							ID     Phase                                                  Task Name                                   Forecasted Start     Forecasted Finish    Actual Finish     Variance                                                Resource
  1             PUCT Filing & Notice of Intent to Opt in to CR’s to Allow for Testing                       11/17/2004 8:00        11/17/2004 8:00 11/17/2004 8:00 0 days        Sarah Fisher (NEC TDSP)
  2             Get Current CR Listing From AEP                                                             11/26/2004 8:00        11/26/2004 8:00 11/26/2004 8:00 0 days        Richard Byrne (AEP)
  3             Flight Test 0105 Registration Deadline                                                       12/8/2004 8:00         12/8/2004 8:00   12/8/2004 8:00 0 days
  4             PUCT Territory Filing                                                                          1/7/2005 8:00          1/7/2005 8:00    1/7/2005 8:00 0 days      Jo Campbell
  5             Restate Comp Meter Decision ( will not offer Competitive Metering)                           1/17/2005 8:00         1/17/2005 8:00   1/17/2005 8:00 0 days       Sarah Fisher (NEC TDSP)
  6             Get Current ESI ID listing from AEP                                                          1/28/2005 8:00        1/28/2005 17:00 1/28/2005 17:00 0 days        Richard Byrne (AEP)
  7             AEP Forwards ESI Substation Information                                                      2/3/2005 17:00        2/11/2005 17:00 2/11/2005 17:00 0 days        Richard Byrne (AEP)
  8             AEP Forwards ESI Feeder and Meter Information                                                2/14/2005 8:00        2/14/2005 17:00 2/14/2005 17:00 0 days        Richard Byrne (AEP)
  9             General Full Choice Transition Plan                                                          2/7/2005 17:00         2/7/2005 17:00   2/7/2005 17:00 0 days       Richard Byrne (AEP)
 10             NEC TDSP Assigns ESI IDs                                                                     2/18/2005 8:00        2/18/2005 17:00 2/18/2005 17:00 0 days        Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 11             NEC sends Xref ESI ID list to ERCOT                                                          3/10/2005 8:00        3/10/2005 17:00 3/10/2005 17:00 0 days        Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 12             Submit Detailed Transition Dates to ERCOT, AEP TCC, PUCT, REPs                                 3/1/2005 8:00          3/1/2005 8:00    3/1/2005 8:00 0 days      John Sims (NEC TDSP)[20%],Avan Irani (NEC TDSP)[40%],Warren Hoelscher (NEC TDSP)[40%]
 13             AEP Forwards 14 Month Meter Data Set for Profile ID Validation                               3/11/2005 8:00         3/11/2005 8:00   3/11/2005 8:00 0 days       Richard Byrne (AEP)
 14             Code of Conduct Filing (1st filing submitted will review for revisions)                      3/11/2005 8:00         3/11/2005 8:00   3/11/2005 8:00 0 days       Sarah Fisher (NEC TDSP)
 15             NEC Submit 14 Month Meter Data to ERCOT for Profile ID Validation                            3/16/2005 8:00         3/16/2005 8:00   3/16/2005 8:00 0 days       Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 16             Retail Market Test 0105                                                                     12/15/2004 8:00        3/18/2005 17:00 3/18/2005 17:00 0 days
 17             CRs Setup Prod Conn w/ NEC TDSP                                                              3/21/2005 8:00         3/21/2005 8:00   3/21/2005 8:00 0 days       Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 18             NEC/REP Billing issues Meeting                                                               4/8/2005 17:00         4/8/2005 17:00   4/8/2005 17:00 0 days       Eloise Flores
 19             Submit Approved Profile IDs to ERCOT (90 Days Prior)                                        4/13/2005 17:00        4/13/2005 17:00 4/13/2005 17:00 0 days        Eloise Flores (NEC TDSP)
 20             NEC Code of Conduct Meeting                                                                 4/15/2005 17:00        4/15/2005 17:00 4/15/2005 17:00 0 days        Sarah Fisher
 21             NEC/REP Customer Communications                                                             4/21/2005 17:00        4/21/2005 17:00 4/21/2005 17:00 0 days        Sarah Fisher
 22             ERCOT to send current impacted CR listing to NEC for use in transition letter input          5/16/2005 8:00        5/16/2005 17:00 5/16/2005 17:00 0 days
 23             DLF Methodology Submitted to ERCOT for Approval (60 days Prior)                             6/16/2005 17:00        6/16/2005 17:00 6/16/2005 17:00 0 days        Frank Wilson (NEC TDSP)
 24             Send 814_20s to create ESI IDs (60 Days Prior)                                               6/20/2005 8:00        6/20/2005 17:00 6/20/2005 17:00 0 days        Eloise Flores (NEC TDSP)
 25             Notify NEC certified CRs of new ESI IDs                                                     11/23/2004 8:00        2/14/2005 17:00 2/14/2005 17:00 0 days        Sarah Fisher (NEC TDSP)
 26             Begin Billing for System Benefit Fund                                                        8/16/2005 8:00        8/16/2005 17:00 8/16/2005 17:00 0 days        Linda Johnson (NEC TDSP)
 27             STEC Submits Revised NOIE Meter Points Form                                                 5/16/2006 17:00        5/16/2006 17:00 5/16/2006 17:00 0 days
 28             Submit Name Change NCI to ERCOT (at completion of transition)                                5/1/2006 17:00         5/1/2006 17:00   5/1/2006 17:00 0 days
 29             Retail Market Test 0705                                                                        6/8/2005 8:00        8/9/2005 17:00   8/9/2005 17:00 0 days
 30             Retail Market Test 1005                                                                      9/21/2005 8:00       12/16/2005 17:00 12/16/2005 17:00 0 days
 31             Retail Market Test 0106                                                                     12/14/2005 8:00       12/14/2005 17:00 12/14/2005 17:00 0 days
 32             Retail Market Test 0406                                                                      3/15/2006 8:00        3/15/2006 17:00 3/15/2006 17:00 0 days
 33             PUCT Territory Filing Approved                                                               6/16/2005 8:00        6/16/2005 17:00 6/16/2005 17:00 0 days
 34             Transition Period                                                                           6/20/2005 17:00        5/19/2006 17:00 5/19/2006 17:00 0 days
 35             Phase 1 Transition Period Tasks (2190 ESI IDs)                                              6/20/2005 17:00        8/22/2005 17:00 8/22/2005 17:00 0 days
 36   Phase 1   NEC Request Current CRs Forwards ESI Billing Phase 1 ESI IDs (60 days prior)                6/20/2005 17:00        6/20/2005 17:00 6/20/2005 17:00 0 days        Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 37   Phase 1   NEC Request Current CRs Forwards ESI Billing Phase 2 ESI IDs (60 days prior)                6/24/2005 17:00        6/24/2005 17:00 6/24/2005 17:00 0 days        Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 38   Phase 1   NEC notifies PUCT of nonresponsive CRs on phase 1 billing request                            7/4/2005 17:00         7/4/2005 17:00   7/4/2005 17:00 0 days       Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 39   Phase 1   Current CRs Forward Phase 1 ESI ID Billing Information                                       7/1/2005 17:00         7/1/2005 17:00   7/1/2005 17:00 0 days       Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 40   Phase 1   ERCOT pull ROR on transition period 1 ESI IDs                                               7/13/2005 17:00        7/13/2005 17:00 7/13/2005 17:00 0 days        Mike Davis (ERCOT)
 41   Phase 1   NEC mail transition letter/welcome kit (30 days prior)                                      7/18/2005 17:00        7/18/2005 17:00 7/18/2005 17:00 0 days        Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 42   Phase 1   Receive recent 1 month meter data from AEP for Phase 1 AEP ESI IDs                           7/15/2005 8:00         7/15/2005 8:00   7/15/2005 8:00 0 days       Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 43   Phase 1   Notify ROR for AEP ESI IDs of New ESI ID                                                    7/15/2005 17:00        7/15/2005 17:00 7/15/2005 17:00 0 days        Mike Davis (ERCOT)
 44   Phase 1   NEC TDSP sends NEC RD AREP data file                                                         7/28/2005 8:00         7/28/2005 8:00   7/28/2005 8:00 0 days       Eloise Flores (NEC TDSP)
 45   Phase 1   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                               7/18/2005 17:00        7/18/2005 17:00 7/18/2005 17:00 0 days        Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 46   Phase 1   Current CRs Forward Phase 2 ESI ID Billing Information                                       7/7/2005 17:00         7/7/2005 17:00   7/7/2005 17:00 0 days       Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 47   Phase 1   NEC notifies PUCT of nonresponsive CRs on phase 2 billing request                            7/8/2005 17:00         7/8/2005 17:00   7/8/2005 17:00 0 days       Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 48   Phase 1   Eligibility Date                                                                               8/1/2005 8:00          8/1/2005 8:00    8/1/2005 8:00 0 days
 49   Phase 1   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                       8/1/2005 17:00         8/1/2005 17:00   8/1/2005 17:00 0 days       Eloise Flores (NEC TDSP),Sarah Fisher (NEC TDSP),Mike Davis (ERCOT)
 50   Phase 1   Current CR for Phase 1 AEP ESI IDs Submits 814_24 on old ESI ID                              8/1/2005 17:00         8/1/2005 17:00   8/1/2005 17:00 0 days       Sarah Fisher,Richard Byrne (AEP)
 51   Phase 1   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                   8/5/2005 17:00         8/5/2005 17:00   8/5/2005 17:00 0 days       Eloise Flores (NEC TDSP)
 52   Phase 1   NEC TDSP submit unassigned ESI IDs to NEC RD                                                   8/8/2005 8:00          8/8/2005 8:00    8/8/2005 8:00 0 days      Eloise Flores (NEC TDSP)
 53   Phase 1   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                    8/8/2005 17:00         8/8/2005 17:00   8/8/2005 17:00 0 days       Wendy Ohrt (NEC RD)
 54   Phase 1   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs      8/17/2005 8:00         8/17/2005 8:00   8/17/2005 8:00 0 days       Wendy Ohrt (NEC RD)
 55   Phase 1   Enter Competition                                                                            8/18/2005 8:00         8/18/2005 8:00   8/18/2005 8:00 0 days
