PUBLIC PRIVATE PARTNERSHIP (PPP) PROJECTS IN SCHOOLS


PROJECT LIST

The attached list gives brief details of schools PPP projects in England as of
5 September 2005, categorised as follows:

1.    Signed deals - operational.

2.    Signed deals - under construction.

3.    Projects in procurement.

4.    BSF Projects in procurement.

5.    Signed projects supported by New Deal for Schools (NDS) grant.




FUNDING FOR PROJECTS

      DfES funding for projects is either in the form of:

1.    PFI Credits, which provide revenue support to LEAs to help meet private sector
      annual charges; and/or

2.    For Voluntary Aided schools only, also in the form of annual revenue grant to VA
      schools to meet private sector annual charges.




Project details are based on our best knowledge to date, but are subject to
change and may not be fully accurate in all respects.




                                           1
1.    Signed deals - operational
Barking and Dagenham                    LEA Contact
Capital Value £39,760,000             James Hodgson
Barking & Dagenham - Two              020 8227 3030
Schools                               james.hodgson@lbbd.gov.uk

This project is for one new additional secondary school (Jo Richardson Community
School) and for the refurbishment and expansion of the existing Eastbury Secondary
School. Both schools will have an extensive range of community facilities and Jo
Richardson School will also have a Joint Service Centre funded by £4.76 million in
PFI Credits from the ODPM. The contract was signed on 30 March 2004 with
Bouygues UK Ltd and full services will commence in September 2005.



Bedfordshire                            LEA Contact
Capital Value £24,200,000             John Goldsmith
Mid-Bedfordshire Schools Upper        01234 228196
Schools Project                       john.goldsmith@bedscc.gov.uk

This project involves the expansion, refurbishment and redevelopment of 2 schools
(Samuel Whitbread Community College and Harlington Upper School). The contract
was signed with Galliford Try in December 2003 and full services commenced in
September 2005.




Birmingham                             LEA Contact
Capital Value £50,600,000             Peter Farrell
Birmingham 1 - Ten Schools            0121 303 8847
                                      peter_farrell@birmingham.gov.uk

This was a grouped refurbishment project involving a mixture of 10 primary and
secondary schools. The project addressed the backlog of repairs and maintenance,
which also included increasing the available accommodation at some sites. The
project was signed with Galliford in February 2000. The first handovers took place in
February 2001 followed by partial handovers in September 2001. All schools were
fully operational by July 2002.




                                          2
Bolton                                   LEA Contact
Capital Value £10,100,000              Stuart Knight
Bolton - Castle Hill School            01204 331350
                                       stuart.knight@bolton.gov.uk

This project rebuilt Castle Hill Primary School and provided a Learning Resources
Centre, offering facilities to the wider community. The contract was signed with
Melville Dundas on 12 April 2002 but this was subsequently taken over by Dawn
Construction in 2003. The school opened on 6 October 2003. This project is jointly
funded by DfES (£3.2 million) and ODPM (£6.9 million).


Brent                                    LEA Contact
Capital Value £9,000,000               David Lerner
Brent - JFS School                     020 8206 3178
                                       lerner@jfs.brent.sch.uk

This project relocated the Jews Free School (JFS) from Camden to Brent. The new
school is larger, having had an increase of 500 places to make 2000. The contract
was signed with Jarvis Plc in January 2001 and the school opened in September
2002. The DfES contribution to this project was £9 million in PFI credits and £7.88
million in VA grant; with land sales and other capital contributions the total capital
value of the project was £41.563 million.




Brighton and Hove                         LEA Contact
Capital Value £25,300,000              Gillian Jordan
Brighton & Hove - four schools         01273 293515
                                       gillian.jordan@brighton-hove.gov.uk

This project extended and refurbished 4 secondary schools and provided new
facilities for a community library and community association at Patcham. Additionally
Patcham Junior School had a new dining hall and a youth centre moved into the
former library premises. The contract was signed with Jarvis Projects on 7 March
2002 and the project became operational on 1 April 2003. The project was jointly
funded by DfES (£24.533 million) and ODPM (£467 000).




                                           3
Calderdale                              LEA Contact
Capital Value £53,900,000             Steve Freeborn
Calderdale - Grouped Schools          01773 746474
Project                               stevefreeborn@btconnect.com

This project will build one new primary school, refurbish two high schools and
build two new high schools. The contract was signed with Babcock and
Brown in July 2003 and the schools were completed ready for the new
academic year in September 2005..




Camden                                  LEA Contact
Capital Value £20,900,000             Steve Pyman
Camden - Haverstock School            020 7974 4030
                                      steve.pyman@camden.gov.uk

This is a redevelopment project which will rebuild Haverstock Secondary
School, thereby increasing its permanent capacity by one form of entry, plus
an increased 6th form provision of 150 pupils, moving from 1050 to 1250 pupils
 by 2007. The contract was signed with Kajima in October 2003 and the
school is scheduled for the first phase to open in October 2004 and for full
completion by September 2005.


Cheshire                               LEA Contact
Capital Value £17,200,000             Garry Chesworth
Cheshire - Ellesmere Port & Neston    01244 602441
Schools                               garry.chesworth@cheshire.gov.uk

This project has rebuilt and modernised five primary schools and provided
sports and drama facilities at a secondary school, all in Ellesmere Port. This
project is jointly funded by DfES (£16.1 million) and ODPM (£1.1 million). The
contract was signed in October 2002 with the Eric Wright Group and the
project became operational in September 2003.




                                          4
Cornwall                               LEA Contact
Capital Value £60,700,000             Barry Austin
Cornwall 1                            01872 322708
                                      baustin@cornwall.gov.uk

This project repaired and rationalised four split-site secondary schools and
their feeder primaries. This received the Department's endorsement as one of
five large grouped NDS PPP pilots. The contract was signed in March 2001
with NewSchools and became operational on 27 July 2001.




Coventry                               LEA Contact
Capital Value £24,300,000             Ashley Simpson
Coventry - Caludon Castle School      02476 831508
                                      ashley.simpson@coventry.gov.uk

This project is for one new build replacement 1500 place secondary school
(Caludon Castle), incorporating community sports and library facilities. The
contract was signed with Coventry Education Partners (builders Galliford Try)
on 7 December 2004 and full services commenced in September 2005 for
phase 1 of the project (main school buildings) with phase 2 (sports facilities
and other educational areas) following in 2006.


Darlington                             LEA Contact
Capital Value £34,900,000             Kevin Duffy
Darlington - Five Schools Project     01325 388818
                                      kevin.duffy@darlington.gov.uk

The key features of this project are: to create an "Education Village" to bring
together Houghton Secondary, Springfield Primary and Beaumont Hill Special
School; to relocate Harrowgate Hill Infant School to an extended site currently
occupied by Harrowgate Hill Junior School and in the process amalgamate the
schools into one primary school. The contract was signed on 30 March 2004
with Kajima and full services commenced in September 2005.




                                          5
Derbyshire                          LEA Contact
Capital Value £29,000,000          Gerald Tommy
Derbyshire 1 - Grouped Schools PFI 01629 580000
Project                            gerald.tommy@derbyshire.gov.uk

This project rebuilt and replaced unsuitable and poor condition buildings at
Chapel-en-le-Frith and Tupton Hall Secondary Schools and provided places for
pupils with Special Educational Needs in an integrated facility on the
Chapel-en-le-Frith site. The contract was signed in March 2001 with Babcock
& Brown Properties. The project became operational on 28 April 2003.



