion efficiency
Boiler performance Feed rates of coal, sorbent Humidification Gas velocities Heat rate deviations and gas
The demonstrations
will produce
data to fully characterize of the
both
the boilers and the GR-SI process and for engineering commercial applications. applied The process performance to a large population sulfur coal.
data obtained U.S. utility the cyclic
can be directly stations
of existing In addition,
using high and medium
34
nature
of the operation
of these host site units will give a good varying load
characterization conditions.
of the GR-SI process under
Analyses of the flue gas and coal will also be made. analytical reductions, results will provide ESP efficiency the basis for evaluating
These SO2 and NOx Further, gas
and process controllability. data for material
and solids analyses will provide calculations reliability on sulfur evaluation.
balance for data
and sorbent
species important
Based on the SO2 removal economics proposed technical utility
and operability
results, process Since the
will be determined demonstration and economic
for the GR-SI process.
is at a commercial
scale, the resulting applicable to other
analyses will be directly
situations.
3.3.3.2
Identification
of Features
that Increase Potential
for
Commercialization
The current expanded However,
energy
policy of the United
States includes applications.
the
use of coal in utility
and industrial concern
acid rain is a recognized with
and the increased
use of
coal is not to conflict development resulting
environmental technology
goals and thus requires to control the pollutants
of cost-effective
from coal combustion.
35
To achieve these environmental SO2 emissions objective from fossil fuel-fired
goals the reduction boilers
of NOx and
has been a major
of the DOE, the EPA and major boiler/burner for many years. efforts This is demonstrated by a number to
manufacturers of concurrent develop
that have been and are being conducted burners and improved combustion
lower-NOx
techniques.
Once commercially economical minimal
proven,
the GR-SI process will provide control
an
means for simultaneous
of SO2 and NOx. The cost of this process are especially
space requirement features
and competitive which
also important applicable
make this technology boilers.
to the retrofit
of existing
This process consists of proven, such as nozzles, Some boiler reburn furnace pumps, blowers
commercially and pneumatic
available
equipment systems. of the into the
transport
modifications
are required air nozzles.
for installation
gas and burnout it can be injected
If sorbent
is injected
with the burnout
air. Since the sorbent of the boiler,
can also be injected boiler performance
into the ductwork
downstream
need not be impaired. natural
Due to the replacement performance may be the tube gas
of lo-20% enhanced
of the coal with by the smaller
gas, boiler
quantities
of ash passing through
banks when duct injection has recently been falling
is used. Since the price of natural and is approaching are expected
the cost of coal in to be minor.
some areas, fuel cost differences
36
In summary
commercialization
of this technology
will be aided by:
Simultaneously SO2 emissions Lowering Requiring Relatively
reducing
NOx emissions
by up to 60% and
by SO?/0or more cost space
capital minimal
easy retrofit of the boiler
Little or no derating Flexibility Using commercially Having types. been proven
available
components popular boiler
on three different
Thus, success of this program effective, pollutants expected market. economical associated to significantly approach
will establish to controlling
that GR-SI is an the two major is
with acid rain. penetrate
As such, the technology the large pre-NSPS boiler
3.3.3.3
Comparative Commercial
Merits
of Project and Projection and Market Acceptability
of Future
Economics
The GR-SI process, assuming technology, injection complete
successful
demonstration
of the
will be one of the most developed processes. burner It will also offer
of the sorbent to
a viable alternative
replacement
for NOx control.
37
One attractive demonstrated which operate
feature
of this project
is that the technology
will be all of
on three different under varying
size and types of boilers, This will provide different sorbent
loads.
a good and on into the of
demonstration different
of the process under
conditions injection
coals. It will also demonstrate
boiler and in the downstream flexibility to potential
duct, thus offering
a high degree
customers.
Factors which include adequate disposal on-site
contribute availability
to minimizing of natural
the cost of this project gas at two of the sites, of sorbent and waste
ESP capacity, areas.
and availability
The GR-SI process is intended utilities which
to provide
technology from
options existing
for boiler
desire to reduce SO2 emissions SO2 reduction technology
units. Existing desulfurization technology
includes
wet flue gas The need for new
and lime spray dryer processes. development
arises from the fact that the existing cost, which certain makes their application which include boiler life and
processes are high in capital particularly problems expensive presented under
scenarios
by regulations.
