Iowa Separation Agreements
W
Description
Iowa Separation Agreements document sample
Document Sample


IOWA LIVESTOCK
REGULATIONS UPDATE
IOWA PORK PRODUCERS
ASSOCIATION
June 12, 14, 15, 2006
Eldon McAfee
DNR AUTHORITY
Proposed operations or expansions
Proposed rule – on June 19 EPC agenda for
final adoption
Will go into effect August 23, 2006
List of factors DNR Director is to consider to:
Amend requirements to construct or operate
Deny a permit, manure management plan,
or construction
DNR’s authority under this rule is in addition to
all other state and federal requirements
ANIMAL CAPACITY Animal weight
capacity and animal unit capacity
Constructed before 2002 legislation – AWC -
maximum number of animals confined at any time in a
confinement operation multiplied by the average
weight during a production cycle
Constructed or expanded after 2002 legislation – AUC
- maximum number of animals confined at any one
time in a confinement operation multiplied by the
animal unit factor
Animal unit factor – swine
.4 - more than 55 pounds, .1 – 15 to 55
Under Iowa law, the AUC of a confinement operation
is not included in calculating the AUC of an open
feedlot operation – federal EPA regs currently require
adding together if both have same species
CONFINEMENT OPERATIONS
Adjacency - one operation or two?
To determine if a permit or manure management
plan is required, and if concrete standards apply:
Two CFO’s are considered to be one operation
when:
There is common ownership or management, and
They are adjacent; or
Utilize a common area or system for manure
application
Adjacent – CFO’s within:
1,250 feet if the combined AUC is <1,000
2,500 feet if the combined AUC is >1,000
CONFINEMENT OPERATIONS
Adjacency - One operation or two?
To determine required separation distances:
Two CFO’s are considered to be one operation when:
There is common ownership or management, and
They are adjacent
Adjacent – CFO’s within:
1,250 feet if the combined AUC is <3,000 for
finishing or nursery (<1,250 AUC for farrow-gest. or
<2,700 AUC for farrow to fin.)
1,500 ft. if the combined AUC is >3,000 but <5,000
for finishing or nursery (>1,250 but <2,000 AUC for
farrow-gest. or >2,700 but <5,400 AUC for farrow to
fin.)
2,500 feet if the combined AUC is >5,000 for
finishing or nursery (>2,000 AUC for farrow-gest. or
>5,400 AUC for farrow to fin.)
CONFINEMENT OPERATIONS
Adjacency - one operation or two?
DNR rules definition of adjacent has not
been revised since the 2002 legislation
The rules definition still follows the
animal weight capacity requirements for
adjacency that were in effect before the
2002 legislation
The definition of adjacency in the Iowa
Code, as set forth in these slides, is the
definition that must be followed
CONFINEMENT OPERATIONS
One or two?
Common management
Iowa law (DNR rule):
Significant control of day-to-day
operations
DNR interpretation:
Common management if two producers
contract feed hogs for the same owner if
the owner has the right to control
marketing, feed rations, or vet services
Environmental regulation compliance
What if advice from DNR is incorrect?
2004 Iowa Supreme Court case:
Business required to get a solid waste
disposal permit when DNR employee
initially incorrectly advised that a permit was
not required
Court ruled DNR employee was acting in
good faith and within his duties even though
the employee made an erroneous
interpretation of the law
Advice from DNR on regulations
What if it is incorrect?
