									BUILD UP GREATER CLEVELAND ANNUAL REPORT
                          FISCAL YEARS 2007 – 2008
TABLE OF CONTENTS

 BUILD UP GREATER CLEVELAND ............................................ 01


 CITY OF CLEVELAND ............................................................ 03


 CLEVELAND-CUYAHOGA COUNTY PORT AUTHORITY ................. 06


 CUYAHOGA COUNTY ENGINEER ............................................ 08


 NORTHEAST OHIO REGIONAL SEWER DISTRICT ....................... 11


 GREATER CLEVELAND REGIONAL TRANSIT AUTHORITY .............. 14


 OHIO DEPARTMENT OF TRANSPORTATION ............................. 17


 SUMMARY .......................................................................... 18


 APPENDICES ....................................................................... 19


 CONTACT ............................................................................ 37
                                           BUILD UP GREATER CLEVELAND
                                           A TRADITION OF REGIONAL LEADERSHIP
                                           For 25 years, Build Up Greater Cleveland (BUGC) has effectively served as
                                           a regional advocate and coordinator for investment in and improvement of
                                           Greater Cleveland’s infrastructure. BUGC, a program of the Greater Cleveland
                                           Partnership (GCP) in conjunction with the Cleveland Engineering Society (CES),
                                           serves as an invaluable guiding force in northeast Ohio.

                                           BUGC stakeholders and partners recognize that Greater Cleveland’s “hidden
                                           assets” (streets, bridges, water and sewage systems, public transportation) are
                                           often taken for granted while the demand for improvements is significant and the
                                           resources limited.

                                           Greater Cleveland’s infrastructure network demands regular monitoring and
                                           maintenance. Improvements are constant, costly and routinely extend across
                                           municipal boundary lines. Over the last 25 years, BUGC has helped to attract
                                           more than $6 billion of infrastructure and transportation funding to Greater
                                           Cleveland to improve our bridges, roadways, waterways and public utilities. But
                                           there is much more to do.

                                           In 2007 and 2008, BUGC invested more than $638 million in capital projects
                                           throughout Cuyahoga County to maintain and enhance the existing public
                                           infrastructure system. Road improvements represent the largest expenditure.
                                           BUGC allocated nearly $272 million in contracts to road projects. BUGC’s
                                           commitment to reinvesting in aging infrastructure extends well beyond the
                                           surface. Over the last two years, BUGC has invested approximately $165 million
                                           in water infrastructure improvements. The overall extent of BUGC’s two-year
                                           capital investment is as follows:
                                           BUGC CAPITAL INVESTMENTS • 2007 / 2008 • ($’s IN THOUSANDS)
                                           CONTRACTS LET
                                                             Agency                2007             2008                  Total
STAKEHOLDERS & PARTNERS                      Roads
•	City	of	Cleveland                          City of Cleveland                      $ 14,686             $ 37,992     $ 52,678
                                             County Engineer                        $ 34,485             $ 10,931     $ 45,416
•	Cleveland-Cuyahoga	County                  ODOT - District 12 (Cuyahoga)          $ 45,479             $ 111,459    $ 156,938
	 Port	Authority                             RTA                                    $ 5,891              $ 10,742     $ 16,633
                                                                 Subtotal Roads     $ 100,541            $ 171,124    $ 271,665
•	Cleveland	Engineering	Society              Bridges
                                             City of Cleveland                      $      5,826         $        0   $    5,826
•	Cuyahoga	County	Engineer                   County Engineer                        $      6,791         $    5,424   $   12,215
                                             ODOT - District 12 (Cuyahoga)          $     14,769         $    4,352   $   19,121
•	Greater	Cleveland	Partnership              RTA                                    $      2,130         $    4,120   $    6,250
                                                               Subtotal Bridges     $     29,516         $   13,869   $   43,412
•	Greater	Cleveland	Regional                 Sewer
	 Transit	Authority                          County Sanitary Engineer               $ 4,366              $ 4,086      $ 8,452
                                             NEORSD                                 $ 59,773             $ 39,387     $ 99,160
•	Northeast	Ohio	Areawide                                        Subtotal Sewer     $ 64,139             $ 43,473     $ 107,612
	 Coordinating	Agency
                                             Transit                                $ 38,526             $ 11,412     $ 49,938
•	Northeast	Ohio	Regional	Sewer	District     Water                                  $ 54,914             $ 110,074    $ 164,988