Short remaining installation, technology
lack of available of compliance GR-SI technology installation
space for retrofit using the existing is characterized
can increase the cost options. By contrast,
by low capital
cost and minor
space requirements.
38
An economic
comparison
of wet limestone
flue gas desulfurization
and GR-SI technology
was made at the 200 MWe, 300 MWe and cost for GR-SI is estimated at being less
400 MWe level. The capital
than half that for wet flue gas desulfurization.
The electric implement extensive
utility
generating
companies
are expected
to outlays,
technology plant
that does not require or extreme into existing significant
large capital
modifications
operational plants without
difficulties. displacing
CR-9 can be incorporated other equipment Operation operating
or requiring
new real estate. affected. The the
of the plant will not be significantly
costs for the GR-SI process are estimated captures only SOx, not both
to be about
same as FGD, which does GR-SI.
NOx and SOx as
The drive toward acceptance sorbent control, approach
lower
capital
cost is evidenced
by the rapid
of spray dryer technology in Europe. to other
in the U.S. and of boiler for a higher level of SO2
injection relative
The potential
low cost technologies
makes this
particularly
desirable.
39
4.0
ENVIRONMENTAL
CONSIDERATIONS
The PON requires Participant information
that,
upon award to submit
of financial
assistance,
the
will be required as specified
the environmental J of the PON. This detailed will be used as the basis for by DOE for the conof
in Appendix information
site- and project-specific site-specific selected sidered,
NEPA documents
to be prepared
project.
Such NEPA documents in full compliance
shall be prepared,
and published
with the requirements decision
40 CFR 1500-I 508 and in advance beyond preliminary design.
of a go/no-go
to proceed
Federal funds from the CCT Program design, construction, operation
will not be provided and/or dismantlement
for detailed
until the NEPA process has been successfully
completed.
30
5.0
PROJECT MANAGEMENT
5.1
Overview
of Manaqement
Orqanization
The project the principal administration Manager responsible Officers technical
will be managed contact with
by EER’s Project Director. regarding
He will be the
DOE for matters
of the agreement.
In his absence, the EER Project The DOE Contracting Officer is
will have this authority. for all contract matters
and the DOE Contracting (COTR) is responsible for
Technical
Representative
liaison and monitoring
of the project.
A Participants personnel from
Committee
will be formed
and will be composed Department
of
EER, DOE, GRI and the State of Illinois Resources (ENR). This Committee
of Energy and Natural as needed correcting
will meet advice on
to review the project, any deficiencies.
assess plans and provide
A Senior Review Committee senior representatives make up the Participants provide targeted pertinent
(SRC) will be formed
and will consist of whose personnel
of the same organizations Committee.
The Committee
serves to
a more encompassing to influence information
view of the project, activities
and hence, it is through supplying available.
decision-making
that may not have been otherwise
In addition
to DOE, the project
co-funders
are the State of Illinois
and the Gas Research Institute.
41
5.2
Identification
of Respective
Roles and Responsibilities
- DOE
The DOE shall be responsible project, and for granting
for monitoring
all aspects of the required by this
or denying
all approvals Officer
Agreement. representative Cooperative
The DOE Contracting
is the authorized related to the
of the DOE for all matters Agreement.
The DOE Contracting Technical
Officer
will appoint
a Contracting
Officer’s
Representative
(COTR) who is the authorized matters may: and has the authority to
representative issue “Technical
for all technical Advice” which
0
Suggest
redirection a shifting
of the Cooperative of work pursuit emphasis of certain
Agreement between
effort, work areas which
recommend
or tasks, and suggest assist in accomplishing
lines of inquiry, of Work.
the Statement
0
Approve information
those technical required
reports,
plans,
and technical to the
to be delivered Agreement.
by the Participant
DOE under this Cooperative
The DOE COTR does not have the authority advice which:
to issue any technical
0
Constitutes Statement
an assignment of Work.
of additional
work
outside
the
42
In any manner estimated Cooperative
causes an increase or decrease
in the total of the
cost, or the time required Agreement.
for performance
Changes
any of the terms, conditions, Agreement.
or specifications
of the
Cooperative
Interferes
with the Participant’s of the Cooperative
right to perform Agreement.
the terms
and conditions
All technical
advice shall be issued in writing
by the DOE COTR.
