CPM IS. . . . .

 DETAIL PLANNING OF ENTIRE PROJECT

 SEPARATE FROM JOB-SITE DAY TO DAY

SCHDEULING

 USED FOR REPORTING AND ANALYZING

JOB-SITE SCHEDULING EFFORS

 A CONTRACT REQUIREMENT

ORIGINAL CPM. . . .

 BEST INITIAL PLAN FOR THE PROJECT

 FORCES DETAIL PLANNING AND

THOUGHT

 ESTABLISHES EARLY WARNING SYSTEM

FOR DELAY (MILESTONES)

 FULLY SYNCRONIZED TO THE PROJECT

 HAS ONE CRITICAL PATH

Initial Input Dos and Don‟ts

 Do provide information on the forms and in the level of detail

required by the contract and Lead Contractor.

 Do break the work down into all phases if the project is phased.

 Do provide Submit, Approve, and Fab & Deliver activities for all

materials and equipment that is not “off the shelf”.

 Do provide as a Level 1 minimum, Activity Name, Duration in

workdays, and graphic to indicate sequence.

 Do provide as Level 2 Man-hour and Cost loading of each activity.

 Do ask questions if you need to.

 Don‟t assume that the Lead Contractor will do this for you.

 Don‟t subrogate your scheduling privilege to someone else, you

may live to regret it.

 Don‟t „pad‟ the duration days; you don‟t really want to wind up on

the Critical Path unless it is true.

Architects and Owners

 On Multi-prime state contracts encourage the

primes to comply with the Lead Contractors

instructions for initial input and updating. Your

Lead Contractor is charged with the task. Failure

to enforce this may result in paying damages on

the project.

 Enforce the contract as it relates to each Prime

Contractor‟s, input, review, signing, and

updating. This will work to protect the owner from

delay damages.

 Negotiate time for change orders when they

happen and not at the end of the project.

CPM UPDATING

 REQUIRED TO CAUSE CPM TO MIRROR

(SYNCRONIZE) TO THE ACTUAL

PROJECT

 UPDATES RELY UPON ACCURATE

INFORMATION

 UPDATE INFORMATION COMES FROM

FIELD PERSONEL

 OFTEN REQUIRES MORE THAN ONE

PASS

CPM Updating Dos and Don‟ts

 Do read the printed instructions on how to prepare for and

perform your update.

 Do provide the starts and finish dates for completed

activities, and start date and remaining duration on started

but incomplete activities.

 Don‟t assume that just because an activity is complete that

you do not have to report it‟s start and finish date.

 Do use the provided form and complete it properly.

 Don‟t try to provide projected start or finish dates, the

software will do that.

 Do call and ask for help if you need it.

 Do relate all remaining durations to the set data date.

SCHEDULE UPDATE INPUT

FORM



PROJECT: _______________________________________________ COMPANY REPORTING: _____________________________



DATA DATE: ______________________



SCHEDULE PERCENT REMAINING ACTUAL ACTUAL REMARKS

ACTIVITY COMPLETE DURATION START FINISH

NUMBER DATE DATE

SCHEDULE UPDATE INPUT

FORM



PROJECT: _______________________________________________ COMPANY REPORTING: _____________________________



DATA DATE: ______________________



SCHEDULE PERCENT REMAINING ACTUAL ACTUAL REMARKS

ACTIVITY COMPLETE DURATION START FINISH

NUMBER DATE DATE

CPM ANALYSIS

 REMOVE / RESOLVE INCORRECT

INFORMATION

 LOCATES PROBLEM AREAS

 REVISE LOGIC/DURATIONS TO MIRROR

RECOVERY

 COORDINATE RECOVERY AMONG

PARTICIPANTS

 PROVIDE A NEW PLAN TO COMPLETE ON

TIME

RECOVERY

 CONTRACTOR(S) WITH NEGATIVE FLOAT

MUST PROVIDE THE RECOVERY PLAN

 LEAD CONTRACTOR TO ASSIST AND

COORDINATE AMONG CONTRACTORS

 LEAD CONTRACTOR TO SUBMIT TO

OWNER /A/E A REVISED CPM SCHEDULE

 ALL AGREE TO REVISED SCHEDULE

HELPS . . .

 FIELD PERSONEL MUST BECOME VERY

FAMILIAR WITH ACTIVITY NUMBERS

– LIST ON DAILY REPORTS

– ENCOURAGED BY PROJECT MGRS

 WHEN UPDATING REVIEW EACH

ACTIVITY

 DON‟T FORGET TO UPDATE

PROCUREMENT ACTIVITIES


Share This Document


Related docs
Other docs by Double Header
by registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!