 56   Phase 1   AEP TDSP final read old AEP ESI IDs                                                          8/18/2005 8:00         8/18/2005 8:00   8/18/2005 8:00 0 days       Richard Byrne (AEP)
 57   Phase 1   NEC TDSP Reads new NEC ESI IDs                                                               8/18/2005 8:00         8/18/2005 8:00   8/18/2005 8:00 0 days       Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
 58   Phase 1   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        8/22/2005 17:00    8/22/2005 17:00    8/22/2005 17:00    0 days   Richard Byrne (AEP)
 59             Phase 2 Transition Period Tasks                                                            7/20/2005 8:00    8/26/2005 17:00    8/26/2005 17:00    0 days
 60   Phase 2   ERCOT pull ROR on transition period 2 ESI IDs                                              7/20/2005 8:00     7/20/2005 8:00     7/20/2005 8:00    0 days   Mike Davis (ERCOT)
 61   Phase 2   NEC mail transition letter/welcome kit (30 days prior)                                    7/25/2005 17:00    7/25/2005 17:00    7/25/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 62   Phase 2   Receive recent 1 month meter data from AEP for Phase 2 AEP ESI IDs                        7/22/2005 17:00    7/22/2005 17:00    7/22/2005 17:00    0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 63   Phase 2   Notify ROR for AEP ESI IDs of New ESI ID                                                  7/22/2005 17:00    7/22/2005 17:00    7/22/2005 17:00    0 days   Mike Davis (ERCOT)
 64   Phase 2   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             7/25/2005 17:00    7/25/2005 17:00    7/25/2005 17:00    0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 65   Phase 2   NEC Request Current CRs Forwards ESI Billing Phase 3 ESI IDs (60 days prior)               7/29/2005 0:00     7/29/2005 0:00     7/29/2005 0:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 66   Phase 2   NEC TDSP sends NEC RD AREP data file                                                         8/5/2005 8:00      8/5/2005 8:00      8/5/2005 8:00   0 days   Eloise Flores (NEC TDSP)
 67   Phase 2   Current CRs Forward Phase 3 ESI ID Billing Information                                    8/11/2005 17:00    8/11/2005 17:00    8/11/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 68   Phase 2   NEC notifies PUCT of nonresponsive CRs on phase 3 billing request                         8/12/2005 17:00    8/12/2005 17:00    8/12/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 69   Phase 2   Eligibility Date                                                                             8/8/2005 8:00      8/8/2005 8:00      8/8/2005 8:00   0 days
 70   Phase 2   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                       8/8/2005 0:00      8/8/2005 0:00      8/8/2005 0:00   0 days   Mike Davis (ERCOT),Eloise Flores (NEC TDSP),Sarah Fisher (NEC TDSP)
 71   Phase 2   Current CR for Phase 2 AEP ESI IDs Submits 814_24 on old ESI ID                              8/8/2005 0:00      8/8/2005 0:00      8/8/2005 0:00   0 days   Sarah Fisher,Richard Byrne (AEP)
 72   Phase 2   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  8/16/2005 0:00     8/16/2005 0:00     8/16/2005 0:00    0 days   Wendy Ohrt (NEC RD)
 73   Phase 2   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    8/23/2005 8:00     8/23/2005 8:00     8/23/2005 8:00    0 days   Wendy Ohrt (NEC RD)
 74   Phase 2   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 8/12/2005 8:00     8/12/2005 8:00     8/12/2005 8:00    0 days   Eloise Flores (NEC TDSP)
 75   Phase 2   NEC TDSP submit unassigned ESI IDs to NEC RD                                               8/15/2005 8:00     8/15/2005 8:00     8/15/2005 8:00    0 days   Eloise Flores (NEC TDSP)
 76   Phase 2   Enter Competition                                                                          8/24/2005 8:00     8/24/2005 8:00     8/24/2005 8:00    0 days
 77   Phase 2   AEP TDSP final read old AEP ESI IDs                                                       8/24/2005 17:00    8/24/2005 17:00    8/24/2005 17:00    0 days   Richard Byrne (AEP)
 78   Phase 2   NEC TDSP Reads new NEC ESI IDs                                                             8/24/2005 8:00     8/24/2005 8:00     8/24/2005 8:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
 79   Phase 2   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        8/26/2005 17:00    8/26/2005 17:00    8/26/2005 17:00    0 days   Richard Byrne (AEP)
 80             Phase 3 Transition Period Tasks                                                           7/29/2005 17:00     10/7/2005 0:00     10/7/2005 0:00    0 days
 81   Phase 3   NEC Request Current CRs Forwards ESI Billing Phase 4 ESI IDs (60 days prior)              7/29/2005 17:00    7/29/2005 17:00    7/29/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 82   Phase 3   Current CRs Forward Phase 4 ESI ID Billing Information                                    8/11/2005 17:00    8/11/2005 17:00    8/11/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 83   Phase 3   ERCOT pull ROR on transition period 3 ESI IDs                                             8/26/2005 17:00    8/26/2005 17:00    8/26/2005 17:00    0 days   Mike Davis (ERCOT)
 84   Phase 3   NEC mail transition letter/welcome kit (30 days prior)                                    8/29/2005 17:00    8/29/2005 17:00    8/29/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 85   Phase 3   Receive recent 1 month meter data from AEP for Phase 3 AEP ESI IDs                        8/30/2005 17:00    8/30/2005 17:00    8/30/2005 17:00    0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 86   Phase 3   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                              9/1/2005 17:00     9/1/2005 17:00     9/1/2005 17:00    0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC)
 87   Phase 3   Notify ROR for AEP ESI IDs of New ESI ID                                                   9/5/2005 17:00     9/5/2005 17:00     9/5/2005 17:00    0 days   Mike Davis (ERCOT)
 88   Phase 3   NEC TDSP sends NEC RD AREP data file                                                         9/9/2005 8:00      9/9/2005 8:00      9/9/2005 8:00   0 days   Eloise Flores (NEC TDSP)
 89   Phase 3   NEC notifies PUCT of nonresponsive CRs on phase 4 billing request                         8/12/2005 17:00    8/12/2005 17:00    8/12/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
 90   Phase 3   Eligibility Date                                                                           9/15/2005 0:00     9/15/2005 0:00     9/15/2005 0:00    0 days
 91   Phase 3   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     9/15/2005 0:00     9/15/2005 0:00     9/15/2005 0:00    0 days   Eloise Flores (NEC TDSP),Sarah Fisher (NEC TDSP),Mike Davis (ERCOT)
 92   Phase 3   Current CR for Phase 3 AEP ESI IDs Submits 814_24 on old ESI ID                            9/15/2005 0:00     9/15/2005 0:00     9/15/2005 0:00    0 days   Sarah Fisher,Richard Byrne (AEP)
 93   Phase 3   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 9/22/2005 8:00     9/22/2005 8:00     9/22/2005 8:00    0 days   Eloise Flores (NEC TDSP)
 94   Phase 3   NEC TDSP submit unassigned ESI IDs to NEC RD                                               9/23/2005 8:00     9/23/2005 8:00     9/23/2005 8:00    0 days   Eloise Flores (NEC TDSP)
 95   Phase 3   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  9/26/2005 0:00     9/26/2005 0:00     9/26/2005 0:00    0 days   Wendy Ohrt (NEC RD)
 96   Phase 3   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    9/29/2005 8:00     9/29/2005 8:00     9/29/2005 8:00    0 days   Wendy Ohrt (NEC RD)
 97   Phase 3   Enter Competition                                                                         9/27/2005 17:00    9/27/2005 17:00    9/27/2005 17:00    0 days
 98   Phase 3   AEP TDSP final read old AEP ESI IDs                                                       9/27/2005 17:00    9/27/2005 17:00    9/27/2005 17:00    0 days   Richard Byrne (AEP)
 99   Phase 3   NEC TDSP Reads new NEC ESI IDs                                                            9/27/2005 17:00    9/27/2005 17:00    9/27/2005 17:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
100   Phase 3   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                         10/7/2005 0:00     10/7/2005 0:00     10/7/2005 0:00    0 days   Richard Byrne (AEP)
101             Phase 4 Transition Period Tasks                                                           8/26/2005 17:00     10/7/2005 0:00     10/7/2005 0:00    0 days
102   Phase 4   ERCOT pull ROR on transition period 4 ESI IDs                                             8/26/2005 17:00    8/26/2005 17:00    8/26/2005 17:00    0 days   Mike Davis (ERCOT)
103   Phase 4   NEC mail transition letter/welcome kit (30 days prior)                                    8/29/2005 17:00    8/29/2005 17:00    8/29/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
104   Phase 4   Receive recent 1 month meter data from AEP for Phase 4 AEP ESI IDs                        8/30/2005 17:00    8/30/2005 17:00    8/30/2005 17:00    0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC)
105   Phase 4   Notify ROR for AEP ESI IDs of New ESI ID                                                  8/29/2005 17:00    8/29/2005 17:00    8/29/2005 17:00    0 days   Mike Davis (ERCOT)
106   Phase 4   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                              9/1/2005 17:00     9/1/2005 17:00     9/1/2005 17:00    0 days   Eloise Flores (NEC TDSP)
107   Phase 4   NEC Request Current CRs Forwards ESI Billing Phase 5 ESI IDs (60 days prior)               9/2/2005 17:00     9/2/2005 17:00     9/2/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
108   Phase 4   Current CRs Forward Phase 5 ESI ID Billing Information                                    9/15/2005 17:00    9/15/2005 17:00    9/15/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
109   Phase 4   NEC notifies PUCT of nonresponsive CRs on phase 5 billing request                         9/16/2005 17:00    9/16/2005 17:00    9/16/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
110   Phase 4   NEC TDSP sends NEC RD AREP data file                                                       9/15/2005 0:00     9/15/2005 0:00     9/15/2005 0:00    0 days   Eloise Flores (NEC TDSP)
111   Phase 4   Eligibility Date                                                                          9/15/2005 17:00    9/15/2005 17:00    9/15/2005 17:00    0 days
112   Phase 4   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    9/15/2005 17:00    9/15/2005 17:00    9/15/2005 17:00    0 days   Eloise Flores (NEC TDSP),Sarah Fisher (NEC TDSP),Mike Davis (ERCOT)
113   Phase 4   Current CR for Phase 4 AEP ESI IDs Submits 814_24 on old ESI ID                           9/15/2005 17:00    9/15/2005 17:00    9/15/2005 17:00    0 days   Sarah Fisher,Richard Byrne (AEP)
114   Phase 4   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 9/22/2005 8:00     9/22/2005 8:00     9/22/2005 8:00    0 days   Eloise Flores (NEC TDSP)