Dorset                                LEA Contact
Capital Value £15,600,000           Andy Ray
Dorset - The Sir John Colfox County 01305 225391
Secondary School                    a.r.ray@dorsetcc.gov.uk

A Design, Build, Finance and Operate (DBFO) project rebuilt The Sir John
Colfox County Secondary School in Bridport. Dorset County Council and
Jarvis (Colfox) Ltd signed the PFI contract on 18 November 1997 and the new
school services started in September 1999.




Dudley                               LEA Contact
Capital Value £22,000,000           Catherine Ludwig
Dudley 2 - Paragon Project          01384 814243
                                    catherine.ludwig@dudley.gov.uk

This project involved the rebuilding of Colley Lane Primary School and
Summerhill Secondary School. The contract was signed between Dudley
Metropolitan Borough Council and Newmount (a consortium comprising King
Sturge, Wiltshiers FM and Ballast & Noble) in January 2002. The scheme
became fully operational in September 2003.




                                        6
Dudley                                 LEA Contact
Capital Value £29,550,000             Catherine Ludwig
Dudley 1 - Grid for Learning          01384 814243
                                      catherine.ludwig@dudley.gov.uk

A DBFO project which provides networked IT services including e-mail,
training and maintenance to all 110+ Dudley LEA schools. The contract was
signed with Research Machines/BT in January 1999 and service delivery
commenced immediately afterwards.




Ealing                                 LEA Contact
Capital Value £33,100,000             Gary Redhead
Ealing 1 - Ealing Schools Project     020 8758 5414
                                      gredhead@ealing.gov.uk

This project will provide two new build 2 form entry primary schools, including
nursery places (replacing Downe Manor and Ravenor Primary Schools), a
new 3 form entry primary school with nursery and a hearing impaired unit
(replacing Gifford Primary School) and a new 7 form entry high school
(replacing Brentside High School). The contract was signed with Kajima on 18
 December 2002 and all schools should be fully operational by the end of
November 2004.



East Riding of Yorkshire               LEA Contact
Capital Value £26,000,000             Chris Standing
East Riding of Yorkshire -            01482 393092
Bridlington Schools PFI               chris.standing@eastriding.gov.uk

This was a six school project which included refurbishment, rebuilding and
consolidation onto one site of two secondary schools and refurbishment and
new building of four primary schools in Bridlington. The contract was signed
in December 2000 with Jarvis and full services commenced on 29 April 2003.




                                          7
East Sussex                              LEA Contact
Capital Value £19,000,000              Ian Woodland
East Sussex - Peacehaven Schools       01273 481552
PFI Scheme                             ian.woodland@eastsussexcc.gov.uk

A five school project which included a new secondary school and the
rebuild/refurbishment of four infant/primary schools including nursery
provision in Peacehaven. The contract was signed with Peacehaven Schools
Ltd in March 2000 and the first primary school opened in January 2001. The
scheme became fully operational in January 2002.



Enfield                                  LEA Contact
Capital Value £15,900,000              Jim Forsyth
Enfield - Highlands Secondary          020 8379 3188
School                                 jim.forsyth@enfield.gov.uk

This was a DBFO project for a new secondary school in Enfield for 1240
pupils. The contract was signed with Laing Hyder in March 1999. Services
commenced in September 2000 and the school was officially opened by the
Prime Minister in February 2001.




Enfield                                  LEA Contact
Capital Value £38,800,000              Jim Forsyth
Enfield -Joint Schools Project         020 8379 3188
                                       jim.forsyth@enfield.gov.uk

This project will provide a new build primary school, a rebuilt existing infant
school, as well as an extended and refurbished secondary school. This was
an innovative scheme in that it was procured jointly with the London Borough
of Newham. The contract was signed with Equion plc in September 2003 and
the scheme became fully operational in July 2005.




                                          8
Essex                                  LEA Contact
Financially Free Standing             Gordon Powell
Essex 2 - Tendring Schools            01245 436701
                                      gordon.powell@essexcc.gov.uk

This was an innovative project as the LEA successfully reached contract
signature with Academy Services (Tendring) Ltd in October 2001, without the
benefit of PFI credits. The provider is a joint venture between the Kier Group
Plc and Dexia Public Finance Bank. The DfES contributed £1 million of NDS
grant towards the scheme. The project gaver new facilities at 12 primary
schools in NE Essex with a capital value of £14 million. The schools became
operational in phases from November 2002 to September 2004.



Essex                                  LEA Contact
Capital Value £35,700,000             Gordon Powell
Essex 3 - Clacton-on-Sea              01245 436701
Education Project                     gordon.powell@essexcc.gov.uk

This project will provide a new secondary school and upgrade two of the
existing secondary schools in Clacton-on-Sea as well as community facilities
that will support regeneration in the town. Each school will contain a Joint
Service Centre funded by the ODPM. The contract was signed with QED in
November 2003 and interim services commenced immediately. The project
became operational in September 2005.


Essex                                  LEA Contact
Capital Value £11,100,000             Gordon Powell
Essex 1 - Debden Park High School     01245 436701
(Loughton)                            gordon.powell@essexcc.gov.uk

This is a new secondary school in Loughton. The contract was signed with
Jarvis Projects in March 2000 and the project became operational on 4
September 2001.




                                          9
Haringey                                LEA Contact
Capital Value £62,500,000              Chris Parr
Haringey - Grouped Secondary           020 8489 3386
Schools                                chris.parr@haringey.gov.uk

This project provided one new secondary school and refurbished seven
existing secondary schools. The contract was signed with Jarvis Plc in
October 2000. All schools were operational by September 2003 with final
construction work finished on the Sports Hall at one site in May 2004.




Havering                                 LEA Contact
Financially Free Standing              Suzanne Philipps
Havering - Frances Bardsley            01708 447368
School                                 suzannephilipps@francesbardsley.haver
                                       ing.sch.uk
This is a financially free-standing project at a Foundation School which
rationalises the school onto one site. This will bring considerable benefits to
the school, its staff and pupils. The contract was signed in December 2002
and the scheme became fully operational in June 2004. The capital value is
£7.6 million.



Hillingdon                             LEA Contact
Capital Value £18,356,000            David Tully
Hillingdon - Barnhill Community High 01895 250076
School                               dtully@hillingdon.gov.uk

This project provided a new 1450 place secondary school for Hillingdon. The
project was initially led by the Funding Agency for Schools (FAS), who
worked closely with the London Borough of Hillingdon. The contract was
signed in November 1998 between the school's Governors and Jarvis Plc.
The new school services started in September 1999.




                                           10
Kent                                     LEA Contact
Capital Value £11,600,000              John Lattimore
Kent - Swanscombe Schools              07876 763585
                                       john.lattimore@kent.gov.uk

This project combined the second phase of a new secondary school and the
provision of a new primary school in Swanscombe. The contract was signed
in March 2001 with NewSchools and became fully operational on 1 September
2003.




Kingston Upon Hull                       LEA Contact
Capital Value £3,904,000               John Bates
Kingston upon Hull - Victoria Dock     01482 613505
Primary School                         john.bates@hullcc.gov.uk

The LEA signed a DBFO contract in July 1998 with the Sewell Group to build
and operate a new one-form entry primary school in the Victoria Dock
redevelopment area of the city. The Deputy Prime Minister officially opened the
 school on 29 January 1999. In January 2001 the school doubled in size to
meet parental demand, some three years ahead of original plans.



Kirklees                                LEA Contact
Capital Value £59,200,000              Andrew Jessop
Kirklees 1 - Twenty schools            01484 225176
                                       andrew.jessop@kirklees.gov.uk

This project will repair, refurbish and operate 20 schools. The project also has
 DfES endorsement as one of the five NDS PPP pilots. The contract was
signed in March 2001 with Jarvis Plc. The first school opened in April 2003
and the remainder of the project was completed by September 2005.




