Environmental Information Volume for CWLP Lakeside Station Boiler No Enhancing the use Eastern and Midwestern Coals by Reburning Sorbent Injection

Click to download
ENHANCING THE USE OF EASTERN AND MIDWESTERNCOALS BY GAS REBURNING-SORBENTINJECTION ENVIRONMENTAL INFORMATION VOLUME for CWLP LAKESIDE STATION, BOILER NO. 7 Submitted Energy and Environmental Irvine, by: Research Corporation 18 Mason CA 92718 January 1988 TABLE OF CONTENTS 1.0 2.0 INTRODUCTION. ....................... PROJECT DESCRIPTION .................... 2.1 2.2 2.3 2.4 2.5 Existing Facility. .................. 2.1.1 Site Description. ............... 2.1.2 Description of Existing Process ........ Technical Project Description ............ Description of Activities .............. 2.3.1 Description of Project Phases ......... 2.3.2 Description of Installation Activities Project Source Terms ................. 2.4.1 Project Resource Requirements ......... 2.4.2 Project Discharges .............. Potential EHSS Receptors ............... 1-1 2-l ;:: 2-6 2-13 2-16 2-16 2-16 2-20 2-21 2-27 2-29 3-1 Quality, 3-l 3-3 ::: ::: 4-l :I: 4-3 4-4 4-4 44:; 5-l 5-l .... 2:: 5-3 5-4 .... 3.0 EXISTING ENVIRONMENT ................... 3.1 3.2 3.3 3.4 3.5 3.6 Atmospheric Resources: Meteorology, Air andNoise ...................... Land Resources .................... Water Resources ................... Ecological Resources ................. Socioeconomic Resources ............... Energy and Materials Resources ............ 4.0 CONSEQUENCES THE PROJECT ................ OF 4.1 4.2 4.3 4.4 4.5 4.6 4.7 5.0 Impacts ................. Atmospheric Land Impacts ..................... Water Quality Impacts ................ Ecological Impacts .................. Socioeconomic Impacts ................ Energy and Materials Impacts ............. Impact Sumnary .................... REGULATORYCOMPLIANCE ................... 5.1 5.2 Regulations and Permit Requirements ......... Anticipated Permit Modifications ........... 5.2.1 Air Permit Modifications ........... 5.2.2 Solid Waste/Water Permit Modifications 5.2.3 Other Required Permits ............ ii / 1.0 INTRODUCTION On December 19, funds instituted gas, 1985, to President Reagan To implement signed clean this that Public coal law, Law No. 99-190, projects of of this or coal the Department The goal efficiently clean with to displace which between Energy program oil provides industry (DOE) is conduct a Clean emerging or to cost-shared technology and government. Coal Technology technologies coal the This with Program. to evaluate than are designed Individual of future injection for and natural are utilize available more cleanly, feasibility sorbent economically projects applications coal project of in-boiler currently to technology. intended of emerging combining control demonstrate consnercial a clean the purpose technologies. gas reburning of nitrogen volume is concerned of oxides and sulfur. Corporation project with sorbent (EER) is currently involving injection cofiring and/or The Energy making pulverired coal preparations coal to: and Environmental to conduct with natural Research a demonstration gas in combination cleaning 0 Allow for cost effective reduction prior 601. with of NOx and SO2 emissions to New Source from coal-fired Standards a Provide purchasing. The combination sorbent main zone. sorbent reduction with atmosphere sequential heat injection release are of to injected of boilers constructed Performance (NSPSI [40 CFR Part the utility industry increased flexibility in coal technologies (GR-SI). zone to produce the to be demonstrated, introduction a homogeneous. rich zone, slightly gas of natural air reburning with involves gas above the oxygen-deficient and calcium-based is effective radical in the species as a At the downstream end of this into by the burnout gas duct. reaction Gas reburning which injection in which react NOx emissions produce MR. of hydrocarbon process NO to form nitrogenous coupling intermediates The sorbent step, l-l in the oxygen-deficient can be viewed the calcium-based sot-bent of an activation (limestone step, The calcium equipment. furnace or hydrate) the While sulfate will is duct calcines to produce with CaO, and a heterogeneous particulate alternative. sulfation sulfate. control upper where CaO reacts injection gas phase SO2/SO3 to form calcium removed by the plant is a technical project. program representing conducted the by EER will of sorbent subsequently be used in this injection The technology three Illinois utility technology: Illinois fired. Central wall demonstration boilers focus on range of pre-NSPS boiler Power Co., Hennepin Station, Unit 1; 80 MWe tangentially Illinois Light Co., Edwards Station, Unit 1; 117 MW, front fired. CWLP, Lakeside the actions Station, to Unit at 7; 40 MWe cyclone Lakeside Station fired. and the Springfield This volume details impacts of of be taken environmental of these this actions. Information documents Volume is to facilitate