									                                                    Los Angeles Community College District Proposition A/AA Bond Program
                                               BuildLACCD CONTRACTOR'S JOB BOARD - QUARTERLY LOOK AHEAD SCHEDULE
                                                                          915 Wilshire Blvd., 810 Floor, Los Angeles, CA 90017

              THIS SPREADSHEET IS ONLY A LOOK AHEAD. FOR ACTUAL PRE-BID AND BID OPENING DATES, log on to www.build-laccd.org click on
            "Contracting & Bidding Site", then " Universal Reprographics" link. This information does not supersede the project plans and specifications.

2nd Quarter
                      Type of            Approx. Sq.                 Estimated    LEED        Design
 Campus                                              Project Type                                            CPM Team                           Project/Description                         Job Walk   Bid Awarded
                      Facility               Ft.                      Budget     Certified     Team
                                                                                                                              Selective demolition, removal of certain interior
                                                                                                                              partitions, patching of walls, ceilings, floors where walls
                                                                                                                              ere removed; reconfigure lights and mechanical
                                                                                                                              systems within existing ceiling grid to allow for new
                                                                                                             BuildLACCD       room configurations, provision for new systems
                Video Conferencing
 District                                   N/A      Modernization    $475k         No          N/A          Xavier Ortiz     furniture electrical and telecommunications                    4/1/08       Yes
                      Centers
                                                                                                           (213) 503-7946     connections (furniture N.I.C.), paint all walls, new
                                                                                                                              telecommunications wiring throughout, some new
                                                                                                                              electrical outlets, patch and paint walls in the
                                                                                                                              designated District Campuses locations offices and,
                                                                                                                              provide structural connections for cabinet millwork.
                                                                                                             Ann Kovara       The items to be procured are broken down for the
                 CDC Furniture and
 District                                   N/A      Procurement       N/A          No          N/A          BuildLACCD       purposes of bidding into: Furniture and Equipment for           N/A          No
                    Equipment
                                                                                                           (213) 996-2578     Child Development Centers.
                                                                                                               Harris &
               RWGPL - Site Utilities                                                                         Associates    Project will expand existing facility to house a new
  City         Infrastructure (Central     3,854      Renovation       $15M                    ARUP       Christopher Dunn chiller and rooftop cooling tower.                               1/30/08       Yes
                        Plant)                                                                             (323) 953-4000
                                                                                                                x3089
                                                                                                                            Renovation project to include addition of a storefront,
                                                                                                               Harris &     interior demolition/renovation for revised
                                                                                                              Associates    classrooms/labs and offices, and replacement of
                                                                                             The Albert
  City             Franklin Hall          102,845     Renovation      $13.5M        No                    Christopher Dunne existing plumbing fixtures and mechanical equipment.
                                                                                               Group
                                                                                                           (323) 953-4000 Additional electrical is per the classroom and office
                                                                                                                x3089       layouts and Sitework is limited to protecting and/or
                                                                                                                            replacing existing landscaping.
                                                                                                                            Provide consruction contract support to the campus
                                                                                                                            Move Management Team in the following areas:
                                                                                                                            General Construction- carpenters,
                                                                                                                            partitions/workstations, new partitions, demount
                                                                                                                            whiteboards and tack boards, install whiteboards and
                                                                                                                            tack boards, remove and replace ADA Ramp Railing to
                                                                                                                            allow furniture access, mount curtain rods for blinds,
                                                                                                                            haul away debris to nearest certified approved landfill,
                                                                                                                Jacobs
                 Temp Facilities R5                                                                                         install the wall mounting attachment for one flat sxreen
                                                                                                             Bob Herman
  East        Replacement (AKA) Move        N/A       Renovation      $100k         No          N/A                         TV, remove wall/shelving fastners, seismically fasten           3/21/08       Yes
                                                                                                           (323) 859-2330
                 Manager Support                                                                                            shelving to wall, etc. Electrical - provide and install
                                                                                                                 x102
                                                                                                                            final electrical connections for partititions from panel to
                                                                                                                            base feed. Hook-up of AV equipment: for cable TV
                                                                                                                            sets. Install electronic lecterns, install wall mounted
                                                                                                                            speakers or projectors, install electrical conduit and
                                                                                                                            cables for "Smart Boards" with IT connection. Remove
                                                                                                                            and reinstall classroom roll down projection screen,
                                                                                                                            etc. Plumbing- Provide and install wwater line for 4
                                                                                                                            refrigerators for icemakers. Provide and install
                                                                                                                            commercial gas stoves and commerical gas dryers
         R:/Outreach/QtrlyLookahead_April08-Dec08_042408                                         1 of 9
                                                                                                 Jacobs       Work consists of site preparation and 36 month lease,
            Campus Swing Space-
                                                                                               Bob Herman     delivery and installation and removal of seven (7) new
East           Temporary Art             N/A     Relocation     $1.6M   No                                                                                                  5/5/08    No
                                                                                             (323) 859-2330   modular single story buildings. Please refer to Notice
              Department Reloc
                                                                                                  x102        To Bidders for additional scope of work..
                                                                                                              Contractors to provide the supply and installation of
                                                                                                              non-water supplied urinals for select LACCD College
                                                                                                              campuses, and satellite or future campus locations.
                                                                                                              This Invitation to Bid is one in a series of Bids that
                                                                                                              will be solicited for each campus for this type of
                                                                                                              work. Bidders must supply a zero-water consumption
                                                                                                              urinal that is District State Architect approved prior to
                                                                                                 Jacobs       bidding. Bidders must provide the labor for the
             Retrofit/Installation of             Supplier /                                                  installation of all urinals to be fully functional,
                                                                                               Bob Herman
East        Non-Water Use Urinals        N/A      Rebate /      $338k   No        N/A                         throughout the campus, as directed by the Program             5/8/08    No
                                                                                             (323) 859-2330
            (Cartridge Type Model)               Installation                                                 Manager, College Project Manager, or their authorized
                                                                                                  x102
                                                                                                              representatives. Bidders are required to provide
                                                                                                              material receipts for each unit installed to allow the
                                                                                                              District to pursue rebates attained through the
                                                                                                              Metropolitan Water District of Southern California
                                                                                                              (MWD). Currently, the rebate value for each retrofit
                                                                                                              urinal is up to $1,225. The District anticipates that the
                                                                                                              rebates will off-set the Total Bid Price for this Bid.
                                                                                                              Bid out by the City of Monterey Park: The project will
                                                                                                              develop a Transit Center in conjunction with the
                                                                                                              redevelopment of the campus of ELAC which will
                                                                                                              create an off - street terminal which will provide a hub
                                                                                                 Jacobs       for the following transit entities: MTA, City of
                                                                                               Bob Herman     Montebello and City of Monterey Park. The Transit
East            Transit Center                   Renovation     $1M     No       TBD
                                                                                             (323) 859-2330   Center will be designed to provide an attractive and
                                                                                                  x102        safe environment for transit passengers. The waiting
                                                                                                              area will be equipped with bus shelters, seating , trash
                                                                                                              receptacles, informational kiosks, informational
                                                                                                              signage, lighting, landscaping, paving and security
                                                                                                              cameras and emergency telephone.
                                                                                                 Jacobs
                                                                                                              Scope includes the construction a temporary parking
              Southgate Parking                                                                Bob Herman
East                                             Renovation     TBD     No        IPD                         lot for the East Los Angeles College - South Gate
                Resurfacing                                                                  (323) 859-2330
                                                                                                              Campus.
                                                                                                  x102
                                                                                                 Jacobs
                                                                                 P2S
              Baseball Fencing &                                                               Bob Herman     Scope includes additional fencing, asphalt paving and
East                                     N/A        New         $2.2M   No    Engineering,
                   Paving                                                                    (323) 859-2330   drainage
                                                                                  Inc.
                                                                                                  x102
                                                                                                              Work consists of demolition of an existing 1,6400 S.F
                                                                                                              Child Development Center and construction of one-
                                                                                                              story 17,257 S.F Child Development Center and
                                                                                              Pinnacle One    related infrastructure work at the new CDC building
              Child Development                                                               Nghi Nghiem     site. Work includes: The ground up construction of a
Harbor                                  17,257      New         $7.8M   Yes      PBWS                                                                                       4/10/08   No
                    Center                                                                   (310) 835-0466   word frame, Type 5, NR construction with major
                                                                                                  x105        structural members of steel and the completion of all
                                                                                                              ancillary tasts including all underground utilities, finish
                                                                                                              site work and landscaping. See Notice to Bidders for
                                                                                                              additional scope of work.




