REQUEST FOR CHANGE REPORT APRIL Add Delete Scope Change

Reviews
REQUEST FOR CHANGE REPORT APRIL 2007 Add/Delete/ Scope Change/ Substitution-A(Add) or D(Delete) Increase or Decrease to Current Contract Date Received Solicitation Number Prime Contractor Project Description Subcontractor Certified Y/N Subcontract Amount Scope of Work Managing Department Project Manager GFE Required? Y/N Action Date Approved Y/N Notes 1 4/2/2007 2 4/3/2007 BROWN & ROOT/ESPEY PADDEN PW98300055 JOINT VENTURE WALLER CREEK TUNNEL ENGINEERING SVCS FOR ELECTRIC POWER DELIVERY PW02300023 POWER ENGINEERS SYSTEM MUNIZ CONCRETE + PW05200107 CONTRACTING OSCAR RENDA PWC0035 CONTRACTING INC OSCAR RENDA CONTRACTING INC 2006 MISCELLANEOUS BRIDGE MAINTENANCE AWU-RMMA 24" TRANSMISSION MAIN AWU-RMMA 24" TRANSMISSION MAIN ADA SIDEWALK RAMP & BIKEWAY IMPROVEMENTS ROTATION LIST ADA SIDEWALK RAMP & BIKEWAY IMPROVEMENTS ROTATION LIST ADA SIDEWALK RAMP & BIKEWAY IMPROVEMENTS ROTATION LIST ADA SIDEWALK RAMP & BIKEWAY IMPROVEMENTS ROTATION LIST Scope Change VANCE E. POWELL III, MAI, SRA DAVID HOFFMAN & COMPANY SCR CONSTRUCTION AARON CONCRETE N Increase $ 34,500.00 Economic Evaluation Electrical Upgrades to Moonlight Towers Watershed Gary Kosut N 4/6/2007 Y Change in contract amount. Scope Change N Increase $ 7,425.00 AE Street & Bridge AWU Dorothy Kester N 4/5/2007 Y 3 4 4/10/2007 4/10/2007 Add Add N Y N/A N/A $ $ 94,700.90 Asphalt Plug Expansion joint system Concrete Curb & Gutter, Driveways 30,000.00 Asphalt Paving & Concrete Repair Pirouz Moin Gary Jackson N N 4/18/2007 4/12/2007 Y Y Change in contract amount. There are no MBE or WBE firms certified for the scope of work at the time of the request. To increase MBE or WBE participation. Pricing from certified firm was not competitive or did not respond to solicitation to submit pricing Unavailability after reasonable notice to proceed. 5 4/10/2007 PWC0035 Add 6 4/10/2007 PW0400026 HALFF ASSOCIATES Substitution - D DIRTCO LP WHM TRANSPORTATION ENGINEERING N N/A $ 268,700.00 AWU Gary Jackson Y 4/16/2007 Y N N/A Unknown Management Consulting PW Diane Rice N 4/19/2007 Y 6a 4/10/2007 PW0400026 HALFF ASSOCIATES ALAN PLUMER ASSOCIATES, INC. ALAN PLUMER ASSOCIATES, INC. Substitution - A 7 4/10/2007 PW0400026 Substitution - D BOWMAN - MELTON WHM TRANSPORTATION ENGINEERING VICKREY & ASSOCIATES INC Y N/A $ 38,300.00 Management Consulting PW Diane Rice N 4/19/2007 Y Like Kind Unavailability after reasonable notice to proceed. N N/A Unknown Civil Engineering PW Diane Rice N 4/17/2007 Y 7a 4/10/2007 PW0400026 Substitution - A Y N/A Unknown 8 9 9a 4/17/2007 4/23/2007 4/23/2007 10 4/25/2007 DAVCAR ENGINEERING CIVIL ENGINEERING SERVICES ROTATION 2006-2008 PW0630003 SERVICES RMMA-AIRPORT RD. WW PW06200050 LEWIS CONTRACTORS IMPROVEMENTS RMMA-AIRPORT RD. WW PW06200050 LEWIS CONTRACTORS IMPROVEMENTS GEN. CIVIL ENGINEERING SVCS ROTATION LIST 2006PW06300003 WESTON SOLUTIONS 2008 Add Substitution - A Substitution - D SCHULTZ & ASSOCIATES ANN WILSON CONSTRUCTION TRAVIS PAVING & EXCAVATION CO N Y Y N/A N/A N/A $ $ $ Civil Engineering Consulting for Water Treatment Plant Controls & Instrumentation 16,000.00 Paving & Resurfacing 57,862.54 Street Paving & Resurfacing 49,616.00 Street TRAFFIC CONTROL DESIGN TRAFFIC & TRANSPORTATION ENGINEERINGTRAFFIC CONTROL DESIGN PW Diane Rice N 4/17/2007 Y Like Kind Pricing from certified firm was not competitive or did not respond to solicitation to submit pricing PW PW PW Steve Nelson PHIL SALYER PHIL SALYER Y Y N 4/26/2007 4/30/2007 4/30/2007 Y Y Y Trying to stay ahead from liquidated damages failure of performance Substitution - A AXIOM ENGINEERS Y N/A Unknown PW STEVE NELSON