for This compliance report with J of all is to air has been The purpose DOE's preparation the the National in Clean Coal a project prepared relevant provide permits are also Environmental Policy with the environmental required Environmental accordance Technology description health, safety, Act of 1969 (NEPA). provided Notice The goal as an analysis Elimination permit the guidelines Program Opportunity therein. as well Discharge by DOE in Appendix (PON) and contains of this of document all Current information requested applicable environmental, and socioeconomic (EHSS) issues. modifications. and National described, Pollutant as well System (NPDES) permits as anticipated 1-2 2.0 This presents project, requirements impacted addressed; which 2.1 2.1.1 this PROJECT DESCRIPTION section a brief describes describes technical anticipated All only the existing facility activities, EHSS areas is at defines that afforded could Lakeside project Station, resource be for description project and lists cursory of the GR-SI technology demonstration potentially factors tenuous. and discharges, however, retrofit Existing Site by the project. data requested treatment demonstration in Appendix J of the DOE PON are those technology Facility makes applicability Description Station and the adjacent in Sangamon of 2-4. accessible Illinois have traffic Terminal Interstate for Lakeside a water Lakeside all by rail Central, lines highway Station treatment Station Railroad and truck. Norfolk running spur line are plant The Illinois and Western, within 3 miles is in place taken from city and of and Lake which of Dallman Station occupy a 75-acre section in as indicated illustrated site of the Fig- Lakeside on the city ures view plot of 2-1 of plan northwest shore of Lake Springfield, County, the site station features in the southeast Illinois, is Springfield and 2-2. Figure 2-3, presented The layout and specific in Figure is in the aerial on the station are identified Lakeside Terminal, Baltimore the plant supplies Springfield. Oallman to this 7 for Station feeder plant site. potable operational Springfield. Gulf site. Station Mobile and Ohio, and Ohio Railroads An Illinois not though Water water A major used. operates to the 55 runs adjacent on the site natural will to the supplies CWLP also and to the entire provides line gas pipeline currently of the plant gas to the be connected gas to Unit on the south end of the site; a branch site at the west boundary to provide the GR-SI technology demonstration. 2-l +Lakesfde Power Station, '-\ Sangamon County, Illinois \ I , il .hu 1”* Figure 2-?. Location of CWLP Lakeside 2-2 Station. Approximate l/8 I Figure 2-3. Aerial view of Lakeside 2-4 0 I Station. Scale l/8 (miles) j/4 I Coal Storage Area LAKESIDE (Cyclone) From Dallman Station Approximate 1p0 0 plot Scale 100 pllan. (feet) 200 Figure 2-4. Lakeside Power Station 2-5 Lakeside GR-SI coal storage intermittent per day collected 2.1.2 from pile Station has three which to operational will is about Station electrical 15 miles generating in Unit northeast 7. units. Unit The 7 fires into a is is technology Logan is which demonstration County, maintains Lakeside be conducted of Springfield. runoff Runoff The coal delivered by truck capacity. rate into flow and unloaded Coal pile personnel. a minimal reserve and has an annualized (MGO), based in a pond, Description and pond water of Existing contains but have not average of 0.019 million Lake Springfield. gallons on measurements made by Lakeside is discharged Process Lakeside units units project in Figure Coal the plant with are Station three capacity been coal-fired used in the steam electric past coal five generating 20 MWe The as shown years. a total licensed 2-5. Unit net generating in Unit of 100 MWe. Two additional boiler, will and ash be conducted 7 fires analyses 7, a 40 MWe cyclone-fired bituminous 2-l. fires a total 7 fired in Table medium sulfur Testing from Logan County. were done for 1985. During Plant in 1986. average is the The two of coal station of coal. of coal are given Unit These analyses Company in lb/hr tons 39,480 of 41,700 coal output by Commercial operation, indicate 7,392 lb/hr that hours capacity, and Engineering full-load records Assuming rate Unit in coal 7 currently 7 fired year, Unit Unit per at an annualized of 35 MWe. which percent. tons total of 11,282 7 nominal 1986. in 1986. the Unit Based on boiler 1986 capacity 7 accounted for together factor was 28.6 generation stations Therefore, 1986. on the CWLP site consumed 815,000 of the 5.1 percent usage in An electrostatic emissions. downstream collection depending Solid plant of area the air precipitator a cold preheater. side (ESPl unit, is used which ft2/(1000 to control means that size ft3/minI. time. particulate it operates SCA varies The ESP is The variable ESP has specific (SCA) ranging from 333-1000 in operation on the number of units waste streams furnace at a given the fly from the boiler bottom ash. include ash collected by the from ESP and the These waste streams are exempted 2-6 , I j::; :;:I :: ,: ::.:: ;:i: !; *.; ,::i ,::: hi ,:,:,w L g -y:‘# ii . ,;:,iqllii;, .