       R:/Outreach/QtrlyLookahead_April08-Dec08_042408                             2 of 9
                                                                                                                   Work consists of construction of a one-story, 47,000
                                                                                                                   S.F. building with a gym, wellness/weight room and
                                                                                                                   locker rooms. The ancillary facilities will include
                                                                                                                   exercise rooms, classrooms, offices, a therapy pool,
                                                                                                                   an adaptive PE room and a trainer's room. A campus
                                                                                                                   police office is also in the building. Work includes: A
                                                                                                                   steel frame structure with some CMU and sheer walls.
                                                                                                     Pinnacle One
                                                                                                                   The building envelope is metal stud construction
                                                                                                   Mark Schoeppner
Harbor     PE and Wellness Center     47,000       New         $16.5M      Yes     Leo A Daly                      finished with cement plaster and corrugated metal               4/16/08   No
                                                                                                    (310) 835-0466
                                                                                                                   siding. The roof is corrugated steel deck with
                                                                                                         x102
                                                                                                                   thermoplastic membrane roofing. Building is heated
                                                                                                                   and cooled by a campus central plant and air handling
                                                                                                                   units mounted on the roof. Abatement of hazardous
                                                                                                                   materials is also included, prior to the demoliton of the
                                                                                                                   existing Physical Education building in accordance with
                                                                                                                   Asbestos and Lead-Based paint survey dated 4/17/6
                                                                                                                   and Asbestos Abatement and Lead-Based Paint
                                                                                                                   Scope of work includes demolition, new were prepared
                                                                                                                   Project Specifications dated 8/1/06. All accessibility,
                                                                                                     Pinnacle One
                                                                                                                   grading and drainage, landscaping, plumbing/irrigation,
           Theater Drama Speech                                                                    Mark Schoeppner
Harbor                                          Renovation   $2.5 to $3M   No    Rosetti Jorgensen                 exterior lighting, exterior electrical, window & door
                  Building                                                                          (310) 835-0466
                                                                                                                   installation, and painting around the Music, Fine Arts,
                                                                                                         x102
                                                                                                                   and Drama building.

