LARP Magnet Program

Reviews
US LHC Accelerator Research Program bnl - fnal- lbnl - slac LARP Magnet Program S. Gourlay LARP Collaboration Meeting Napa, CA October 19, 2004 Directives DOE Guidance “It is our firm intention that the LARP activities serve to explore the limits of the technologies described herein. While the end products of LARP will be applied to the LHC, LARP is not intended to be an engineering an construction service organization to that facility.” “The LARP is not intended to replace existing base program support at the various laboratories in superconducting magnet development and other ongoing areas.” LARP Proposal “have fully developed and proven accelerator-ready magnet designs, ready for production, by about 2012, as required to support the LHC physics program.” LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 2 Magnet Program Goals • Improve long-term physics research opportunities of the LHC by providing magnet options for an LHC luminosity upgrade Large aperture, high gradient quadrupoles (main emphasis) High-aspect ratio, large aperture separation dipoles • Deliverables will be a successful R&D program, leading to accelerator-ready magnet design(s) (production magnets are out of scope) • Develop a collaborative environment between US national labs • Develop world-wide collaboration on high field magnets LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 3 Program Elements and Timeline “Three-year plan” to focus initial effort (FY05 – FY07) Must include development of technology for future US projects But . . . be conservative and focused enough to meet LHC goals. Start aggressively evaluate status and the challenge ahead FY05 Research Technology Base-Building FY08 FY10 FY12 Focused Development Prototype LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 4 Goals of the Three-Year Plan Assess challenges Determine parameter “reach” and scope for development program Aperture Quads and high aspect ratio dipoles Mechanical structures Provide AP with range of options* and understand trade-offs *Key to “dipole first” option is a large aperture dipole in high radiation environment LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 5 Aperture Bigger is better IR performance Radiation load 90 mm is initial baseline aperture Challenging enough! Leaves option of 2-layer coil with G > 200 T/m (Operating) Start with 2 layers of a 4-layer design (TQ1a) Affordable in FY05 Simple cable parameters (2-layer design requires time to study cabling issues) Quick start LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 6 Gradient As a Function of Bore Size 300 300 285 270 tesla 255 m 240 225 210 195 180 165 150 150 35 35 40 45 50 55 60 60 Rbore( Scale) 1000 Gradient as a function of Bore radius Nb3Sn at 1.8K Nb3Sn at 4.35K 0.01    Scale  1   0.01    Scale  2  0.01    Scale  3  0.01    Scale  4  NbTi at 1.8K NbTi at 4.35K mm LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay Organization Superconducting Magnets S.Gourlay Magnet Steering Committee (MSC) – Define program, identify tasks FNAL Representative A.V.Zlobin LBNL Representative G.Sabbi BNL Representative P. Wanderer and assign task managers Lab Representatives G. Sabbi, P. Wanderer, Z. Zlobin Lab representatives oversee tasks/sub-tasks at host laboratory Three Working Groups – Design Studies Model Magnet R&D Supporting R&D Lab Management Representatives S. Gourlay, M. Harrison, R. Stanek LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 8 Management Structure LARP Magnet Program S. Gourlay Task 1 Task 2 Magnet Steering Committee Task 3 Task 4 Working Groups Design Studies Task 5 Model Magnets Supporting R&D LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 9 FY04 Activities LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 10 FY04 Quadrupole Development • Design Studies –Dual-bore –Aperture –Geometries • Support Structure –Design and hardware 0 22 44 0 10 20 30 40 Rel. field errors (x10E-5) Rel. field errors (x10E-5) 0 2 4 6 8 10 12 14 16 18 20 0 2 4 6 8 10 12 14 16 18 20 LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 11 FY04 Dipole Development • Based on “Dipole-first” IR design –Large aperture, asymmetric –Non-cos-theta –Split coil geometry –High field, high radiation environment LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 12 FY04 Sub-scale Development •Magnet parameters –Clear bore 110 mm –Peak field 11 T –Gradient 100 T/m Uses existing coil design ~ $25k in additional parts LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 13 Racetrack Quadrupole with Sub-scale Coils Clear bore: 110 mm Magnet short sample Iss = 11.4 kA Bpeak = 11.2 T (in the end) Gss = 95 T/m Stored energy at Iss = 175 kJ Inductance at Iss = 2.7 mH F┴ F║ 21 Quenches to 93% of short sample LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 14 FY05 Program TQ1a – 2/4 layer 90mm quad Fabricate and test Open-midplane dipole 3-D mechanical design Thermal analysis Sub-scale