Test Plan for binutils porting on BF533

Version No. 1.7

Released On june 9, 2004

Author(s) Omkar Murthy

Reviewed By Pradip Shah







Table of Contents



 1 Introduction

 2 Test Items

 3 Features To Be Tested

 4 Features Not To Be Tested

 5 Approach

o 5.1 Code Inspections

o 5.2 Unit Testing

o 5.3 System Testing

o 5.4 Regression Testing

o 5.5 Acceptance Testing

 6 Item Pass/Fail Criteria

 7 Suspension Criteria and Resumption Requirements

 8 Test Deliverables

 9 Testing Tasks

 10 Environmental Needs

 11 Responsibilities

 12 Staffing and Training Needs

 13 Schedule

 14 Risks and Contingencies

 15 Approvals

 To Do List

 Revision History

1 Introduction



Analog Devices Inc., hereinafter referred to as “ADI”, is a world leader in high

performance signal processing solutions. ADI positions the ADSP-BF53x family, also

known as the Blackfin Processor, as a full-fledged highly integrated system-on-a-chip

(SoC) solution for the next generation of digital communication and connected media

applications.



For the first member of this family – the ADSP BF535 – ADI has completed a port of the

uCLinux embedded operating system. It now intends to make available uCLinux for

other processors in the family, namely the ADSP BF531/2/3 processors.



This work involves three main components:

1. Linux Port, Bootloader and Library support

2. Peripheral device drivers for the Board.

3. Compiler tool chain



The objectives and tasks of the test effort as stated as follow:



Objectives



- Perform tests for binutils ported for on BF533 platform.







Tasks



- Test environment setup

- Regression Test









2 Test Items



The test plan for binutils details the various tests to be executed, test procedure,

schedule and deliverables.

Following tests will be performed:

1. Regression tests are carried out to ensure that the functionality and behavior

of the binutils hasn‟t changed while changes were done in the source code.

3 Features To Be Tested



Following tools will be tested under binutils

All the test cases will be maintained under respective sub directories named same as tool

name like gas, bfd, ld.

Test cases in correspondig subdirectories will be executed using dejagnu.



Tools Test cases and Description

1. gas create subdirectory bfin and include BF533 architecture and

instruction specific testcases.

Following categories of tests will be created.

1. 533 instruction set

Arithmetic

Logical

Input/Output

Interrupt

External Hardware Sync/control

Transfer instructions(conditional, unconditional)

Shift

Rotate

String

Iteration(loop, while..,)

Delay

Flag Related

General purpose transfer instructions(copy, move.,)

2. Relocations.



2. ld Special test cases will be created for linker.

relocation tests are listed in a table below

3. bfd Test case “bfin_bfd.c” test for bfd changes

4. binutils-all This subdirectory contains test cases for nm, size,

Objdump,Objcopy, readelf and ar.We will run all of the

existing test cases in this subdirectory.

Also include new test case for objdump, objcopy and

readelf, and nm accordingly.

5.Opcodes A Special tool „asmtesttool‟ is written to test opcodes.

Section 9 below describes the details of testing using this

tool.



Following assembly test cases will be executed:



Functionality/instruction type Testcase(s)

Arithmetic Arith-1.s

Arith-2.s

Arith-3.s

Arith-4.s

Arith-5.s

Arith-6.s

Arith-7.s

Arith-8.s

Arith-9.s



Control code (CC) ControlCode-1.s

ControlCode-2.s

ControlCode-3.s

ControlCode-4.s

Cache control CacheCtrl-1.s

CacheCtrl-2.s

CacheCtrl-3.s

CacheCtrl-4.s



Transefer Transfer-1.s

Transfer-2.s

Transfer-3.s

TestAndSet.s



Return Ret-1.s

Registers Register-1.s

Move Move-1.s

Move-2.s

Move-3.s

Move-4.s

Move-5.s

Logical-1.s

Logical-2.s

Logical-3.s

Logical-4.s

Logical-5.s

Logical-6.s

Logical-7.s



Interrupt Interrupt-1.s

Interrupt-2.s

Interrupt-3.s

Iteration-1.s



Delay Delay.s

Exception Exception-1.s

Exteral control ExtControl-1.s





Following relocation test cases will be executed manually:

Steps:

1.Create object file from the .s files using bfin assembler and linker

Example : bfin-elf-as main.s –o main.o

bfin-elf-as main1.s –o main1.o

bfin-elf-ld main.o main1.o –o main



2.Run bfin-elf-objdump tool on the object file.