                                                                                                     Pinnacle One
                                                                                                                   Construction of new stage rigging, electrical, lighting,
            Theater Rigging and                                $1M to                              Mark Schoeppner
Harbor                                          Renovation                 No    Rosetti Jorgensen                 audio and video in the Theater / Drama/Speech
                 Lighting                                      $1.2M                                (310) 835-0466
                                                                                                                   Building and Music Recital Hall
                                                                                                         x102
                                                                                                                      Project consists of an Entrance Monument plaza and a
                                                                                                                      structure located on the campus corner of Hubbard
                                                                                                                      Avenue and Eldridge Boulevard. The project includes
                                                                                                                      a contemporary cast-in-place concrete mission style
                                                                                                                      tower and a steel structure of approx. 30 feet in height,
                                                                                                                      with an integral LED matrix display sign and fixed
                                                                                                        GSE
                                                                                                                      lettering identifying the campus name. Along with the
Mission     Entrance Monument          30'         New          $1M        N/A   Quatro Design     Nick Quintanilla                                                                4/15/08   No
                                                                                                                      tower, a steel trellised arcade and cast-in-place
                                                                                                   (818) 367-7236
                                                                                                                      support structure are part of the project as well. The
                                                                                                                      project also includes extensive landscaping, irrigation,
                                                                                                                      accent lighting, a "dry arroyo" landscape feature and
                                                                                                                      decorative concrete paved areas and walkways. In
                                                                                                                      addition, relocation of a 4" gas line and other
                                                                                                                      underground utilities are part of this project.
                                                                                                                      Demolition of existing interior wall partitions and
                                                                                                                      finishes, and existing infrastructure, including, but not
                                                                                                                      limited to electrical lighting systems, therostats,
                                                                                                                      mechancial ductwork, piping and fixtures. New work
                                                                                                        GSE
           Instructional Building -                                                                                   shall include the construction of full height hard-wall
Mission                                N/A       Remodel       $970k       No    Quatro Design     Nick Quintanilla                                                                5/6/08    No
             Culinary & Faculty                                                                                       partitions and reinstallation of new lighting, fire alarm,
                                                                                                   (818) 367-7236
                                                                                                                      and related electrical, mechanical, and plumbing
                                                                                                                      systems. New work will also include, but not be limited
                                                                                                                      to new case-work, flooring, and suspended ceiling
                                                                                                                      systems.




      R:/Outreach/QtrlyLookahead_April08-Dec08_042408                                   3 of 9
                                                                                                                 Construction of a new 2-story building with a basement
                                                                                                                 level and a loading dock at the basement level. The
                                                                                                                 C.B.C. designated construction type is "TYPE IV
                                                                                                                 Heavy Timber" with primary structural components
                                                                                                                 being poured-in-place concrete and structural steel
                                                                                                                 with brace frames. The building totals approx. 73,000
                                                                                                   GSE
            Family & Consumers                                                                                   SF and will house the culinary arts departments and
Mission                              73,000        New       $44.5M    Yes                    Nick Quintanilla                                                                 5/6/08   No
              Studies Building                                                                                   the campus bookstore. Major building components
                                                                                              (818) 367-7236
                                                                                                                 include approx. 15,000 SF of varius kitchen laboratory
                                                                                                                 spaces and production kitchen areas, a kitchen
                                                                                                                 demonstration lecture hall, a student dining hall, a
                                                                                                                 presentation dining room, extensive walk-in coolers
                                                                                                                 and freezers, kitchen storage and delivery area. For
                                                                                                                 additional scope of work, please refer to Notice To

