					                                    Agenda Item #   Page #




                                      l
                                     Ea
        TO:                          CHAIR AND MEMBERS
                          ENVIRONMENT AND TRANSPORTATION COMMITTEE
                                  MEETING ON JANUARY 14,2008
       FROM:                         RON STANDISH, P.Eng.
                             DIRECTOR, WASTEWATER AND TREATMENT
I!
1    SUBJECT   1
                             ENVIRONMENTALAND ENGINEERING SERVICES

                              APPOINTMENT OF CONSULTING ENGINEER
                                                                                                   II
                                    INNOVATION PARK PHASE 2  -

                                    RECOMMENDATION

That, on the recommendation of the Director, Wastewater and Treatment, Environmental and
Engineering Services, the following actions BE TAKEN with respect to the appointment of a
consultant for Innovation Park, Phase 2 (Capital Project ID1168):

(a)      Earth Tech Canada Inc., 285 King Street, Suite 300, London, Ontario, N6B 3M6 BE
         APPOINTED Consulting Engineers for the Detailed Design for the said project in the
         amount of $135,000.00 in accordance with Council Policy 7(9A);

 (b)     the financing for the project BE APPROVED in accordance with the “Sources of
         Financing Report” attached hereto as Appendix ” A ;

 (c)     the consulting fees for the project BE IN ACCORDANCE with the estimate, on file,
         which are based upon the Suggested Schedule of Fees for Engineering Projects,
         recommended by Professional Engineers Ontario and in accordance with Council Policy
         7(9A), Clause (e);

 (d)     the approvals given herein BE CONDITIONAL upon the Corporation entering into a
         formal contract with the consultant for the work.


                     PREVIOUS REPORTS PERTINENT TO THIS MATTER

 For background, please refer to Agenda and Reports Section of the City’s website:
     - Item 4 of the Planning Committee Agenda 2003-04-14: “Airport Road South Area Study
        Terms of Reference”.
     - Item 6 of the Environment and Transportation Committee Agenda 2004-06-07:
        “Appointment of Consulting Engineer Airport Road South Area Water and Sewer Trunk
        Servicing”.
     - Item 2 of the Environment and Transportation Committee Agenda 2004-07-26:
        “Appointment of Consulting Engineer Airport Road South Industrial Park - Phase 1”.
     - Item 3 of the Environment and Transportation Committee Agenda 2004-11-08:
        “Appointment of Consulting Engineer Airport Road South Industrial Park - Phase 1”.
     - Item 5 of Board of Control Agenda 2005-06-22: “Contract Award -Tender 05-56 Airport
         Road South Industrial Park Phase 1 Stage 1”


1
I                                       BACKGROUND                                            I]
 Purpose:

 Earth Tech Canada Inc. had been retained to complete the Environmental Assessment, prepare
 the Phase 1 and 2 draft plan, and the detail design and construction administration for Phase 1
 of Innovation Park (formerly known as Airport Road South Industrial Park). The purpose of this
 report is to recommend Earth Tech Canada complete the detail design of Phase 2 of Innovation
 Park.
                                      Agenda Item #




                                       151
Discussion:

The overall Airport Road South Industrial Area is generally bounded by Old Victoria Road to the
west, Thames River to the north, City of London boundary to the east and Highway 401 to the
south, and the total area is in the order of approximately 600 hectares (1500 acres), of which
the City owns approximately 240 hectares (593 acres). Innovation Park is being developed in
four phases, noting Phase 1 was constructed in 2005 (see Appendix “ B for reference map).
Phase 2 is located south of Phase 1, west of Veterans Memorial Parkway, north of Bradley
Avenue and east of Old Victoria Road and comprises approximately 30 hectares (75 acres).

The consultant assignment recommended in this report will complete the detail design of Phase
2 of the park. Earth Tech’s design activities will address the servicing, roadways, grading and
all related approvals. In addition, Earth Tech will provide construction administration and site
inspection during the construction phase.