~ ‘. I; i Figure 2-5. Schematic of Lakeside 2-7 Station Unit No. 7 Boiler. TABLE 2-I. COAL AND ASH ANALYSES Illinois As Received Coal Dry Basis Fuel Proximate Property Analysis 39.70 Fixed Carbon Volatile Matter Ash Moisture Ultimate Analysis 33.72 8.90 17.69 48.23 40.96 10.81 Carbon Hydrogen Nitrogen Chlorine Sulfur Ash Oxygen Moisture Heating Value as Fired (Etu/lb) (oFI 58.00 4.05 1.11 0.10 2.80 8.90 7.35 17.69 10,460 70.47 4.92 1.35 0.12 3.40 10.81 8.93 Ash Fusion Temp. Reducing Initial Deformation Softening (H = WI Softening (H = l/2 Fluid Ash Density (g/cm31 WI 1945 1990 2120 2280 2.2 Coal Grindability (Hardgrove) 52 2-8 esearch Corporation 12 January 1988 Dr. Earl Evans Department of Energy Pittsburgh Energy Technology P.O. Box 10940 Pittsburgh, PA 15236-0940 Dear Earl: Center Enclosed please find a copy of the revised Environmental Information Volume for Lakeside Station. We have addressed the comments made by you, Tom Willis in our conference call of December 18, 1987. Copies Ruppel , and Bill We are prepared to send, upon your are being sent to you and Bill Willis. notification, the additional copies you will require for distribution to DOE If you have any headquarters and/or environmental review personnel. questions or comments, please do not hesitate to call. Sincerely, L. P. Nelson Program Manager Environmental Management Division LPN:mhh Enclosure cc: Mr. Dr. Dr. Dr. Mr. Harry Ritz, DOE William Willis, SAIC William Bartok, EER Blair Folsom, EER Peter Maly, EER 18 Mason l him CA 92718 l (714) 859-8851 l Telex 181787 . FAX 859.3194 RCRA Subtitle 0.25 ash pond 3711 miles to percentage, C Hazardous on-site the flow Waste rate regulations for disposal. ash from flow diagram and are sluiced Based on coal Unit rate flow which of bottom 2-6, rates. includes approximately flow rate and ash ponds of fly 7 to the ash pond during ash to the ash representing 7 generated and Lakeside Unit full-load is tons full-load Dallman operation 2710 lb/hr. conditions of ash in stations, water ash is 785 lb/hr. The process for 1986. Unit Average flow in Figure 7, shows these of 72,535 Springfield The CWLP plant, a total generated from tons of ash in 1986. is used for fly This 2-2. Process by the utility. Creek, National plant pH, total units. concentration which to file once-through ash and bottom water Unit flow Effluent runs monthly Average from Pollutant suspended rates nonash. as Process contact Fly waste the Lake cooling from other by the ash applications are sluiced are 1.0 is Lakeside utility and for and Dallman summarized into requires flow year transporting units. and bottom to an ash pond. ash pond also receives water water Lake measured requirement from the Springfield Elimination water oils these 9/l . Unit (scfm). Calculations full-load pounds (1.45 parts Utility lb/hr in Table Sugar the rate, 7 sluice averages pond MGD, as measured The plant's discharged to the Sangamon River. System (NPDES) permit reports from for 2-3. detailing all a recent Current Discharge effluent and of are 0.32 values solids, reports monitoring and greases parameters Lakeside and Dallman as determined from monthly presented in Table ash pond sulfate is about 7 currently Air emissions requires of flow air rate at a flow include and sulfur emitted rate of 84,100 content standard that ft3/min during C5.31 of 1000 boilers. of 3.3 concern presently is SO2, NO, and particulates. indicate at a rate cyclone at a rate assuming of of 2211 lb/hr NOx emissions fired at a rate based on coal operation SO2 is Btu This million million, lb/MBtu). per per (0.008 (lb/MBtu)l. value is a value that NOx is emitted calculated typical particulates of 603 lb/hr lb/MBtu). which indicate measurements are emitted 2-9 - --. Z-10 TABLE 2-2. PROCESSWATER FLOW RATES Source Circulating Boiler Water Flow Rate (MGD) 0.92 290 Sluice Water Runoff 0.019 1.0 (intermittent) Coal Pile 2-11 TABLE 2-3. AVERAGE ASH POND EFFLUENT WATER PARAMETERS Parameter Flow Rate (MGD) PH TSS (mg/l) Oils/grease(mg/l) High Low 2.88 a.40 Average 4.80 a.77 9.88 7.05 9.06 14.88 6.20 0.05 3.30 1.10 2-12 2.2 Technical Laboratory-scale Project Description of the in the M. A., reburning 1970's "Reduction concept (e.g. were originally Wendt, J. 0. L., Trioxide and Symposium (Inter1973, p. 897). but mainly work at when scale in scale in Japan, investigations United States and Matovich, by Secondary Fuel conducted Sternling, Nitrogen national) More with the oil in the early C. V., Oxides it of Sulfur Pittsburgh, scale and pilot Injection." Institute, at full Fourteenth on Combustion, fired systems. fuel circa is The Combustion demonstrated Recent potential natural recently has been extensive gas. research EER has developed Tennessee with higher locations demonstrated in of the reburning