           Campus Administrative                                                                   GSE           This project includes remodelling the office space &
Mission      Services Building        N/A        Remodel     $1.03 M   No    Steven Fader     Nick Quintanilla   updating all the code requirements for Administrative
                 Remodel                                                                      (818) 367-7237     Wing of Campus Administrative services Building


                                                                                                                 The scope of this highly specilized project includes
                Campus-Wide                                                                        GSE
                                                                                                                 installation of new equipment for Fire Safety in the
Mission      Infrastructure - Fire    N/A        Remodel     $500 K    No       Psomas        Nick Quintanilla
                                                                                                                 existing 5 campus buildings & intigrating new builidings
            Safety Systems (FSS)                                                              (818) 367-7236
                                                                                                                 to the existing Fire Safety systems.

                                                                                                                 The proposed development includes the extension of
                                                                                                                 Eldridge Avenue from Harding Street eastward to
                                                                                                                 Maclay Street, on-site develoment for the Health and
                                                                                                   GSE           PE, Fitness Center and a surface parking lot, Maclay
            RWGPL - Extended
Mission                               N/A        Remodel      $1M      No       Psomas        Nick Quintanilla   Street improvents to accomodate the Eldridge Avenue
           Campus Improvements
                                                                                              (818) 367-7237     connection and future traffic demands, intersetion
                                                                                                                 improvements at Harding/Eldridge and Maclay/Eldridge
                                                                                                                 and new utility infrastructure to and within the subject
                                                                                                                 property.


                                                                                                   GSE           This project includes approximately 60.764 Sq Ft of
            Family & Consumers
Mission                              60,764        New       $41.6 M   YES      Quatro        Nick Quintanilla   Culnary arts facility. Facilities includes kitchens, dining
              Science Building
                                                                                              (818) 367-7237     spaces, faculty offices, & student space.


                                                                                                                 The scope of this highly specilized project includes
                Campus-Wide                                                                        GSE
                                                                                                                 installation of new equipment for Campus security in
Mission    Infrastructure - Campus    N/A        Remodel     $500K     No       Plan Net      Nick Quintanilla
                                                                                                                 the existing 5 campus buildings & intigrating new
           Security Systems (CSS)                                                             (818) 367-7236
                                                                                                                 builidings to the existing security systems.
                                                                                                             This project consists of the delivery, setup, and
                                                                                                             removal upon completion of lease for both DSA and
                                                                                                 Swinerton   Department of Housing (DOH) trailers for a two year
                 Temporary
Pierce                                N/A       Renovation    $2M      No    Amador/Whittle   Andrew Ramsey term lease with the option of a year extension.                    4/1/08   Yes
              Classroom/Office
                                                                                              (818) 710-8409 Number and type of trailers required are to be as
                                                                                                             shown in the construction drawing set. The sitework
                                                                                                             will also be completed under the same contract and to
                                                                                                             be released as on bid package.
                                                                                                                 Project consist of abatement and demolition of existing
                                                                                                 Swinerton       barn structures and construction of a 7-acre parking
                                                                              Carden-Ten
Pierce        East Parking Lot        N/A       Renovation   $2.6M     NO                      Richard Nasr      lot, including associated curb and gutter, street             4/8/08   No
                                                                               Architects
                                                                                              (213) 896-3484     lighting, underground utilities, grading, landscaping,
                                                                                                                 striping and signage.

      R:/Outreach/QtrlyLookahead_April08-Dec08_042408                              4 of 9
                                                                                                                  Exhibition and Events Center Project consists of
                                                                                                                  grading and utilities, a parking lot, adding surfacing to
                                                                                                                  existing arenas, a new toilet building, and lighting
                                                                                                                  poles. In addition to DSA approved drawings of the
                                                                                                   Swinerton      following Non DSA alternates are included: Alternate
              Animal Sciences and                                                Berliner
 Pierce                                 N/A         other       $2.4M    NO                      Richard Nasr     #1- Horseman's Fundamental & Shade Structure;               5/6/08   No
               Exhibition Center                                                Associates
                                                                                                (213) 896-3484    Alternate #2- Judges Station; Alternate #3- Water
                                                                                                                  Station and Manure Storage. Animal Science Project
                                                                                                                  consist of Structures A, B, C, D, E, new Fire Road,
                                                                                                                  Widened Paper Tree Road, Walkways, new fencing,
                                                                                                                  update Restrooms in (E) Bldg., new underground
                                                                                                               Project consists of construction of new wellness pool
                                                                                                               and existing pool refurbishment. Plans also include
                                                                                                               alterations to and modernization of the South
                                                                                                   Swinerton   Gymnasium; Moderniation of the North Gymnasium,
               Physical Education
 Pierce                                 N/A      Renovation     $13.5M   No       Psomas        Andrew Ramsey and stadium field house. Scope also includes the                5/8/08   No
                  Renovation
                                                                                                (818) 710-8409 refurbishing of the concessions building, restrooms,
                                                                                                               baseball and softball fields: ADA path of travel to the
                                                                                                               tennish courts and football field and refurbishing of the
                                                                                                               existing bleachers and ADA access at the stadium.