115   Phase 4   NEC TDSP submit unassigned ESI IDs to NEC RD                                               9/23/2005 8:00     9/23/2005 8:00     9/23/2005 8:00    0 days   Eloise Flores (NEC TDSP)
116   Phase 4   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  9/26/2005 17:00    9/26/2005 17:00    9/26/2005 17:00   0 days   Wendy Ohrt (NEC RD)
117   Phase 4   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs     9/29/2005 8:00     9/29/2005 8:00     9/29/2005 8:00   0 days   Wendy Ohrt (NEC RD)
118   Phase 4   Enter Competition                                                                          9/29/2005 17:00    9/29/2005 17:00    9/29/2005 17:00   0 days
119   Phase 4   AEP TDSP final read old AEP ESI IDs                                                        9/29/2005 17:00    9/29/2005 17:00    9/29/2005 17:00   0 days   Richard Byrne (AEP)
120   Phase 4   NEC TDSP Reads new NEC ESI IDs                                                             9/29/2005 17:00    9/29/2005 17:00    9/29/2005 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
121   Phase 4   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                          10/7/2005 0:00     10/7/2005 0:00     10/7/2005 0:00   0 days   Richard Byrne (AEP)
122             Phase 5 Transition Period Tasks                                                             10/7/2005 8:00   11/22/2005 17:00   11/22/2005 17:00   0 days
123   Phase 5   NEC/AEP provide final Phase 5 ESI ID listing for ROR pull                                   10/7/2005 8:00     10/7/2005 8:00     10/7/2005 8:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
124   Phase 5   ERCOT pull ROR on transition period 5 ESI IDs                                             10/12/2005 17:00   10/12/2005 17:00   10/12/2005 17:00   0 days   Mike Davis (ERCOT)
125   Phase 5   Notify ROR for AEP ESI IDs of New ESI ID                                                  10/14/2005 17:00   10/14/2005 17:00   10/14/2005 17:00   0 days   Mike Davis (ERCOT)
126   Phase 5   NEC mail transition letter/welcome kit (30 days prior)                                    10/14/2005 17:00   10/14/2005 17:00   10/14/2005 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
127   Phase 5   NEC receive recent 1 month meter data from AEP for Phase 5 AEP ESI IDs                    10/14/2005 17:00   10/14/2005 17:00   10/14/2005 17:00   0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC),David Lowder (NEC TDSP)
128   Phase 5   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             10/17/2005 17:00   10/17/2005 17:00   10/17/2005 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
129   Phase 5   NEC Request Current CRs Forward remaining Phase 5 ESI Billing ESI IDs (30 days prior)      10/14/2005 0:00    10/14/2005 0:00    10/14/2005 0:00   0 days   Sarah Fisher (NEC TDSP)
130   Phase 5   Current CRs Forward Phase 5 ESI ID Billing Information                                    10/24/2005 17:00   10/24/2005 17:00   10/24/2005 17:00   0 days   Sarah Fisher (NEC TDSP)
131   Phase 5   NEC notifies PUCT of nonresponsive CRs on phase 5 billing request                         10/25/2005 17:00   10/25/2005 17:00   10/25/2005 17:00   0 days   Sarah Fisher (NEC TDSP)
132   Phase 5   NEC TDSP sends NEC RD AREP data file                                                      10/28/2005 17:00   10/28/2005 17:00   10/28/2005 17:00   0 days   David Lowder (NEC TDSP),Eloise Flores (NEC TDSP)
133   Phase 5   Eligibility Date                                                                          10/31/2005 17:00   10/31/2005 17:00   10/31/2005 17:00   0 days
134   Phase 5   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    10/31/2005 17:00   10/31/2005 17:00   10/31/2005 17:00   0 days   Eloise Flores (NEC TDSP)
135   Phase 5   Current CR for Phase 5 AEP ESI IDs Submits 814_24 on old ESI ID                           10/31/2005 17:00   10/31/2005 17:00   10/31/2005 17:00   0 days   Richard Byrne (AEP),Jane Eyanson (AEP)
136   Phase 5   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 11/8/2005 17:00    11/8/2005 17:00    11/8/2005 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
137   Phase 5   NEC TDSP submit unassigned ESI IDs to NEC RD                                               11/9/2005 17:00    11/9/2005 17:00    11/9/2005 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
138   Phase 5   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                 11/10/2005 17:00   11/10/2005 17:00   11/10/2005 17:00   0 days   Wendy Ohrt (NEC RD)
139   Phase 5   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   11/15/2005 17:00   11/15/2005 17:00   11/15/2005 17:00   0 days   Wendy Ohrt (NEC RD)
140   Phase 5   Enter Competition                                                                         11/16/2005 17:00   11/16/2005 17:00   11/16/2005 17:00   0 days
141   Phase 5   AEP TDSP final read old AEP ESI IDs                                                       11/16/2005 17:00   11/16/2005 17:00   11/16/2005 17:00   0 days   Richard Byrne (AEP)
142   Phase 5   NEC TDSP Reads new NEC ESI IDs                                                            11/16/2005 17:00   11/16/2005 17:00   11/16/2005 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
143   Phase 5   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        11/22/2005 17:00   11/22/2005 17:00   11/22/2005 17:00   0 days   Richard Byrne (AEP)
144             Phase 6 Transition Period Tasks                                                           10/28/2005 17:00    12/9/2005 17:00    12/9/2005 17:00   0 days
145   Phase 6   NEC/AEP provide final Phase 6 ESI ID listing for ROR pull                                 10/28/2005 17:00   10/28/2005 17:00   10/28/2005 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
146   Phase 6   ERCOT pull ROR on transition period 6 ESI IDs                                             10/31/2005 17:00   10/31/2005 17:00   10/31/2005 17:00   0 days   Mike Davis (ERCOT)
147   Phase 6   Notify ROR for AEP ESI IDs of New ESI ID                                                    11/4/2005 0:00     11/4/2005 0:00     11/4/2005 0:00   0 days   Mike Davis (ERCOT)
148   Phase 6   NEC mail transition letter/welcome kit (30 days prior)                                      11/4/2005 0:00     11/4/2005 0:00     11/4/2005 0:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
149   Phase 6   NEC receive recent 1 month meter data from AEP for Phase 6 AEP ESI IDs                      11/3/2005 0:00     11/3/2005 0:00     11/3/2005 0:00   0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC),David Lowder (NEC TDSP)
150   Phase 6   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                               11/4/2005 0:00     11/4/2005 0:00     11/4/2005 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
151   Phase 6   NEC Request Current CRs Forward remaining Phase 6 ESI Billing ESI IDs (30 days prior)      11/7/2005 17:00    11/7/2005 17:00    11/7/2005 17:00   0 days   Sarah Fisher (NEC TDSP)
152   Phase 6   Current CRs Forward Phase 6 ESI ID Billing Information                                     11/17/2005 0:00    11/17/2005 0:00    11/17/2005 0:00   0 days   Sarah Fisher (NEC TDSP)
153   Phase 6   NEC notifies PUCT of nonresponsive CRs on phase 6 billing request                         11/18/2005 17:00   11/18/2005 17:00   11/18/2005 17:00   0 days   Sarah Fisher (NEC TDSP)
154   Phase 6   NEC TDSP sends NEC RD AREP data file                                                       11/18/2005 0:00    11/18/2005 0:00    11/18/2005 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
155   Phase 6   Eligibility Date                                                                           11/21/2005 0:00    11/21/2005 0:00    11/21/2005 0:00   0 days
156   Phase 6   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     11/21/2005 0:00    11/21/2005 0:00    11/21/2005 0:00   0 days   Eloise Flores (NEC TDSP)
157   Phase 6   Current CR for Phase 6 AEP ESI IDs Submits 814_24 on old ESI ID                            11/21/2005 0:00    11/21/2005 0:00    11/21/2005 0:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
158   Phase 6   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 11/28/2005 0:00    11/28/2005 0:00    11/28/2005 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
159   Phase 6   NEC TDSP submit unassigned ESI IDs to NEC RD                                               11/29/2005 0:00    11/29/2005 0:00    11/29/2005 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
160   Phase 6   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  11/30/2005 0:00    11/30/2005 0:00    11/30/2005 0:00   0 days   Wendy Ohrt (NEC RD)
161   Phase 6   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs     12/5/2005 0:00     12/5/2005 0:00     12/5/2005 0:00   0 days   Wendy Ohrt (NEC RD)
162   Phase 6   Enter Competition                                                                           12/6/2005 0:00     12/6/2005 0:00     12/6/2005 0:00   0 days
163   Phase 6   AEP TDSP final read old AEP ESI IDs                                                         12/6/2005 0:00     12/6/2005 0:00     12/6/2005 0:00   0 days   Richard Byrne (AEP)
164   Phase 6   NEC TDSP Reads new NEC ESI IDs                                                              12/6/2005 0:00     12/6/2005 0:00     12/6/2005 0:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
165   Phase 6   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                         12/9/2005 17:00    12/9/2005 17:00    12/9/2005 17:00   0 days   Richard Byrne (AEP)
166             Phase 7 Transition Period Tasks                                                           10/28/2005 17:00     12/7/2005 0:00     12/7/2005 0:00   0 days
167   Phase 7   NEC/AEP provide final Phase 7 ESI ID listing for ROR pull                                 10/28/2005 17:00   10/28/2005 17:00   10/28/2005 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
168   Phase 7   ERCOT pull ROR on transition period 7 ESI IDs                                             10/31/2005 17:00   10/31/2005 17:00   10/31/2005 17:00   0 days   Mike Davis (ERCOT)
169   Phase 7   Notify ROR for AEP ESI IDs of New ESI ID                                                    11/4/2005 0:00     11/4/2005 0:00     11/4/2005 0:00   0 days   Mike Davis (ERCOT)
170   Phase 7   NEC mail transition letter/welcome kit (30 days prior)                                      11/4/2005 0:00     11/4/2005 0:00     11/4/2005 0:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
171   Phase 7   NEC receive recent 1 month meter data from AEP for Phase 7 AEP ESI IDs                      11/3/2005 0:00     11/3/2005 0:00     11/3/2005 0:00   0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC),David Lowder (NEC TDSP)
172   Phase 7   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                               11/4/2005 0:00     11/4/2005 0:00     11/4/2005 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
173   Phase 7   NEC Request Current CRs Forward remaining Phase 7 ESI Billing ESI IDs (30 days prior)      11/7/2005 17:00    11/7/2005 17:00    11/7/2005 17:00   0 days   Sarah Fisher (NEC TDSP)