Participant
The Participant performance Statement
(EER) will be responsible under this Cooperative
for all aspects of project as set forth in the
Agreement
of Work.
The Participant’s for the technical performed under
Project
Director
is the authorized performance Agreement. for all matters
representative of all work to be He will be the between Project the
and administrative this Cooperative point of contact
single authorized Participant
and DOE. In his absence the Participant’s
43
Manager with
will be authorized
to represent will interrelate sponsors
the Participant between
in contacts
DOE. The Participant project
the govern-
ment and all other Management
as shown
in Figure 4, Project
Structure.
Industry
Panel
EER will establish industry,
an Industry
Panel to transfer
the project
results to
to encourage
commercialization
and to receive comments in Phase 1 and the project. expected
from the panel members. will meet periodically The panel will include to be directly sorbent involved
This panel will be formed throughout
(at least annually) representatives in the application possibly
from organizations
or use of gas reburningincluding: DOE, GRI, EPRI, sorbent Panel will to ensure
injection
technology, equipment
EPA, electric suppliers,
utilities
vendors,
fuel suppliers, The Industry guidance
utilities
and architect/engineers. and provide possible,
review the status of the project that, to the maximum industry needs. extent
the project
will meet
Participants
Committee
The Participants
Committee
will consist of representatives
from but
DOE, GRI, ENR, and EER. This Committee at least once each quarter, to review
will meet as needed, assess future
the project,
44
z I I[ I I I : ZZE-‘E.SE ma,E a=0 0 II3
I I
zg XE ‘GE - % 0 fE 20” \ \ \
45
plans, recommend correcting intended the project organization direct EER.
shifts in emphasis
and provide
advice on is involved in
any deficiencies. to be a working
The Participants group of personnel
Committee directly
and will ensure that the objectives will be met. The Participants
of each participating will not
Committee
Senior Review Committee
The project Committee overview
review
organization
will be the Senior Review for the administrative
(SRC) that will be responsible of the project.
The SRC will be composed members participants. the Committee representing
of executive
level individuals
with
DOE, the Participant, may change another
and the co-funding its representative(s) on
Each Participant by designating
Senior Manager.
The SRC of the
will meet at least annually, Participant’s in nature Committee.
or at the request The Committee management
of any member
will function authority.
as advisory
and has no specific
46
5.3
Summary
of Project Implementation
and Control
Procedures
All work to be performed divided
under the Cooperative
Agreement
is
into three Phases. Those phases are:
o o o
Phase I: Phase II: Phase IO:
Design and Permitting Construction Operation, Disposition and Start-Up Data Collection, Reporting and
As shown
in Figure 5, there will be a one month overlap
pause between Phases II and in
Phases I and II and an eight month III. It should the overall be noted project, that although
between
there will be phase overlap
there will be no phase overlap scheduled
at any one site. for the month
This plan will also accommodate installation project of equipment. was selected.
test site outages
It is for these reasons a fifty-four
period
Budget
periods
will be established with
to coincide
with the project sufficient period. with the
phases. Consistent
P.L. 99-190, DOE will obligate
funds to cover its share of the cost for each budget Throughout technical, the course of this project, management, reports
dealing
cost and environmental will be prepared
monitoring to
aspects of the project DOE.
by EER and provided
47
:?Is3? I
48
5.4
Key Aqreements Information
lmpactinq
Data Riqhts, Patent Waivers
and
Reportinq
Since EER is a small business, during patent this demonstration
patent project
rights to discoveries will remain with
made
EER. Standard The
and data clauses for a small business will apply. will have unlimited under this Cooperative rights in technical Agreement.
government produced
data first
5.5
Procedures
for Commercialization
of Technoloqy
As part of the project, GR-SI technology. inventions
EER will produce
a design
manual
for the or
In the event that know
how is developed
are made EER will attempt to other
to sell the know
how or with used
licenses to use the inventions engineering and construction
business concerned
or the production
of equipment
in these technologies.