                                                                                                                  The scope of work addresses re-configuration of the
                                                                                                                  facility to reflect changed curriculum needs and
                                                                                                                  modifications of some areas based on increased use.
                                                                                                     CCG
                                                                                                                  The four racquetball rooms, no longer used for
Southwest   PE Gym, Pool, Bleachers     N/A      Renovation     $1.3M    No    Cannon/KDG        Ed Bilezikjian
                                                                                                                  racquetball, will be reconfigured into a classroom and
                                                                                                (323) 241-1750
                                                                                                                  aerobics room. Showers will be added in the women’s
                                                                                                                  locker room, and repairs will be made to address
                                                                                                                  maintenance issues.
                                                                                                                  The renovation and modernization of the 77,300 SF
                                                                                                                  Lecture Laboratory Building includes water-proofing the
                                                                                                     CCG          roof and exterior skin of the building, a complete
              Lecture Laboratory                                               LHA a division
Southwest                              78,700    Renovation     $5.6M    Yes                     Ed Bilezikjian   upgrade to the air conditioning system, modernization
            Building- Modernization                                            of GKKWorks
                                                                                                (323) 241-1750    of data/voice technology, and the incorporation of state-
                                                                                                                  of-the-art, smart classroom technology to the majority
                                                                                                                  of the classrooms.

              Lease Agreement for                                                                    AVA       Buildig a Restoration and Modernization (Swing Space
  Trade        Modular Buildings                Modernization   $180k    No       PBWS          Deba Mohapatra Lease Component). See Notice to Bidders for scope               N/A     No
                  (Equipment)                                                                   (213) 763-7392 of work.


                                                                                                               Construction to provide utility connection to modular
                                                                                                               building. Los Angeles Trade Technical College
              Lease Agreement for                                                                              (LATTC is soliciting Bids from potential contractors to
                                                                                                     AVA       select one general contractor along with qualified
            Modular Buildings (Swing
  Trade                                 N/A      Renovation     $400k    No       PBWS          Deba Mohapatra subcontractors for construction of a trailer park               N/A     No
               Space Installation
                                                                                                (213) 763-7392 consisting of 16 total buildings. The modular buildings
                  Component)
                                                                                                               will be leased for 24 months with month-to-month lease
                                                                                                               extension beyond. For additional scope of work,
                                                                                                               please refer to Notice To Bidders.




      R:/Outreach/QtrlyLookahead_April08-Dec08_042408                                5 of 9
                                                                                                            Work consists of interior and exterior improvements to
                                                                                                            the existing building, a new lobby addition, mechanical
                                                                                                            building addition, exterior courtyard, exterior plaza and
                                                                                                            minor parking improvements. Work includes: A
                                                                                                            structural upgrade to the building including new
                                                                                                            concrete shear walls, foundations floor and roof
                                                                                                            diaphrams and framing, horizontal steel trusses and
                                                                                                  AVA
          Building A Restoration                                                                            anchorage. Site Improvements include landscaping,
Trade                                 N/A      Modernization   $40M     No    Tetra Design   Deba Mohapatra                                                               4/29/08    No
           and Modernization                                                                                pavement and drainage, planters, benches, lighting,
                                                                                             (213) 763-7392
                                                                                                            utilities and parking modifications. Building systems
                                                                                                            include new HVAC, plumbing, electrical, lighting,
                                                                                                            security and telecomm./data. Additional improvements
                                                                                                            include new and renovated elevators, new wheelchair
                                                                                                            lifts, new ceilings, walls, flooring, finishes, windows,
                                                                                                            stairs, ramps, railings, hardware casework, equipment
                                                                                                            and signage.