174   Phase 7   Current CRs Forward Phase 7 ESI ID Billing Information                                     11/17/2005 0:00     11/17/2005 0:00     11/17/2005 0:00    0 days   Sarah Fisher (NEC TDSP)
175   Phase 7   NEC notifies PUCT of nonresponsive CRs on phase 7 billing request                         11/18/2005 17:00    11/18/2005 17:00    11/18/2005 17:00    0 days   Sarah Fisher (NEC TDSP)
176   Phase 7   NEC TDSP sends NEC RD AREP data file                                                       11/18/2005 0:00     11/18/2005 0:00     11/18/2005 0:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
177   Phase 7   Eligibility Date                                                                           11/21/2005 0:00     11/21/2005 0:00     11/21/2005 0:00    0 days
178   Phase 7   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     11/21/2005 0:00     11/21/2005 0:00     11/21/2005 0:00    0 days   Eloise Flores (NEC TDSP)
179   Phase 7   Current CR for Phase 7 AEP ESI IDs Submits 814_24 on old ESI ID                            11/21/2005 0:00     11/21/2005 0:00     11/21/2005 0:00    0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
180   Phase 7   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 11/28/2005 0:00     11/28/2005 0:00     11/28/2005 0:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
181   Phase 7   NEC TDSP submit unassigned ESI IDs to NEC RD                                               11/29/2005 0:00     11/29/2005 0:00     11/29/2005 0:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
182   Phase 7   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  11/30/2005 0:00     11/30/2005 0:00     11/30/2005 0:00    0 days   Wendy Ohrt (NEC RD)
183   Phase 7   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs     12/5/2005 0:00      12/5/2005 0:00      12/5/2005 0:00    0 days   Wendy Ohrt (NEC RD)
184   Phase 7   Enter Competition                                                                           12/6/2005 0:00      12/6/2005 0:00      12/6/2005 0:00    0 days
185   Phase 7   AEP TDSP final read old AEP ESI IDs                                                         12/6/2005 0:00      12/6/2005 0:00      12/6/2005 0:00    0 days   Richard Byrne (AEP)
186   Phase 7   NEC TDSP Reads new NEC ESI IDs                                                              12/6/2005 0:00      12/6/2005 0:00      12/6/2005 0:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
187   Phase 7   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                          12/7/2005 0:00      12/7/2005 0:00      12/7/2005 0:00    0 days   Richard Byrne (AEP)
188             Phase 8 Transition Period Tasks                                                             12/2/2005 0:00      1/14/2006 0:00      1/14/2006 0:00    0 days
189   Phase 8   NEC/AEP provide final Phase 8 ESI ID listing for ROR pull                                   12/2/2005 0:00      12/2/2005 0:00      12/2/2005 0:00    0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
190   Phase 8   ERCOT pull ROR on transition period 8 ESI IDs                                               12/6/2005 0:00      12/6/2005 0:00      12/6/2005 0:00    0 days   Mike Davis (ERCOT)
191   Phase 8   Notify ROR for AEP ESI IDs of New ESI ID                                                    12/9/2005 0:00      12/9/2005 0:00      12/9/2005 0:00    0 days   Mike Davis (ERCOT)
192   Phase 8   NEC mail transition letter/welcome kit (30 days prior)                                      12/9/2005 0:00      12/9/2005 0:00      12/9/2005 0:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
193   Phase 8   NEC receive recent 1 month meter data from AEP for Phase 8 AEP ESI IDs                      12/9/2005 0:00      12/9/2005 0:00      12/9/2005 0:00    0 days   Eloise Flores (NEC TDSP),Leo Kalips (NISC),David Lowder (NEC TDSP)
194   Phase 8   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                              12/12/2005 0:00     12/12/2005 0:00     12/12/2005 0:00    0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
195   Phase 8   NEC Request Current CRs Forward remaining Phase 8 ESI Billing ESI IDs (30 days prior)       12/9/2005 0:00      12/9/2005 0:00      12/9/2005 0:00    0 days   Sarah Fisher (NEC TDSP)
196   Phase 8   Current CRs Forward Phase 8 ESI ID Billing Information                                     12/19/2005 0:00     12/19/2005 0:00     12/19/2005 0:00    0 days   Sarah Fisher (NEC TDSP)
197   Phase 8   NEC notifies PUCT of nonresponsive CRs on phase 8 billing request                          12/20/2005 0:00     12/20/2005 0:00     12/20/2005 0:00    0 days   Sarah Fisher (NEC TDSP)
198   Phase 8   NEC TDSP sends NEC RD AREP data file                                                       12/22/2005 0:00     12/22/2005 0:00     12/22/2005 0:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
199   Phase 8   Eligibility Date                                                                           12/27/2005 0:00     12/27/2005 0:00     12/27/2005 0:00    0 days
200   Phase 8   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     12/27/2005 0:00     12/27/2005 0:00     12/27/2005 0:00    0 days   Eloise Flores (NEC TDSP)
201   Phase 8   Current CR for Phase 8 AEP ESI IDs Submits 814_24 on old ESI ID                            12/27/2005 0:00     12/27/2005 0:00     12/27/2005 0:00    0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
202   Phase 8   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                    1/3/2006 0:00       1/3/2006 0:00       1/3/2006 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
203   Phase 8   NEC TDSP submit unassigned ESI IDs to NEC RD                                                  1/4/2006 0:00       1/4/2006 0:00       1/4/2006 0:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
204   Phase 8   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                     1/5/2006 0:00       1/5/2006 0:00       1/5/2006 0:00   0 days   Wendy Ohrt (NEC RD)
205   Phase 8   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs       1/9/2006 0:00       1/9/2006 0:00       1/9/2006 0:00   0 days   Wendy Ohrt (NEC RD)
206   Phase 8   Enter Competition                                                                           1/10/2006 0:00      1/10/2006 0:00      1/10/2006 0:00    0 days
207   Phase 8   AEP TDSP final read old AEP ESI IDs                                                         1/11/2006 0:00      1/11/2006 0:00      1/11/2006 0:00    0 days   Richard Byrne (AEP)
208   Phase 8   NEC TDSP Reads new NEC ESI IDs                                                              1/12/2006 0:00      1/12/2006 0:00      1/12/2006 0:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
209   Phase 8   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                          1/14/2006 0:00      1/14/2006 0:00      1/14/2006 0:00    0 days   Richard Byrne (AEP)
210             Phase 9 Transition Period Tasks                                                           12/19/2005 17:00      2/2/2006 17:00      2/2/2006 17:00    0 days
211   Phase 9   NEC/AEP provide final Phase 9 ESI ID listing for ROR pull                                 12/19/2005 17:00    12/19/2005 17:00    12/19/2005 17:00    0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
212   Phase 9   ERCOT pull ROR on transition period 9 ESI IDs                                             12/27/2005 17:00    12/27/2005 17:00    12/27/2005 17:00    0 days   Mike Davis (ERCOT)
213   Phase 9   Notify ROR for AEP ESI IDs of New ESI ID                                                  12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Mike Davis (ERCOT)
214   Phase 9   NEC mail transition letter/welcome kit (30 days prior)                                    12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
215   Phase 9   NEC receive recent 1 month meter data from AEP for Phase 9 AEP ESI IDs                    12/29/2005 17:00    12/29/2005 17:00    12/29/2005 17:00    0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
216   Phase 9   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
217   Phase 9   NEC Request Current CRs Forward remaining Phase 9 ESI Billing ESI IDs (30 days prior)     12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Sarah Fisher (NEC TDSP)
218   Phase 9   Current CRs Forward Phase 9 ESI ID Billing Information                                     1/11/2006 17:00     1/11/2006 17:00     1/11/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
219   Phase 9   NEC notifies PUCT of nonresponsive CRs on phase 9 billing request                          1/12/2006 17:00     1/12/2006 17:00     1/12/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
220   Phase 9   NEC TDSP sends NEC RD AREP data file                                                       1/12/2006 17:00     1/12/2006 17:00     1/12/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
221   Phase 9   Eligibility Date                                                                            1/16/2006 0:00     1/16/2006 17:00     1/16/2006 17:00    0 days
222   Phase 9   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     1/16/2006 17:00     1/16/2006 17:00     1/16/2006 17:00    0 days   Eloise Flores (NEC TDSP)
223   Phase 9   Current CR for Phase 9 AEP ESI IDs Submits 814_24 on old ESI ID                            1/16/2006 17:00     1/16/2006 17:00     1/16/2006 17:00    0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
224   Phase 9   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 1/23/2006 17:00     1/23/2006 17:00     1/23/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
225   Phase 9   NEC TDSP submit unassigned ESI IDs to NEC RD                                               1/24/2006 17:00     1/24/2006 17:00     1/24/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
226   Phase 9   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  1/24/2006 17:00     1/24/2006 17:00     1/24/2006 17:00    0 days   Wendy Ohrt (NEC RD)
227   Phase 9   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    1/30/2006 17:00     1/30/2006 17:00     1/30/2006 17:00    0 days   Wendy Ohrt (NEC RD)
228   Phase 9   Enter Competition                                                                          1/31/2006 17:00     1/31/2006 17:00     1/31/2006 17:00    0 days
229   Phase 9   AEP TDSP final read old AEP ESI IDs                                                        1/31/2006 17:00     1/31/2006 17:00     1/31/2006 17:00    0 days   Richard Byrne (AEP)
230   Phase 9   NEC TDSP Reads new NEC ESI IDs                                                             1/31/2006 17:00     1/31/2006 17:00     1/31/2006 17:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
231   Phase 9   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                          2/2/2006 17:00      2/2/2006 17:00      2/2/2006 17:00    0 days   Richard Byrne (AEP)
232              Phase 10 Transition Period Tasks                                                          12/19/2005 17:00      2/2/2006 17:00      2/2/2006 17:00    0 days