magnets TQ2 – 2-layer 90mm quad Engineering design Dipole and/or quad as resources permit Heat x-fer, support structure, fab, assembly, etc. Combine with materials studies? Conductor and Cable Conductor procurement* Cable R&D *Conductor Development Program Long magnet issues Base program 15 LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay FY05 Task Distribution TQ1a Design/Analysis – LBNL/FNAL Winding – FNAL Reaction – LBNL Impregnation – LBNL Quadrupole Development Design Studies - FNAL/LBNL Dipole Development Design Studies – BNL Assembly – LBNL Test – BNL Conductor and Cable Measurements – BNL/LBNL/FNAL Cabling – LBNL Sub-Scale Tests (hold-back victim) Fabrication – LBNL/BNL Test – BNL LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 16 FY06 – Build and test 2 “more complex” Nb3Sn quadrupole models – Include two mechanical structure schemes – Build and test a “simplified” open mid-plane Nb3Sn dipole – Develop infrastructure for a long coil – Conductor and material development – Major conductor procurement LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 17 Long Magnet R&D Very high priority but funding limited Infrastructure Reaction furnace Handling VPI chamber or fixture Materials cost As proposed at last collaboration meeting. Topic for discussion – Can we improve the schedule? Is there a better way? FY04, 05 – Study issues (No budget – base program) FY06 – Infrastructure development FY07 – Fabrication and test of 3 – 4 m coil (long sub-scale) Essential first step - cost effective - established baseline with sub-scale coils LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 18 Task Distribution 3000 2500 2000 1500 1000 500 0 FY05 FY06 Quads Dipoles Long Mag Sub-scale Cond/Cable R&D Cond Proc LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 19 Three-Year Program LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 20 At the end of the “Three-year” plan – Some limited participation from CERN – CARE program Networking activities (ongoing) NED’s birthday New collaborative opportunities – Participation by KEK? – Several LARP magnets (new experience base) – Conductor progress – Maybe some LHC operating experience New directions? LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 21 LAPAC Comments – Recommend concentrating resources on a limited number of options. Main effort should be on quadrupoles, and effort on dipoles should be limited: “Given the limited resources the magnet program must be well focused on the most demanding challenge given the present knowledge of the luminosity upgrade layouts.” “Consequently the red line through the program must be to go from short quadrupole models as fast as possible to the first long quadrupole magnet and to reduce the parallel tracks to a minimum.” “… it may be worthwhile … to select a baseline design and to stick to it for the short model and long prototype magnet fabrication.” => FY05 program is consistent with LAPAC. FY06 program will be tuned based on LAPAC advice as well as experience with FY05 program. LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 22 Goals for the Meeting FY05 • Program details • Revise and update task sheets Establish framework for FY06 and FY07 programs Organization • WG and MSC meetings • Videoconferences LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 23 Summary Proposed funding profile is modest given program goals – We must maintain expected funding and base program support in order to be successful The program should integrate and utilize all available program resources – Broad-based R&D program to establish a firm technological foundation and provide a variety of options – Focused development to achieve LHC priorities LARP Collaboration Meeting October 2004 LARP Magnet Program – S. Gourlay 24

Related docs
LARP Magnet Program Meeting Summary
Views: 5  |  Downloads: 0
LARP Magnet Program Steve Gourlay
Views: 31  |  Downloads: 0
LARP Magnet 5-year plan V6.ppt
Views: 0  |  Downloads: 0
U.S. LARP MAGNET PROGRAM
Views: 0  |  Downloads: 0
The LARP Collimation Program
Views: 12  |  Downloads: 0
LARP-NSF Cryo Experimental Work Proposal
Views: 1  |  Downloads: 0
LARP Document Database
Views: 2  |  Downloads: 0
LARP Collaboration Meeting 8, April 2007
Views: 0  |  Downloads: 0
premium docs
Other docs by delontewest De...
Rental agreement
Views: 2977  |  Downloads: 35
Sample Executive Summary Momentex LLC
Views: 223  |  Downloads: 3
WAIVER OF NOTICE OF MEETING
Views: 177  |  Downloads: 5
Option to sell and option of first purchase
Views: 241  |  Downloads: 5
Gamers
Views: 118  |  Downloads: 0
Monroe Doctrine info
Views: 191  |  Downloads: 0
Alternative form
Views: 142  |  Downloads: 0
Form 8839 Qualified Adoption Expenses
Views: 147  |  Downloads: 1
Extension of Commercial Lease
Views: 243  |  Downloads: 3
Gamers[0]
Views: 130  |  Downloads: 0
Chapter 7 bankruptcy
Views: 557  |  Downloads: 19
Form 8812 Additional Child Tax Credit
Views: 838  |  Downloads: 11