                                          11
Lambeth                                 LEA Contact
Capital Value £20,400,000             Farukh Akbar
Lambeth - Lilian Baylis School and    020 7926 9776
Resource Centre                       fakbar@lambeth.gov.uk

This project will provide a new secondary school on a new site to replace the
existing school, plus a new Community Resource Centre to be built on the
same site. It is supported by £17.4 million PFI credits from DfES for the school
and £3 million from other Government Departments for the community aspects.
 The contract was signed with Focus Education on 25 March 2003 and the
school was officially opened by the Prime Minister and the Secretary of State
for Education on 26 April 2005.



Lancashire                              LEA Contact
Capital Value £13,400,000             Roger Rymer
Lancashire - Fleetwood High           01772 534757
School                                roger.rymer@fin.lancscc.gov.uk

This project rebuilt/refurbished Fleetwood High School, which included
consolidation onto a single site. The contract was signed in March 2001 with
the Eric Wright Group and the school opened on 2 September 2002.




Leeds                                  LEA Contact
Capital Value £4,100,000              Geoffrey Catley
Leeds - Cardinal Heenan High          0113 224 3469
School                                geoffrey.catley@educationleeds.co.uk

This DBFO scheme involved the rebuilding of a voluntary-aided (VA)
secondary school. The contract was signed on 4 June 1999 with Jarvis Plc.
The new school opened in September 2000.




                                          12
Leeds                                   LEA Contact
Capital Value £45,200,000              Phil Crotty
Leeds 1 - 7 Schools                    0113 247 4271
                                       phil.crotty@educationleeds.co.uk

This project of 7 schools involves the provision of a new primary school and
the replacement/refurbishment of four further primary schools and two
secondary schools. The contract was signed with Mowlems in November
2001 and the scheme became fully operational in September 2003.




Leeds                                   LEA Contact
Capital Value £32,000,000              David Outram
Leeds 2 - Ten Primary Schools          0113 247 4461
                                       david.outram@educationleeds.co.uk

The project involves converting 13 existing infant and junior schools into 10
primary schools, which includes the complete new build of three schools.
Meeting facilities will be made available to the wider community, in addition to
existing and developing community learning and recreation provision. The
contract was signed on 22 April 2004 with QED. One school was completed
in March 2005 and the rest were completed by September 2005.


Lewisham                                 LEA Contact
Capital Value £4,300,000               Vic Campbell Macdonald
Lewisham - Catering PFI Project        020 8314 6302
                                       vic.campbell-macdonald@lewisham.gov.
                                       uk
The Council signed a contract with Chartwells to provide all school meals from
Lewisham's 66 school kitchens for a 10-year contract period. The contract
also covered the provision of social services meals ("meals on wheels" etc)
and Town Hall catering. It involved extensive replacement of kitchen facilities.
 The contract was signed in February 1999 with services commencing
immediately afterwards.




                                           13
Liverpool                                LEA Contact
Capital Value £20,400,000              Rob Mason
Liverpool - Speke/Garston Lifelong     0151 494 2555
Learning Centre                        rob.mason@liverpooldev.co.uk

This project involved the replacement of a secondary school and the provision
of a Lifelong Learning Centre, together with new and enhanced community
facilities. The project was jointly funded by DfES (£10.8 million) and ODPM
(£9.6 million). The contract was signed in April 2001 with Education Solutions
and all services were fully operational by October 2002.



Manchester                               LEA Contact
Capital Value £3,700,000               Dave Carty
Manchester 1 - Temple School PFI       0161 234 1263
Project                                d.carty@notes.manchester.gov.uk

This project provided a replacement primary school in the Cheetham Hill area of
 Manchester and it also involved the release of other land for redevelopment.
The contract was signed with Norwich Union PPP in March 2000 and the
school opened on 3 September 2001.




Merton                                   LEA Contact
Capital Value £56,600,000              Josephine Mahaffey
Merton - Age of Transfer               020 8545 3140
                                       josephine.mahaffey@merton.gov.uk

This project will extend and refurbish the LEA's secondary schools as part of
a wider reorganisation project, to switch from three tier to two tier schooling,
affecting six Community High Schools. The contract was signed with
NewSchools on 25 November 2002 and became fully operational in December
2004.




                                          14
Newcastle upon Tyne                      LEA Contact
Capital Value £47,100,000              Frank Jordan
Newcastle 1 - Six schools              0191 211 5362
                                       frank.jordan@newcastle.gov.uk

This project will replace one secondary school, three middle schools, one
primary school and one first school. Each of the existing six schools will be
replaced with a new purpose-built facility, designed in conjunction with the
users of the schools themselves. The contract was signed with Focus
Education on 18 April 2002 and the project became fully operational in
November 2004.


Newham                                   LEA Contact
Capital Value £30,000,000              John Turnbull
Newham - New Schools Project           020 8430 3236
                                       john.turnbull@newham.gov.uk

This project provided two new primary schools and a new secondary school
to meet the demand for new places in the area. The contract was signed in
March 2001 with Norwich Union PPP. The first new primary school and the
new secondary school opened in September 2002; the second primary
school opened in September 2003.



North Tyneside                           LEA Contact
Capital Value £33,500,000              Simon Brown
North Tyneside - Four schools          0191 200 1087
project                                simon.brown@northtyneside.gov.uk

This is a project for 4 new schools - a primary and a high school in Wallsend
and 2 new first schools in Monkseaton/Whitley Bay. The contract was signed
with Kajima (Europe) on 20 December 2002. Two schools reached service
commencement in November 2003, one in January 2004 and the final one
became operational in September 2004.




                                          15
North Yorkshire                       LEA Contact
Capital Value £7,241,000             Bernadette Jones
North Yorkshire - Grouped scheme     01609 532218
of 4 schools                         bernadette.jones@northyorks.gov.uk

This was a project to replace a group of four primary schools. The contract
was signed in March 2001 with Accord Plc and became fully operational on 8
April 2002




Northamptonshire                      LEA Contact
Capital Value £23,700,000            G Milner
Northamptonshire 1 - Wooldale        01604 237789
Centre for Learning                  gmilner@northamptonshire.gov.uk

The Wooldale Centre for Learning Project will provide a new 1670 place, 5 - 18
 school (the Caroline Chisholm School) on a greenfield site. It includes
extensive community facilities and SEN provision. The contract was signed
with Kajima (Europe) on 28 March 2003 and became fully operational in
September 2004.



Nottinghamshire                        LEA Contact
Capital Value £17,200,000            John Buttery
Nottinghamshire 1- East Leake        01159 772365
Schools                              john.buttery@education.nottscc.gov.uk

This scheme involved the replacement of Harry Carlton Comprehensive School
 and Lantern Lane Primary School, along with the development of existing and
new sports facilities in partnership with Rushcliffe Borough Council. The
contract was signed with Keystage on 18 April 2002 and the scheme became
fully operational in September 2003.




                                         16
Portsmouth                             LEA Contact
Capital Value £12,400,000             Mike Fowler
Portsmouth - Miltoncross              02392 841207
Secondary School                      mike.fowler@portsmouthcc.gov.uk

Portsmouth signed a contract with Grannag - a consortium of King Sturge,
Ballast Wiltshire, Mott McDonald and Royal Bank of Scotland - to design, build,
finance and operate a new, 1000 place secondary school. The contract was
signed in March 1999 and the new school opened in September 2000.