233   Phase 10   NEC/AEP provide final Phase 10 ESI ID listing for ROR pull                                12/19/2005 17:00    12/19/2005 17:00    12/19/2005 17:00    0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
234   Phase 10   ERCOT pull ROR on transition period 10 ESI IDs                                            12/27/2005 17:00    12/27/2005 17:00    12/27/2005 17:00    0 days   Mike Davis (ERCOT)
235   Phase 10   Notify ROR for AEP ESI IDs of New ESI ID                                                  12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Mike Davis (ERCOT)
236   Phase 10   NEC mail transition letter/welcome kit (30 days prior)                                    12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
237   Phase 10   NEC receive recent 1 month meter data from AEP for Phase 10 AEP ESI IDs                   12/29/2005 17:00    12/29/2005 17:00    12/29/2005 17:00    0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
238   Phase 10   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
239   Phase 10   NEC Request Current CRs Forward remaining Phase 10 ESI Billing ESI IDs (30 days prior)    12/30/2005 17:00    12/30/2005 17:00    12/30/2005 17:00    0 days   Sarah Fisher (NEC TDSP)
240   Phase 10   Current CRs Forward Phase 10 ESI ID Billing Information                                    1/11/2006 17:00     1/11/2006 17:00     1/11/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
241   Phase 10   NEC notifies PUCT of nonresponsive CRs on phase 10 billing request                         1/12/2006 17:00     1/12/2006 17:00     1/12/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
242   Phase 10   NEC TDSP sends NEC RD AREP data file                                                       1/23/2006 17:00     1/23/2006 17:00     1/23/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
243   Phase 10   Eligibility Date                                                                           1/23/2006 17:00     1/23/2006 17:00     1/23/2006 17:00    0 days
244   Phase 10   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     1/23/2006 17:00     1/23/2006 17:00     1/23/2006 17:00    0 days   Eloise Flores (NEC TDSP)
245   Phase 10   Current CR for Phase 10 AEP ESI IDs Submits 814_24 on old ESI ID                           1/23/2006 17:00     1/23/2006 17:00     1/23/2006 17:00    0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
246   Phase 10   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 1/31/2006 17:00     1/31/2006 17:00     1/31/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
247   Phase 10   NEC TDSP submit unassigned ESI IDs to NEC RD                                                2/1/2006 17:00      2/1/2006 17:00      2/1/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
248   Phase 10   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                     2/1/2006 0:00       2/1/2006 0:00       2/1/2006 0:00   0 days   Wendy Ohrt (NEC RD)
249   Phase 10   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs       2/6/2006 0:00     2/6/2006 17:00      2/6/2006 17:00    0 days   Wendy Ohrt (NEC RD)
250   Phase 10   Enter Competition                                                                           2/7/2006 17:00      2/7/2006 17:00      2/7/2006 17:00    0 days
251   Phase 10   AEP TDSP final read old AEP ESI IDs                                                         2/7/2006 17:00      2/7/2006 17:00      2/7/2006 17:00    0 days   Richard Byrne (AEP)
252   Phase 10   NEC TDSP Reads new NEC ESI IDs                                                              2/7/2006 17:00      2/7/2006 17:00      2/7/2006 17:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
253   Phase 10   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                          2/9/2006 17:00      2/9/2006 17:00      2/9/2006 17:00    0 days   Richard Byrne (AEP)
254              Phase 11 Transition Period Tasks                                                          12/19/2005 17:00      2/9/2006 17:00      2/9/2006 17:00    0 days
255   Phase 11   NEC/AEP provide final Phase 11 ESI ID listing for ROR pull                                12/19/2005 17:00    12/19/2005 17:00    12/19/2005 17:00    0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
256   Phase 11   ERCOT pull ROR on transition period 11 ESI IDs                                              1/2/2006 17:00      1/2/2006 17:00      1/2/2006 17:00    0 days   Mike Davis (ERCOT)
257   Phase 11   Notify ROR for AEP ESI IDs of New ESI ID                                                    1/5/2006 17:00      1/5/2006 17:00      1/5/2006 17:00    0 days   Mike Davis (ERCOT)
258   Phase 11   NEC mail transition letter/welcome kit (30 days prior)                                    12/30/2006 17:00    12/30/2006 17:00    12/30/2006 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
259   Phase 11   NEC receive recent 1 month meter data from AEP for Phase 11 AEP ESI IDs                     1/2/2006 17:00      1/2/2006 17:00      1/2/2006 17:00    0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
260   Phase 11   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                               1/5/2006 17:00      1/5/2006 17:00      1/5/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
261   Phase 11   NEC Request Current CRs Forward remaining Phase 11 ESI Billing ESI IDs (30 days prior)      1/5/2006 17:00      1/5/2006 17:00      1/5/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
262   Phase 11   Current CRs Forward Phase 11 ESI ID Billing Information                                    1/19/2006 17:00     1/19/2006 17:00     1/19/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
263   Phase 11   NEC notifies PUCT of nonresponsive CRs on phase 11 billing request                         1/20/2006 17:00     1/20/2006 17:00     1/20/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
264   Phase 11   NEC TDSP sends NEC RD AREP data file                                                       1/20/2006 17:00     1/20/2006 17:00     1/20/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
265   Phase 11   Eligibility Date                                                                            1/27/2006 0:00      1/27/2006 0:00      1/27/2006 0:00    0 days
266   Phase 11   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     1/27/2006 17:00     1/27/2006 17:00     1/27/2006 17:00    0 days   Eloise Flores (NEC TDSP)
267   Phase 11   Current CR for Phase 11 AEP ESI IDs Submits 814_24 on old ESI ID                           1/27/2006 17:00     1/27/2006 17:00     1/27/2006 17:00    0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
268   Phase 11   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                  2/3/2006 17:00      2/3/2006 17:00      2/3/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
269   Phase 11   NEC TDSP submit unassigned ESI IDs to NEC RD                                                2/6/2006 17:00      2/6/2006 17:00      2/6/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
270   Phase 11   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                   2/7/2006 17:00      2/7/2006 17:00      2/7/2006 17:00    0 days   Wendy Ohrt (NEC RD)
271   Phase 11   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    2/13/2006 17:00     2/13/2006 17:00     2/13/2006 17:00    0 days   Wendy Ohrt (NEC RD)
272   Phase 11   Enter Competition                                                                           2/14/2006 0:00      2/14/2006 0:00      2/14/2006 0:00    0 days
273   Phase 11   AEP TDSP final read old AEP ESI IDs                                                         2/14/2006 0:00      2/14/2006 0:00      2/14/2006 0:00    0 days   Richard Byrne (AEP)
274   Phase 11   NEC TDSP Reads new NEC ESI IDs                                                              2/14/2006 0:00      2/14/2006 0:00      2/14/2006 0:00    0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
275   Phase 11   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                          2/9/2006 17:00      2/9/2006 17:00      2/9/2006 17:00    0 days   Richard Byrne (AEP)
276              Phase 12 Transition Period Tasks                                                           1/13/2006 17:00      3/3/2006 17:00      3/3/2006 17:00    0 days
277   Phase 12   NEC/AEP provide final Phase 12 ESI ID listing for ROR pull                                 1/13/2006 17:00     1/13/2006 17:00     1/13/2006 17:00    0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
278   Phase 12   ERCOT pull ROR on transition period 12 ESI IDs                                             1/20/2006 17:00     1/20/2006 17:00     1/20/2006 17:00    0 days   Mike Davis (ERCOT)
279   Phase 12   Notify ROR for AEP ESI IDs of New ESI ID                                                   1/24/2006 17:00     1/24/2006 17:00     1/24/2006 17:00    0 days   Mike Davis (ERCOT)
280   Phase 12   NEC mail transition letter/welcome kit (30 days prior)                                     1/24/2006 17:00     1/24/2006 17:00     1/24/2006 17:00    0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
281   Phase 12   NEC receive recent 1 month meter data from AEP for Phase 12 AEP ESI IDs                    1/23/2006 17:00     1/23/2006 17:00     1/23/2006 17:00    0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
282   Phase 12   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                              1/24/2006 17:00     1/24/2006 17:00     1/24/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
283   Phase 12   NEC Request Current CRs Forward remaining Phase 12 ESI Billing ESI IDs (30 days prior)     1/24/2006 17:00     1/24/2006 17:00     1/24/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
284   Phase 12   Current CRs Forward Phase 12 ESI ID Billing Information                                     2/7/2006 17:00      2/7/2006 17:00      2/7/2006 17:00    0 days   Sarah Fisher (NEC TDSP)
285   Phase 12   NEC notifies PUCT of nonresponsive CRs on phase 12 billing request                            2/8/2006 0:00       2/8/2006 0:00       2/8/2006 0:00   0 days   Sarah Fisher (NEC TDSP)
286   Phase 12   NEC TDSP sends NEC RD AREP data file                                                        2/9/2006 17:00      2/9/2006 17:00      2/9/2006 17:00    0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
287   Phase 12   Eligibility Date                                                                           2/13/2006 17:00     2/13/2006 17:00     2/13/2006 17:00    0 days
288   Phase 12   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     2/13/2006 17:00     2/13/2006 17:00     2/13/2006 17:00    0 days   Eloise Flores (NEC TDSP)
289   Phase 12   Current CR for Phase 12 AEP ESI IDs Submits 814_24 on old ESI ID                           2/13/2006 17:00     2/13/2006 17:00     2/13/2006 17:00    0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
290   Phase 12   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                2/20/2006 17:00   2/20/2006 17:00   2/20/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