Sorbent concept, injection particularly was also at that full reburning originally 1970's 1960 and Authority's 1970 and was demonstrated (TVA) Shawnee Power Plant TVA demonstrated through the potential use of Large scale Valley in the early proper rather poor results. levels sites and advanced Subsequently, could sorbent be achieved materials. significantly injection U.S. for capture work at several of this technology and Canadian SO2 control. EER's reductions reductions sorbent those scale spectrum has begun to confirm most of recent up to if with pilot 70 percent a hydrated optimized scale from typical results indicate that 60 percent Sulfur reburning are typical for NOx with of can be achieved injection pre-NSPS NOx levels. by combining These data injection is used. dioxide can be achieved sorbent gas appear obtained systems. reburning-sorbent to be generally a wide in full of primary fuels and they achievable The objectives data base demonstrating and vary applications technologies. utility the full conducted boilers using of to the current project are to provide of this a comprehensive boiler of combination the performance promote the design of GR-SI in pre-NSPS utility characteristics could comnercialization and operating demnstration a total utility Since population. three of pre-NSPS address will varying be widely, no single pre-NSPS adequately widely Consequently. of three boilers demonstrations with 2-13 characteristics. as applied Figure boiler. NO that (CH) with nitrogen 60 percent as well be useful is is The GR-SI systems to each specific 2-7 illustrates gas is in HCN which produced lower NOx control, that host unit. will be designed for optimum performance the application injected zone. the reaction includes allows NO is of GR-SI in a tangentially reduced of by a hydrocarbon NH via NCO. N at high from the NOx emission fired radical Molecular and provide process unit does could Natural producing NH2 at above the main heat release formation of NO with reduction usage. Thus, to future this zone to reburn produced by the which temperature temperatures reduction (<22OOoFl. in coal The GR-SI system will reburning reduction The pre-NSPS Lakeside NOx regulations. sorbent temperature Injection injection; as from the not have an NOx emission to the plant 2-7 constraint. in response locations to sulfur hydroxide. sulfur firing 7 boiler, because In Figure these injection 2250°F is for For duct the (A, 6, is four are shown for upper capture. capture the furnace an injection three of and C) correspond necessary to maximize of calcium can fired is help both while Unit injection. location is also will Illinois The preliminary unit. gas; Upper furnace of approximately D provides since SO2 This be used is to injection the amount performance. be to reduce coal. but could Sorbent thus, plan included required injection cyclone reduction A humidifier the SO2 strategy existing humidification emissions emission for inject will of solid Solid system. ash which, to lime/fly from product placement commercial and precipitator by 50 percent with not required any future the upper will by existing furnace increase. using the regulations on this compliance the increase waste SO2 regulations, material sorbent being will into the amount of solid generated in the flue waste The solid be managed plant's current wet sorbent handling with fly waste from GR-SI is a blend of unreacted prepared dryer landfills. applications. lime, for sludge spray stable of a calcium has similar sludge This due to the presence ash/scrubber lime-based produces for and value characteristics or the solid hardens may also after have disposal waste systems. Such a blend construction 2-14 SECORDARY SH ic 0 \ TO ESP AN0 STACI _____' C -. 0 _ .Ir 7 ! I I .-- * , I I I C B -' Y e A -. w -c .- PRInARV SH \ -D REBURNIWG ZORE 3 COAL[ MAIN HEAT - RELEASE ZONE -1 -.__----- ---- FUWACE AIR PREHEATER Figure 2-7. Application for NO,/SO, of gas reburning control. sorbent injection 2-15 2.3 2.3.1 Description Description The GR-SI project of Activities of Project will take Phases 53 months to complete. in three phases: This initial phase plan will testing. transfer. will begin Following equipment panel. and Disposition. of Phase 2 and unit data will will be and test be made to the will The process after DOE be and will culminate injection for An industry EER will conduct the technology demonstration Phase l--Design in the panel the detailed for the systems project 0 and Permitting. design Lakeside construction of site. gas reburning A program and demonstration and sorbent be prepared equipment will be established to initiate and Startup. and will out at last technology This a Phase L--Construction Phase approval, installed engineering 1 is completed and checked will phase 16 months. injection site. the gas reburning designs and sorbent Lakeside be presented Collection, with to the industry Reporting, the final stages All 0 Phase 3--Operation, Phase