Redbridge                               LEA Contact
Capital Value £20,000,000             John Stevens
Redbridge - Oaks Park School          020 8708 3061
                                      john.stevens@redbridge.gov.uk

This project built a new provision 1450-place secondary school on the Barley
Mow site. The contract was signed on 27 July 2001 with Norwich Union PPP.
The school became fully operational on 28 April 2003.




Richmond upon Thames                    LEA Contact
Capital Value £23,800,000             Jessica Saraga
Richmond upon Thames - Primary        020 8891 7562
Schools                               j.saraga@richmond.gov.uk

This project has provided 6 fully serviced primary schools through a single
contract. There are 2 new schools and 4 expanded and re-modelled/rebuilt
schools, spanning a contract period of 30 years. The contract was signed
with Jarvis Plc in June 2002 and the scheme became fully operational in
September 2004.




                                         17
Salford                                  LEA Contact
Capital Value £16,200,000              Judy Edmonds
Salford 1- Special Schools Project     0161 778 0140
                                       judy.edmonds@salford.gov.uk

This project will replace three SEN High Schools with two new facilities on
more appropriate sites. These new facilities will address the serious
shortfalls identified in recent OFSTED reports, which were critical of several
areas of the resources and accommodation. The contract was signed with
Jarvis Plc on 20 March 2003 and all the schools were fully operational from
January 2005.


Sandwell                                LEA Contact
Capital Value £17,000,000              Melanie Dudley
Sandwell - Five Schools PFI Project    0121 569 8374
                                       melanie_dudley@sandwell.gov.uk

This project will replace 5 primary schools that complements regeneration
proposals in the authority. The contract was signed on 29 September 2003
with Total Schools and service commencement was phased from October
2004 to December 2004.




Sheffield                                LEA Contact
Capital Value £58,800,000              Simon Holmesmith
Sheffield Schools Phase 1              0114 273 6293
                                       simon.holmesmith@sheffield.gov.uk

This project was one of the five large grouped PPP pilots supported through
the New Deal for Schools. Sheffield's scheme involved the
rebuilding/operation of four secondary schools and two primary schools. The
contract was signed with Tilbury Douglas in April 2000 and all schools have
been operational since September 2001.




                                           18
Sheffield                                LEA Contact
Capital Value £31,600,000              Simon Holmesmith
Sheffield Schools Phase 2              0114 273 6293
                                       simon.holmesmith@sheffield.gov.uk

This is the second phase of Sheffield's PFI scheme - to replace two schools
which are in very poor condition, including one currently operating on a split
site. The contract was signed with the Priorgate Consortium on 31 March
2004 and is scheduled to be fully operational by April 2005.




Southampton                             LEA Contact
Capital Value £42,646,000              Dave Kitson
Southampton - Three Secondary          02380 833643
Schools                                dave.kitson@southampton.gov.uk

This project expanded and replaced 3 secondary schools. The project forms
part of wider regeneration plans. The contract was signed in October 2001
with Pyramid Schools and the scheme became operational on 1 September
2003.




Staffordshire                           LEA Contact
Capital Value £13,783,000              Ann Stansby
Staffordshire - Two Schools            01785 278839
                                       ann.stansby@staffordshire.gov.uk

Staffordshire's project linked the rebuilding of Sir Graham Balfour Secondary
School and the extensive refurbishment of Cooper Perry School. The contract
 was signed with Norwest Holst in March 2000 and full services commenced
in January 2002.




                                          19
Stockton-on-Tees                        LEA Contact
Capital Value £6,400,000              John Hegarty
Stockton on Tees - Community          01642 526477
Campus at Ingleby Barwick             john.hegarty@stockton.gov.uk

The LEA worked in partnership with the Diocese of York to provide a new
600-place Church of England secondary school, a 210-place community
primary school and a nursery unit in the new town of Ingleby Barwick. The
contract was signed on 23 April 2002 with the Robertson Group. The schools
 opened in September 2003.



Sunderland                             LEA Contact
Capital Value £17,744,000             George Blyth
Sunderland - Sandhill View School     0191 553 1804
                                      george.blyth@sunderland.gov.uk

This project has rebuilt Sandhill View School and provided new facilities for
the wider community. It was jointly funded by DfES (£12 million) and ODPM
(£5.744 million). The contract was signed in August 2001 with Jarvis Plc and
the school became operational on 16 September 2002; the all weather sports
facilities became operational in April 2003.



Tameside                                LEA Contact
Capital Value £20,900,000             Elaine Todd
Tameside - Hattersley Schools         0161 342 3238
                                      elaine.todd@mail.tameside.gov.uk

This was a school rationalisation project involving the removal of surplus
places and the replacement of one secondary and two primary schools. The
project was part of a wider regeneration programme. The contract was
signed in June 2002 with Pyramid Schools and became fully operational on 28
April 2003.




                                         20
Torbay                                   LEA Contact
Capital Value £14,400,000               Susan Williams
Torbay - Westlands & Homelands          01803 207987
Schools                                 susan.williams@torbay.gov.uk

This project involved the rebuild of Westlands Bilateral School and Homelands
Primary School, including nursery provision. The contract was signed with
Jarvis in March 2000. Westlands Bilateral School opened in September 2001
and Homelands Primary Schools was completed on 4 September 2002.




Tower Hamlets                            LEA Contact
Capital Value £19,300,000               Barry Gooden
Tower Hamlets - Mulberry School         020 7364 4314
                                        barry.gooden@towerhamlets.gov.uk

This project has rebuilt Mulberry School, including school and community
sports facilities. The project has joint funding by DfES (£17.4 million) and ODPM
 (£1.9 million). The contract was signed on 15 May 2002 with the Miller Group
and the main school became operational in July 2003; the sixth form block
became operational in August 2004.



Walsall                                   LEA Contact
Capital Value £8,200,000                Simon Wareing
Walsall - St Thomas More VA             0161 214 0306
School                                  simon.wareing@echarris.com

This project involved the replacement of a voluntary aided secondary school.
It relocated St Thomas More Catholic Comprehensive School, a 1300-place
school in Willenhall, and there was also further development of all-weather
sports facilities including 12 five-aside football pitches that are available for
school and community use. The contract was signed with Babcock & Brown
in May 2002 and the school became fully operational on 28 April 2003.




                                           21
Waltham Forest                          LEA Contact
Capital Value £18,500,000             Kirsten Shiels
Waltham Forest - The Lammas           020 8527 5544
Community School                      kirsten.shiels@edu.lbwf.gov.uk

This project has provided a new secondary school in Leyton. The contract
was signed with NewSchools in February 2000 and the school became
operational in September 2001.




West Sussex                             LEA Contact
Capital Value £53,200,000             Julian Harris
West Sussex - Crawley schools         01243 777854
scheme                                julian.harris@westsussex.gov.uk

The Crawley schools scheme intends to build a new secondary school in the
Maidenblower area, to rebuild 2 existing schools at Ifield and Thomas Bennett
Community Colleges and the continuation of the facilities management of the 3
schools. The contract was signed on 16 January 2004 with HBG Construction
 Ltd and full services commenced in September 2005.



Wiltshire                              LEA Contact
Capital Value £38,800,000             Mike Swabey
Wiltshire - North Wiltshire Schools   01225 713021
                                      mikeswabey@wiltshire.gov.uk

This project combined the building of a new school in Chippenham, the
replacement of Wotton Bassett School and the replacement on a single site of
Malmesbury Primary School. The contract was signed with the White Horse
Education Partnership in October 2000 and the scheme became fully
operational in March 2002.