•	Ohio	Department	of		Transportation         Port                                   $       495          $     150    $       645
	 -District	12                                         Grand Total Contracts Let    $ 288,131            $ 350,129    $ 638,260
                                                                                                                                    01
     BUGC is a successful model of how regional
     cooperation can benefit our community.
     Created in 1983 at the urging of then-
     Mayor George Voinovich, BUGC has worked
     closely with its partners and stakeholders,
     encouraging efficient and focused spending of
     precious tax dollars to preserve and upgrade
     our infrastructure.

     Greater Cleveland’s infrastructure – its roads,
     bridges, water and sewage systems and more
     – form the foundation of our community. It’s
     expensive to maintain and upgrade. BUGC, its
     stakeholders and its partners are committed to
     getting the most out of every dollar spent on
     enhancing our infrastructure.

     In late 2008, BUGC began the process
     to secure resources from the Federal
     Government under the proposed economic
     stimulus plan. A significant portion of the
     $787 billion federal stimulus package focuses
     on investment in the country’s infrastructure
     network in order to create jobs and impact
     to the economy. According to the Federal
     Highway Administration, $1.25 billion in
     infrastructure investment creates nearly
     35,000 jobs in our communities. BUGC
     stakeholders have identified $2.8 billion in
     projects requests and have submitted the
     unified package to local, state and federal
     government officials.

     The results of the stimulus package are taking
     shape. The BUGC stakeholders and partners
     continue their collaborative efforts to advance
     key infrastructure, transportation and public
     utility projects for the betterment of Greater
     Cleveland and northeast Ohio.

     To date, northeast Ohio has received over
     $260 million for key infrastructure and
     transportation projects. What follows are
     descriptions of some of the infrastructure
     goals and accomplishments for BUGC’s five
     public stakeholders for fiscal years 2007-2008.




02
CITY OF CLEVELAND                                                                         Since	2007,	the	
                                                                                         City	has	invested	
The City of Cleveland (the “City”) has targeted infrastructure improvements and
maintenance as essential to the City’s vitality and growth. The City continuously       nearly	a	quarter	of	
makes substantial infrastructure investments that allow Cleveland to function
better today and to grow its economic base in the future. These initiatives are
                                                                                        a	billion	dollars	in	
costly, and funding sources are often strained.                                          rehabilitation	of	
INFRASTRUCTURE IMPROVEMENTS A PRIORITY                                                roadways,	bridges	and	
                                                                                       water	infrastructure.
In 2006, the City conducted a thorough assessment of its capital needs, its ability
to pay for capital improvements and its capacity to complete major development
projects that had been guaranteed funding. Upon conclusion of that assessment,
the City confirmed its substantial capital needs, but its funding capacity was
greatly insufficient in comparison.

Thus the City has limited recourse to address such financial challenges.
Historically, the City utilizes general obligation bonds, its full faith and credit
debt instrument to finance public improvements including infrastructure.
Because debt capacity was limited, the City made the decision to forego a general
obligation bond issuance until 2007 in order to increase its ability to borrow.

In 2007, the City issued $45 million in general obligation bonds. The majority
of the bond revenues was utilized by the City’s Division of Engineering and
Construction for infrastructure improvements. In 2007, the City awarded more
than $20 million in infrastructure improvement construction contracts.
CITY - ENGINEERING & CONSTRUCTION:
2007 TOP FIVE PROJECTS ($’s IN THOUSANDS)
                                            Additional Funding Sources

          Project               City        State    Local     Issue 1   Total
 Cornell Road Bridge            $ 1,745                        $ 4,081    $ 5,826
 Bridge Replacement

 West 150 St.                   $ 657       $ 500   $ 1,093    $ 3,013    $ 5,263
 Reconstruction

 Ward Resurfacing               $ 4,400                                   $ 4,400

 Kamm’s Corner Duct Bank        $ 2,308                                   $ 2,308
 Enhancement

