Acrobat PDF

Scott Keeley Siemens Building Technologies and Colin Covington Three Rivers Solid Waste Authority 11th Annual LMOP Conference Proceedings

Click to download
Reviews
Shared by: EPADocs
Stats
views:
53
rating:
not rated
reviews:
0
posted:
5/14/2008
language:
English
pages:
0
....... A Public Private Partnership Success Three Rivers Solid Waste Kimberly Clark Siemens Building Technoligies Direct Use Landfill Gas Project Scott Keeley Colin Covington Laura Dzamka Siemens Building Technologies 1 ....... Siemens Building Technologies 2 ....... Roles • Three Rivers Solid Waste Authority: Owner/Developer • Kimberly Clark: Gas Purchaser • Siemens Building Technologies: Partner/Developer/Operator Siemens Building Technologies 3 ....... Project History and Timeline Three Rivers Began investigation late 2005 Issued RFQ for partner 1st Quarter 2006 Selected Siemens 2nd quarter 2006 Direct Use Project with KC selected Oct 2006 Detailed Engineering and contracts completed April 07 Financial Closure Sep 07 Construction began Oct. 07 Construction to be completed April 08 Two year development and construction schedule Siemens Building Technologies 4 ....... Siemens Role • Energy Development partner: Evaluated options and helped Three Rivers select direct use model • Turnkey project completion including long term operations and maintenance contract • Long term performance risks Implementation and operations responsibilities and risks shifted to Siemens Siemens Building Technologies 5 ....... Gas Curve LFG RECOVERY PROJECTION GRAPH Three Rivers Landfill 3,500 Potential Recovery Projected Recovery 3,000 LFG Flow at 50% Methane (cfm) Actual Recovery 2,500 2,000 1,500 1,000 500 0 2005 2010 2015 2020 2025 2030 Siemens Building Technologies 6 ....... Why Direct Use • Most Efficient use of the Gas • Kimberly Clark can use all the gas the landfill is projected to produce • Helped a local employer reduce costs • Created the most economic value Three Rivers Siemens Building Technologies 7 ....... Pipeline Construction Siemens Building Technologies 8 ....... Three Rivers Regional Landfill elected to own the project • Allowed Three Rivers to retain control of the project decisions • Tax exempt financing structures available to Three Rivers • Comprehensive Performance contract with Siemens shifted project risks and responsibility to Siemens • Three Rivers owns the project and all long term revenue • Three Rivers retains C02 credits • Created the most economic value for Three Rivers with limited risk Siemens Building Technologies 9 ....... Three Rivers Regional Landfill • • • • • • Received first waste July, 1998 250,000 TPY 30 mm cubic yards total capacity Active to 2075 – easily expandable Population base of 400,000 Operated as independent enterprise Siemens Building Technologies 10 ....... Tax exempt bond structure • Effective Rate of less than 5% • Created new hurdles • Added 4 months to development cycle Siemens Building Technologies 11 ....... Gas Verification Hurdle • Funding required that gas flows needed to be verified • Hired HDR as independent engineer but could not certify that gas flows would make project viable • Solution: Installed system and measured flows prior to making commitment • Final flow measurement was slightly less than projected reducing debt service coverage • Solution: Create back end loaded debt payments during periods when flows will be greater and issued CABs for the collection system, deferring payments for 15 years. Siemens Building Technologies 12 ....... Variability in Gas Prices Hurdle • Contract pricing structure was indexed to natural gas. If prices fell below market projections, then project did not meet Debt Service Coverage requirements. • Solution: Add floor price to manage this risk. Offered price cap to Kimberly Clark in return. Siemens Building Technologies 13 ....... Legal Authority Hurdle • TRSWA did not have legal authority to fund project anywhere other than landfill property. • Solution: Utilize captive non profit corporation, TRA, Inc. and issue certificates of completion through this entity. Siemens Building Technologies 14 ....... Boiler Modifications • Kimberly Clark could not internally justify expenses for the boiler modifications, so these costs had to be financed by the developer. Because the modifications would benefit a private corporation, they could not be funded on a tax exempt basis. • Solution: Fund these through TRA using a separate series of taxable certificates of completion. Siemens Building Technologies 15 ....... Three Rivers Benefits • Creates Environmental Benefits • Creates Savings for local employer • Creates new cash flow Siemens Building Technologies 16 ....... Environmental Benefits • Removing 41,000 Vehicles • 58,000 acres of trees • 23,000,000 gallons of gas Siemens Building Technologies 17 ....... C02 Credit Sales • Collection system is voluntary until June 2008 • Creates 1000 tons C02 Credits the first year • Early installation of wells should generate another 15,000 tons per year Siemens Building Technologies 18

Related docs
premium docs
Other docs by EPADocs
TORTS -- MASTER
Views: 749  |  Downloads: 70
Revivor agreement
Views: 184  |  Downloads: 3
adr107
Views: 91  |  Downloads: 0
IP Table2
Views: 296  |  Downloads: 9
Resources in World History
Views: 408  |  Downloads: 9
Harris v Jones
Views: 251  |  Downloads: 4
Change My Heart O God
Views: 286  |  Downloads: 4
Bankruptcy proceedings representation
Views: 283  |  Downloads: 4
Herbs for Labor
Views: 600  |  Downloads: 8
ManualExemptionAgreementForm6_14_04
Views: 128  |  Downloads: 0
de147
Views: 98  |  Downloads: 0
de140
Views: 84  |  Downloads: 0
Conversion
Views: 180  |  Downloads: 0
Above All
Views: 221  |  Downloads: 3
Knowing You
Views: 192  |  Downloads: 3