Example: bfin-elf-objdump –D main

bfin-elf-objdump –r main



3.Verify whether all the relocations are resolved correctly or not.



Relocation type Test case(s)

Call call_main.s

call_main1.s

if.cc.jump ccjump_main.s

ccjump_main1.s

jump.l jumpl_main.s

jumpl_ain1.s

jump.s jumps_main.s

jumps_main1.s

Lsetup lsetup_main.s

lsetup_main1.s

preg=target pregeq_main.s

pregeq_main1.s

rN=target rNeq_main.s

rNeq_main1.s

Arithmetic relocations Arith_main.s

Arith_main1.s









4 Features Not To Be Tested



- C++ features will not be tested.

- Following tools under binutils will not be tested: gprof, dlltool and gasp.









5 Approach



5.1 Unit Testing



- Relocation testing. VDSP compatible relocations are being introduced in the

port. Relocation testing will test these relocations. Refer Section 8 for specific

tests that will be performed.

- Assembler testing. Assembler will be tested at the unit level. Refer Section 8

for details of the tests that will be run.





5.2 Integration Testing



All regression tests will be run on following platforms during acceptance

- SuSe Linux

- cygwint Linux.

5.3 System Testing



No Separate System testing is planned for binutils.

Note : Assembler and linker will be tested along with the gcc during system testing.

Binutils utilities will also undergo testing individually as described in this document.





5.4 Regression Testing



Regression tests are carried out regularly to ensure that the functionality and

behavior of the binutils hasn‟t changed while changes were done in the source code



Regression testing involves following steps

 Get the latest sources for binutils from the CVS repository.

 Compile and Build the binutils.

 Run binutils test suites using dejagnu tools. (Section 15 below describes the test

execution)



5.5 Performance and Stress Testing



No specfic performance or stress testing is planned for binutils. Gcc stress testing

does some testing of assembler and linker.





5.6 Documentation Testing



Document changes will be reviewed.





5.7 Beta Testing



NA.





5.8 Additional Testing



NA.







6 Item Pass/Fail Criteria



Regression Test:

There will be a set of expected results for these tests, which will be used by the tool

to decide whether the test is fail or pass.

Analyse the logs produced by dejagnu tools. Look at fails and cross check the

dejagnu tool‟s result by reproducing the error.

All the test cases flagged as unexpected fail or pass by dejagnu are considered as

fail.

All other tests are considered as having passed.



Opcode test:

‘asmtesttool’ reads each assembly instruction and compares with the expected opcode.

Depending on the results of comparison, the tools print the instruction and pass or fail against

them. An example is given as follows:





Example: Testing Opcode

„asmtesttool‟ test for all BF533 opcodes. It takes input file as command parameter.

Typically format of ininput file will look like

assembly code @ op code value

e.g.

IF CC R0 = SP; @ 0746

opcode value must be in hex.

No line should carry more then one set of assembly code. However there is no limitation

for number of lines in any input file.



OPTIONS

Other optional parameters are (preceded by '-' charecter):

'd': Show lots of debug info.

'e': Show only error (Supress the OK statement).

's': Suppress assembler error messages.

'h': Show this help statement



Running ‘asmtesttool’

set the envirnment variable BFIN_ASM_PATH to blackfin assembler path.

e.g export BFIN_ASM_PATH=/usr/bfin/binutils/bin/bfin-as



cd into the directory where your asmtesttool and input file is present.

Command : ./asmtesttool myinputfile

Above command will generate output for every line of inputfile, whether it fais or

succeed.



Alternatively the command : ./asmtesttoo –es myinputfile

will only show output for line which will get failed and also supress the assembler

messages.