N 5/2/2007 Y Like Kind 10a 4/25/2007 11 12 4/25/2007 4/30/2007 PW06300003 WESTON SOLUTIONS AUSTIN PWC0046 UNDERGROUND INC SMITH CONTRACTING PW06200022 CO INC SOUTHWEST PW06200018 CONSTRUCTORS GEN. CIVIL ENGINEERING SVCS ROTATION LIST 20062008 ACWP EAST 11TH STREET ALLEY ACWP-GOVALLE 5- JOHNSON CREEK MANCHACA ROAD BRANCH LIBRARY IMPROVEMENTS Substitution - D Add Add WHM TRANSPORTATION ENGINEERING ACCUTECH SURVEYING VICKERY & ASSOCIATES INC DIMENSIONS UNLIMITED N N Y N/A NA NA $ $ Unknown PW PW PW STEVE NELSON BRENDA BAKER MIKE PEATROSS MANDO CUBRIEL N N N 5/2/2007 5/1/2007 5/4/2007 Y Y Y Unavailability after reasonable notice to proceed. Solicitation goals are being met. To increase MBE or WBE participation. Unable to deliver automatic entrance sliding doors. 600.00 RPLS SURVEYING 2,900.00 SURVEYING GLASS/WINDOW SLIDING DOOR 9,895.00 INSTALLATION 13 4/30/2007 Delete N NA $ Library N 5/2/2007 Y Additions 6 Deletions 1 Request for Change Summary for April 2007 Substitutions Scope Changes 4 2 4 Certified firms Added, Replacing 3 Non-Certified/ 1 Certified 0 Total 13 A Sub-contractors or sub-consultants may be added to a contract for the following reasons There are no MBE or WBE firms certified for the scope of work at the time of the request Certified Non-Certified 2 4 0 1 0 2 1 2 3 4 5 6 7 Substitutions of sub-contractors or sub-consultants shall be permitted only on the following bases unavailability after receipt of reasonable notice to proceed failure of performance financial incapacity refusal by the subcontractor or sub-consultant to honor bid or proposal price mistake of fact or law about the elements of the scope of work of a solicitation where a reasonable price cannot be agreed failure of the sub-contractor or sub-consultant to meet insurance, licensing or bonding requirements the subcontractor's or sub-consultant's withdrawal of its bid or proposal B C D E F G To increase MBE or WBE participation Change in contract amount Solicitation goals are being met Pricing from Certified firms was not competitive or did not respond to solicitation to submit pricing Specification requirements or prior work with the project Like kind Reasons for denying a Request for Change of Compliance Plan Good Faith Efforts documentation was not included with request or failed to complete good faith efforts requirements Sub-contractor or sub-consultant was added to contract without DSMBRs prior written authorization H I Page 1 of 1

Related docs
CHANGE DELETE FORM CHANGE DELETE FORM
Views: 3  |  Downloads: 0
Scope
Views: 29  |  Downloads: 0
Scope Change Request Form
Views: 71  |  Downloads: 17
request for change template
Views: 44  |  Downloads: 3
Scope Change Request
Views: 235  |  Downloads: 50
How To Delete a Participant
Views: 14  |  Downloads: 0
REQUEST-CHANGE management
Views: 3  |  Downloads: 0
Project Change Request Form
Views: 90  |  Downloads: 0
REPORT OF CHANGE
Views: 12  |  Downloads: 0
Other docs by Booby Gibson
Intermix Media Inc Ammendments and Bylaws
Views: 144  |  Downloads: 0
adopt210
Views: 105  |  Downloads: 0
Form 8829 Expenses for Business Use of Your Home
Views: 574  |  Downloads: 7
Board Resolution Designating a Purchasing Agent
Views: 241  |  Downloads: 4
Letter of Intent to Purchase a Business
Views: 3328  |  Downloads: 315
Checklist for purchasing used vehicles
Views: 366  |  Downloads: 10
My first "Celebrity Blog"
Views: 368  |  Downloads: 0
Users marcsigal Desktop term papers bus_rubric01
Views: 196  |  Downloads: 0
CUSTOMER COMPLAINT RESPONSE LETTER
Views: 5153  |  Downloads: 65
Dirty Joke Cheat
Views: 993  |  Downloads: 11
Maytag Corp Ammendments and Bylaws
Views: 260  |  Downloads: 3