                                                                                                            This is for the renovation of existing building (approx.
                                                                                Breen             AVA
         Fashion & Cosmetology                                                                              69,000 GSF) HVAC Systems including HVAC major
Trade                                 N/A       Renovation     $2.7M    Yes   Engineering,   Deba Mohapatra
         Building- HVAC Upgrade                                                                             components, VAV boxes, new boiler, hazardous
                                                                                  Inc.       (213) 763-7392
                                                                                                            materials abatement, etc..
                                                                                                              Project consists of site renovation including hardscape,
         RWGPL- Fulton Entry and
                                                                                                   URS        landscape, irrigation, walkways, accessible ramps and
          Monarch Square and
Valley                               350,000    Renovation     $3.4M    No      Berliner     Rinaldo Veseliza stairs, bus/car drop off, a new bus shelter and             4/2/08     No
          RWGPL Wayfinding &
                                                                                             (818) 756-0953 pedestrian lighting. Project area is approximately
            Site Furniture I
                                                                                                              350,000 SF and wayfinding signage and installation of
                                                                                                              new site furniture.
                                                                                                   URS
                                                                                                              See Notice to Bidder under current opportunities or
Valley    IT Dept. Improvements       N/A      Procurement      N/A     No        N/A        Rinaldo Veseliza                                                              N/A      4/8/08
                                                                                                              Universal Reprogramphics links.
                                                                                             (818) 756-0953

                                                                                                               Project consists of approx. 103,000 S.F. of newly
                                                                                                               constructed general lecture classrooms, laboratories
         Allied Health and Science
Valley                               103,000       New         $160k    Yes       N/A                          dedicated to the study of Life Sciences, Physical          4/3/08     No
            Center (IT Systems)
                                                                                                               Scienxes and Nursing Clinical curricula. This project is
                                                                                                               LEED Certified.
                                                                                                              New construction of approx. $25,900 SF Child
                                                                                                              Development Center on an approx. 2.18 acres of site
                                                                                                              improvement. Work consists of a one story type V-non-
                                                                                                   URS        rated, wood frame, slab on grade, fully fire sprinklered
            Child Development
Valley                               25,900        New         $11.5M   No     Card Ten      Rinaldo Veseliza building. Work includes: demolition, abatement,             4/29/08    No
                  Center
                                                                                             (818) 756-0953 sitework, concrete, CMU, carpentry, roofing, doors and
                                                                                                              windows, finishes, food service euipment, plumbing,
                                                                                                              HVAC, electricl wiring, fire protection, security system,
                                                                                                              and other systems. Refer to Notice to Bidders for
                                                                                                              additional scope of work.
                                                                                                               The items to be procured are broken down for the
            Purchase of Dance                                                                                  purposes of bidding into one (1) Bid Category(ies)
Valley                                N/A        Purchase       N/A     No        N/A              N/A                                                                     N/A       No
          Studio Flooring Surface                                                                              consisting of the following:Dance Stuido Flooring; Step
                                                                                                               Flooring Surface; and 5-gallon kit for installation.




     R:/Outreach/QtrlyLookahead_April08-Dec08_042408                               6 of 9
                                                                                                                                This is a competitive bid for the purchase by LACCD of
                                                                                                                                the following Gym Complex and Equipment for its
                                                                                                                                colleges throughout the LA area. The items to be
                                                                                                               Ann Kovara
               Purchase of Gym                                                                                                  procured are broken down for the purposes of bidding
  Valley                                     N/A      Procurement       N/A          No           N/A          BuildLACCD                                                                   N/A        4/29/08
             Complex and Equipment                                                                                              into one (1) Bid Category(ies) consisting of the
                                                                                                             (213) 996-2578
                                                                                                                                following: Exterior Canopy, Bleachers, Dance Room
                                                                                                                                Equipment and installation of owner furnished
                                                                                                                                equipment and accessories.
                                                                                                                                This is a competitive bid for the purchase by LACCD of
                                                                                                                                the following Gym Complex and Equipment for its
                   Purchase of                                                                                 Ann Kovara
                                                                                                                                colleges throughout the LA area. The items to be
  Valley       Miscellaneous Sports          N/A      Procurement       N/A          No           N/A          BuildLACCD                                                                   N/A        4/29/08
                                                                                                                                procured are broken down for the purposes of bidding
                    Equipment                                                                                (213) 996-2578
                                                                                                                                into one (1) Bid Category(ies) consisting of the
                                                                                                                                following: Miscellaneous Sports Equipment.
                                                                                                                              Work consists of selected demolition and hazardous
                                                                                                                              abatement work, refurbishment of classrooms and
                                                                                                                              offices, selected mechanical, plumbing and electrical
                                                                                                                   URS        system work. Work includes hazardous material
                                                                                               Gonzalez
  Valley        Art/Music Phase II           N/A       Renovation      $550k         No                      Rinaldo Veseliza abatement, painting, new windows, new doors and              4/24/08       No
                                                                                               Goodale
                                                                                                             (818) 756-0953 frames, new door hardware, new markerboards, new
                                                                                                                              tackboards, new projectors, flooring and projection
                                                                                                                              screens, new powered entry door, new audio visual
                                                                                                                              systems and other incidentals, misc. wood framing,
                                                                                                                              foundations, exterior finishes and windows.
                                                                                                                   URS        Project includes removal of existing and installation of
  Valley       RWGPL- General Ph I         220,000     Renovation      $2.6M        Yes         Berliner     Rinaldo Veseliza new landscaping and site furniture at Fulton Court and
                                                                                                             (818) 756-0953 Monarch Square of area approximately 220,000 SF.
                                                                                                                                Contractors to provide the supply, rebate and
                                                                                                                                installation of non-water supplied urinals for select
               Retrofit/Installation of                 Supplier /                                             BuildLACCD
                                                                                                                                LACCD College campuses, and satellite or future
  West        Non-Water Use Urinals          N/A        Rebate /       $125k         No           N/A          Albert Safille                                                              3/25/08       Yes
                                                                                                                                campus locations. This invitation to Bid is one in a
              (Cartridge Type Model)                   Installation                                           213) 996-2244
                                                                                                                                series of Informal Bids that will be solicited for each
                                                                                                                                campus for this type of work. See Notice To Bidders
                                                                                                                                for additional bid specifications.
3rd Quarter
                      Type of             Approx. Sq.                 Estimated    LEED         Design
 Campus                                               Project Type                                             CPM Team                           Project/Description                     Job Walk   Bid Awarded
                      Facility                Ft.                      Budget     Certified      Team
                                                                                                                 Jacobs
                                                                                                               Bob Herman       Scope includes replacing the exisitng E3/E5 bldgs with
  East          E3/E5 Replacement           45,000     Renovation      $7.2M        Yes        WWCOT
                                                                                                             (323) 859-2330     a 3-story 45,000 sq. ft. classroom building
                                                                                                                  x102