                                         22
2.    Signed deals - under construction



Barnsley                                LEA Contact
Capital Value £54,002,000             Stephen Mair
Barnsley - Thirteen schools           01226 773612
                                      stephenmair@barnsley.gov.uk

The Barnsley Schools PFI project consists of 13 new build primary schools.
The contract was signed in May 2005 with Mowlem plc and service
commencement will be phased from April 2006 to April 2007.




Bexley                                 LEA Contact
Capital Value £35,100,000             Mike Ellsmore
Bexley - Three Schools                020 8303 7777
                                      mike.ellsmore@bexley.gov.uk

This project will rebuild/refurbish Bexleyheath School and Welling School and
build a sports hall at Chislehurst & Sidcup Grammar School. The contract was
signed in March 2004 with the Investors in the Community Consortium (whose
 main partners are Mill Group, Skanska, Kier Support Services and Nationwide
Building Society). Full services are expected to commence in December 2005.



Bristol                                LEA Contact
Capital Value £57,300,000             Gordon Clements
Bristol - Grouped Schools Project     0117 922 4271
(Phase 1A)                            gordon_clements@bristol-city.gov.uk

This project will rebuild/refurbish four secondary schools, including SEN
provision in the form of an autistic unit at one of the schools. The contract
was signed on 31 March 2004 with HBG Construction Ltd and all schools are
expected to be operational from 1 September 2006.




                                         23
Cornwall                               LEA Contact
Capital Value £71,000,000             Barry Austin
Cornwall 2 - Truro schools            01872 322708
                                      baustin@cornwall.gov.uk

This project is for a new- build 1350 place secondary school, a new 210 place
 primary school and the extension and modernisation of 15 existing primary
schools, in the Truro and Penryn clusters. The contract was signed with
Interserve/Pyramid Schools on 31 March 2004 and all schools are scheduled
to be operational by September 2007.



Croydon                                 LEA Contact
Capital Value £21,786,000             Robert Bollen
Croydon - Ashburton School            020 8686 4433
                                      robert.bollen@croydon.gov.uk

The project will rebuild Ashburton Community School and Lifelong Learning
Centre. Funding is also being given by DCMS (£4.686 million) to replace
Ashburton Library and provide "world class" leisure facilities. The contract
was signed on 27 May 2004 with Jarvis plc and the new school is scheduled
to open in March 2006, with the all-weather pitches to be available from June
2006.


Derby                                  LEA Contact
Capital Value £43,830,000             Mike Melluish
Derby - Grouped Schools               01332 255533
                                      mike.melluish@derby.gov.uk

This project involves the rebuilding of two primary schools, the amalagamation
and rebuilding of two further primary schools and the rebuilding of two
secondary schools, one of which is on a split site. The contract was signed
with Vinci Investments Plc on 23 December 2004 and full services for each
school will be phased from August 2005 to October 2006.




                                         24
Derbyshire                              LEA Contact
Capital Value £38,200,000              Gerald Tommy
Derbyshire 2 - Long Eaton and          01629 580000 x7301
Newbold Replacement Schools            gerald.tommy@derbyshire.gov.uk
Project

This involves the rationalisation of two split-site schools (the Long Eaton
School and Newbold Community School). Each school will be replaced with a
new build on its existing site. The contract was signed with Babcock &
Brown on 6 August 2004 and is scheduled to be fully operational by February
2006.



Devon                                    LEA Contact
Capital Value £79,000,000              Richard Buzzacott
Devon - Six Schools Project            01392 382617
                                       rbuzzaco@devon.gov.uk

This project will remodel a primary school and replace five high schools. The
contract was signed with Mowlem plc in 26 March 2004. The primary school
opened on 18 April 2005 and services in the high schools will be phased from
 September 2005 to January 2006.




Ealing                                  LEA Contact
Capital Value £61,800,000              Gary Redhead
Ealing 2 - Three schools               020 8758 5414
                                       gredhead@ealing.gov.uk

This project will involve the rebuild of two secondary schools on their existing
sites and one primary school on an adjacent site. The contract was signed on
 5 July 2005 with the Seafort Consortium (comprising King Sturge, Costain
Group, Mitie and NIB Capital Bank) and all schools should be operational by
September 2006.




                                          25
Harrow                                   LEA Contact
Capital Value £19,500,000              Johanna Morgan
Harrow - Special Schools PFI           020 8424 7525
                                       johanna.morgan@harrow.gov.uk

This project will rebuild two purpose-built schools for pupils with severe and
complex learning difficulties. In addition, one will also cater for
visually-impaired secondary-aged pupils in partnership with the Royal National
Institute for the Blind. The contract was signed with the Mill Group on 2
September 2003 and is due to be fully operational in February 2006.



Herefordshire                            LEA Contact
Capital Value £19,500,000              Louise Whitesman
Herefordshire - Whitecross High        01432 261876
School                                 lwhitesman@herefordshire.gov.uk

The project involves a new build replacement of Whitecross School, a 6 form
entry High School, on a new site in Hereford. It will serve 900 students in the
11-16 age range in the north-west quadrant of Hereford City and will include
the provision of a wide range of community resources on the school campus.
The contract was signed with Stepnell Ltd on 18 January 2005 and full
services are expected to commence in July 2006.


Kirklees                                LEA Contact
Capital Value £25,200,000              Michael Hall
Kirklees 2 - Special Schools           01484 221536
Reorganisation                         michael.hall@kirklees.gov.uk

This project aims to rationalise SEN provision (7 schools reducing to 4). In
addition there will be a new special school for pupils with profound and
complex educational needs. Separate primary/secondary accommodation and
facilities will be provided. The contract was signed on 6 May 2005 with QED
and services will commence from September 2006 in two schools and
September 2007 in the rest.




                                          26
Leeds                                    LEA Contact
Capital Value £117,510,000              Phil Crotty
Leeds 3 & 4 - Secondary & Post 16       0113 2474271
PFI Project                             phil.crotty@educationleeds.co.uk

This is a DBFO scheme for five secondary schools and one primary school
(including the closure of four secondary schools, the rebuilding of four
existing secondary schools, opening a new secondary school on a new site
and the rebuild of one existing primary school). The contract was signed with
Investors in the Community on 7 April 2005 and schools should become
operational from September 2006.


Lincolnshire                             LEA Contact
Capital Value £14,100,000               Katie Read
Lincolnshire - Seven Schools            01522 553216
Project                                 katie.read@lincolnshire.gov.uk

This project of seven schools involves new build to satisfy basic need and
replacement of poor condition split site buildings onto a single site. The project
has a strong SEN content, addresses failing schools and seeks to combat
rural deprivation. The contract was signed in September 2001 with Focus
Education. Six of the seven schools opened in phases from September 2002
to September 2003; the final school is currently under construction and is due
to be fully operational by March 2006.



Liverpool                                LEA Contact
Capital Value £76,000,000               Ken McCandless
Liverpool - Grouped Schools             0151 233 8222
Project                                 ken.mccandless@liverpool.gov.uk

This project is tackling the condition and suitability needs of 18 of Liverpool's
most dilapidated schools through rebuild/refurbishment. The contract was
signed with Jarvis projects in September 2001. By August 2004, 14 schools
were operational and the others are expected to be completed by July 2006.




                                           27
Manchester                               LEA Contact
Capital Value £35,000,000              Bernard Core
Manchester 2 - Wright Robinson         0161 234 4162
Sports College                         b.core@manchester.gov.uk

This project will provide a new 1800 place secondary school (Wright Robinson Sports
College). The contract was signed in July 2005 with Hochtief PPP Solutions (UK) Ltd
and the school is scheduled to open in September 2006.