 Avenue District Phase 1                                                  $ 1,715
 Reconstruction                 $ 1,715
                                                                                                            03
     The City awarded more than $37 million in contracts in 2008 leveraging over $148 million in
     other capital project investment in roads, bridges, transit, and water improvements throughout           The	City	sold	
     its urban core. Major capital improvements are as follows:
                                                                                                               nearly	$144	
     CITY - ENGINEERING & CONSTRUCTION:
     2008 TOP FIVE PROJECTS ($’s IN THOUSANDS)
                                                                                                             million	in	water	
                                                      Additional Funding Sources                             revenue	bonds	
       Project                        County      County      State     Local      Issue 1       Total       to	fund	capital	
       Quincy Avenue
       Rehabilitation                   $ 2,112                                    $ 4,929         $ 7,041    improvement	
       Berea Road                       $ 257     $ 2,820              $ 1,840     $ 282           $ 5,199   projects	during	
       Rehabilitation
                                                                                                                2007-2008.
       Big Creek Watershed              $ 1,412                        $ 517       $ 2,936         $ 4,865
       Stormwater

       Avenue District                  $ 4,656                                                    $ 4,656
       Phase 2 & 3
       Ward                             $ 4,400                                                    $ 4,400
       Resurfacing


     MAJOR PROJECT SNAPSHOT 2008 - 2012

     In 2008, the City identified 42 capital projects in various stages of planning, design, and/or
     construction resulting in an investment of nearly $280 million in road and bridge rehabilitation
     improvements in the City over a five-year period. The City’s investment in the top three capital
     projects - the Euclid Corridor Transportation Project, Fulton Road Bridge and the West 3rd Lift
     Bridge - total $163 million in capital improvements and represent more than 58 percent of its
     projected infrastructure investment from 2008 to 2012.

     DIVISION OF WATER

     The City also operates the eighth largest water supply system in the United States that serves
     the City and 73 suburban municipalities in Cuyahoga, Medina, Summit and Geauga counties.
     The Division of Water (the “Division”) service area covers more than 640 square miles and serves
     more than 1.5 million people. The Division contracted for approximately $55 million in capital
     improvements in 2007, leveraging $98 million in other resources. Funds were primarily used
     to address continuing renovations at the Morgan, Baldwin and Nottingham plants, equipment
     and rehabilitation of water mains and the implementation of the coordinated Geographical
     Information System.

     CITY - DIVISION OF WATER:
     2007 TOP FIVE PROJECTS
                         Project                           Funding Source                 Total
      Morgan East Reservoir Project                   WSRLA Loan / Revenue Bonds       $ 42.9 million
      Cleaning & Cement Mortar Lining of                     Revenue Bonds             $ 6.3 million
      Distribution Mains - Areas A & B
      General Engineering Services IV                       Operating Revenue          $ 2.8 million
      Highland - Trebisky Water Main Rehabilitation         Operating Revenue          $ 1.7 million
      Installation of Chlorine and Water                     Revenue Bonds             $ 627 thousand
      Quality Monitors



04
 In 2008, the Division let more than $110 million in contracts for capital
improvements.
CITY - DIVISION OF WATER:
2008 TOP FIVE PROJECTS
                Project                       Funding Source              Total
 Morgan Water Works Plant
 Pretreatment and Residuals              WSRLA Loan / Revenue Bonds   $ 42.4 million
 Fairmount Pump Station Rehabilitation         Revenue Bonds          $ 24.0 million
 Kirtland Pump Station Rehabilitation        Operating Revenue        $ 17.9 million
 Cleaning & Cement Mortar Lining of          Operating Revenue        $ 6.2 million
 Distribution Mains - Areas A & B
 Hosting and Managed Services                  Revenue Bonds          $ 6.0 million



The five largest projects total $96 million and account for 88 percent
of the total contracts let in 2008. In fiscal years 2008-2012, the City
will invest more than $278 million in water improvement projects.

