HISPEC/DESPEC Meeting at GSI, 21 February 2006   C. Scheidenberger (GSI)
Comparison of layouts: LoI vs. TP

                 LoI (2004)                      TP (2005)




HISPEC/DESPEC Meeting at GSI, 21 February 2006               C. Scheidenberger (GSI)
Comparison to the experimental area of other facilities



     LEB                          UNILAC            ISOLDE          JYFL
     35 x 28 m2                   58 x 43 m2       47 x 20 m2       50 x 24 m2
     (~1000 m2)                   (~2500 m2)       (~1000 m2)       (~1200 m2)




LoI: 25 x 35 = 875 m2

TP: 35 x 35 = 1225 m2
* Annex buildings ?
* Storage, workshop, labs ?                      after extension:
* Office space ?                                   72 x 20 m2
* Control room, electronics ?                      (~1400 m2)
HISPEC/DESPEC Meeting at GSI, 21 February 2006                      C. Scheidenberger (GSI)
Radiation shielding

Example:

400 MeV/u                                                                                 controlled
12C  Cu                                                                                  area

109 per s
                                                                                           free
                                                                                           access




       For a first-order estimate of the dose rates expected with other secondary beams,
       the numbers can be scaled wit mass number and intensity, and within some restrictions
       with specific kinetic energy
HISPEC/DESPEC Meeting at GSI, 21 February 2006                                 C. Scheidenberger (GSI)
Conclusion


  The following questions (and maybe some more....) should be answered by
  HISPEC/DESPEC in spring 2006:

  • beam parameters: max. intensity (107 ?), max. energy (100 MeV/u ?)
  • access to LEB experimental area:
       • gate size of the hall?
       • crane needed? if so: maximum weight to be handled?
  • access to experimental cave: gate for equipment (dimensions?)
  • detailed plan of beam line
  • detailed plan of experimental area (inside concrete shielding)
  • besides the pure floor space for the experiment:
       • where will the DAQ, electronics, control room be located (containers, shacks,...)?
       • is a detector lab needed NEXT to the experimental area?
       • is a workshop needed?
       • is office space needed next to the experimental area?
        give numbers (square-meters), and ideally provide 3D-drawings!

  .....civil engineering of buildings 6a and 6b will be finalized in summer 2006
  .....the more detailed knowledge exists the easier will be the planning


HISPEC/DESPEC Meeting at GSI, 21 February 2006                                     C. Scheidenberger (GSI)

								