                                                                                                                  GSE           The scope of this project is to relocate LADWP
              RWGPL -LADWP Water
 Mission                                     N/A        Remodel        $ 200 K       No         Psomas       Nick Quintanilla   waterline which crosses the Health, Fitness, & PE
                Line Relocation
                                                                                                             (818) 367-7237     building.

                                                                                                                               Renovate 36,082 GSF including upgrades to basic
                                                                                                                               electrical and plumbing systems, modifications to
                                                                                                                 Swinerton
                                                                                                                               HVAC systems, renovation of restrooms, technology
  Pierce        Fine Arts & Music           36,082     Renovation      $1.7M        NO        Johnson Fain   Isabella Golovaty
                                                                                                                               and communications upgrades, new floor finishes, new
                                                                                                              (818) 610-6527
                                                                                                                               paint interior and exterior, window treatments, ADA
                                                                                                                               upgrades as needed.




         R:/Outreach/QtrlyLookahead_April08-Dec08_042408                                           7 of 9
                                                                                                                             Renovate 14,000 GSF including new windows, new
                                                                                                                             roofs, upgrades to basic electrical and plumbing
                                                                                                               Swinerton
                                                                                                                             systems, modifications to HVAC systems, renovation
  Pierce          Faculty Office          14,000       Renovation    $1.3M        NO        Johnson Fain   Isabella Golovaty
                                                                                                                             of restrooms, technology and communications
                                                                                                            (818) 610-6527
                                                                                                                             upgrades, new floor finishes, new paint interior and
                                                                                                                             exterior, window treatments, ADA upgrades as needed.

                                                                                                                             Renovate 28,550 GSF including modifications to the
                                                                                                                             rigging, catwalks and acoustical design in the stage
                                                                                                               Swinerton
                 Theater Building-                                                                                           area, stage lighting and sound system improvements,
  Pierce                                  28,550       Renovation    $1.5M        NO        Johnson Fain   Isabella Golovaty
                  Performing Arts                                                                                            modifications to HVAC system, renovation of
                                                                                                            (818) 610-6527
                                                                                                                             restrooms, technology and communications upgrades,
                                                                                                                             new floor finishes, ADA upgrades as needed.
                                                                                                                             Renovate 18,000 GSF including new windows,
                                                                                                                             upgrades to basic electrical and plumbing systems,
                                                                                                               Swinerton
                                                                                                                             modifications to HVAC systems, renovation of
  Pierce       Business Education         18,000       Renovation    $1.1M        NO        Johnson Fain   Isabella Golovaty
                                                                                                                             restrooms, technology and communications upgrades,
                                                                                                            (818) 610-6527
                                                                                                                             new floor finishes, new paint interior and exterior,
                                                                                                                             window treatments, ADA upgrades as needed.

                                                                                                               Swinerton     Removal & replacement of existing parking lot along
  Pierce       RWGPL-Parking Lot 1          N/A        Renovation    $3.7M        NO         PSOMAS        Isabella Golovaty with selected landscape improvements, an added fire
                                                                                                            (818) 610-6527 lane and revised layout.