City capital infrastructure improvement projects are financed primarily
through the use of general obligation bond proceeds, State Issue 2 and
Local Transportation Improvement Programs. However, the volatility
of the current economic market warrants that the City maximizes its
investment in capital projects in an effort to stimulate economic and
community revitalization efforts throughout its core business districts
and neighborhoods. The City recognizes that a coherent infrastructure
                                                                                       West Shoreway Conceptual    Hope Memorial Bridge
strategy is necessary to promote long-term economic growth.




MAKING CLEVELAND A CITY OF CHOICE


                                                                                       Fulton Road Bridge




The	City	will	invest	over	$278	million	in	
water	improvement	projects	throughout	
 Greater	Cleveland	from	2008	to	2012.
                                                                                       Columbus Road Lift Bridge

                                                                                                                                          05
     CLEVELAND-CUYAHOGA COUNTY PORT AUTHORITY
      The Cleveland-Cuyahoga County Port Authority (the “Port”) serves as an
      economic engine for Greater Cleveland, and is positioned to further bolster and
      grow our region’s economy in numerous ways.

      While the impact of the Port’s maritime activities are significant, the Port’s
      development financing program also serves as a catalyst for infrastructure
      improvements and other economic development activities in Greater Cleveland.

      Historically, the Port has served as a key public partner in the advancement of
      catalytic real estate projects that drive the resurgence of economic investment
      in the region. Since 1993, the Port has financed more than $1.5 billion worth of
      capital improvements and economic development projects that are integral to
      advancing Greater Cleveland’s economy.

      Established in 1997, the Port’s Bond Fund Program provides long-term, fixed
      interest rate financing of $1 million to $10 million to credit worthy businesses,
      governments and non-profit organizations for owner-occupied industrial,
      commercial, non-profit and infrastructure projects. The Port has issued more
      than $274 million in bonds over the last two years to local businesses to finance
      capacity-building infrastructure projects, assist in key land acquisition, and        The	Port’s	
      generate and spur job growth. Examples of the Port’s investments include:
                                                                                             maritime	
      PORT AUTHORITY:
      TOP FIVE PROJECTS 2007 - 2008 • ($’s IN THOUSANDS)                                     activities	
       Project                                                                Total           support	
       Cleveland Clinic th
       Carnegie / E. 89 Street                                            $ 157,000         11,000	jobs	
       Science Park Cleveland                                             $ 81,000        that	generate	
       Laurel School - Geauga County                                      $ 16,000
       Euclid Avenue Housing                                              $ 15,000
                                                                                           $572	million	
       Brush Wellman - Ottawa County                                      $ 5,000          in	personal	
       TOTAL FINANCED                                                     $ 274,000          incomes.



06
MARITIME

While the Port provides financing to community and economic
development projects, it also recognizes the need to substantially
invest in its own infrastructure and operations. Industry experts
forecast cargo traffic will exceed the current capacity of many
coastal ports by 2020, thus providing additional incentive for the
Port to assess its future growth opportunities.

In 2007, major maritime capital improvements consisted of:
	 •	 Installation	of	bulkheading	at	the	Old	River	Property	
     at a cost of $494,551
                                                                     Port Warehouses          Working Ship
	 •	 Investment	of	$492,000	for	the	construction	of	new
     dock face

	 •	 Replacement	of	timber	curb	totaling	$75,000.

In 2008, the Port allocated $150,000 toward dock and
warehouse capital improvements.

LOOKING AHEAD . . . PORT RELOCATION

The Port is seeking to grow its current lines of business through
the creation of additional and/or new Port facilities to handle
bulk cargo, break-bulk cargo and ultimately containerized cargo.
                                                                     Tugboats
The existing port facility, which encompasses a 44-acre bulk
terminal and a 1,850 linear foot dock, is insufficient to handle
the anticipated demands of the continuous growth of next-
generation cargo and containerization. The aforementioned
potential growth in existing and new lines of business
necessitates a significant improvement in the Port’s facilities.
The footprint of the port will need to accommodate increased
demands.

The Port’s ambitious plans for the future call for the relocation
of its facilities at an estimate cost of $575 million. The Port’s
growing physical infrastructure needs are perhaps the most
dominant reason for a new facility. The Port’s preferred             Working Ship
relocation to E. 55th Street would provide improved intermodal
logistics and investment opportunities.