will tested results available industry 3 will last for will panel. of GR-SI is rather it will begin 29 months. one year to industry. Data concurrent Following over into DOE approval, a guideline results the host a range of conditions. will be compiled manual which The project be presented The demonstration technology technology 2.3.2 but not intended conducted Activities the GR-SI 2-16 as a first generation of several of specific build upon the results individual demonstrations Description now being by the EPA and others. of Installation section as part describes of the The following will be undertaken specific technology installation demonstration tasks that by EER personnel, concern liability, subjected safety risk rules of injury The conducted plant but to will personnel an ethical be fully and local since All responsibility risks. enforced labor. to Worker ensure this safety that is a primary a financial are not and the health in any industrial unreasonable to workers. equipment project, an employer appropriate has not only occupational program workers throughout to minimize GR-SI installation steps: work at Lakeside Station will be in a series Procurement Initial Final Checkout Correction three, of five 1. 2. 3. 4. 5. Step outage at the installation installation (normal [outage) unit operation) of deficiencies final is the installation, key element will schedule power in time must correspond determining the to a normally installation load if a fall scheduled schedule. requirements outage until in this to of is and and this time are The specific scheduled there the regard. procure the final Most silos, items general conduct possible. and fitting etc., will low but load long outage the period lead depend on the utility's For example, than anticipated to delay request may elect The program EER will and the condition no major problems, the items schedule of the unit. the utility spring. flexibility, demand is greater in the fall the outage authorization the completion must be flexible To maximize design of the need as soon as possible following specifications. equipment will be standard directly injectors, work short outage items such as piping, A limited specific modifications. to the valves, number of etc. will The be to extent and will be obtained from vendors. to meet site windbox off site to be custom-fabricated to will the limit during equipment requirements. These include the the gas and sorbent fabrication/assembly This required the approach procurement and installation custom maximum the amount of time-consuming periods. installation 2-17 The initial operation following on-site installation installation step will installation work where all will work during be divided is conducted requires unit into two during steps: normal outage. an unit The and the final equipment Sorbent Sorbent Sorbent Sorbent step which a unit operation: be installed and storage and transport and injection control normal 1. 2. 3. 4. 5. 6. 7. A plot silo is unloading feeding piping injection equipment. equipment. equipment assembly. assembly. assembly. except showing for final connections. of the sorbent storage gas piping Gas injector and controls assembly. installation Station 2-B. complete Instrumentation plan of Lakeside the location shown in Figure is to The intent flexibility The following 1. 2. 3. 4. 5. 6. the initial installation installation during an outage: during in time to provide outage. on completing equipment the final a scheduled must be installed Windbox modifications. Furnace Final Final Final or duct penetrations for control for gas injectors, overfire air ports or sorbent injectors. equipment. connections gas plumbing. instrumentation connections. ESP upgrades. tubes handling in air are will the lined with qualified asbestos All to minimize boiler heat loss, materials. that asbestos and some be EER all removal Boiler asbestos conducted will include applicable guidelines, be required. modification asbestos including disposal a requirement work will by a contractor to work with specifications be satisfied, and proper contractor's OSHA and EPA regulations monitoring requirements, considerations. z-18 LAKESIDE (Cyclone) "--. nrptoximate 1po Figure 2-8. Plot plan of Lakeside P Station. Scale 190 (feet) TO 2-19 It single will be is not given necessary outage to items installing if that all the final installation work be completed penetrations, at a scheduled following the initial furnace/duct to during the outage prior installation. completion available. outage. of Consideration windbox the initial would This modifications installation reduce and ESP upgrades a scheduled of effort of the steps: selection and equipment becomes the intensity required the final at Construction include 0 natural gas pipeline Lakeside Station will the following Final route 0 0 e Each Station entirely will required supplies, materials matched. Unit will 2.4 This technology categories 7. of Materials