                                                                                                                             Renovation/reconstruction of North & South
                                                                                                               Swinerton
                                                                                             Steinberg                       Gymnasiums, existing pool and deck, addition of a
  Pierce       PE Facilities-General        N/A        Renovation    $14.2M       NO                       Isabella Golovaty
                                                                                             Architects                      Wellness pool; renovations to Football Stadium and
                                                                                                            (818) 610-6527
                                                                                                                             related support facilities, various play fields
                                                                                                                 URS        Include demolition of existing buildings and construct a
  Valley     Student Services Center      41,200          New         $16M        Yes        Steinberg     Rinaldo Veseliza new Student Services Center of approx. 41,200 SF 2
                                                                                                           (818) 756-0953 story structural steel building.
                                                                                                               Turner
                                                                                                            Robert Miller    This project will provide the permanent second access
  West           Permanent Road             N/A           New         $20M         No         Psomas
                                                                                                           (310) 202-2575    road.
                                                                                                                x204
                                                                                                               Turner        This Building will provide all services from the
  West        Student Service Annex        3,000          New         $3M         Yes          COA          Robert Miller    bookstore except textbook slaes. There will also be a
                                                                                                           (310) 202-2575    coffee bar and site upgrades.
                                                                                                                x204
                                                                                                               Turner
                                        1500 seats &                                                        Robert Miller    This project will provide 1500 seats grand stand, a
  West       Grandstand & Restrooms                       New        $1.5M         No         WWCOT
                                          2,000 SF                                                         (310) 202-2575    small concession stand, and restroom.
                                                                                                                x204
                                                                                                               Turner
               Utility Infrastructure                                                                       Robert Miller    This project will provide the infrastructure to support
  West                                      N/A           New         $3M          No         WWCOT
                      Phase II                                                                             (310) 202-2575    our new buildings.
                                                                                                                x204

4th Quarter
                     Type of            Approx. Sq.                 Estimated    LEED         Design
 Campus                                             Project Type                                             CPM Team                          Project/Description                     Job Walk   Bid Awarded
                     Facility               Ft.                      Budget     Certified      Team
                                                                                                                          Reconditioning of the Campus 4160 KVA switchboard
             Emergency Lighting, Fire
                                                                                                                AVA       including installation of four (4) 5KV switches in 2
             Alarm and Security Sys,
  Trade                                     N/A           New        $820K        Yes       ME Engineers   Deba Mohapatra existing buildings south of the campus; site electrical
                  Electrical Site
                                                                                                           (213) 763-7392 trenching; installation high voltage feeders; electrical
                   Distribution
                                                                                                                          manhole, etc.


         R:/Outreach/QtrlyLookahead_April08-Dec08_042408                                         8 of 9
                                                                                                       Scope of work includes installation of emergency
                                                                                            URS
         Emergency Lighting/Fire                                                                       lighting, fire alarm and security systems i.e. lighting
Valley                                           Other      $1M     No     Arup       Rinaldo Veseliza
          Alarm/Security System                                                                        control relay, fire alarm control panel and scurity
                                                                                      (818) 756-0953
                                                                                                       camera, etc. throughout the campus
                                                                                                       Construct a new Library / Learning Resource Center
                                                                                                       facility of approx. 89,000 SF, with reinf. concrete
                                                                                                       spread footings and grade beams, steel columns and
                                                                                                       bracing, reinforced concrete slab on grade and
                                                                                            URS        structural steel framing. Steel framed roof with
            Library/ Resource                                             Pfeiffer
Valley                              90,350        New       $33M    Yes               Rinaldo Veseliza concrete filled metal deck. Lath and plaster exterior
             Learning Center                                              Partners
                                                                                      (818) 756-0953 cladding, insulated window glazing, metal panels, alum
                                                                                                       glazed doors, sunscreens and trim. Roofing includes
                                                                                                       flat "Cool roofing." Includes four exterior concrete filled
                                                                                                       metal pan stairs and one 2-stop hydraulic elevator. Full
                                                                                                       M/E/P/Fire Protection. LEED project.
                                                                                                       Renovation of approx. 15,700 SF Art Building, includes
                                                                                            URS
                                                                                                       demolition, repalcement of doors and windows, new
Valley     Life Science Building    15,700     Renovation   $850K   Yes   Caldwell    Rinaldo Veseliza
                                                                                                       walls, refurbishing floor, painting of wall/ceiling, and
                                                                                      (818) 756-0953
                                                                                                       installation of communication and security systems.




     R:/Outreach/QtrlyLookahead_April08-Dec08_042408                         9 of 9

								