Newham                                  LEA Contact
Capital Value £29,050,000              Peter Richardson
Newham - Joint Schools Project         020 8430 5007
                                       peter.richardson@newham.gov.uk

This project will provide a new 1500 place new build secondary school. This
was an innovative scheme in that it was procured jointly with the London
Borough of Enfield. The contract was signed in September 2003 with Equion
plc and the scheme became fully operational in September 2005.




Nottinghamshire                          LEA Contact
Capital Value £131,620,000             Jon Hawketts
Nottinghamshire 2 - Bassetlaw          01159 772365
Phases 1 & 2                           jon.hawketts@education.nottscc.gov.uk

This is a two-phase project to transform secondary education in the
Bassetlaw region of Nottinghamshire. The first phase will rebuild four
secondary schools, refurbish a special school and provide a new sixth form
centre which will operate in partnership with the Learning & Skills Council and
North Nottinghamshire FE College. Phase two will improve the secondary
school infrastructure in this area. The contract was signed on 12 July 2005
with Transform Schools consortium and services will commence from




                                          28
Redcar and Cleveland                    LEA Contact
Capital Value £48,900,000             Tina Robinson
Redcar & Cleveland - Grouped          01642 444189
schools                               pfi_education@redcar-cleveland.gov.uk

The project will provide a new Roman Catholic (RC) primary school to replace
two small RC primaries, a new community primary school to replace two small
community primary schools, two new replacement secondary schools (one
aided and one non-aided) and refurbishment of three community secondary
schools. The contract was signed with Mowlem Robertson consortium on 20
April 2005. The primary schools are scheduled to be finished in Spring 2006
with the secondary schools in Autumn 2006.



Rotherham                              LEA Contact
Capital Value £71,400,000             Graham Sinclair
Rotherham - Grouped Schools           01709 822648
                                      graham.sinclair@rotherham.gov.uk

This project involves major capital investment for new build schools at 3
secondary schools and 7 primary schools and significant refurbishing and
remodelling of 3 secondary and 2 primary schools (15 in total). The contract
was signed with Transform Schools (Rotherham) Ltd on 13 June 2003 and
completion of the scheme will be phased from April 2004 until January 2007.



Sheffield                               LEA Contact
Capital Value £61,100,000             Simon Holmesmith
Sheffield Schools Phase 3             0114 273 6293
                                      simon.holmesmith@sheffield.gov.uk

This is the third phase of the Sheffield Schools' PFI project - for two new
secondary schools, one primary school and the primary phase of a new 3-16
school. The project also includes a new swimming pool funded by DCMS at
one of the secondary schools. The contract was signed on 29 April 2005
with Academy Services and the first school is scheduled to open in April
2006.




                                         29
South Tyneside                           LEA Contact
Capital Value £18,663,000              Stanley Johnson
South Tyneside - Boldon High           0191 424 7771
School                                 stanley.johnson@s-tyneside-mbc.gov.uk

The South Tyneside project will replace Boldon High School on its existing site. It
includes funding from DCMS for a 250-seat theatre and 25 metre swimming pool.
The contract was signed in April 2005 with MJ Gleesons and full services should
commence in January 2007.




Stoke-on-Trent                           LEA Contact
Capital Value £93,000,000              Mike Inman
Stoke on Trent - Schools Grouped       01782 236338
Pilot Scheme                           johnmichealinman@stoke.gov.uk

This project is providing energy, energy management and repair and maintenance
work to all 100+ maintained schools in Stoke-on-Trent. This was one of the five large
grouped PPP pilots supported through New Deal for Schools. The contract was
signed between Stoke City Council and Transform Schools (Stoke) in November
2002. Work has started for a five year programme, which will be completed in
October 2005.


Swindon                                 LEA Contact
Capital Value £62,800,000              Neil Selby
Swindon - North Swindon Schools        01793 463532
PFI                                    nselby@swindon.gov.uk

This seven school project will provide three new primary schools, one new
secondary, two special schools (one primary and one secondary) and a
replacement building for Hreod Parkway Secondary School. All seven new
schools will be in the northern sector of Swindon. The contract was signed
with Equion on 1st April 2005 and the first schools are scheduled to open in
January 2007.




                                          30
Telford and Wrekin                      LEA Contact
Capital Value £70,010,000             Tracy Penrose
Telford & Wrekin - Hadley Learning    01952 202234
Community Incorporating Jigsaw        tracy.penrose@telford.gov.uk

An innovative project funded by both DfES and DCMS, providing a new
secondary school, a new primary school and a special school, with a new,
part residential children's centre with SEN and mainstream foundations units
on a second site. It also includes an arts & drama centre, extensive provision
for sports and recreation, and other community facilities. The contract was
signed on 15 March 2005 with Pyramid Schools (Hadley) Ltd and full services
are due to commence in September 2006 for the secondary school and



Tower Hamlets                          LEA Contact
Capital Value £89,164,000             Barry Gooden
Tower Hamlets - Grouped Schools       020 7364 4314
                                      barry.gooden@towerhamlets.gov.uk

This is a large group PPP pilot project supported by New Deal for Schools,
New Deal for Communities and Sure Start. It addresses educational
deficiencies, a backlog of maintenance work and energy conservation and
management involving 27 schools (reducing to 25 due to an amalgamation of
three establishments). The contract was signed with Babcock & Brown on 28
 June 2002. All schools will receive interim services from September 2002
with full services in all schools from September 2007.



Waltham Forest                         LEA Contact
Capital Value £53,600,000             Chris Loy
Waltham Forest 2 - Grouped            020 8496 8167
Schools Project                       chris.loy@ce.lbwf.gov.uk

This project involves 8 schools with both new build and refurbishment. The
contract was signed on 15 March 2004 with Academy Services and interim
services commenced immediately. Construction should be completed by April
2006.




                                         31
Wirral                                LEA Contact
Capital Value £58,500,000            Polly Paulson
Wirral - Nine school project         0151 691 8115
                                     pollypaulson@wirral.gov.uk

This project involves the complete replacement of two schools and the
extension, refurbishment and maintenance of seven schools. The contract
was signed with Jarvis Plc in March 2001. Full services commenced in all
secondary schools by September 2004 and the primary school is scheduled to
 be operational in March 2005.



York                                  LEA Contact
Capital Value £15,400,000            Damon Copperthwaite
York - Four schools                  01904 554218
                                     damon.copperthwaite@york.gov.uk

This project is for the replacement of four primary schools: Hob Moor Primary
School, St Barnabas' CE Primary School, St Oswald's CE Primary School and
the new Hob Moor Oaks Primary School, together with community facilities.
The contract was signed with the Sewell Group in January 2005 and services
 will commence from September 2005 to March 2006.




                                         32
3.    Projects in procurement


Birmingham                             LEA Contact
                                      Peter Farrell
Birmingham 2 - Thirteen Schools       0121 303 8847
                                      peter_farrell@birmingham.gov.uk

This is the second Birmingham schools PFI project. It includes 13 schools (1
nursery, 10 primary and 2 secondary). One infant school and one primary
school will amalgamate; the then 12 schools will be rebuilt.


Doncaster                              LEA Contact
                                      Andy Tompkinson
Doncaster - Two schools               01302 736700
                                      andy.tompkinson@doncaster.gov.uk

This project is to rebuild two secondary schools (Mexborough and Edlington)
on their existing sites. Both new schools will have 1344 places for students
aged 11-18 years old.




Gateshead                               LEA Contact
                                      John Devlin
Gateshead - Group of Schools          0191 433 2900
                                      johndevlin@gateshead.gov.uk

This project is for the rebuild of two secondary schools and three primary schools
and the relocation and rebuild of two primary schools (of which one is VA) onto the
same site.