MORE THAN A WORKING WATERFRONT


                                                                     Existing Port Facility

                                                                                                             07
     CUYAHOGA COUNTY ENGINEER                                                                 Since	2002,	the	
                                                                                            State	of	Ohio	has	
      The Cuyahoga County Engineer has an array of vital duties in the nation’s 23rd
      most populous county. The engineer’s responsibilities include the construction,        spent	more	than	
      maintenance and repair of all roads and bridges that fall under the jurisdiction of     $315	million	on	
      the Cuyahoga County Commissioners.
                                                                                            365	bridges	in	141	
      The engineer oversees the maintenance and reconstruction of 239 bridges, and
      assists municipalities with the improvement of 794 miles of county roadway. The
                                                                                            separate	projects.
      engineer also has direct responsibility for 22 miles of roadway in the county’s              -	Ohio	Department
      two townships.                                                                                 of		Transportation

      The tragic 2007 Minneapolis bridge collapse has resulted in a heightened
      awareness about the structural integrity of our nation’s bridges. While failures
      such as the one in Minneapolis are extremely rare, rigorous state and county
      inspections combined with decades of repair are necessary in providing a reliable
      and safe bridge system.

      The County Engineer annually inspects its bridges to determine capital
      improvement priorities. The County’s current inventory includes 84 bridges
      built before 1950. The average age of bridges under the County’s control is
      about 49 years. Due to their age, an intensive maintenance and repair program is
      required. Rehabilitation is possible to extend the useful life of the structure but
      replacement may be necessary to ensure the health and safety of those using the
      transportation system. In either case, improvements are designed to extend the
      useful life of a bridge by 20 to 50 years.




            From	2001	-	2008,	the	County	Engineer
            has	spent	nearly	$1	million	annually	in	
08
              maintenance	for	County	Bridges.
FUNDING

Large scale road and bridge improvement projects warrant
intergovernmental coordination. To the highest extent possible, the County
seeks to leverage its resources with federal and state funds. Capital project
funding is largely dependent upon two primary factors - availability of
funding and project type. Most projects are financed by a combination of
federal, state and local funds. On average, for qualifying projects, nearly
80% of funding is provided by federal and state resources with 20%
provided by the local government.

The County Engineer works with the Northeast Ohio Areawide
Coordinating Agency (NOACA) to access key federal funding. For fiscal
years 2008-2011, NOACA has allocated more than $61 million for capital
projects in Cuyahoga County through its Transportation Improvement
Program.
                                                                                Columbus Road Lift Bridge

Like federal dollars, state matching dollars vary by program. The Ohio
Department of Transportation (ODOT) is the state agency that participates
in the local infrastructure process for roads and bridges. ODOT must
approve all federally funded projects. ODOT also provides the local
match for federally funded projects on state or interstate routes. ODOT’s
contribution of resources for the County Engineer’s five-year capital
improvement plan focuses Cuyahoga County Engineer predominately upon
state route bridge projects. The average participation by the State is 20% of
project costs.

ODOT’s Bridge Rehabilitation and Replacement Fund has proven to be an
invaluable resource for the County Engineer because construction costs for
federal bridge projects are usually matched at a rate of 80 percent federal,
20 percent local. The local match for bridge projects is provided through the
County Engineer’s revenue sources.

At a local level, the County Engineer works closely with municipalities,
assisting with the planning, financing and construction phase on many
                                                                                Miles Road Bridge
projects. Local governments provide matching funds for road and bridge
projects. Most often these funds are leveraged by county resources.
Collaboration with local municipalities is imperative because local
projects represent more than half of the County Engineer’s projects
during the next five years and allow the County to meet local and regional
infrastructure needs. Resources for the County Engineer’s portion of
capital improvements come from two major revenue sources. The first is
a $5 Motor Vehicle License Fee enacted in 1968. The second is a $7.50
Motor Vehicle Fee enacted in 1987 as a result of the growing need for
improvements in the transportation system. In 1987, the Board of County
Commissioners authorized a $10 increase in Motor Vehicle License Fees.
This increase is split between the County and municipalities, with $7.50 to
the County and $2.50 to municipalities.