291   Phase 12   NEC TDSP submit unassigned ESI IDs to NEC RD                                              2/20/2006 17:00   2/20/2006 17:00   2/20/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
292   Phase 12   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                 2/21/2006 17:00   2/21/2006 17:00   2/21/2006 17:00   0 days   Wendy Ohrt (NEC RD)
293   Phase 12   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   2/27/2006 17:00   2/27/2006 17:00   2/27/2006 17:00   0 days   Wendy Ohrt (NEC RD)
294   Phase 12   Enter Competition                                                                          2/28/2006 0:00    2/28/2006 0:00    2/28/2006 0:00   0 days
295   Phase 12   AEP TDSP final read old AEP ESI IDs                                                        2/28/2006 0:00    2/28/2006 0:00    2/28/2006 0:00   0 days   Richard Byrne (AEP)
296   Phase 12   NEC TDSP Reads new NEC ESI IDs                                                             2/28/2006 0:00    2/28/2006 0:00    2/28/2006 0:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
297   Phase 12   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                         3/3/2006 17:00    3/3/2006 17:00    3/3/2006 17:00   0 days   Richard Byrne (AEP)
298              Phase 13 Transition Period Tasks                                                          2/10/2006 17:00   3/30/2006 17:00   3/30/2006 17:00   0 days
299   Phase 13   NEC/AEP provide final Phase 13 ESI ID listing for ROR pull                                2/10/2006 17:00   2/10/2006 17:00   2/10/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
300   Phase 13   ERCOT pull ROR on transition period 13 ESI IDs                                            2/22/2006 17:00   2/22/2006 17:00   2/22/2006 17:00   0 days   Mike Davis (ERCOT)
301   Phase 13   Notify ROR for AEP ESI IDs of New ESI ID                                                   2/24/2006 0:00    2/24/2006 0:00    2/24/2006 0:00   0 days   Mike Davis (ERCOT)
302   Phase 13   NEC mail transition letter/welcome kit (30 days prior)                                    2/24/2006 17:00   2/24/2006 17:00   2/24/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
303   Phase 13   NEC receive recent 1 month meter data from AEP for Phase 13 AEP ESI IDs                   2/25/2006 17:00   2/25/2006 17:00   2/25/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
304   Phase 13   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             2/24/2006 17:00   2/24/2006 17:00   2/24/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
305   Phase 13   NEC Request Current CRs Forward remaining Phase 13 ESI Billing ESI IDs (30 days prior)    2/24/2006 17:00   2/24/2006 17:00   2/24/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
306   Phase 13   Current CRs Forward Phase 13 ESI ID Billing Information                                   3/10/2006 17:00   3/10/2006 17:00   3/10/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
307   Phase 13   NEC notifies PUCT of nonresponsive CRs on phase 13 billing request                        3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
308   Phase 13   NEC TDSP sends NEC RD AREP data file                                                      3/10/2006 17:00   3/10/2006 17:00   3/10/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
309   Phase 13   Eligibility Date                                                                          3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days
310   Phase 13   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Eloise Flores (NEC TDSP)
311   Phase 13   Current CR for Phase 13 AEP ESI IDs Submits 814_24 on old ESI ID                          3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
312   Phase 13   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                3/17/2006 17:00   3/17/2006 17:00   3/17/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
313   Phase 13   NEC TDSP submit unassigned ESI IDs to NEC RD                                              3/20/2006 17:00   3/20/2006 17:00   3/20/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
314   Phase 13   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                 3/21/2006 17:00   3/21/2006 17:00   3/21/2006 17:00   0 days   Wendy Ohrt (NEC RD)
315   Phase 13   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   3/27/2006 17:00   3/27/2006 17:00   3/27/2006 17:00   0 days   Wendy Ohrt (NEC RD)
316   Phase 13   Enter Competition                                                                         3/28/2006 17:00   3/28/2006 17:00   3/28/2006 17:00   0 days
317   Phase 13   AEP TDSP final read old AEP ESI IDs                                                       3/28/2006 17:00   3/28/2006 17:00   3/28/2006 17:00   0 days   Richard Byrne (AEP)
318   Phase 13   NEC TDSP Reads new NEC ESI IDs                                                            3/28/2006 17:00   3/28/2006 17:00   3/28/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
319   Phase 13   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        3/30/2006 17:00   3/30/2006 17:00   3/30/2006 17:00   0 days   Richard Byrne (AEP)
320              Phase 14 Transition Period Tasks                                                          2/10/2006 17:00   3/31/2006 17:00   3/31/2006 17:00   0 days
321   Phase 14   NEC/AEP provide final Phase 14 ESI ID listing for ROR pull                                2/10/2006 17:00   2/10/2006 17:00   2/10/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
322   Phase 14   ERCOT pull ROR on transition period 14 ESI IDs                                            2/24/2006 17:00   2/24/2006 17:00   2/24/2006 17:00   0 days   Mike Davis (ERCOT)
323   Phase 14   Notify ROR for AEP ESI IDs of New ESI ID                                                  2/28/2006 17:00   2/28/2006 17:00   2/28/2006 17:00   0 days   Mike Davis (ERCOT)
324   Phase 14   NEC mail transition letter/welcome kit (30 days prior)                                    2/24/2006 17:00   2/24/2006 17:00   2/24/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
325   Phase 14   NEC receive recent 1 month meter data from AEP for Phase 14 AEP ESI IDs                   2/27/2006 17:00   2/27/2006 17:00   2/27/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
326   Phase 14   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             2/28/2006 17:00   2/28/2006 17:00   2/28/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
327   Phase 14   NEC Request Current CRs Forward remaining Phase 14 ESI Billing ESI IDs (30 days prior)    2/28/2006 17:00   2/28/2006 17:00   2/28/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
328   Phase 14   Current CRs Forward Phase 14 ESI ID Billing Information                                   3/10/2006 17:00   3/10/2006 17:00   3/10/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
329   Phase 14   NEC notifies PUCT of nonresponsive CRs on phase 14 billing request                        3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
330   Phase 14   NEC TDSP sends NEC RD AREP data file                                                      3/14/2006 17:00   3/14/2006 17:00   3/14/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
331   Phase 14   Eligibility Date                                                                          3/13/2006 17:00   3/15/2006 17:00   3/15/2006 17:00   0 days
332   Phase 14   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    3/13/2006 17:00   3/15/2006 17:00   3/15/2006 17:00   0 days   Eloise Flores (NEC TDSP)
333   Phase 14   Current CR for Phase 14 AEP ESI IDs Submits 814_24 on old ESI ID                          3/13/2006 17:00   3/15/2006 17:00   3/15/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
334   Phase 14   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                3/20/2006 17:00   3/20/2006 17:00   3/20/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
335   Phase 14   NEC TDSP submit unassigned ESI IDs to NEC RD                                              3/21/2006 17:00   3/21/2006 17:00   3/21/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
336   Phase 14   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                 3/22/2006 17:00   3/22/2006 17:00   3/22/2006 17:00   0 days   Wendy Ohrt (NEC RD)
337   Phase 14   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   3/29/2006 17:00   3/29/2006 17:00   3/29/2006 17:00   0 days   Wendy Ohrt (NEC RD)
338   Phase 14   Enter Competition                                                                         3/30/2006 17:00   3/30/2006 17:00   3/30/2006 17:00   0 days
339   Phase 14   AEP TDSP final read old AEP ESI IDs                                                       3/30/2006 17:00   3/30/2006 17:00   3/30/2006 17:00   0 days   Richard Byrne (AEP)
340   Phase 14   NEC TDSP Reads new NEC ESI IDs                                                            3/30/2006 17:00   3/30/2006 17:00   3/30/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
341   Phase 14   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        3/31/2006 17:00   3/31/2006 17:00   3/31/2006 17:00   0 days   Richard Byrne (AEP)
342              Phase 15 Transition Period Tasks                                                          2/10/2006 17:00    4/6/2006 17:00    4/6/2006 17:00   0 days
343   Phase 15   NEC/AEP provide final Phase 15 ESI ID listing for ROR pull                                2/10/2006 17:00   2/10/2006 17:00   2/10/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
344   Phase 15   ERCOT pull ROR on transition period 15 ESI IDs                                             3/2/2006 17:00    3/2/2006 17:00    3/2/2006 17:00   0 days   Mike Davis (ERCOT)
345   Phase 15   Notify ROR for AEP ESI IDs of New ESI ID                                                   3/3/2006 17:00    3/3/2006 17:00    3/3/2006 17:00   0 days   Mike Davis (ERCOT)
346   Phase 15   NEC mail transition letter/welcome kit (30 days prior)                                    2/24/2006 17:00    3/3/2006 17:00    3/3/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
347   Phase 15   NEC receive recent 1 month meter data from AEP for Phase 15 AEP ESI IDs                    3/2/2006 17:00    3/2/2006 17:00    3/2/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
348   Phase 15   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                              3/3/2006 17:00    3/3/2006 17:00    3/3/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
349   Phase 15   NEC Request Current CRs Forward remaining Phase 15 ESI Billing ESI IDs (30 days prior)     3/3/2006 17:00    3/3/2006 17:00    3/3/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
350   Phase 15   Current CRs Forward Phase 15 ESI ID Billing Information                                   3/17/2006 17:00   3/17/2006 17:00   3/17/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
351   Phase 15   NEC notifies PUCT of nonresponsive CRs on phase 15 billing request                        3/18/2006 17:00   3/18/2006 17:00   3/18/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