Excavation Pipefitting these natural within procurement steps will be coordinated route selected is shown for in by CILCO. installation Figure 2-9. owner This of the route trunk lies pipeline. The tentative of the Lakeside installation and equipment welding All will activity be to equipment. practices adjacent gas pipeline the boundaries of the CWLP plant. of CILCO. include and material The pipeline The materials piping, handling be conducted for will the by the Gas Division pipeline construction equipment, will fittings, excavation The pipeline From this meet applicable terminal as described Source Terms characterizes codes and comaon industrial be routed point. previously to convenient the remainder termination of construction be conducted Project section under equipment installation. all of the source can discharges. terms of the GR-SI the demonstration of resource project. requirements Source and project terms be divided into 2-20 Lake Springfield Approximate Scale (feet) Figure 2-9. Tentative route of natural gas pipeline to Lakeside Station. 2.4.1 Project Project Resource resource Requirements requirements include 2-10 is requirements energy, a diagram below. land, water, with labor, important the GR-SI materials, process technology and other flow rates. resources. project Figure detailing The resource associated demonstration are identified Energy Requirements Additional onstration required sumption consumption standard flow. percent 87.384 Full to for energy requirements fuel. the Coal coal lb/hr. associated with increase It operating to decrease rate will the GR-SI technology equipment that capacity and natural the natural will in electrical demgas gas gas 19 to include the rate ft3imin. load 32.120 electrical site for is about host usage power to run sorbent The estimated 400 kW. site will at full decrease air flow as reburnfng power conbe 1275 is estimated due to the added natural by approximately increase slightly feed rate is expected Combustion standard ft3/mfn. Land Requirements The GR-SI technology control will ancillary anticipated host site site for the technology procedures be constructed itself systems is demonstration utility within within with to is outside ensure available entirely implemented associated of land involves boiler. CWLP plant the existing the existing that adequate for the retrofit The natural boundaries. boiler plant structure there boundaries. compact, of two emission gas pipeline Since the is no The on and the on an existing GR-SI are relatively requfrenmnt pipeline Sufficient hardware. has been examined space space is available storage location and installation of the sorbent and feeding of all equipment. required convenient 2-22 i Water Requirements The GR-SI However, process personnel average more will sluice based process does not require will of the utilization because the ash. ash loading from its of water, sorbent indicate value Calculations current per se. injection by EER that the of 1.0 sluice generate water water be required increase will in fly increase an increased requirement amount of fly on amount MGD to 2.0 MGD. Labor Requirements Labor operation performance. labor skills. requirement, locally A breakdown Operation additional existing During oversee test plant operation by EER using will be required of the is still for the equipment a relatively labor requirements of the that crew installation hardware, small is GR-SI these installation effort to provide of the GR-SI equipment, of system the largest can be managed and specialized 2-4. very little by the program. to and maintenance Although it and verification represents which both general available of labor presented systems tasks will in Table requires and maintenance it is anticipated staff EER test operations labor; may be conducted training also be available upon completion personnel procedures. will of a brief periods, and maintenance verification will Performance additional Materials labor tasks for be conducted tests. by EER test crews. No be required these Requirements material the requirement During of silo. site. course the for the GR-SI technology 4160 lb/hr 15,000 for tons sorbent demonstration be are be of sorbent will The primary is a calcium to required. expected stored During based sorbent. be used at the sorbent operation, program, Approximately of Ca(OHl2 will 150 tons of sorbent in the site's The raw material 2-24 is limestone TABLE 2-4. CONSTRUCTIONLABOR REQUIREMENTS Task Duration (months) Community Supplied Labor (hrs) Phase 1: Phase 2: Phase 3: Total Baseline Testing Construction GR-SI Testing 1 16 12 29 240 3,360 2,000 5,600 2-25 for which will the state of Illinois as part is a major producer. process. from The sorbent to be tested be selected of the demonstration will be purchased sorbent acid silo Construction Construction and small hardware materials include items. will also local dioxide distributors. equipment, piping ash needed for materials and handling Sulfuric and carbon locally. pond pH adjustment Transportation be purchased Requirements impacting usage. three usage 7 will trucks will by ZO-ton after transportation The sorbent per day for trucks; decrease, will will be decrease be trucked in coal usage The main factors and increase require delivered Unit truck 2.4.2 7. required to for in approximately Lakeside coal Unit coal for Because sorbent in and will by be delivery. 