                                                                                Main Avenue Bridge          09
     In 2007, the County Engineer oversaw more than $46 million in major
     capital improvements projects. It strategically invested in the rehabilitation
     and reconstruction of the existing transportation system as opposed to new
     construction projects.

     COUNTY ENGINEER:
     2007 TOP FIVE PROJECTS ($’s IN THOUSANDS)
                                                 Additional Funding Sources

                Project            County        Federal    Local     Issue 1       Total

      Eastland Road                   $ 3,481    $ 14,853   $ 1,296                 $ 19,630
      Berea Road                      $ 550                 $ 1,913   $ 2,463       $ 4,926
      Warrensville Center Road        $ 373      $ 3,311    $ 454                   $ 4,138    Schaaf Road Bridge          Wolf Road Bridge
      Warrensville Center             $ 352      $ 2,056                            $ 2,408
      Road Bridge
      Wilson Mills Road               $ 1,604                $ 401                  $ 2,005

     In 2008, the County Engineer let nearly $22 million in capital
     improvement construction. Its primary objective was maintenance and
     rehabilitation of its existing inventory. The projects identified below
     best illustrate the County Engineer’s emphasis on addressing existing
     infrastructure needs first:

     COUNTY ENGINEER:
     2008 TOP FIVE PROJECTS ($’s IN THOUSANDS)
                                                 Additional Funding Sources
                                                                                               Columbus Road Lift Bridge
               Project             County        Federal    Local     Issue 1       Total

      Cook Road / Sterns Road         $ 1,019     $ 2,290   $ 2,387   $ 300          $ 5,996
      Columbus Road Lift Bridge       $ 1,500                         $ 1,500        $ 3,000
      Snow Road                       $ 289       $ 2,310             $ 289          $ 2,888
      Rockside                        $ 197       $ 1,786                            $ 1,985
      Road Bridge                                                     $         2

      Lewis Road                      $ 1,123               $ 481                    $ 1,604

     The County Engineer’s five-year Capital Improvements Program for
     2008-2011 consists of a $185.9 million investment in 65 capital road
     and bridge projects. Rehabilitation and reconstruction of the existing
     transportation system over the next five years will focus on three
     specific areas: road grade, drain and pave projects; bridge and culvert                   Whiskey Island Bridge       Crocker Road - Sterns Road
     rehabilitation/replacement and road repair/resurfacing.


     OUR BUSINESS IS ROADS, BRIDGES
     AND LAND RECORDS


                                                                                               Veteran’s Memorial Bridge

10
NORTHEAST OHIO REGIONAL SEWER DISTRICT
Since its inception in 1972, the Northeast Ohio Regional Sewer District (the
“District”) has made significant contributions to wastewater collection and
treatment, storm water management, and water quality issues throughout
Greater Cleveland. The District operates three major wastewater treatment
facilities – Easterly, Southerly and Westerly. Its service area encompasses the City
of Cleveland and 59 other communities in Cuyahoga and Summit counties. The
benefit the District provides the approximately one million persons it serves
extends beyond artificial community boundaries. It safely and efficiently returns
clean water to Lake Erie after proper wastewater treatment.

FUNDING

Over the years, the District has seen the availability of federal financing for
capital sewer improvement and wastewater treatment projects greatly diminish.
In the 1970s and 1980s, federal grants were a primary source for financing
capital projects and the District was very successful in obtaining these funds.
However, in 1990 the federal government discontinued its construction grants
program which fundamentally changed the way the District pursued future
financing of its capital projects. The District began placing greater emphasis
on obtaining loans from the federally capitalized, Ohio Clean Water State
Revolving Loan Program known as the Water Pollution Control Loan Fund
(WPCLF), which provides below-market rate loans. In addition to WPCLF
funds, the District utilizes internally generated funds and proceeds from the
sale of revenue bonds to finance capital projects. Nonetheless, capital project
financing continues to be a rather challenging endeavor that requires the District
to be both proactive in its pursuit of financing to meet capital expenditures and
strategic in the manner in which it allocates those funds. The District’s success in
achieving this balance is further magnified as the Ohio Environmental Protection
Agency established new provisions in 2007 that significantly limits allocation of
funds in the state. As a result of its limited borrowing capacity and the lack of
federally funded grants, the District expects it will need to increase the amount
of internally generated funds for its capital projects.