Audubon county producer required to get a
construction permit on referral to the Iowa Attorney
General even though DNR field and state office
advised that a permit was not required
Osceola county producers denied a construction
permit by EPC because no P Index was included with
MMP. DNR had approved the permit application
based on DNR policy that allowed P Index to be
submitted before first manure application if soil
samples could not be taken
Muscatine county producer required to stop
construction and obtain a stormwater discharge permit
even though DNR had given him an outdated brochure
that stated a permit was required if more than 5 acres
was disturbed (law changed to more than 1 acre in
2003)
DNR ENFORCEMENT
If a violation occurs:
Monetary penalties – up to $10,000
Require corrective action
Require confinement operations to get a discharge
permit (NPDES/operating permit) if an accidental
discharge occurs
Request that the Iowa Environmental Protection
Commission (EPC) refer the violation to the Iowa
Attorney General for enforcement
Referral to the Attorney General results in:
No new construction or expansion while case is
pending in court
Higher monetary penalties – up to $5,000 per
day per violation
Potential habitual violator status (3 strikes and
then no new construction or expansion for 5
years after the last strike)
All monetary penalties are required by law to go to
DNR’s animal compliance fund
DNR ENFORCEMENT
Environmental self audits
Initiated by business owner to determine
environmental compliance
Benefits:
Immunity from penalties if a violation discovered
during audit and promptly reported to DNR, before
DNR investigates
Confidentiality of audit report
No immunity from penalties if:
DNR not properly notified
Violations are intentional or result in injury to
persons, property or environment
Substantial economic benefit giving violator a clear
economic advantage over competitors
MANURE MANAGEMENT PLANS
Original (new) filed with DNR & county
Formed storage
More than 500 animal units capacity (1,250 head of
swine weighing more than 55 pounds or 5,000
head weighing 15 to 55 pounds)
Constructed or expanded after 5/31/85
Earthen storage- DNR construction permit
DNR interpretation: Upon transfer of operation
“New” MMP
MMP fees and indemnity fund fees
Transfers may include family transfers & forming a
corporation
Transferee loses grandfather status for phase-in of
P Index
MANURE MANAGEMENT PLANS
Annual updates
To DNR and county
Short form detailing changes in MMP or statement that
there are no changes
May use table values in updates submitted to
DNR each year & then apply manure based
actual sample values if amend plan before
manure applied (do not have to submit amended
plan to DNR)
Compliance fee - $.15/a.u. – if contract feeding,
livestock owner required to pay fee
DNR using “tier” system to score producers on
compliance to determine how often the operation will
be inspected
MANURE MANAGEMENT PLANS
Recordkeeping
Records - must be kept on site or at a
residence or office of the owner or
operator within 30 miles of the site
DNR recordkeeping form – not
mandatory, producer can use own form
Current MMP
Rate, methods and date(s) of app.
Field location and number of acres
MANURE MANAGEMENT PLANS
Recordkeeping – commercial N & P
For manure applications after 8/25/05, MMP
records must include dates and application
rates of commercial N & P on fields receiving
manure – including land farmed by someone
else where manure is applied under an
application agreement.
DNR cannot bring an enforcement action for
over application of N or P on land farmed by
someone else unless the producer “knew or
should have known” that commercial N or P
would result in N or P exceeding legal limits.
MANURE MANAGEMENT PLANS
Recordkeeping – commercial N & P
Producer must obtain statement from
farmer who owns, rents, or leases each
field receiving manure specifying the
planned commercial N and P fertilizer
rates to be applied to each field
DNR form, but can use own form for
individual situations
MANURE MANAGEMENT PLANS
Manure application agreements
As part of overall manure management program,
producers should review manure agreements to
ensure compliance with DNR rules and proper
application of manure and other soil nutrients
Agreements should clearly state that the crop
producer will comply with the nitrogen and phosphorus
limits in the manure management plan and that the
crop producer will provide the dates and application
rates of commercial nitrogen and phosphorus to the
livestock producer
Approval of agreement by landowner’s mortgage
lender
Address nuisance and other potential liability
MANURE MANAGEMENT PLANS
DNR policy
Crop available N during first crop year after manure
application
Previously – DNR allowed less than 100%
Beginning 8/25/04 – new MMP’s - use 100% based
on ISU Pub. Pm-1811
Can use less than 100% if provide DNR with
supporting credible information
Existing operations may continue to use less than
100% without supporting info until the first P Index
based MMP is due
Nitrogen in addition to amounts allowed in MMP may
be applied up to amounts recommended by soil or
crop nitrogen test for optimum crop yield
MANURE MANAGEMENT PLANS
EPC proposal
“not allow manure management plans to
specify that liquid manure be applied to
land planted to soybeans with a three to
four year phase in period for holders of
the existing manure management plans
and for provisions to allow exceptions for
wet years or when it becomes too late to
plant other crops”
Scheduled for July 17 agenda for release
for public comment
MANURE MANAGEMENT PLANS
Phosphorus index
In addition to N requirements
Phased in based on date of original MMP
Before 4/1/02 – P Index required with first annual
update MMP on or after 8/25/08
On or after 4/1/02 & before 10/25/04 – P Index
required with first annual update MMP on or after
8/25/06
On or after 10/25/04 – must comply with P Index
Note: DNR has determined that an MMP submitted
for an expansion of an existing operation is an original
MMP – an MMP for a modification without expansion
of animal numbers is not an original MMP
MANURE MANAGEMENT PLANS
Phosphorus index –DNR rules
Calculated every 4 years, more often if PI inputs
change
P Index categories (not the same as soil test):
Very low (0-1)- N based MMP
Low (>1-2) N based MMP
Medium (>2-5)
Manure may be applied at N based rates if
current and/or planned soil conservation and P
mgt practices predict the PI will not exceed the
medium category at the next PI determination
Manure not applied in excess of 2 times the P
removed over crop rotation
If follow P based rates in these categories, soil
samples can cover up to 20 acres
MANURE MANAGEMENT PLANS
Phosphorus index –DNR rules
P Index categories (not the same as soil test):
High (>5-15)
(>5-10) Until 12/31/08, manure may be
applied at P based rates if practices
adopted to reduce the PI to medium for
the next determination
(intent – be able to continue applying
manure while implementing practices)
(>10-15) no manure application
(intent – no additional manure
applications until practices
implemented to reduce PI to medium)
Very high – no manure application
MANURE MANAGEMENT PLANS
Phosphorus index –DNR rules
Phosphorus based rates:
P applications over the crop schedule
limited to crop removal unless additional P
recommended by soil tests
P from a manure application cannot exceed
crop removal from the next 4 planned crops
P crop removal = optimum yield X P
removal rate for each crop (.375 lbs. P/bu.