20 trucks Coal is currently per day will 24 trucks only per day are required Therefore, delivery GR-SI is implemented. per day. the total traffic be 23 trucks Project Significant Discharges waste discharge streams from the boilers site, employing emission the of fly have (0.58 (2.66 GR-SI ash been lb/ lb/ are technology and spent targets established. MBtul. MBtu). anticipated. Solid to the expected of include sorbent. stack emissions for and a solid demonstration NOx and S02, waste consisting respectively, to 241 lb/hr to 1105 lb/hr At the technology reduction 60 and 50 percent NOx emissions of SO2 are are expected expected to decrease to decrease Emissions No changes in CO, unburned hydrocarbons, or particulate emissions waste is expected of sorbent. from its of the to change in both Flow current fly rate level of fly flow rate and composition to about coal which ash, due addition ash collected by the ESP is 5390 lb/hr. 27 percent not to increase of 785 lb/hr be 12 percent rate, The new composition CaSO4. and 61 percent ash will Ca(OH)2. Bottom ash flow GR-SI will 2-26 affect per se, will coal decrease to 2200 lb/hr during full-load operation because of reduced consumption. anticipated water of solid calculations cause the will waste. in liquid be required Based show that waste stream effluent because on the average flow discharge GR-SI will rate will expected from the ash generate increase sorbent Calculadesign will be that an by to Changes pond. increased water about the tions work used during level carbon acid to within Oil solids water form tion water below with done. Coal change. will controlling concentration calcium rate, fly will for in are,also More sluice amount increase, 21 percent ash will will be done, compliance project the dioxide addition ash amount of sluice to 5.80 MGD. The addition during permit Possible include the alkaline in water of 9. of unreacted and spent to become more alkaline. when detailed action also acid will be performed with pond Phase 1 of the project, the method of corrective limits injection water. for with pH. to determine pti will be monitored the ptl of the the pH or bubbling processes, lower operation. through limit loadings solids neutraliration measures sulfuric acid) to lower In both of these (CO2 reacts to form carbonic the permit and grease are not anticipated regulatory include increasing because to change. limit the Total suspended Options time with for of the Sulfate SD2 to injecuse water be be not be maintained suspended below the chemical of 15 mg/l. residence reacts in the pond and using is expected sulfate. sluice water standards, It will agents Phase is 1 of concentration discharge means to enhance settling the sorbent will rate. to increase rate, which to the will The amount of increase flow to Sugar Creek is required specify reduce project, also that sulfate be necessary depend on sorbent pond pH, and pond hydroxide to meet Illinois sulfate concentration. general must be The plant's quality concentration treat the effluent design project pile runoff 500 mg/l. precipitating during Sulfate pile size to chemically concentration. during This will work will operation. will assessed when detailed be monitored not expected to change and thus coal 2-27 Coal result contributions In addition, slightly. increasing Canadian leachability increase usage coal-based will from decrease metals sorbent expected have Cote, 1984, as a result loading will at of the GR-SI than levels project, those or to and as a metals from coal. increase with of 805, and be no of decrease. to be smaller current In general, are expected to remain that shown pH is Studies pH (e.g. leachability and Constable, Special Since decrease, effluent of metals T. W., Technical there is decreases Publication loading to as a result P. L. p. in 53). to either 'Development Data Base on Waste Leachability, are in metals both expected ASTM, Philadelphia, coal-based metals expected levels or groundwater the GR-SI project. 