                                                                                       11
                                    CAPITAL PROJECTS

                                    In 2007, the District issued more than $126 million in Wastewater Improvement
                                    Revenue Bonds for the purpose of providing funds for the acquisition, construction, and
                                    improvement of water resource projects. By year’s end, the District had nearly $1.5
                                    billion invested in capital assets. The District’s most prominent construction project
                                    to date is the $200 million Mill Creek Tunnel, which is designed to reduce combined
                                    sewer overflows (CSOs) to the environment. The Mill Creek Tunnel, the District’s first
                                    large CSO project, is under construction and near completion. When complete the
                                    15,600 foot long tunnel will be capable of storing more than 70 million gallons of CSO
                                    volume annually. Twelve communities will benefit from the project as the tunnel relieves
                                    currently overloaded, combined storm and sanitary sewers. In addition, 13 of 27 outfalls
                                    now discharging to Lake Erie, the Cuyahoga River, Cranwood Creek and Wolf Creek
                                    will be eliminated upon its completion.
                                    NEORSD:
                                    2007 TOP FIVE PROJECTS ($’s IN THOUSANDS)

                                                     Project                       NEORSD           State                     Total
                                     Relining and Replacement Contract                             $ 11,593                      $ 11,593
                                     Flats East Bank Neighborhood                    $ 8,000                                     $ 8,000
                                     Second Stage Aeration Tank                      $ 5,953                                     $ 5,953
                                     Heights / Hilltop Interceptor                   $ 4,245                                     $ 4,245
                                     Final Clarifier Rehabilitation                  $ 3,422                                     $ 3,422
                                    The District did not issue any new revenue bonds for capital improvements in 2008 but
                                    it allocated more than $39 million for contracts for capital maintenance and equipment
                                    replacement.

                                    While bond financing is considered the secondary source of funding after it has
                                    exhausted other less expensive alternatives, the District also relies on fees to finance a
                                    considerable portion of its capital improvements. The most recent sewer rate increase,
                                    approved in 2007, is due to expire in 2011. The increase will generate about $200
                                    million in additional revenue over the five-year time period.
                                    NEORSD:
                                    2008 TOP FIVE PROJECTS ($’s IN THOUSANDS)

                                                        Project                       NEORSD                Total
                                     Bridge Rehabilitation                               $ 7,604                    $ 7,604
                                     Valley Belt Gravity Sewer                           $ 6,056                    $ 6,056
                                     Westerly Interceptor Box Culvert                    $ 5,117                    $ 5,117
                                     Heights / Hilltop Interceptor                       $ 3,837                    $ 3,837
    One	dollar	of	                   Final Clarifier and Aeration Rehabilitation         $ 3,161                    $ 3,161
  water	and	sewer	                  The District’s five-year capital improvement plan (2008-2012) identifies the investment
   infrastructure	                  of more than $792 million in improvements to sewer treatment plants, interceptor
                                    rehabilitation and combined sewer overflow control enhancements. While the investment
investment	increases	               is necessary to meet current and future operational and infrastructure needs, the CSO
GDP	in	the	long	term	               controls and wastewater facility improvements are unfunded but costly federal mandates.
                                    The CSO controls mandate, for example, dictates the investment of approximately $3.2
      by	$6.35.                     billion dollars of capital investments. In March 2005, the District adopted a 30-year
                                    schedule to design and construct a $2 billion CSO Long Term Control Plan (the “CSO
     -Bureau	of	Economic	Analysis   LTCP) to limit pollution caused by CSOs. The CSO LTCP calls for the construction of
                                    103 miles of tunnels and connecting sewers and is designed to substantially reduce CSO
12                                  discharges by nearly 90 percent within 20 years of construction.
LOOKING AHEAD . . . SUSTAINABLE INFRASTRUCTURE

Over the years, the District has positioned itself to continue to meet the
level of service and regulatory requirements demanded by its customers,
its Board of Trustees and regulatory agencies. From 1995 to 2003, the
District performed facilities planning studies to develop a plan to further
reduce CSO throughout the service area to meet the mandates of the
federal CSO Policy. These studies resulted in plans to build storage
tunnels throughout the combined sewer service area, as well as smaller
consolidated sewers, storage tanks and other improvements.

