					                 Integrated Wireless
                 Network (IWN)
                 Eastern Washington
                 Project Briefing
                 August 8, 2005

August 8, 2005      Washington State Patrol   1
Agenda
    1. Background Information
    2. Project Scope
    3. Project Schedule
    4. Project Budget
    5. Risk Assessment and mitigation strategies
    6. Issues
    7. Quality Assurance
    8. Questions




August 8, 2005                  Washington State Patrol   2
1. Background Information
   Washington State Patrol Communication System History
         Voice radio communication operations for over 50 years.
         Analog microwave communication operations for over 30 years.
         Telephone system operations for approximately 20 years.
         Digital microwave communication operation for approximately 10
          years.
   Current Snapshot
         Statewide voice radio, analog microwave, digital microwave,
          telephone systems, mobile data systems, and data networks.
         Statewide systems support federal, state, and local public safety
          agencies.
         Full support and emergency support 24 x 7



August 8, 2005                  Washington State Patrol                   3
2. Project Scope
   Project Scope is broken into four major components:
        Civil Site Work
        Microwave Backbone Work
        Independent Validation and Verification (Quality Assurance)
        System Testing and Acceptance




August 8, 2005                 Washington State Patrol                 4
   2. Project Scope
                                                                                      Northern Border Module




                                                                          Eastern
                                                                         Washington
                                                                          Module




                                Seattle Module




                     Portland
                     Module




                 Oregon Coast
                    Module




                                                 Oregon
                                                   I-5
                                                 Module              Eastern Oregon Module




August 8, 2005                                            Washington State Patrol                              5
3. Project Schedule
   Phased delivery of planning, design and
    construction services
        June 2, 2005 – December 31, 2005 (DOJ)
           DOJ approved project on June 2, 2005
           Prepare engineering, zoning and construction documents
           Perform due diligence and critical path engineering studies
           Finalize construction documents and secure zoning approval
           Procure critical lead time equipment

        September 1, 2005 (DOJ)
           Commence phased site construction

        January 1, 2006 – December 31, 2006, (DOJ and
           WSP)
                Phased delivery of Radio Ready sites
        June 2007 (DOJ)
           IWN communication system operational

August 8, 2005                    Washington State Patrol             6
                                                         INTEGRATED WIRELESS NETWORK (IWN) EAST TIMELINE
                                                         DEPARTMENT OF JUSTICE – WASHINGTON STATE PATROL

                                                                                                                                  12/31/2005
                                                                                                                           Mt. Spokane - Radio Ready

                                     6/23/2005
                                                                                                          9/1/2005
                               SIEC Approved IWN East
               6/9/2005                                                                    Alcatel Awarded Contract and Start Work
            ISB Notification                                   8/8/2005
         Tom Wallace assigned                              ISB Presentation


                                       7/14/2005
                                  1st ISB Notification
                                                                                                          9/30/2005 - 11/29/2005          12/14/2005 - 12/20/2005
                                                                                                               Factory Build             Factory Acceptance Testing




                       7/1/2005                8/1/2005                 9/1/2005           10/1/2005              11/1/2005           12/1/2005

        6/7/2005                                                                                                                                           12/31/2005

                                           8/3/2005 - 8/5/2005
                                Negotiations with Alcatel to finalize contract

                                                                                                                                                             12/31/2006
                                                                             1/1/2006 - 12/31/2006                                                     All Sites Radio Ready
                                                                      Upgrade 29 additional Microwave Sites




                    2/1/2006    3/1/2006     4/1/2006      5/1/2006     6/1/2006   7/1/2006    8/1/2006       9/1/2006   10/1/2006   11/1/2006 12/1/2006

         1/1/2006                                                                                                                                           12/31/2006



               On Time                     Completed                  Current Question on timing              Over Due                  Critical Dates




August 8, 2005                                                          Washington State Patrol                                                                                7
4. Project Budget
   Overall Project Budget
         Approximately $30,000,000
         No match requirement – 100% federal funding
   State Project Budget
         Estimated budget $11,489,500
         7 project FTEs – 100% federally funded