352   Phase 15   NEC TDSP sends NEC RD AREP data file                                                      3/19/2006 17:00   3/19/2006 17:00   3/19/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
353   Phase 15   Eligibility Date                                                                          3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days
354   Phase 15   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Eloise Flores (NEC TDSP)
355   Phase 15   Current CR for Phase 15 AEP ESI IDs Submits 814_24 on old ESI ID                          3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
356   Phase 15   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                3/20/2006 17:00   3/20/2006 17:00   3/20/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
357   Phase 15   NEC TDSP submit unassigned ESI IDs to NEC RD                                              3/21/2006 17:00   3/21/2006 17:00   3/21/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
358   Phase 15   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                 3/21/2006 17:00   3/21/2006 17:00   3/21/2006 17:00   0 days   Wendy Ohrt (NEC RD)
359   Phase 15   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    4/3/2006 17:00    4/3/2006 17:00    4/3/2006 17:00   0 days   Wendy Ohrt (NEC RD)
360   Phase 15   Enter Competition                                                                          4/4/2006 17:00    4/4/2006 17:00    4/4/2006 17:00   0 days
361   Phase 15   AEP TDSP final read old AEP ESI IDs                                                        4/4/2006 17:00    4/4/2006 17:00    4/4/2006 17:00   0 days   Richard Byrne (AEP)
362   Phase 15   NEC TDSP Reads new NEC ESI IDs                                                             4/4/2006 17:00    4/4/2006 17:00    4/4/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
363   Phase 15   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                         4/6/2006 17:00    4/6/2006 17:00    4/6/2006 17:00   0 days   Richard Byrne (AEP)
364              Phase 16 Transition Period Tasks                                                          2/28/2006 17:00   4/17/2006 17:00   4/17/2006 17:00   0 days
365   Phase 16   NEC/AEP provide final Phase 16 ESI ID listing for ROR pull                                2/28/2006 17:00   2/28/2006 17:00   2/28/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
366   Phase 16   ERCOT pull ROR on transition period 16 ESI IDs                                            3/13/2006 17:00   3/13/2006 17:00   3/13/2006 17:00   0 days   Mike Davis (ERCOT)
367   Phase 16   Notify ROR for AEP ESI IDs of New ESI ID                                                  3/14/2006 17:00   3/14/2006 17:00   3/14/2006 17:00   0 days   Mike Davis (ERCOT)
368   Phase 16   NEC mail transition letter/welcome kit (30 days prior)                                    3/14/2006 17:00   3/14/2006 17:00   3/14/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
369   Phase 16   NEC receive recent 1 month meter data from AEP for Phase 16 AEP ESI IDs                    3/10/2006 0:00    3/10/2006 0:00    3/10/2006 0:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
370   Phase 16   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             3/14/2006 17:00   3/14/2006 17:00   3/14/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
371   Phase 16   NEC Request Current CRs Forward remaining Phase 16 ESI Billing ESI IDs (30 days prior)    3/14/2006 17:00   3/14/2006 17:00   3/14/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
372   Phase 16   Current CRs Forward Phase 16 ESI ID Billing Information                                   3/28/2006 17:00   3/28/2006 17:00   3/28/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
373   Phase 16   NEC notifies PUCT of nonresponsive CRs on phase 16 billing request                        3/29/2006 17:00   3/29/2006 17:00   3/29/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
374   Phase 16   NEC TDSP sends NEC RD AREP data file                                                      3/28/2006 17:00   3/28/2006 17:00   3/28/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
375   Phase 16   Eligibility Date                                                                          3/29/2006 17:00   3/29/2006 17:00   3/29/2006 17:00   0 days
376   Phase 16   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    3/29/2006 17:00   3/29/2006 17:00   3/29/2006 17:00   0 days   Eloise Flores (NEC TDSP)
377   Phase 16   Current CR for Phase 16 AEP ESI IDs Submits 814_24 on old ESI ID                          3/29/2006 17:00   3/29/2006 17:00   3/29/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
378   Phase 16   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 4/4/2006 17:00    4/4/2006 17:00    4/4/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
379   Phase 16   NEC TDSP submit unassigned ESI IDs to NEC RD                                               4/5/2006 17:00    4/5/2006 17:00    4/5/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
380   Phase 16   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  4/6/2006 17:00    4/6/2006 17:00    4/6/2006 17:00   0 days   Wendy Ohrt (NEC RD)
381   Phase 16   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   4/12/2006 17:00   4/12/2006 17:00   4/12/2006 17:00   0 days   Wendy Ohrt (NEC RD)
382   Phase 16   Enter Competition                                                                         4/13/2006 17:00   4/13/2006 17:00   4/13/2006 17:00   0 days
383   Phase 16   AEP TDSP final read old AEP ESI IDs                                                       4/13/2006 17:00   4/13/2006 17:00   4/13/2006 17:00   0 days   Richard Byrne (AEP)
384   Phase 16   NEC TDSP Reads new NEC ESI IDs                                                            4/13/2006 17:00   4/13/2006 17:00   4/13/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
385   Phase 16   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        4/17/2006 17:00   4/17/2006 17:00   4/17/2006 17:00   0 days   Richard Byrne (AEP)
386              Phase 17 Transition Period Tasks                                                          3/24/2006 17:00   5/10/2006 17:00   5/10/2006 17:00   0 days
387   Phase 17   NEC/AEP provide final Phase 17 ESI ID listing for ROR pull                                3/24/2006 17:00   3/24/2006 17:00   3/24/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
388   Phase 17   ERCOT pull ROR on transition period 17 ESI IDs                                             4/6/2006 17:00   3/28/2006 17:00   3/28/2006 17:00   0 days   Mike Davis (ERCOT)
389   Phase 17   Notify ROR for AEP ESI IDs of New ESI ID                                                   4/7/2006 17:00    4/7/2006 17:00    4/7/2006 17:00   0 days   Mike Davis (ERCOT)
390   Phase 17   NEC mail transition letter/welcome kit (30 days prior)                                     4/7/2006 17:00    4/7/2006 17:00    4/7/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
391   Phase 17   NEC receive recent 1 month meter data from AEP for Phase 17 AEP ESI IDs                    4/6/2006 17:00    4/6/2006 17:00    4/6/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
392   Phase 17   1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                              4/7/2006 17:00    4/7/2006 17:00    4/7/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
393   Phase 17   NEC Request Current CRs Forward remaining Phase 17 ESI Billing ESI IDs (30 days prior)     4/7/2006 17:00    4/7/2006 17:00    4/7/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
394   Phase 17   Current CRs Forward Phase 17 ESI ID Billing Information                                   4/21/2006 17:00   4/21/2006 17:00   4/21/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
395   Phase 17   NEC notifies PUCT of nonresponsive CRs on phase 17 billing request                        4/22/2006 17:00   4/22/2006 17:00   4/22/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
396   Phase 17   NEC TDSP sends NEC RD AREP data file                                                      4/21/2006 17:00   4/21/2006 17:00   4/21/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
397   Phase 17   Eligibility Date                                                                          4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days
398   Phase 17   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Eloise Flores (NEC TDSP)
399   Phase 17   Current CR for Phase 17 AEP ESI IDs Submits 814_24 on old ESI ID                          4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
400   Phase 17   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                4/27/2006 17:00   4/27/2006 17:00   4/27/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
401   Phase 17   NEC TDSP submit unassigned ESI IDs to NEC RD                                              4/28/2006 17:00   4/28/2006 17:00   4/28/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
402   Phase 17   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  5/1/2006 17:00    5/1/2006 17:00    5/1/2006 17:00   0 days   Wendy Ohrt (NEC RD)
403   Phase 17   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    5/8/2006 17:00    5/8/2006 17:00    5/8/2006 17:00   0 days   Wendy Ohrt (NEC RD)
404   Phase 17   Enter Competition                                                                          5/9/2006 17:00    5/9/2006 17:00    5/9/2006 17:00   0 days
405   Phase 17   AEP TDSP final read old AEP ESI IDs                                                        5/9/2006 17:00    5/9/2006 17:00    5/9/2006 17:00   0 days   Richard Byrne (AEP)
406   Phase 17 NEC TDSP Reads new NEC ESI IDs                                                             5/9/2006 17:00    5/9/2006 17:00    5/9/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
407   Phase 17 AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        5/10/2006 17:00   5/10/2006 17:00   5/10/2006 17:00   0 days   Richard Byrne (AEP)
408            Phase 18 Transition Period Tasks                                                          3/24/2006 17:00   5/12/2006 17:00   5/12/2006 17:00   0 days
409   Phase 18 NEC/AEP provide final Phase 18 ESI ID listing for ROR pull                                3/24/2006 17:00   3/24/2006 17:00   3/24/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
410   Phase 18 ERCOT pull ROR on transition period 18 ESI IDs                                            4/10/2006 17:00   4/10/2006 17:00   4/10/2006 17:00   0 days   Mike Davis (ERCOT)
411   Phase 18 Notify ROR for AEP ESI IDs of New ESI ID                                                  4/11/2006 17:00   4/11/2006 17:00   4/11/2006 17:00   0 days   Mike Davis (ERCOT)
412   Phase 18 NEC mail transition letter/welcome kit (30 days prior)                                     4/7/2006 17:00    4/7/2006 17:00    4/7/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
413   Phase 18 NEC receive recent 1 month meter data from AEP for Phase 18 AEP ESI IDs                   4/10/2006 17:00   4/10/2006 17:00   4/10/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
