					                                                                                               PRODUCT GUIDE
                                                                                                SPECIFICATION




Specifier Notes: This product guide specification is written according to the Construction Specifications
Institute (CSI) 3-Part Format. The section must be carefully reviewed and edited by the Architect or
Engineer to meet the requirements of the project and local building code. Coordinate this section with
other specification sections and the drawings. Delete all “Specifier Notes” when editing this section.




                                                 SECTION 03155

                                             FLOOR JOINT FILLER



Specifier Notes: This section covers Euclid “Euco 700” semi-rigid, industrial floor joint filler for interior
concrete construction and control joints.

ACI 302.1R, Paragraph 9.10.1 advises to defer joint filling and sealing as long as possible to minimize
the effects of shrinkage-related joint opening on the filler or sealant. If the joint should be filled before
most of the shrinkage has occurred, separation should be expected between the joint edge and the joint
filler, or within the joint filler itself.

ACI 302.1R, Paragraph 9.10.2 indicates semi-rigid epoxy fillers should be installed full-depth in saw-cut
joints, and at least 1 inch (50 mm) deep in formed joints. Consult Euclid for assistance in editing this
section for the specific application.

This product is also available as “Euco 700 Gel”, a standard-setting, thick-paste consistency material for
special applications. Consult Euclid for more information.


PART 1        GENERAL

1.1     SECTION INCLUDES

  A.    Semi-rigid, industrial concrete floor joint filler.

1.2     RELATED SECTIONS


Specifier Notes: Edit the following list of related sections as required for the project. List other sections
with work directly related to this section.

  A.    Section 03300 - Cast-in-Place Concrete.

1.3     REFERENCES

  A.    ACI 302.1R - Guide for Concrete Floor and Slab Construction.



 Euco 700                                          03050 - 1
 B.   ASTM C 109 - Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or [50-mm] Cube
      Specimens).

 C.   ASTM D 570 - Water Absorption of Plastics.

 D.   ASTM D 638 - Tensile Properties of Plastics.

 E.   ASTM D 2240 - Rubber Property—Durometer Hardness.

1.4   SUBMITTALS

 A.   Comply with Section 01330 - Submittal Procedures.

 B.   Product Data: Submit manufacturer’s product data, including surface preparation and
      application instructions.

 C.   Manufacturer’s Certification: Submit manufacturer’s ISO 9001/9002 certification.

1.5   QUALITY ASSURANCE

 A.   Manufacturer’s Qualifications: ISO 9001/9002 registered or provide proof of documented quality
      assurance system. Quality assurance system shall be registered by independent registrar
      accredited by ANSI Registrar Accreditation Board (ANSI-RAB) or by another internationally
      recognized body.

1.6   DELIVERY, STORAGE, AND HANDLING

 A.   Delivery: Deliver materials to site in manufacturer’s original, unopened containers and
      packaging, with labels clearly identifying product name and manufacturer.

 B.   Storage: Store materials in clean, dry area in accordance with manufacturer’s instructions.
      Keep containers sealed until ready for use.

 C.   Handling: Protect materials during handling and application to prevent damage or contamination.

1.7   ENVIRONMENTAL REQUIREMENTS

 A.   Do not apply joint filler when concrete surface or air temperatures are below 40 degrees F
      (4 degrees C).


PART 2     PRODUCTS

2.1   MANUFACTURER

 A.   The Euclid Chemical Company, 19218 Redwood Road, Cleveland, Ohio 44110. Toll Free
      (800) 321-7628. Phone (216) 531-9222. Fax (216) 531-9596. Web Site
      www.euclidchemical.com.




Euco 700                                    03050 - 2
2.2    MATERIALS

 A.    Industrial Concrete Floor Joint Filler: Euco 700 semi-rigid industrial floor joint filler.
       1.   Type: 2-component, semi-rigid epoxy.
       2.   Compliance: ACI 302.1R recommendations for joint fillers used in control and construction
            joints.
       3.   Compressive Strength, ASTM C 109, 72 Hours: 3,000 psi (20.7 MPa).
       4.   Tensile Strength, ASTM D 638, 7 Days: 690 psi (4.6 MPa).
       5.   Elongation, ASTM D 638, 7 Days: 55 percent.
       6.   Water Absorption, ASTM D 570, 72-Hour Immersion: 1.1 percent.
       7.   Shore D Hardness, ASTM D 2240, 7 Days: 55.
       8.   Shore A Hardness, ASTM D 2240: Greater than 100.
       9.   USDA approved.


Specifier Notes: Euco 700 is also available in colors for use with colored dry shake floor hardener
applications. Consult Euclid for availability.


       10.   Color: [Gray] [ _______________ ].


PART 3       EXECUTION

3.1    EXAMINATION

 A.    Examine joints in concrete floors to receive joint filler. Notify Architect if joints are not acceptable.
       Do not begin surface preparation or application until unacceptable conditions are corrected.

3.2    SURFACE PREPARATION

 A.    Prepare joints in accordance with manufacturer’s instructions.

 B.    Ensure joints are clean, dry, and sound.

 C.    Remove from joints and joint edges dirt, dust, debris, oil, grease, paint, curing compounds,
       sealers, residue, and other materials that may act as a bond breaker.

 D.    Floor Cracks: Rout-out and clean cracks. Square crack edges.

Specifier Notes: Based on ACI 302.1R recommendations, joint filler should be deferred as long as
possible to allow for minimal additional slab shrinkage. Consult ACI 302.1R comments regarding
concrete shrinkage, joint filling, and user expectations.

  E.   Ensure concrete is a minimum of 28 days old.

3.3    APPLICATION

  A.   Apply joint filler to control and construction joints in concrete floors in accordance with
       manufacturer’s instructions.

  B.   Mix components in accordance with manufacturer’s instructions.

Euco 700                                       03050 - 3
 C.   Fill joint or crack full depth with joint filler for proper load transfer. Do not use backer rod, sand,
      or other fill material to reduce volume.

 D.   Pour joint filler into joints in accordance with manufacturer’s instructions. Fill joints 2/3 full and
      allow filler to settle. Complete filling within 1 hour to level of floor or overfill joints.

 E.   Cut or grind joint filler flush with floor within 24 hours after placement.

 F.   Do not use joint filler in expansion or isolation joints.

3.4   PROTECTION

 A.   Protect floors from traffic until joint filler has cured.


                                             END OF SECTION