of corn, or other credible data)
MANURE MANAGEMENT PLANS
Phosphorus index –DNR rules
Fields – PI calculated for each field. Fields must be
contiguous-not separated by a road, river, creek, etc.
Soil type to calculate PI must be most erosive soil map
unit that is at least 10% of the total field
Soil sampling - Every 4 years
Samples for each 10 acres (20 acres if PI vl, l, or m
and apply manure on P rates)(fields up to 15 acres
– one sample)
Samples averaged for soil test level of a field
Existing soil tests may be used if they meet DNR
requirements
MMPs for construction, if previous soil tests are
less than 4 years old and don’t meet requirements,
they may still be used if new soil tests meeting
DNR requirements are taken within one year after
the MMP is approved
CONSTRUCTION-FORMED STOR.
500 animal units or less (small AFO)
Separation distances from water bodies (500 ft. from
creek, etc.) & wells
No construction in 100 yr. floodplain of navigable
river, etc. - determine if on alluvial soils – if so,
determination from DNR regarding 100 yr. floodplain
Tile around footings for below ground storage (or
certification that groundwater table is below the
structure)
Stormwater discharge permit if area disturbed during
construction is more than 1 acre
CONSTRUCTION-FORMED STOR.
500 & 1,000 animal units
MMP & construction design statement to DNR &
county 30 days before construction
Note: All information on the MMP & CDS be
completed correctly – DNR has taken the position
that the 30 day period does not start if certain info is
not correct or is missing
Meet construction design stds. (including tile around
footings or cert. regarding groundwater level)
Meet required separation distances
No construction in 100 yr. floodplain of navig. river,
etc.
Stormwater discharge permit if area disturbed during
construction is more than 1 acre
See www.iowadnr.com/afo/forms.html for forms
CONSTRUCTION-FORMED STOR.
1,000 animal units or more
Construction permit app. to DNR & county (DNR has
60 days to act but can extend for add. 30 days)
Engineer required if 3,000 or more a.u.’s (1,250 a.u.’s
for farrow gest or 2,750 a.u.’s for farrow to finish)
Const. design statement if no engineer req’d
Meet construction design stds. (including tile around
footings or eng. cert. regarding groundwater level)
Meet required separation distances
No construction in 100 yr. floodplain of navig. river
Manure management plan
Stormwater discharge permit if area disturbed during
construction is more than 1 acre
See www.iowadnr.com/afo/forms.html for forms
CONSTRUCTION-FORMED STOR.
1,000 animal units or more
Master matrix
Not required if expansion up to 1666 a.u.’s if site
constructed as of 4/1/02 or if county has not
adopted matrix
Producer selects criteria – county scores – DNR
independently scores if county rejects
Legally enforceable - part of permit
Supporting documentation, including design,
operation, and maintenance plans.
Note: If the necessary supporting documention
is not included, DNR takes the position that it
may reject the permit application (even if a
county passes the matrix) because the matrix is
a part of the permit
Also triggers county’s 14 day right to appeal
issuance of permit
CONSTRUCTION-FORMED STOR.
1,000 animal units or more – 6/15/05 DNR rule
Construction permit required if any construction of a
manure storage structure occurs on site
Permit required even if no physical construction or
alteration if there is an increase in manure volume or a
modification in the manner manure is stored. Unless
increases or modifications are:
Within the limits of a previously issued const. permit
Determined insignificant by DNR (e.g., double
stocking weaned pigs in a wean-to-finish barn)
No permit required for repairs or additions to a building
such as fans, slats, gates, roofs or covers
Plans for repair or modification to a manure structure
must be submitted to DNR to determine if a permit is
required
CONSTRUCTION
Stormwater discharge permit
Required if the total area disturbed is more than one
acre - activities that further cropping are exempt
To obtain a stormwater discharge permit for
construction activities:
Publish a form notice in 2 newspapers with the
largest circulation in the area
Prepare a pollution prevention plan that includes
measures to be implemented to control erosion
during construction and until a permanent ground
cover is established. This plan must be in place at
the time the notice of intent is submitted to DNR
and must be kept on site
Submit a notice of intent to be covered by the state
general stormwater discharge permit to DNR at
least 24 hours before construction begins. Attach
proof of publication of public notice to the notice of
intent and filing fee.