EER’s interest
in commercializing
GR-SI is
also in the license fees and consulting lations where this technology
to the licensees at instalis
can be used. Since the technology by EER, their experience will
being developed also be valuable
and demonstrated as consultants.
The market enhanced emissions million
for low cost retrofit by regulatory from changes
SO2 control which stations.
technology reductions
can be in SO2 20
require
non-NSPS utility
Currently, from electric
about
tons per year of SO2 are emitted
generating
49
stations
which
emit over 1.2 Ibs. of SO2 per million States, representing capacity. about
BTU’s in the
Eastern United fired electric reductions
175,000 MWe of coal SO2 emission share of
generating would affect
Any required
the availability
of a proportionate project is to
this capacity. demonstrate utility
The purpose the commercial
of the proposed readiness
of the GR-SI technology of those sitewill be the lowest
for
application,
and to allow in which option.
clear definition
specific situations cost compliance
these technologies
The raw sorbent projected be required, adequate.
availability
is sufficient Additional
to handle haulage
current
and
CR-9 requirements. but existing
of lime would to be in an exists in
rail/truck
capacity
is expected
The solid waste produced
will increase
resulting
increase in the tonnage the U.S. a surplus even larger Therefore,
of waste disposed.
There currently
in the available capacity
supply of natural
gas. There is an system. the
unused feedstock
in the natural
gas delivery
availability
is not expected
to restrain
commercialization
of this technology.
for the proposed easily be performed industry. would nature
technology,
manufacturing
of equipment within the that
will
due to the large overcapacity fabrication
There are no unusual preclude
requirements
the use of existing components existing power
manufacturing
facilities.
The
of the individual with
makes the GR-SI technology plant and environmental
very compatible manufacturing
methods.
50
6.0
PROJECT COST AND EVENT SCHEDULING
6.1
Project Baseline Costs
The total
estimated
cost for this project
is $29,998,253.
The share in the
Participants’
cash contribution
and the Government
costs of this project
are as follows: Dollar Share (8) Percent Share (%)
PHASE I Government Participants PHASE II Government Participants PHASE III Government Participants TOTAL PROJECT Government Participants 14,998,253 15,000,000 50 50 1,764,986 1,764,986
2: :?I :i
Cash contributions
will be made by the co-funders
as follows:
DOE: GRI: State of Illinois: TOTAL
S14,998,253 1o,ooo,ooo 5,000,000 $29,998,253
51
At the beginning
of each Phase, DOE will obligate
sufficient
funds
to pay its share of the expenses for that phase.
6.2
Milestone
Schedule
The overall
project
will be completed
in 54 months
after award
of
the Cooperative
Agreement.
Phase 1 which
involves
permitting,
preliminary after award
and final design, and continue for
will start for all sites immediately fifteen months. Upon completion in the project.
of Phase 1, there will be a pause of the pause, Phase month. Each test the
of one month
Upon completion the thirty-third
2 will start and continue
through
site will have its own 8 month installations and checkouts
period
in order to complete for Phase 2.
required
Following
is the anticipated
Phase 3 schedule
for each test site:
Testing
on the tangentially
fired unit located
at the Illinois month of the
Power Site is scheduled project
to start in the thirtieth months.
and last for eighteen
Testing
on the wall fired unit located to start in the twenty-fifth in eighteen months.
at the CILCO site is month and be
scheduled completed
52
Testing
on the cyclone fired unit located to start in the thirty-fourth months.
at the CWLP site is and last for
scheduled eighteen
month
The final months completion
of the program
will involve
site restorations project.
and
of the final report
for the overall
53
6.3
Recoupment
Plan
In response
to the stated
policy of the DOE to recover contribution to the project, in accordance
an amount the Participant
up to the Government’s has agreed
to repay the Government Plan included
with the
Recoupment/Repayment Agreement.
in the Cooperative
54