Acrobat PDF

Environmental Information Volume for CILCO Edwards Station Boiler No Enhancing the use Eastern and Midwestern Coals by Reburning Sorbent Injection

Click to download
Reviews
2-3 I I Figure 2-3. Aerial view of Edwards power station. Approximate I 0 2-4 Scale I/8 (miles) 4 l/4 I I 2-5 . currently Illinois Kentucky delivered delivered reserves of coal). for fires coal coal to is the coals is from central by rail Illinois directly and three Runoff into and from eastern Approximately to the site, then units trucked pile to Kentucky. of The the is Coal tons of and delivered delivered to site is runoff into by truck. dock 75 percent the site. and 25 percent sufficient 250,000 flow rate by barge a nearby placed is the a storage containing 56 days operation Coal is pile gallons discharged of of all (approximately intermittent Illinois Process coal-fired wall fired and has an average is collected River. 0.056.million pond water 2.1.2 per day (MGD). in an ash pond, Description Edwards Station net Unit coal the Existing three has steam electric boiler, generating will high units be con2-5. sulfur were 1987. q . ' . with ducted Unit a total in 1 fires generating consisting Illinois capacity of 740 MWe. The project 15 weight low sulfur 2-l. load percent coal 1, a 117 MWe front a blend from as shown in Figure of nominally and 85 percent are given Testing during Plant in three 1986 rate, bituminous Kentucky. done for from eastern Coal and ash analyses plant 95,190 tons of station tons of by Commercial 1 design lb/hr of coal. coal heat coal, in Table full records units Unit These analyses Company in Unit in that operation and Engineering indicate Based on the Unit approximately 1 fired 1;308,33g 16 percent 49.9 percent. An electrostatic emissions. downstream ft2/(1000 Solid plant pond RCRA Subtitle for 208,676 1 fires 1986 Unit fired about was of coal. Therefore, usage. and all at Edwards Station 1 accounted 1 capacity for factor In 1986. the Unit precipitator a cold side preheater. (ESP) unit, is used which to control that collection particulate it operates area of 137 The ESP is of the air ft3/min). waste streams furnace means The ESP has specific from the boiler bottom ash. flow 2-6 Waste regulations include the fly ash collected are exempted to an on-site by the from ash ESP and the disposal. These waste rate streams C Hazardous and are sluiced Based on coal and ash percentage, calculations -w’U* mu. YLU L il. ta-.mtw 132” q. n. Al, “.Y . L7I.I w. e. II . I.“.“..% II I.-a I.-. h.-mnYr-mlEZ -cu .yui.Y .*Yw. LI/Ima 1. -t,Jnn.. .,a, . r ,/ta. IV 0 VW .Llf”.NLn.. ..U. -“.L3s”nL~u Figure 2-5. Schematic of Edwards Station 2-7 Unit No. 1 Boiler. TABLE 2-1. EDWARDSSTATION UNIT 1 COAL PROPERTIES Low-Sulfur Fuel Properties KeC%ky Proximate Analysis (Dry) 57.40 36.65 5.95 6.15 13.438 High-Sulfur Illinois Coal Fixed Carbon Volatile Matter Ash Moisture (as received) (as fired) (Dry) 49.52 39.28 11.20 16.59 10.635 Heat Value (Btu/lb) Ultimate Analysis Carbon Hydrogen Nitrogen Chlorine Sulfur Ash Oxygen Ash Fusion Temp. Reducing (OF1 80.00 5.08 1.45 0.13 0.69 5.96 6.69 71.05 4.99 1.24 0.05 2.99 11.20 8.48 Initial Deformation Softening (Ii = W) Softening (ii = l/2 Fluid W) 2370-2700 + 2540-2700 + 2630-2700 + 2700 + 1,975 2,090 2,195 2.305 2-a indicate the 851 lb/hr. conditions indicate units that during is full-load lb/hr, flow full Unit 1 at operation and flow diagram load, 1 generated 76,014 in flow rate rate of fly 2-6, flow tons ash from Unit 1 to ash pond for that 4724 Unit of bottom Figure 12,208 ash to the ash pond is representing rates. of ash, Plant and all baseline records three The process in 1986 shows these tons at Edwards Station Process water cooling flow generated of ash. River is used for fly Illinois water is once-through ash. River required Elimination water and to of these for submit flow water. ash are by Unit into the rate. as .- from the adjacent applications is provided The average water the High, from National plant low, and oils rates Illinois non-contact Boiler Process sluiced 1 is Illinois (NPDES) pH, taken total from 2-3. monitoring in Table Unit (scfm). full pounds sulfur This which tests (0.168 2.2 load per value is 1.17 water and for transporting in Table the ash 2-2. pond effluent values ash and bottom make-up water by demineralized amount of sluice Pollutant to monitor and average reports are sumnarized Fly and bottom discharged to an ash pond. MGO. River. permit Effluent The plant's requires solids. Discharge System monthly suspended reports. and greases from parameters 12 successive monitoring 1986 and 1987 are presented: I currently Air emissions million is operation. requires SO2 is Btu NOx is air at a flow include rate of 254,000 at a rate of standard 1712 lb/hr ft3/min During Cl.43 and of concern (lb/MBtu)], emitted assuming of S02, NO, and particulates. from coal 1269 lb/hr of 