See www.iowadnr.com/afo/forms.html for forms
SEPARATION DISTANCES
Residences, businesses, road rights of way, etc.
CFO’s with formed manure storage and more than 500
AUC are subject to separation distances regardless of
whether a DNR permit is required-all new or
expanding CFO’s with earthen storage are subject to
separation distances
Residences, businesses, churches, schools, public
use areas, and road rights-of-way
Public use areas include parks and cemeteries
(pioneer cemeteries (6 or fewer burials in the last 50
years) are exempt)
For a worksheet and separation distance tables see:
www.iowadnr.com/afo/files/distreq.pdf
SEPARATION DISTANCES
Residences, businesses, etc.
Exemptions:
Written waiver from owner of residence, etc. – must
be recorded with county recorder
Also may want to include:
Covenant-not-to sue for nuisance
Approval by residence mortgage holder
Expansion of CFO -- use distances in effect at time
CFO constructed (if CFO constructed before any
distances required, 1995-1999 distances apply)
<2x cap.,<1,000 AUC, and new structure built
further from residence, etc.
Residence, etc. built after CFO began operation
DNR rules state that dry manure structures are
exempt - however, this exemption was eliminated by
2002 legislation & DNR rules have not been updated
SEPARATION DISTANCES
Road rights of way
100 feet from the right-of-way
Exemptions:
Small animal feeding operations (500 or
less animal units)
Waiver from state or county
DNR rules state that there is an exemption if
trees are planted between the structure and
the road right of way – however, this
exemption was eliminated by the 2002
legislation and DNR rules have not been
updated
SEPARATION DISTANCES
Water bodies – rivers, creeks, wells, etc.
1,000 feet - Ag drainage wells, sinkholes, navigable
waters (major water sources -- rivers, etc. from list in
DNR rules – new list goes into effect on 4/16/06)
500 feet - Surface inlets to ag drainage wells & water
sources (creeks,etc.)
2,500 feet - Designated wetlands (designated as
protected by U.S. Dept. of Interior or DNR; and owned
and managed by the U.S. government or DNR
Wells – formed manure storage
200 feet from a shallow well
100 feet from a deep well
Can request variance from DNR
SEPARATION DISTANCES
Water bodies – rivers, creeks, wetlands, etc.
Distances for water sources, major water sources or
designated wetlands do not apply to:
Farm ponds – defined as body of water:
Wholly on the lands of a single owner, or group
of joint owners
No connection to public waters
Less than 10 surface acres
Privately owned lakes – defined as any lake:
Not subject to federal control covering navigation
Owned by an individual, group of individuals, or
a nonprofit corporation
Which is not open to the use of the general
public but is used exclusively by the owners and
their personal guests.
SEPARATION DISTANCES
Water bodies – rivers, creeks, wetlands, etc.
Distances for water sources, major water sources or
designated wetlands do not apply to:
CFO structures using secondary containment
barriers
DNR rules:
Structure surrounding or downslope
Contain 120% of manure stored above grade
Can be concrete and/or earth
Cannot have a relief outlet or valve
Earthen barriers must meet percolation &
design standards
SEPARATION DISTANCES
Water bodies – rivers, creeks, wetlands, etc.
Distances for water sources, major water sources or
designated wetlands do not apply to:
CFO structures using secondary containment
barriers
DNR policy – requirements in addition to rules:
Must submit site-specific plan with permit
app. or before populating if no permit
required
Liquid manure: barrier must be design by an
engineer or NRCS
Below grade storage:
Contain 50% of manure stored below
grade
Dry manure storage:
No on-site stockpiling outside of structure
Contain 10% of manure stored
Percolation & design standards do not
apply
COMPOSTING
Mortalities – New DNR rules
Detailed DNR rules regarding operation and siting-
DNR recommends that they be contacted before
operation begins
Mortalities may be composted off-site at another
livestock operation without a permit – no restriction on
distance and do not have to be from the same owner
or operator
12 inch bulking agent cover, 6-12 inches between
carcasses, and 12-24 inch base depending on size
and number of mortalities
Must be designed for avg. annual death loss
Application of compost to other than cropland needs
DNR approval – pasture?