August 8, 2005                Washington State Patrol   8
4. Project Budget
                            Project Cost Breakdown
 Component Description         Component Cost              Total
Radio Equipment                           $1,716,700
Network Equipment                          $l,890,800
Power Equipment                             $453,400
Spares and Test Equipment                   $468,400
Antennas and Feed Line                      $880,600
Heating and A/C                               $84,000
Maintenance (2 yrs.)                        $256,000
Alcatel Professional                      $2,370,600
Services
Sales Tax (Total of above                       $722,800
components )
Subtotal                                                           $8,843,300
WSP Project Staff                            $1,652,600
Contingency                                    $993,600
Total                                                         $11,489,500
August 8, 2005                  Washington State Patrol                         9
5. Risk Assessment and Mitigation
   Strategies
   Wildfire
         Project work is being spread into three areas simultaneously;
          Spokane, Vancouver, Snoqualmie Pass.
         Schedule projection is that work will focus into one primary area
          in spring ’06 prior to fire season.
   Winter weather conditions
         High sites will be primary focus prior to winter conditions.
         Multiple construction crews will be assigned in each area to
          compress high site civil work schedule.
         WSP’s snowcats and other winter equipment will be assigned as
          needed.
         Low risk sites will be primary focus during typical winter weather
          months.

August 8, 2005                  Washington State Patrol                   10
   5b. Winter Condition Risk




August 8, 2005   Washington State Patrol   11
5. Risk Assessment and Mitigation
   Strategies
   Limited Personnel
         Identified as a major risk in first phase
         Pursuing competitive contracting
         Project work split between DOJ and WSP.
   Technology
         State’s responsibility limited to proven technologies.
         Pursuing competitive contracting with leading microwave
          manufacturer.
         Standard physical and network layer demarcation points.
   Security
         WSP personnel receive polygraph and background prior to
          employment.
         Network Security – See section 6.
August 8, 2005                 Washington State Patrol              12
6. Issues
   Network Security:
         Personnel – pre-employment polygraph and background.
         Physical equipment – contained within locked and fenced sites.
          Sites monitored remotely for specific alarms.
         Microwave radio system
                Designed in ‘loops’ to avoid single points of failure.
                Connected to external interfaces through standard interfaces.
                Centrally managed system.
         Microwave network system
                Secure traffic is segregated using standard practices.
                Network is based upon open standards
                Access is through WSP existing network security policies.
         IWN Radio System
                DOJ is responsible for ‘application specific’ security.
                WSP’s network will support end-to-end application encryption.

August 8, 2005                       Washington State Patrol                     13
                   •Mobile Repeater




                             •Mobile Radio                    Base Station

   Portable Radio
                                                                    IWN EAST
                                                                    PORTION




           •Computer Aided                                  •Signal Selection
                 •Dispatch                                    •Equipment
                                        •Console

August 8, 2005                    Washington State Patrol                       14
August 8, 2005   Washington State Patrol   15
6. Issues
   Civil work program management services will
    include:
         Architectural/electrical/HVAC/R56 site design
         Civil Engineering / site and compound layout / shelter layout
         Regulatory review and approvals
         Zoning representation and building permit
         Equipment procurement
         Construction planning
         Construction management
         Final site punch-list walk & acceptance testing for the site to be
          Radio Ready
         Target date to for the first site to be Radio Ready is December
          31, 2005 with a phased delivery through December 31, 2006.


August 8, 2005                  Washington State Patrol                    16
 7. Quality Assurance
   IV&V         process improvements
      More frequent face-to-face meetings
      Greater use of secure portal

   IV&V review of module design plans
     Coverage and site selection
      Traffic loading and capacity analysis
      Inter-site connectivity plans
      Site facilities construction and improvement plans
      Estimated cost review

   Recommendations/concurrence
      Concur  with the Department of Justice’s plans to date, as
        reviewed – June 2, 2005.

August 8, 2005                 Washington State Patrol              17
                 Questions?



August 8, 2005    Washington State Patrol   18

				