                                         33
Hounslow LEA Contact
                                       John Mundy
Hounslow - Heston Schools PFI          020 8583 2177
Project                                john.mundy@hounslow.gov.uk

The project entails the rationalisation of three schools and all associated
buildings at the Heston Campus in Hounslow. The refurbishment of the
buildings will achieve a modern teaching environment with contemporary
educational standards.



Kent                                     LEA Contact
                                       Rebecca Spore
Kent - Six schools (including Hugh     01622 221151
Christie Technology College)           rebecca.spore@kent.gov.uk

This project will provide 6 non-selective secondary schools with a mix of new,
remodelled and refurbished buildings.


Lewisham                                 LEA Contact
                                       David Welch
Lewisham - Grouped Schools             020 8314 6207
Modernisation (PFI) Project            david.welch@lewisham.gov.uk

This project will substantially modernise one special school for pupils with
severe learning difficulties, along with four primary and two secondary
schools.


Newcastle upon Tyne                       LEA Contact
                                       Frank Jordan
Newcastle 2 - Six schools              0191 211 5362
                                       frank.jordan@newcastle.gov.uk

This project will provide new build serviced accommodation at one secondary
school, four primary schools and one special school.




                                           34
Norfolk                                   LEA Contact
                                       Linda Boal
Norfolk 2 - Norwich Area Grouped       01603 638021
Schools PFI Project                    linda.boal@norfolk.gov.uk

This project will rationalise the age of transfer between 11 first and middle
schools and one secondary school in line with the Key Stage ages of transfer.
 It will provide four new build replacement primary schools (to replace 10 first
and middle schools), one new build junior school (to replace one middle
school) and one refurbished secondary school.



Northamptonshire                        LEA Contact
                                       Peter Burrell
Northamptonshire 2 - Northampton       01604 237417
Review                                 pburrell@northamptonshire.gov.uk

The project is to facilitate the schools reorganisation programme in
Northampton Town, moving from a three tier to a two tier system. This will
involve an extensive modernisation programme through which 5 new schools
will be built, 42 will be refurbished and there will be a new learning discovery
centre.



Oldham                                  LEA Contact
                                       Peter Hodkinson
Oldham - Grouped Schools               0161 911 3287
                                       peter.hodkinson@oldham.gov.uk

This project is for two new build replacement schools, transferring existing
split site schools onto single sites.

Peterborough                             LEA Contact
                                       Tony Reinis
Peterborough - Secondary Schools       01733 748103
Scheme                                 tony.reinis@peterborough.gov.uk

This project involves the amalgamation of two secondary schools into one
newly built school in the north west sector of the city. Two further secondary
 schools will be refurbished and expanded.




                                           35
Plymouth                          LEA Contact
                                 Barbara Booth
Plymouth 1&2-Whitleigh Community 01752 307434
Campus & Replacement Primaries   barbara.booth@plymouth.gov.uk

This project will provide serviced accommodation at the Whitleigh Community
Campus and six new build replacement primary schools. At Whitleigh there
will be rebuilding and part refurbishment, to include a secondary school, two
primary schools and a special school (relocated onto the campus). Elsewhere
 in Plymouth, 8 primary, infant and junior schools will be replaced by 6 new
build primary schools, including the amalgamation of separate infant and junior
schools on two sites into single primary schools.



Rochdale                                LEA Contact
                                      John Bollington
Rochdale - Aiming High                01706 865046
                                      john.bollington@rochdale.gov.uk

This project is for the refurbishment and remodelling of one Community High
School with new build provision for an additional 225 special needs pupils
co-located on the same site. Also there will be three new build primary
schools (two with co-located 100 place SEN facilities and one with SEN unit
for 16 hearing impaired pupils).



Salford                                LEA Contact
                                     Judy Edmonds
Salford 2 - High Schools PFI Project 0161 778 0134
                                     judy.edmonds@salford.gov.uk

This project will provide serviced accommodation at three high schools on
existing sites, all of which will be rebuilt.


Slough                                  LEA Contact
                                      Maggie Waller
Slough - Three schools                01753 875744
                                      maggie.waller@slough.gov.uk

This project involves the new build of three schools - one primary and one
secondary school to be re-provided on existing sites and one special school to
 be relocated to the site of and integrated with the secondary school.




                                         36
Worcestershire                          LEA Contact
                                       Peter Parkes
Worcestershire - Bromsgrove            01905 766803
Schools                                pparkes@worcestershire.gov.uk

This project will replace two high schools, two middle schools and three first
schools in the Bromsgrove area.




                                          37
4. Building Schools for the Future (BSF) - Projects in
Procurement

Bradford                                    LEA Contact
                                            Stephen Jones
                                            01274 432851
                                            stephen.jones@bradford.gov.uk

This project involves the rebuilding of 3 large secondary schools: Buttershaw High
School, Tong School and Salt Grammar School.




Bristol                                     LEA Contact
                                            Gordon Clements
                                            01179 224271
                                            gordon_clements@bristol-city.gov.uk

This project involves the rebuilding of 4 secondary schools (and other related
educational facilities) in Brislington School, Hartcliffe Education Campus, Speedwell
Technology College and Whitefield Community School.




Greenwich                                   LEA Contact
                                            Terry Kirkpatrick
Greenwich Schools BSF Phase 1               020 8921 5513
                                            terry.kirkpatrick@greenwich.gov.uk

Rebuilding/renewal/expansion of five secondary schools.




Knowsley                                    LEA Contact
                                            Chris Williams
                                            0151 443 3225
                                            chris.williams@knowsley.gov.uk

This project involves the closure of all eleven secondary schools within the authority
and the building of eight new learning centres.




                                          38
Lancashire                                   LEA Contact
                                             Janet Newton
                                             017725 31259
                                             janet.newton@ed.lancscc.gov.uk

This involves the replacement of 8 secondary schools in Burnley, and 3 secondary
schools in Pendle with 9 new build schools. Eight of the new builds will be procured
via PFI. One of the new builds will be a VA school which shall be conventionally
procured. This will be done in 3 phases, with phase 1 delivering 3 new schools
including a special school co-located with one of the secondary schools.




Leeds                                        LEA Contact
                                             Robert Douglas
Leeds Schools BSF Phase 1                    0113 395 0302
                                             robert.douglas@educationleeds.co.uk

The project involves four new build PFI schools (Allerton High School, Allerton
Grange School, Pudsey Grangefield School and Rodillian School) and two
conventionally-funded refurbished schools (Cockburn High School and Temple Moor
High School) to provide high quality teaching and learning accommodation for
students, staff and the community in inner Leeds.




Leicester                                    LEA Contact
                                             Keith German
Leicester Schools BSF Phase 1                0116 252 7727
                                             keith.german@leicester.gov.uk

This project involves four secondary schools: two will be re-built with PFI credits and
two will be refurbished with conventional funding.




Lewisham                                     LEA Contact
                                             Tony Freeman
                                             020 8314 3797
                                             tony.freeman@lewisham.gov.uk

This project involves the rebuilding of 3 secondary schools: Sedgehill School (PFI
new-build) for 1780 pupils, Northbrook VA School (non PFI) for 750 pupils and
Catford Girls Business & Enterprise College (non PFI) for 900 pupils.