750 parts at a rate presently at emitted a rate of as calculated NOx emissions boilers. are emitted feed rate content. a value (1.06 lbs/MBtu). per million, of 218 lb/hr calculated typical in 1986, wall-fired Based on ESP performance conducted lb/MBtu). Technical Laboratory-scale particulates Project Oescriotion of the reburning in the early 1970's M. A., 2-9 "Reduction concept (e.g. were originally Wendt. J. 0. L.. and Trioxide investigations United States and Matovich, conducted Sternling, in the C. V., of Sulfur f 2-10 I I TABLE 2-2. PROCESSWATER FLOW RATES Source Circulating Cooling Sluice Boiler Water Water Runoff Water Flow Rate (MGDJ 2.6 355 1.17 0.056 Coal Pile i 2-11 TABLE 2-3. ASH POND EFFLUENT WATER PARAMETERS Flow Rate (MGD) Oils/grease(mg/l) 2-12 Nitrogen national) with the oil Oxides it by Secondary has been systems. fuel is Fuel Injection." Institute, at full Fourteenth Pittsburgh, scale Symposium (Inter1973, p. 897). but mainly work at when scale in scale in Japan. on Cotiustion, fired The Combustion demonstrated Recent potential natural 1960 and More recently extensive gas. research and pilot EER has demonstrated reburning in Valley developed Tennessee with higher locations SO2 control. EER's reductions reductions sorbent those scale spectrum most of injection obtained systems. The objectives data base demonstrating and to Since population. using three applications technologies. utility the full conducted characteristics. as applied Figure Natural produced boilers of with of primary recent up to if rather circa of the reburning Sorbent concept, injection particularly was also at that full originally 1970's 1970 and was demonstrated (TVA) Shawnee Power Plant TVA demonstrated through the potential use of Large scale Authority's levels could sorbent in the early proper poor results. and advanced sites Subsequently, be achieved materials. significantly injection U.S. for capture work at several of this technology and Canadian has begun to confirm pilot 70 percent a hydrated optimized scale from typical results indicate that 60 percent Sulfur reburning are typical for NOx with of _ can be achieved pre-NSPS NOx levels. by combining These data injection is used. dioxide can be achieved sorbent gas appear reburning-sorbent to be generally a wide in full fuels and they achievable the current project are to provide of this a comprehensive boiler of combination the performance promote the design of GR-SI in pre-NSPS utility characteristics could with for coasnercialization and operating demonstration a total utility will of three boilers be designed of pre-NSPS address will varying be vary widely, no single pre-NSPS host unit. adequately widely Consequently, The GR-SI systems demonstrations optimum performance to each specific 2-7 illustrates injected zone. the application above the main heat NO is reduced of GR-SI in a wall release radical fired boiler. is gas is in that zone to reburn NO that by a hydrocarbon 2-13 (CH) producing REBURNING GAS Figure 2-7. Application injection for of gas reburniwysorbent NOx/S02 control. 2-14 HCN which allows by the reaction temperatures 60 percent emission the plant the formation of NO with of NH via NCO. Molecular nitrogen is produced N at high temperature and with NH2 at lower (<2200°FI. NOx control. The goal of the GR-SI system is to provide The pre-NSPS Edwards unit does not have an NOx Thus, this NOx emission reduction could be useful to #Ox regulations. location to maximire will is shown for sulfur sorbent injection. of of ._ constraint. in response to future In Figure Upper furnace approximately fired Unit 2-7 an upper furnace injection 2250°F is required is necessary the SO2 strategy because an injection capture. a higher temperature percentage For the walllevels. on this in the 1 boiler, be to fire high sulfur Illinois coal while maintaining SO2 emissions at present The preliminary plan is to inject the sorbent into the upper furnace unit. flue Sorbent gas. injection will increase the amount of solid and performance material Therefore, several ESP modifications upgrades will be assessed during the detailed design phase of the project and implemented during the construction and startup phase. ARong these possible modifications are addition The solid which, lime/fly of plate area, flue gas humidification and SO3 injection. sorbent with or the fly ash to solid _ waste from GR-SI is a blend of a calcium lime, for has similar sludge sludge prepared due to the presence of unreacted ash/scrubber characteristics disposal product from lime-based placement and produces cosssercial spray dryer systems. stable landfills. applications. This waste Such a blend hardens after may also have value for construction solfd Two potential these option off-site detailed options is dry is waste management options current which would involve will be evaluated. system. the solid One of The other to use the plant's landfill. wet handling trucking will disposal. waste to an the permitted design One of these options be chosen during phase of the project. 