2.5 Potential A number proposed water focuses probable on these action. land quality, impact receptors. EHSS Receptors features air force. existing could quality. potentially surface water with be impacted quality, respect impact by the groundSection to these of GR-SI 3 of environmental These include use, labor the and energy environment resources. on characteriring receptors. Section 4 evaluates the probable 2-28 3.0 This Lakeside by the that were EXISTING ENVIRONMENT section Station, proposed mentioned individually Atmospheric The area provides focusing action. in a description on environmental The environment Section in this Resources: Illinois 2.5. section. Meteorology, in which climate for Illinois Air Quality, and Noise site is located cold annual of the of the environmental that into these might the six setting categories is at features is divided Each of be impacted categories characterized 3.1 of central the demonstration with Springfield for provides winters. the entire year. precipitation environment. a typical Figure for According continental to states the warm sunssers and fairly Climatologist, The climate average is typical 3-1 shows wind roses Springfield 4 months throughout State is 33.8 inches. area and not midwestern representative of a local specialized The air Sangamon Illinois criteria Designations February area and for Emissions particulates, Lakeside well noise total quality is in in the federal and is area air of Lakeside quality Station control is area generally for to good. EPA in Air County pollutants, of region 75 (West Central most U.S. the published non-attainment EPA's Geographic Intrastate), a primary SO2 and Status EPA. of attainment N02, Criteria A survey including Attainment Illinois according Pollutants 1985 by the Inventory 18 emit Station at normal delivery the The region is a secondary of there Illinois of suspended revealed plants particulates. that that emit air NOx. in Sangamon County pollutants, are 145 businesses which 86 emit industrial SO2, and 24 emit is in close plant both proximity to the city industrial shaping of Springfield, plants. and coal construction feeding), as as several levels railroads. Lakeside for plant trucks highways, operation (e.g. and other coal pile Current are attributable and Dallman to ongoing Stations. activities, and coal Lakeside 3-l JANUARY BO-YEAR TOTAL (1901-80) APRIL B&YEAR TOTAL (1901-80) OCTOBER B&YEAR JULY TOTAL 11901-80) -YEAR TOTAL (1901-80) For each concentric circle, the wind blows 1 percent of the time from Key: the direction of the line. Thus a line directed vertically downward from the city that passed through 10 circles would indicate that the wind blew from the south 10 percent of the time. Figure 3-1. Wind roses 3-2 for Springfield, Illinois. 3.2 Land Resources Lakeside Station Lowlands divides rolling of feet but is located to in Sangamon County, The Plain the drift Station the plant the Station in this that Illinois. The power Plain hills drift given of by in the Approxwhich is age in Fig plant the broad vicinity, imately itself bedrock. ure area, minimal Although are Water Fayette Illinois yet 3.3 is Central situated adjacent with loess plain map it ponds land in which for the is while the ash Lake Springfield Province. valleys. found the the in Illinoian glacial Lakeside near in the Springfield There are no large age glacial area is itself Physiographfc mature is covers map of are terrain is characterized upland Sangaaron River. and Pennsylvanian 10 underlain A flood From the the flooding, much of Conservation silt loam, Department while 3-2. by pre-Illinoian can be seen that Zone A6 areas surrounding area. is in a Zone C experience plain. there Soil and as The flood a Zone A6 area. are within Lakeside Zone C areas loo-year is urbanired, some farmlands According to the Sangamon County prime or unique for District. most of the soil not considered has indicated area is classified farming. wetlands of Conservation maps have not been published the area near Lakeside Station. Water Resources Lakeside plant for flow discharges Sugar rates which General designation. iron, standards. Creek into and silver Creek flow Creek pond water near Lakeside to Sugar Creek. Ambient Also for water quality 3-1, are which is oxygen, the data including Illinois are Station standards 3-l it are sutmnarized for various in Table included there use and concentrations Use Water Quality From Table flow rate rate generally of contaminants. of the state exceed over never Illinois parameters, which general dissolved standards rmst be met in waters occasionally spilling no specific boron, quality Springfield. discharging rainfall can be seen that water including Lake ft3/s) plants depends on a number of factors, the Spaulding falls below Dam from 3 MGD (4.6 industrial and amount of water due to dam spillage and pond discharge. Sugar Creek. There are no other 3-3 .: : .._~ i .r c, 13 j m y. ‘, i’ ‘1, ,, N .>, /’ / .- I -- 4 TABLE 3-1. WATER QUALITY DATA FOR SUGAR CREEK NEAR SPRINGFIELD (1985). Parameter PH Flow Rate (ft3/s) Dissolved (w/l 1 Barium Oxygen (mg/l) High 8.0 159.0 13.0 0.071 3.6* <.003 0.052 0.008 <0.005 2.7* co.05 0.25 Low 7.1 4.6 5.2* 0.045 Average 7.7 60.0 8.8 0.059 1.73* c.003 Illinois General Use Water Quality Standard 6-9 >6 <5 Boron (mg/ll Cadmium (mg/ll Chloride (mg/l 0.1 (1.0 <.05 <500 x1.0 so.02 0.019 <0.005 0.033 0.005 co.005 Chromium (mg/l Copper (mg/l 1 Iron (mg/l) 0.26 0.87 X0.05 xl.0 co.1 cl.0
Related docs
Other docs by EIA