MANURE APPLICATION
All livestock operations – no pollution
No manure app. within 200 feet of designated
area (800 feet if high quality water resource,
see DNR website for list) unless manure
injected or incorporated on same date or
perm. vegetation 50 ft. around water source &
no manure on 50 ft. area (does not apply to ag
drainage wells)
Designated areas are:
Creeks, rivers, lakes, & designated wetlands
Known sinkhole
Cistern, drinking water or abandoned well
Ag drainage well or surface inlet
Excludes lakes or ponds with no outlet and which
are entirely on one landowner’s land
MANURE APPLICATION
Confinement operations – liquid manure
Must be injected or incorporated in 24 hrs. if
applied within 750 ft. of residence, bus.,
church, school or public use area (250 ft. if use
low pressure spray irrigation - <25 psi, center
pivot < 9 ft. high)
Does not apply if waiver from owner of
residence, etc. or operation has less than 500
animal units capacity
Note: DNR considers incidental spillage (on
endrows, etc.) while injecting as surface
application
STOCKPILING MANURE
Open feedlot operations – 2006 Iowa legislation
Stockpile - store solids outside of a feedlot or structure
or area that drains to a feedlot or structure
Cannot stockpile:
Within 400 feet of a designated area or 800 feet of
a high-quality water resource
Within 200 feet of a surface tile inlet unless steps
taken to ensure runoff will not reach the tile inlet
In a grass waterway or where water pools
On more than 3% slopes unless measures to
contain runoff are implemented
Must remove and land apply solids within 6 months.
Federal EPA & DNR rules: CAFO’s cannot discharge
manure from production areas unless the discharge is
pursuant to an NPDES permit. Definition of production
area includes stockpiles
STOCKPILING MANURE
Confinement Operations
2006 Iowa legislation applies only to
open feedlot operations
DNR taking the position that any
stockpiling of manure from a
confinement operation with more than
1,000 animal units must have a total
containment barrier around the stockpile
– those with less than 1,000 a.u.’s will be
handled on a case-by-case basis
CAFO RULES
Discharge permit (NPDES)
Federal court ruled no discharge permit required if the
operation does not discharge
EPA revising rules following court’s ruling – EPA
extended deadlines for NPDES permits and nutrient
management plans to July 31, 2007
Nutrient management plan part of NPDES permit –
requirements in addition to MMP
DNR has withdrawn its proposed rules awaiting
guidance from federal EPA as a result of the federal
court decision
DNR rules not expected to require confinement
operations in Iowa to have an NPDES permit – unless
the operation has a spill – not clear if a permit can be
required even if there is an accidental spill
CAFO RULES
Discharge permit (NPDES)
DNR now considering discharge permits for
confinement operations which have an accidental
manure spill
DNR rule states that DNR may evaluate any animal
feeding operation to determine if:
Manure from the operation is being discharged into
a water of the state
Manure from the operation is causing or may
reasonably be expected to cause pollution of a
water of the state; or
Manure from the operation is causing or may
reasonably be expected to cause a violation of
state water quality standards
CAFO RULES
Discharge permit (NPDES)
If DNR determines any of these conditions exist, the
operation shall:
Apply for an operation permit upon written
notification from DNR. However, no operation with
less than 300 animal units (750 swine over 55
pounds) shall be required to apply for a permit
unless manure from the operation is discharged
into a water of the state through a man–made
manure drainage system or is discharged into a
water of the state which traverses the operation:
Institute necessary remedial actions to eliminate
the conditions upon written notification from the
department
AIR QUALITY
Dust – DNR rule
Must take reasonable precautions to prevent
particulate matter from becoming airborne “in
quantities sufficient to create a nuisance”
Exemptions:
Farming operations
Dust from ordinary travel on unpaved
roads
DNR interpretation: Dust from construction
activities on farm operations not eligible for the
farming operation exemption
AIR QUALITY
Federal air emissions & Iowa Odor Study
Sign up period for Air Emissions Consent Agreement
closed 8/12/05 – EPA currently sending letters of
acceptance and payment
For farms that commence operation or expand after
the signup deadline, producer may consider taking
steps to comply with federal air emissions laws
If an operation will emit more than 100# of
ammonia or hydrogen sulfide in a 24 hour period,
an operator must file CERCLA and EPCRA reports
after the operation begins
DNR Iowa Odor Study
1,708 readings over 3 years taken on-site, during
manure application, and at residences, etc.
1 exceedance of 7:1 level at “separated location”
Related docs
Get documents about "