 Conclusion:

 Earth Tech has demonstrated an understanding of the City’s requirements for this project and
 will provide value to the City. Their proposal and work program meets the schedule and
 delivery requirements in order for the City to have the ability to proceed with construction of
 Phase 2 when required. Earth Tech staff are also familiar with the project having completed the
 Draft Plan for Phase 1 and 2, the environmental assessment, detail design and construction
 administration for Phase 1 and have provided excellent service.

 It is, therefore, recommended that Earth Tech Canada continue with their activities into detail
 design for Phase 2 of Innovation Park. The engineering fees would be $135,000 exclusive of
 GST.

 There are no anticipated additional operating costs in the Environmental and Engineering
 Services budget in 2008 and subsequent years associated with the approval of this engineering
 assignment.

 Acknowledgements:

 This report was prepared within the Environmental and Engineering Services Department by
 Robert Sutton, Transportation Design Engineer, Transportation Planning and Design Division.


  SUBMITTED BY:



   &/CA                                                    ,E
                                                          RECOMMENDED B Y


                                                            /ziZzLdL               Y
h:ANTONY FEDIW, P. Eng.
  MANAGER
                                                          RON STANDISH, P.Eng.
                                                          DIRECTOR, WASTEWATER AND TREATMENT
  ENGINEERING PLANNING                                    ENVIRONMENTAL AND
 I                                                    I   ENGINEERING SERVICES                     I
                                                                                                   1
 December 19,2007

 Attach:     Appendix “ A - Sources of Financing
             Appendix “8”- Reference Map

 c:        Peter W. Steblin, General Manager of Environmental and
           Engineering Services and City Engineer
           Grant Hopcroft, Director, Intergovernmental and Community Liaison
           Vic Cote, General Manager of Finance & Corporate Services
           Earth Tech Canada Inc.
                                                      APPENDIX 'A'
                                                                                                                  #08001

  Chair and Members
  Environment & Transportation Committee
  RE: Innovation Park - Phase 2
                               -
      Capital Project ID1168 Innovation Park
                                   -
      Earth Tech Canada Inc. $135,000.00
                                                        ma
  FINANCE AND CORPORATE SERVICES DEPARTMENT REPORT ON THE SOURCES OF FINANCING:
                                                                                                        January 4,2008
                                                                                           (Appoint Consulting Engineer)




  Finance and Corporate Services confirms that the cost of this project can be accommodated within the financing
  available for it in the Capital Works Budget and that, subject to the adoption of the recommendations of the Director of
  Wastewater and Treatment, the detailed source of financing for this project is:


                                                      Approved          Committed           This            Balance for
  ESTIMATED EXPENDITURES                               Budget            to Date         Submission         Future Work

  Engineering                                           1,554,637         1,253,586           135,000            166,051
  Construction                                          4,860,000         2,913,738                            1,946,262
  Relocate Utilities                                    1,600,000         1,216,264                              383,736
  Street Lights                                           720,000                                                720,000
  City Related Expenses                                   500,000             89,571                             410,429
  NET ESTIMATED EXPENDITURES                           $9,234,631        $5,473,159          $135,000         $3,626,418

  SUMMARY OF FINANCING:

  Debenture By-Law No. W.-1960-144                      1,500,000                                              1,500,000
  Drawdown from Industrial Oversizing R.F.              2,206,637            816,159          135,000          1,255,478
  Superbuild Funding                                      916,000            916,000                                   0
  Drawdown from London Connect R.F.                     3,491,000          3,491,000                                    0
  Drawdown from Industrial Land R.F.                      250,000            250,000                                    0
  Other Contributions-PUC Contingency Reserve             871,000                                                871,000
  TOTAL FINANCING                                      $9,234,637        $5,473,159          $135,000         $3,626,478

  -
  Notes:
1) There are no anticipated additional operating costs in the Environmental and Engineering Services budget in 2008 and
  subsequent years associated with the appointment of this engineering assignment.




   EH
                                                                                               -6


                                                                                          Madid Hayward
                                                                                                        9
                                                                              Director of Financial Planning & Policy