                                           39
Newcastle                                   LEA Contact
                                            Graham Johnson
                                            0191 211 5386
                                            graham.johnson@newcastle.gov.uk

This project will rebuild Walbottle Campus Technology College. This is part of the
BSF programme for the replacement of eight secondary and two special schools.
The first stage of this procurement will also include the procurement of four primary,
one special and one secondary school through PFI (the Newcastle 2 – Six schools
project). The whole programme (including the schools from the previous PFI round)
will be arranged in one phase (in two parts) under a single procurement exercise.



Sheffield                                   LEA Contact
                                            Chris Dale
Sheffield Schools BSF Phase 1               0114 273 5735
                                            chris.dale@sheffield.gov.uk

This project involves 9 secondary schools. The new build schools being Newfield,
Silverdale, SEN's North and South, KS4 Support College. Partial re-builds being
Yewlands and Firth Park, whilst major refurbishments and/or remodelling being
undertaken at High Storrs and KS3 Inclusion centre.




Solihull                                    LEA Contact
                                            Mark Fenton
                                            0121 704 6643
                                            mfenton@solihull.gov.uk

This project involves the rebuilding of 3 secondary schools and 1 secondary special
school: Park Hall School, Smiths Wood School, Archbishop Grimshaw Catholic
Secondary School and Lanchester Special School.




Waltham Forest                              LEA Contact
                                            Chris Loy
Waltham Forest BSF wave 1 - Sample          020 8496 8167
Schemes project
                                            chris.loy@walthamforest.gov.uk

This project involves four secondary schools; two will merge and be housed in a new
building using PFI credits, and two will be refurbished with conventional funding.




                                          40
5. Signed projects supported by New Deal for Schools
(NDS) grant

Blackpool                                LEA Contact
                                        Paul Sharp
Blackpool - NDS - Collegiate High       01253 476070
School                                  paul.sharp@blackpool.gov.uk

This project constructed an indoor sports centre on the school grounds, which
 is also available for use by another special school. The private sector partner
 contributed capital and was granted a lease to operated the upgraded
facilities out of school hours. Prior to this construction, the school used to pay
 to rent indoor facilities. The project was signed with Uforia in August 2000
and became operational in April 2001.


Cambridgeshire                           LEA Contact
                                        Brian Harris
Cambridgeshire - NDS - Foxton           01223 717361
Primary school                          brian.harris@cambridgeshire.gov.uk

This was a joint Parish Council/District Council/County scheme to rebuild
Foxton Primary School through a combination of funding sources, including the
 Millennium Lottery Fund. The private sector contribution was by way of a
capital receipt linked to planning permission for housing. The contract was
signed with Mills & Douglas in March 2000 and became operational in March
2001.



Devon                                    LEA Contact
                                        Steve Daw
Devon - NDS - Highweek school           01392 382025
                                        sdaw@devon.gov.uk

This was a planning gain scheme, which enabled the school to replace all
temporary accommodation. The contract was signed with Midas Homes and
Devon & Cornwall Housing Association in November 2000 and the project was
 officially opened in October 2002.




                                           41
Hillingdon LEA Contact
                                       David Berman
Hillingdon - NDS - Whitehall Junior    01895 277363
School                                 dberman@hillingdon.gov.uk

This project provided a much-needed extension to the school hall incorporating
 storage and changing facilities. The private sector contribution was linked to
planning gain in relation to new housing. The contract was signed with
Sherman & Co (Ealing) Ltd in March 2000 and the accommodation was handed
 over in October 2000.



Kent                                    LEA Contact
                                       Keith Hargrave
Kent - NDS - Canterbury High
School                                 canterbury@canterbury.kent.sch.uk

This project was to develop new sports facilities at the school. This included
an athletics track, sports hall, dance studio and gymnasium to be shared with
other local schools and the wider community. The contract was signed
between the school and Canterbury Sports Ltd on 27 June 2000 and
completed in September 2001.



Kent                                     LEA Contact
                                       Nick Tricker
Kent - NDS - Weald Grammar             01622 696560
School                                 nick.tricker@kent.gov.uk

This project provided a library extension and a new-build technology room. It
was financed by a mixture of NDS grant, private sector capital injection, PTA
fundraising and LEA funding. The private sector funding was provided by the
school's uniform supplier, which benefits from a franchise arrangement with
the school. The project became operational in September 1999.



Kingston Upon Hull                       LEA Contact
                                       John Bates
Kingston-upon-Hull - NDS - St          01482 613505
Marys College                          john.bates@hullcc.gov.uk

This project provided a new 6th form centre, classrooms, dining facilities and a
 music/drama suite. The contract was signed with the Sewell Group in July
2000. The school began utilising the music/drama facilities in October 2000
and the remainder of the building by January 2001.


                                          42
Lancashire                               LEA Contact
                                       Joanne Ashurst
Lancashire - NDS - Tulketh High        01772 264789
School                                 joanne.ashurst@fin.lancscc.gov.uk

This project provided sports facilities which are available to the school during
school hours and operated by Short-Sided Soccer (SSS) for the benefit of the
local community at other times. SSS are responsible for the maintenance and
capital reinvestment. The contract was signed on 11 May 2001 with Eric
Wright Group. The sports facilities opened in September 2002.



Manchester                              LEA Contact
                                       Bernard Core
Manchester - NDS - Whalley Range       0161 234 7053
High School                            bernard_core@notes.manchester.gov.uk

This project provided a basketball sports hall with a fitness suite and
associated teaching rooms, along with 10 all-weather pitches. Management
and Operating Agreements between the Council, the School, Short-Sided
Soccer and Trafford Basketball Centre were signed on 13 July 2001. Work on
 site was completed in May 2002.



Tower Hamlets                           LEA Contact
                                       Yim Ho-Ayler
Tower Hamlets - NDS - Culloden         020 7364 4315
School                                 edudev@towerhamlets.gov.uk

This project completed the rebuilding of the school. The private sector partner
invested professional time in the project as well as a capital contribution and
has worked with the LEA and school to build on programmes to raise
educational standards. The private sector partner sees its benefit coming
from a better-educated local workforce, which will assist its plans for
expansion. The contract was signed with Mount Avril in October 1999 and the
 school was fully operational in September 2000.




                                          43
Waltham Forest                          LEA Contact
                                       Susan Julian
Waltham Forest - NDS - Heathcote       020 8527 5544
School                                 susan.julian@edu.lbwf.gov.uk

This project provided a music centre incorporating practice rooms and
recording studios. A mixture of NDS grant, private sector capital injection and
LEA funding financed this project. The private sector gain is through the use
of facilities out of school hours. The contract was signed with Keynote
Recording Studios in November 1997 and all work was completed by
September 1998.



West Sussex                             LEA Contact
                                       Sarah Thorp
West Sussex - NDS - Littlehampton      01243 756613
School                                 sarah.thorp@westsussex.gov.uk

This project provided an Information & Learning Centre for the school, the
community and for business use. The private sector partner contributed
capital and is using the centre for their IT training purposes. The contract was
 signed with the Body Shop in June 2000 and the new centre became
operational in September 2001.



West Sussex                             LEA Contact
                                       Sarah Thorp
West Sussex - NDS - Downview           01243 756613
County School                          sarah.thorp@westsussex.gov.uk

This project provided a dual use classroom space, for use as a special needs
room during school hours and as a breakfast/after school/holiday club
managed by a private sector partner in return for a capital contribution. The
contract was signed in December 2000 and the project was operational in
September 2001.


West Sussex         LEA Contact
                                       Sarah Thorp
West Sussex - NDS - East Wittering     01243 756613
School                                 sarah.thorp@westsussex.gov.uk

This project replaced two wooden temporary classrooms and was linked to
the granting of planning permission for new housing. The contract was
signed in March 2000 and became operational in September 2001.


                                          44

								