2-15 2.3 2.3.1 Oescription Description of Activities of Project Phases EER wil 1 conduct the The GR-SI project will take 53 months to complete. technology demonstration project in three phases: @ Phase l--Design in the systems permitting program initiate plan demonstration modifications a and Permitting. This initial phase wi 11 culminate detailed design of gas reburning and sorbent injection for Edwards Station. Gas pipeline design, routing, and activities will testing. will will also for All be conducted the panel will during Phase 1. A and to ._ be prepared transfer. be obtained. and Startup. This phase will begin after‘ and will last 16 months. Following DOE and sorbent out at during injection Station. Phase 2. equipment will Gas pipeline The process and panel. and Disposition. will be be Edwards equipment construction be established permits An industry technology necessary and permit Phase E--Construction Phase 1 is completed approval, installed construction engineering and checked will designs will the gas reburning also be conducted be presented to the industry Reporting, the final 0 Phase 3--Operation. Phase 3 will will tested results available industry last begin 29 months. Data Collection, concurrent Following with stages of Phase 2 and the host unit DOE approval, for one year over a range of conditions. All data and test will be compiled into a guideline manual which will be made to industry. panel. The project results will be presented to the The demonstration technology technology of GR-SI is not intended as a first generation of specific but rather it will build upon the results of several individual demonstrations now being conducted by the EPA and others. 2-16 I I 2.3.2 Description The following of Installation section as part personnel describes of the Activities the specific installation safety tasks that by EER is a primary will be undertaken plant GR-SI technology labor. Worker demonstration personnel, and local concern in any industrial project, since an employer has not only a financial liability, but an ethical responsibility to ensure that workers are not subjected safety risk to unreasonable rules of injury Major will be fully to workers. involved in the construction phase of the project _ risks. enforced All appropriate this occupational health and the throughout program to minimize activities include installation of the gas reburning and sorbent injection equipment. construction of the natural gas pipeline, and implementation of ESP upgrades. The GR-SI equipment a series 1. installation work at Edwards Station will be conducted in of five steps: 2. 3. 4. 5. Procurement Initial installation Final installation Checkout Correction (normal (outage) unit operation) of deficiencies final is the installation, key element schedule will must correspond determining to a normally scheduled schedule. Step three, outage at the and this The specific the installation outage time and the condition depend on the utility's For example, of the unit. load requirements if a fall outage is scheduled but the power demand is greater than anticipated in the fall and there are no major problems, the utility may elect to delay the outage until the low load period in the spring. flexibility, The program EER will must be flexible request in this to of regard. procure the final To maximize schedule long lead time design specifications. authorization the completion items as soon as possible following 2-17 Most of the silos, items etc., will equipment will be standard directly items such as piping, A limited specific valves, nu&er of and will be obtained from vendors. to meet site need to be custom-fabricated requirements. etc. The will be to These include the gas and sorbent injectors. windbox modifications. general approach to the equipment procurement and installation conduct possible. and fitting the fabrication/assembly work off site to the maximum extent This will limit the amount of time-consuming custom installation required during installation step the short outage periods. be divided is into two steps: an The The on-site initial operation following 1. work will where all work installation and the final equipment will Sorbent conducted during normal unit installation be installed and storage step which requires a unit outage. during normal unit operation: equipsmnt. equipment. equipment assetily. unloading 2. 3. 4. 5. 6. 