Test results

Error at line 5: Assembler unable to generate op code for CALL (P1 ;

[omkar@linux testworkshop]$ ./asmtesttool test

Analyzing NOP and expecting opcode value 0(0x0000): OK

Analyzing RTS and expecting opcode value 16(0x0010): OK

Analyzing CLI R0 and expecting opcode value 48(0x 0030): OK

Analyzing JUMP (P0) ; and expecting opcode value 80(0x0050 ): OK

Analyzing CALL (P1 ; and expecting opcode value 28769(0x 07061):__temp.s:

Assembler messages:

__temp.s:3: Error:

parse errorInput text was `'

__temp.s:3: Error:

Parse error.

FAILED

Error at line 5: Assembler unable to generate op code for CALL (P1 ;

Analyzing IF CC R0 = SP ; and expecting opcode value 1862(0x 0746 ): OK



Exit Criteria:

All the test cases (listed above - function to be tested) have been executed and

results are verified, bugs are reported and approved.

There should not be any unexpected failures.









7 Suspension Criteria and Resumption Requirements



N/A.









8 Test Deliverables



Deliverables are listed below.

 Test plans

 Test reports









9 Testing Tasks



N/A.









10 Environmental Needs



The test environment shall be as defined below:









ADSP BF-

Null Modem / Ethernet 531/2/3

cable

JTAG

Host Computer







Hardware



 ADI EZ-KIT Lite BF-533 Development board

 JTAG

 Host computer



Software



 uCLinux Kernel Version 2.4.18 or greater for ADI EZ-KIT Lite BF-533

Development board

 SuSe Linux

 cygwin

 Network drivers



Testing Tools

The following tools will be used:

1. Dejagnu

2. Tracker



Dejagnu

Dejagnu will be used for test execution. Regression testing for binutils will be very

similar to gcc testing. The following procedure will be followed:

1. Organize test cases in the respective subdirectories like gas, ld, bfin etc.,

2. Create a directory „bfin‟ under each of the following directories gas, ld, and

bfin.

3. Copy copy corresponding test cases into each folder.

Test plan RRAP-ADI-TP-001 explains the steps to executed regression tests using

dejagnu.



Tracker

Tracker will be used as the bug-tracking tool. The tool will be exposed to ADI over

the Internet, giving the ability to file bugs and query status.

 Each of the bugs shall be classified into „High‟, „Medium‟ and „Low‟ priority

bugs in the test reports.

 All bugs shall be assigned a unique number and entered into the bug-tracking

system.

 The bugs shall be assigned to the respective module owner. Once the cause of

the bug is identified and its solution has been implemented, the bug will be

moved over to the „Fixed‟ status.

 During subsequent testing, the bug shall either be „Closed‟ or be revoked as

„Open‟.

 The test iterations shall continue until all bugs have been tracked to closure.

11 Responsibilities



- Pradip shah: Project Management

- Omkar: Testing, Test plan creation and execution, Reporting bug(s).







12 Staffing and Training Needs



N/A.









13 Schedule



 Binutils tests will be execution start from on4/01/04 and should

complete on 04/30/04









14 Risks and Contingencies



The project depend on the following:

- Availability of ADI EZ-KIT Lite BF-533 Development board.

- Availability of connectivity to the EZ-KIT lite boards.



So we assume that:

- ADI EZ-KIT Lite BF-533 Development board with all necessary interfaces is

available in time.

- ADI EZ-KIT Lite BF-533 Development board is up with uCLinux and support

network features required for testing.









15 Approvals



Pradip shah, project manager

To Do List







# Who Due What

1 Groucho 4/7/2003 Add code inspection plans

2 Zeppo 4/1/2003 Add acceptance test plans







Revision History



Version/Date Additions/Modifications Prepared/Revised By

0.9 Original put into this format Omkar

1.0 Reviewed by Pradip Shah

1.1 Section 8, Functions to be tested Omkar

1.3 Section for opcode test Omkar

1.4 Elaborated pass/fail criteria Omkar

1.5 Incorporated ADI feedback Omkar

1.6 Accepted ADI changes Omkar

1.7 Changes in section 8 - Added a table which lists Omkar

relocation tests


Share This Document


Related docs
Other docs by X Scape
by registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!