414   Phase 18 1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             4/11/2006 17:00   4/11/2006 17:00   4/11/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
415   Phase 18 NEC Request Current CRs Forward remaining Phase 18 ESI Billing ESI IDs (30 days prior)    4/11/2006 17:00   4/11/2006 17:00   4/11/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
416   Phase 18 Current CRs Forward Phase 18 ESI ID Billing Information                                   4/21/2006 17:00   4/21/2006 17:00   4/21/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
417   Phase 18 NEC notifies PUCT of nonresponsive CRs on phase 18 billing request                        4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
418   Phase 18 NEC TDSP sends NEC RD AREP data file                                                      4/25/2006 17:00   4/25/2006 17:00   4/25/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
419   Phase 18 Eligibility Date                                                                          4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days
420   Phase 18 NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Eloise Flores (NEC TDSP)
421   Phase 18 Current CR for Phase 18 AEP ESI IDs Submits 814_24 on old ESI ID                          4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
422   Phase 18 CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 5/2/2006 17:00    5/2/2006 17:00    5/2/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
423   Phase 18 NEC TDSP submit unassigned ESI IDs to NEC RD                                               5/3/2006 17:00    5/3/2006 17:00    5/3/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
424   Phase 18 NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  5/4/2006 17:00    5/4/2006 17:00    5/4/2006 17:00   0 days   Wendy Ohrt (NEC RD)
425   Phase 18 NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs    5/8/2006 17:00    5/8/2006 17:00    5/8/2006 17:00   0 days   Wendy Ohrt (NEC RD)
426   Phase 18 Enter Competition                                                                         5/11/2006 17:00   5/11/2006 17:00   5/11/2006 17:00   0 days
427   Phase 18 AEP TDSP final read old AEP ESI IDs                                                       5/11/2006 17:00   5/11/2006 17:00   5/11/2006 17:00   0 days   Richard Byrne (AEP)
428   Phase 18 NEC TDSP Reads new NEC ESI IDs                                                            5/11/2006 17:00   5/11/2006 17:00   5/11/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
429   Phase 18 AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        5/12/2006 17:00   5/12/2006 17:00   5/12/2006 17:00   0 days   Richard Byrne (AEP)
430            Phase 19 Transition Period Tasks                                                          3/24/2006 17:00   5/19/2006 17:00   5/19/2006 17:00   0 days
431   Phase 19 NEC/AEP provide final Phase 19 ESI ID listing for ROR pull                                3/24/2006 17:00   3/24/2006 17:00   3/24/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
432   Phase 19 ERCOT pull ROR on transition period 19 ESI IDs                                            4/13/2006 17:00   4/13/2006 17:00   4/13/2006 17:00   0 days   Mike Davis (ERCOT)
433   Phase 19 Notify ROR for AEP ESI IDs of New ESI ID                                                  4/14/2006 17:00   4/14/2006 17:00   4/14/2006 17:00   0 days   Mike Davis (ERCOT)
434   Phase 19 NEC mail transition letter/welcome kit (30 days prior)                                     4/7/2006 17:00    4/7/2006 17:00    4/7/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
435   Phase 19 NEC receive recent 1 month meter data from AEP for Phase 19 AEP ESI IDs                   4/14/2006 17:00   4/14/2006 17:00   4/14/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
436   Phase 19 1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             4/13/2006 17:00   4/13/2006 17:00   4/13/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
437   Phase 19 NEC Request Current CRs Forward remaining Phase 19 ESI Billing ESI IDs (30 days prior)    4/14/2006 17:00   4/14/2006 17:00   4/14/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
438   Phase 19 Current CRs Forward Phase 19 ESI ID Billing Information                                   4/28/2006 17:00   4/28/2006 17:00   4/28/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
439   Phase 19 NEC notifies PUCT of nonresponsive CRs on phase 19 billing request                         5/1/2006 17:00    5/1/2006 17:00    5/1/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
440   Phase 19 NEC TDSP sends NEC RD AREP data file                                                      4/28/2006 17:00   4/28/2006 17:00   4/28/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
441   Phase 19 Eligibility Date                                                                          4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days
442   Phase 19 NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                    4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Eloise Flores (NEC TDSP)
443   Phase 19 Current CR for Phase 19 AEP ESI IDs Submits 814_24 on old ESI ID                          4/24/2006 17:00   4/24/2006 17:00   4/24/2006 17:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
444   Phase 19 CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 5/1/2006 17:00    5/1/2006 17:00    5/1/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
445   Phase 19 NEC TDSP submit unassigned ESI IDs to NEC RD                                               5/2/2006 17:00    5/2/2006 17:00    5/2/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
446   Phase 19 NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                  5/2/2006 17:00    5/2/2006 17:00    5/2/2006 17:00   0 days   Wendy Ohrt (NEC RD)
447   Phase 19 NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   5/15/2006 17:00   5/15/2006 17:00   5/15/2006 17:00   0 days   Wendy Ohrt (NEC RD)
448   Phase 19 Enter Competition                                                                         5/16/2006 17:00   5/16/2006 17:00   5/16/2006 17:00   0 days
449   Phase 19 AEP TDSP final read old AEP ESI IDs                                                       5/16/2006 17:00   5/16/2006 17:00   5/16/2006 17:00   0 days   Richard Byrne (AEP)
450   Phase 19 NEC TDSP Reads new NEC ESI IDs                                                            5/16/2006 17:00   5/16/2006 17:00   5/16/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
451   Phase 19 AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        5/19/2006 17:00   5/19/2006 17:00   5/19/2006 17:00   0 days   Richard Byrne (AEP)
452            Phase 20 Transition Period Tasks                                                          3/24/2006 17:00   5/22/2006 17:00   5/22/2006 17:00   0 days
453   Phase 20 NEC/AEP provide final Phase 20 ESI ID listing for ROR pull                                3/24/2006 17:00   3/24/2006 17:00   3/24/2006 17:00   0 days   Varzavand 'Avan' Irani (NEC),Richard Byrne (AEP)
454   Phase 20 ERCOT pull ROR on transition period 20 ESI IDs                                            4/17/2006 17:00   4/17/2006 17:00   4/17/2006 17:00   0 days   Mike Davis (ERCOT)
455   Phase 20 Notify ROR for AEP ESI IDs of New ESI ID                                                  4/18/2006 17:00   4/18/2006 17:00   4/18/2006 17:00   0 days   Mike Davis (ERCOT)
456   Phase 20 NEC mail transition letter/welcome kit (30 days prior)                                    4/17/2006 17:00   4/17/2006 17:00   4/17/2006 17:00   0 days   Sarah Fisher (NEC TDSP),Richard Byrne (AEP)
457   Phase 20 NEC receive recent 1 month meter data from AEP for Phase 20 AEP ESI IDs                   4/17/2006 17:00   4/17/2006 17:00   4/17/2006 17:00   0 days   Leo Kalips (NISC),Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
458   Phase 20 1 Recent Month Historical Meter Data to ERCOT (30 Days Prior)                             4/18/2006 17:00   4/18/2006 17:00   4/18/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder(NEC TDSP)
459   Phase 20 NEC Request Current CRs Forward remaining Phase 20 ESI Billing ESI IDs (30 days prior)    4/18/2006 17:00   4/18/2006 17:00   4/18/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
460   Phase 20 Current CRs Forward Phase 20 ESI ID Billing Information                                    5/2/2006 17:00    5/2/2006 17:00    5/2/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
461   Phase 20 NEC notifies PUCT of nonresponsive CRs on phase 20 billing request                         5/3/2006 17:00    5/3/2006 17:00    5/3/2006 17:00   0 days   Sarah Fisher (NEC TDSP)
462   Phase 20 NEC TDSP sends NEC RD AREP data file                                                       5/2/2006 17:00    5/2/2006 17:00    5/2/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
463   Phase 20 Eligibility Date                                                                           4/24/2006 0:00    4/24/2006 0:00    4/24/2006 0:00   0 days
464   Phase 20   NEC Certified CRs begin submitting 814_16s to energize new NEC ESI IDs                     4/24/2006 0:00    4/24/2006 0:00    4/24/2006 0:00   0 days   Eloise Flores (NEC TDSP)
465   Phase 20   Current CR for Phase 20 AEP ESI IDs Submits 814_24 on old ESI ID                           4/24/2006 0:00    4/24/2006 0:00    4/24/2006 0:00   0 days   Jane Eyanson (AEP),Richard Byrne (AEP)
466   Phase 20   CRs cutoff date for submitting 814_16s for new NEC ESI IDs                                 5/8/2006 17:00    5/8/2006 17:00    5/8/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
467   Phase 20   NEC TDSP submit unassigned ESI IDs to NEC RD                                               5/9/2006 17:00    5/9/2006 17:00    5/9/2006 17:00   0 days   Eloise Flores (NEC TDSP),David Lowder (NEC TDSP)
468   Phase 20   NEC AREP submits 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs                 5/10/2006 17:00   5/10/2006 17:00   5/10/2006 17:00   0 days   Wendy Ohrt (NEC RD)
469   Phase 20   NEC AREP cutoff for submitting 814_16s remaining new NEC ESI IDs and NEC to AEP ESI IDs   5/17/2006 17:00   5/17/2006 17:00   5/17/2006 17:00   0 days   Wendy Ohrt (NEC RD)
470   Phase 20   Enter Competition                                                                         5/18/2006 17:00   5/18/2006 17:00   5/18/2006 17:00   0 days
471   Phase 20   AEP TDSP final read old AEP ESI IDs                                                       5/18/2006 17:00   5/18/2006 17:00   5/18/2006 17:00   0 days   Richard Byrne (AEP)
472   Phase 20   NEC TDSP Reads new NEC ESI IDs                                                            5/18/2006 17:00   5/18/2006 17:00   5/18/2006 17:00   0 days   Eloise Flores (NEC TDSP),Warren Hoelscher (NEC TDSP)
473   Phase 20   AEP TDSP submits 814_20 Retire for old AEP ESI IDs                                        5/22/2006 17:00   5/22/2006 17:00   5/22/2006 17:00   0 days   Richard Byrne (AEP)

						