7. A plot Sorbent feeding and transport Sorbent piping and injection Sorbent injection control assetily. Gas piping and control assembly. Gas injector assetily. Instrumentation installation plan of Edwards Station except for final connections. storage silo installation installation is shown in Figure in time to provide during a scheduled equiplnent showing a proposed location of the sorbent The intent is to complete the initial 2-8. flexibility on completing the final outage. during an outage: The following 1. must be installed Windbox modifications. Furnace or duct penetrations or sorbent injectors. Final Final connections gas plutiing. connections. for control for gas injectors, equipment. overfire air ports 2. 3. 4. 5. 6. Final instrumentation ESP upgrades. 2-18 I\\ I I\ z \\ 1 Boiler asbestos conducted will applicable guidelines, It single is tubes are insulated with asbestos to minimize heat loss, and some handling will be required. by a contractor qualified in the contractor's OSHA and EPA regulations air monitoring not necessary outage include All boiler modification work will be to work with asbestos materials. EER specifications a requirement that all be satisfied, and proper installation including disposal asbestos removal considerations. at a requirements, that all final work be completed scheduled following the initial installation. Consideration will be given modifications installation to installing the furnace/duct penetrations, windbox and ESP upgrades prior to the completion of the initial items if a scheduled outage during becomes available. the final outage. will for be the This would of effort of the required reduce the intensity Installation conducted pipeline long, project includes potential is natural 2-9. gas pipeline The pipeline the Historic at Edwards Station route selected will be approximately by the Gas Division shown in Figure 3/4 State mile will federal Historic of pipeline of CILCO. The tentative 1 mile Since the . of which involves the impact be on privately Preservation construction. owned property. Preservation funding, Agency, which Officer (SHPO), must evaluate the An archaeological survey may be not disturb any required by the SHPO to demonstrate that the pipeline will sites of archaeological cultural, or historic significance. Construction steps: Preliminary Final engineering title and route search and route selection selection of the natural gas pipeline will include the following Land ownership engineering Right of way negotiation/procurement Archaeological survey materials and equipment procurement Excavation and pipefitting Right of way cleanup 2-20 N t Proposed Pip/line Route f \\ \ \ \ Property Line i ;; II) G -5 = \ \ \ dwrr 14 Approximate 500 I Figure 2-g. 0 500 Tentative route for natural to Edwards Station. 2-21 D:l Scale (feet) 1000 gas pipeline These tasks reveals that the be chosen. will be coordinated route will route by CILCO. that If the archaeological then an alternate will survey or pipeline is unsuitable, be selected route will No final damage any artifacts land of archaeological significance. required metering for the pipeline welding construction supplies, will The adjacent to will The materials and equipment include pipe, fittings, valves, excavation equipment, meet applicable codes natural Unit 1. gas pipeline From this equipment, and material handling equipment. and will match consson industrial will be routed point, previously to convenient under equipment the remaining construction All materials practices. activities termination installation. terminal be conducted 2.4 This divided 2.4.1 as described Project section Source Terms characterizes demonstration all of the areas that Potential requirements could be impacted by areas of impact can be. and project discharges. the GR-SI technology into project. the categories of resource Project Project Resource Requirements requirednts resources. project Figure The resource include energy, land, water, with labor, important the GR-SI resource and other rates. materials, process technology 2-10 is a diagram detailing associated below. flow requirements demonstration are identified Energy Requirements Additional demonstration equipment, increase is estimated energy include and natural in electrical that requirements electrical gas required power consumption associated power with the GR-SI technology injection and ESP It fuel. The estimated at full to run sorbent for the site rate as reburning is about 1400 kW. the natural gas consumption for the host site operating capacity will be 3908 scfm. This value is calculated that 18 percent of the heat input currently provided by coal will 2-22 by assuming be provided I I i;; u-3 -* c$5 xx ‘2 En rI c : 2-23 by natural gas during GR-SI operation. Coal usage will decrease due to the added natural gas flow. Full-load coal feed rate is expected to decrease by approximately 11 percent to 82,311 lb/hr. To maintain SO2 emissions at calculations indicate that the new blend of coal fired by present levels, Unit 1 will be about 57 percent high-sulfur Illinois coal and 43 percent lowKentucky coal. sulfur Land Requirements The GR-SI project procedures on an existing ensure sorbent convenient If used, that adequate location storage involves the utility boiler. space is available equipment. hardware. to the existing ash pond is for waste disposal. If the be transported will to be for retrofit of two emission control The host site on site for Sufficient has been examined to installation of the for - and feeding of all space is available required the option of wet solid waste disposal then no additional land will be required waste disposal landfill. option In this case, dry solid an existing land will Illinois The natural required underground installation. is used then the waste will for waste disposal. permitted landfill, the only land requireemnt that has already been allocated be disposed of in an appropriately solid only for waste regulations. significant pipeline and topsoil Thus after for agricultural land A stretch will The solid waste as defined by requirement of the, project will be for the be be gas pipeline. of land approximately 1 mile long will However, the pipeline will construction. be removed, installation uses. and other stockpiled, and replaced pipeline is completed, after the land will be available Water Requirenmnts The GR-SI process However, humidification Calculations assuming does not require the utilization of water, per se. water will be needed to enhance ESP performance. saturation indicate that the humidification water 2-24 I I I /I requirement used, process the will will be 0.09 water MGO. will more sluice sluice If the wet solid waste disposal option is be required because the sorbent injection amount of fly indicate present that ash. the Calculations Unit 1 sluice based on water generate will an increased rating from its pump capacity increase requirement MGO if MGO. will value of 1.17 MGOto about I.66 the wet disposal If the dry solid by Unit option waste 1. is used. This represents an increase of 0.49 disposal option is.used, then no sluice water be required Labor Requirements Labor operation performance. labor will be required of Although it for installation installation small effort of the GR/SI equipment, of system the largest and maintenance is still the hardware, and verification represents the equipment a relatively requirement, which can be managed by EER using locally available skills. A breakdown of labor required for pipeline is not included Operation additional existing During test plant in Table 2-4. and maintenance it labor to provide both general and specialired requirements is presented in Table 2-4. Labor will be supplied by CILCO or its agent and. construction of the that GR-SI systems requires training very little by the program. to labor; is anticipated staff EER test these tasks may be conducted of a brief will also be available operations upon completion crew personnel procedures. periods, oversee operation Performance additional Materials labor and maintenance verification will tasks will be conducted by EER test crews. No be required for these tests. Requirements material the requiresmnt course of for the GR-SI technology 6470 lb/hr demonstration be The primary is a calcium required. expected During based sorbent. During operation the program. Approximately 2-25 of Ca(OHl2 will to be used at the site. 15.000 tons of sorbent are 150 tons of sorbent will be , TABLE 2-4. PROJECTLABOR REQUIREMENTS 2-26 stored in the site's sorbent silo. for which the state of Illinois tested will be selected The raw material for is a major producer. sorbent is limestone The sorbent to be as part of the demonstration will be purchased process. from local distributors. Construction materials Construction materials include sorbent silo and handling equipment, piping and small hardware items. Sulfuric acid and/or CO2 required for ash pond pH adjustment will also be purchased locally Requiremnts low-sulfur Kentucky and 25 percent coal, 75 percent is delivered by rail dock _ if the wet disposal option is used. Transportation Of the directly to the site, is delivered by barge to a loading and then trucked is all delivered day during increased increase will for for also delivery. deliveries If the to The high-sulfur Illinois coal a short distance to the site. by truck. and requires approximately nine 20-ton trucks per operation. 26 trucks Because the GR-SI process will Illinois require coal, the truck five per day for coal delivery. approximately 31 trucks per day will utilize an will requirement trucks full-load amount of high-sulfur to approximately be trucked during Therefore, full-load option in and will The sorbent' per day be required approximately operation. dry disposal is used, then about 9 trucks per day will be required conditions. solid flow is chosen. rate, haul the solid waste to a landfill, The delivery trucks could potentially This option feed rate, it will is Based on the scheduled duration during assuming full-load be used to backhaul the the landfill the sorbent period. period, that waste to the landfill. and the coal waste will Discharges be assessed after of the test estimated about 1580 truck loads of solid 2.4.2 Project Significant technology and spent be generated the 12-month GR-SI test waste discharge streams from the boilers employing the GR-SI include sorbent. stack emissions and a solid waste consisting of fly ash At the technology demonstration site an emission control 2-27 target expected expected of 60 percent to decrease for NOx has been established. (0.42 lb/MBtuI. are anticipated. to maintain (1.43 lb/MBtu). emissions may be required NOx emissions Emissions are to 508 lb/hr of SO2 are to remain at 1712 lb/hr or particulate modifications levels. of plate area. No changes in CO, unburned Electrostatic particulate emissions SO3 injection hydrocarbons, precipitator at present or addition Modifications may include humidification, Solid waste is expected to change in both flow rate and composition due to the addition of sorbent. Flow rate of fly ash collected by the ESP during full-load operation is expected to increase to about 12,665 lb/hr. The new composition 40 percent of the fly Ca(OH)2. ash will Bottom be 42 percent ash flow rate, coal ash, 18 percent which GR-SI will full CaS04. and per ._ not affect to increase to 954 lb/hr se. is expected with high ash content will be used. Solid waste will be managed either during load because more coal by using the current wet disposal system or by using dry disposal in a permitted .waste management option will be made during detailed technical within disposal. If water, disposal the dry disposal is used, option flow then landfi.11. Choice of a solid' Phase 1 of the project, when the decision include design work will be done. Factors influencing requirements for maintaining ash pond pH and total suspended solids permit limits, and regulatory and economic requirements for dry is used, then Unit rate will based on the expected 1 will require no sluice water and the pond effluent option effluent because decrease to 3.6 MGB. If the wet amount of sluice increase, the will increase sluice will water. water flow rate will increase to 5.3 MGB. Flow rate the increased amount of solid waste will require more of unreacted and spent sorbent to the fly ash The pH of the ash pond The addition cause the waste stream to become smre alkaline. will be adju-sted to meet the permit limit of 9. Monitoring will be done during the testing, and corrective action will be taken as needed to ensure compliance lower the with permit limits for pH. Possible neutraliration measures to pH level in the ash pond include injection with sulfuric acid or 2-28 bubbling processes, of carbon dioxide through limit the alkaline water. In both of these acid) will the acid addition (CO2 reacts in water to form carbonic of 9. to change. Total lower the pH to within Oil the permit and grease loadings are not anticipated suspended solids will be maintained below the regulatory limit of 15 mg/l by increasing the residence time of the water in the pond or using chemical means such as polymeriring the sorbent Coal result contributions In addition, slightly. increasing Canadian agents. reacts with usage will from Sulfate concentration is expected SO2 to form calcium sulfate. decrease metals sorbent as a result loading will of the decrease. to be smaller to increase because GR-SI project, and as a - coal-based are expected In general, metals than those from coal. pH is'expected to remain at current Studies have shown that leachability pH (e.g. Cote. P. L. and Constable, 53). to decrease, effluent Data Base on Waste Leachability, 1984, p. both expected levels levels or to increase of metals decreases with T. W.. "Development of ASTM, Philadelphia, leachability are increase in metals the GR-SI project. 2.5 Potential Special Technical Publication 805, Since coal-based metals loading and' there is expected to be no of or groundwater as a result in either EHSS Receptors A number of environmental features could potentially be impacted by the These include air quality, surface water quality, proposed action. groundwater focuses probable quality, inpact land use, labor force, and energy resources. Section 3 on characterizing receptors. the existing environment with respect to these Section 4 evaluates the probable impact of GR-SI 1 on these receptors. 2-29 . 3.0 EXISTING ENVIRONMENT of the environmental setting features that might be affected into the six categories is characterized at by that This section provides a description Edwards Station. focusing on environmental the proposed action. The environment were mentioned in Section 2.5. individually in this section. 3.1 Atmospheric Resources is divided Each of these categories The area of central Illinois provides a typical continental winters. throughout an agent Peoria states is Figure 3-1 shows B&year According State the year. of the Illinois 34.9 inches. in which the demonstration site is located climate with warm suanters and fairly cold average wind roses for to the Illinois Water Survey, is of a local air is quality typical Peoria for 4 months who is in midwestern State Climatologist, average annual precipitation of the specialized control and both region entire environment. 65 (Durlingtonwhich is a nonof The climate area and not represesentative Peoria County area Pollutants for is in federal The plant SO2 primary published Keokuk attainment standards, Criteria Interstate). according in Hollis Township standards TSP and SO2 secondary Status EPA. A survey to the Geographic in February Designations of Attafnlnent 1985 by the Illinois of Illinois EPA's Air Emissions Inventory Tazewell counties there are 283 businesses air pollutants, The area industrialized, River. Current construction of which 156 emit particulates, imediately but there surrounding are other revealed that in Peoria and and industrial plants that emit 60.emit SO2. and 77 emit NOx. Station is not highly the Edwards industrial plants along the Illinois noise levels at the Edwards plant are attributable to ongoing activities and noraul plant operation (e.g. coal pile shaping and coal feeding). 3-1 , I I /Ii JANUARY 90-YEAR TOTAL (1901-901 APRIL W-YEAR TOTAL (1901-90) OCTOBER 90-YEAR TOTAL (1901-80) JULY 90-YEAR TOTAL (1901-90) Key: For each concentric circle, the wind blows 1 percent of the Thus, a line directed vertically timefromthe direction of the line. downward from the city that passed through 10 circles would indicate that the wind blew from the south 10 percent of the time. Figure 3-l. Wind roses for 3-2 Peoria, Illinois. 3.2 Land Resources Edwards Power Station along by broad in the Plain lies is located the lower in Peoria Illinois County, River Illinois. Province. The power The plain The loess, plant is situated at the edge of the wide valleys. Springfield power plant of the Central upland Illinois Lowland physiographic divides River and shallow, floodplain is characterized composed of thick alluvium and glacial outwash underlain by Pennsylvania age bedrock. A flood zone map of the Edwards Station area from the National Insurance Agency is given minimal region, in Figure flooding. 3-2. Part Unit 1 is in a Zone C region, natural flood gas pipeline plain. which will is an area of to the Illinois for the of the be in a Zone Al3 which is within the loo-year wetlands According Department of Conservation. maps have not been published area around CILCC Edwards Station. There is a great deal of agricultural activity near Edwards Station. According to the Peoria County Soil and Water Oistrict, the soil on which the' plant rests is classified as Fayette silt loam. The pipeline will traverse soils soils that are classified as Fayette silt loam and Sylvan silt for soils cultivated loam. crops, These hay. are considered to have good potential and woodland use. Areas of these pasture, slope are considered to be prims for farming. The natural will require approximately comprised around four-lane 3.3 gas pipeline a right half is currently route having small degrees of was shown in Figure 1 mile farming. land, long. 2-8. The pipeline Of this land, land is of way approximately used for railroad-owned The remaining and publicly of CILCO-owned land, U.S. Highway 24. owned land Water Resources Edwards plant intakes water from and discharges to the Illinois River. Ambient water quality data for the Illinois River at Pekin. which is about are sumnarized in Table 3-1, including one mile south of Edwards Station. 3-3 . *kjyJ=== AREANOI ,hCLUDED TtE6? ._RM * ii.. --_. ~.~f , - 1 y$ a”+ TTY .‘(s / Rwx ,’ v,‘,,~/ mJd x v’7 -** Unft 1 Edwards Station Figure 3-2. Edwards Station 3-4 flood zone map. TABLE 3-1. WATERQUALITY DATA FOR ILLINOIS RIVER AT PEKIN (1965) Parameter PH *Flow Rate (ft3/s) Dissolved Oxygen High 0.2 70,200 13.0 0.08 0.18 0.003 0.009 0.009 4.4** <0.05 0.19 0.0001 0.019 0.58*f 0.18 LOW 7.4 6620 6.1 0.05 0.05 <0.003 <0.005 <0.005 1.4* Average 7.0 20,300 9.4 0.064 0.15 <0.003 <0.005 0.007 2.3** co.05 Illinois General Use Water Quality Standard 6-9 >6 <5
Related docs
Sorbent Technologies Corporation (PDF)
Views: 1  |  Downloads: 0
premium docs
Other docs by EIA
ade-Davis Bill _1864_ - 2
Views: 86  |  Downloads: 0
OSHA SMALL BUSINESS HANDBOOK
Views: 596  |  Downloads: 26
FORM 16B CAPTION SHORT TITLE
Views: 170  |  Downloads: 0
Belize Economic Report for 2006
Views: 229  |  Downloads: 1
Brown v. Board of Education _1954_ - 1
Views: 113  |  Downloads: 0
Sample Executive Summary LiveWire
Views: 241  |  Downloads: 0
FORM 5498 IRA CONTRIBUTION INFORMATION 2005
Views: 93  |  Downloads: 0
OSHA CONSTRUCTION INDUSTRY DIGEST
Views: 618  |  Downloads: 25
Sample Business Plan ProVision Network
Views: 270  |  Downloads: 10