The District has made substantial progress at improving its three
                                                                              Easterly Treatment Plant    Cataract Falls
wastewater treatment facilities. As the District’s service area has grown
and become more urbanized, there has been greater occurrence of
flooding, erosion and water quality problems. The District’s Stormwater
Management Program, scheduled to commence in 2009, will include
maintaining streams and large pipes that carry stormwater, continued
water-quality monitoring and expanding regional watershed planning
and floodplain management in its service area. To date, the District has
invested more than $2.2 billion on wastewater-related projects.

The District estimates that it will need to invest approximately $520
million in capital improvement projects over the next four years. It will
strategically invest in both regulatory driven capital improvements and
rehabilitation driven capital improvements at Easterly, Southerly, and
Westerly and within its collection system. With regard to regulatory          Southerly Treatment Plant
driven improvements, the District will allocate up to $168 million
toward related wet-weather plant improvements at Easterly and
Southerly. The District has identified an estimated $275 million of
renewal/replacement work for Southerly and Easterly, and an additional
$813 million is estimated over the next 10 years for collection system
rehabilitation and other treatment plant projects.




PROTECTING YOUR HEALTH
AND ENVIRONMENT




                                                                              Mills Creek Falls           Westerly Treatment Plant

                                                                                                                                     13
     GREATER CLEVELAND REGIONAL
     TRANSIT AUTHORITY                                                                            RTA	serves	more	
                                                                                                     than	200,000	
     Created in December 1974, the Greater Cleveland Regional Transit Authority (RTA) is
     the largest transit system in Ohio, serving more customers than the transit systems in     customers	per	week	
     Columbus, Cincinnati, Dayton and Toledo combined.
                                                                                                -	eliminating	50,000	
     In 2007, mass transit experienced significant gains in ridership. Americans took           cars	from	roadways	
     10.3 billion trips using public transportation – the highest number since World War
     II. According to the American Public Transportation Association (APTA), “public             in	northeast	Ohio.
     transportation ridership in the US has grown by more than 32 percent, faster than
     highway travel or the U.S. population.” The RTA has experienced six consecutive years
     of steady ridership growth and provided an estimated 57.9 million rides in 2008. RTA’s
     success has not escaped national notice - the American Public Transportation Association
     has designated the RTA as the best transit system in North America.

     RTA’s commitment to provide a quality transportation service extends beyond providing
     good customer service. When RTA eliminates nearly 50,000 vehicles weekly from
     Greater Cleveland roadways, it makes substantial environmental contributions to the
     region. The transit authority has converted its entire fleet to clean diesel vehicles,
     purchased state-of-the-art hybrid vehicles, and incorporated improvements that utilized
     energy efficient design elements and landscaping at its station facilities. During 2007,
     RTA placed great emphasis on facility upgrades, bridge reconstruction, and fleet
     expansion. It authorized nearly $47 million in capital improvements in 2007. RTA’s top
     five capital improvement projects total more than $34 million and represent 75 percent
     of the year’s contracting total. Major construction projects are as follows:

     RTA:
     2007 TOP FIVE PROJECTS ($’s IN THOUSANDS)
                                                 Additional Funding Sources

               Project              Total            Federal         State    Total

      Fair Collection Equipment       $ 2,468        $ 9,873                  $ 12,341
      Ticket Vending Machines         $ 2,139        $ 8,555                  $ 10,694
      HealthLine                      $ 1,402        $ 4,221         $ 191    $ 5,814
      Purchase of Vehicles            $ 830          $ 3,322                  $ 4,152
      Abby Road Bridge
      Reconstruction                  $ 1,968                                 $ 1,968



14
                          In 2008, RTA opened its most significant capital
                          improvement project - the Euclid Corridor Transportation
                          Project (HealthLine). The HealthLine is the largest
                          infrastructure project in Cleveland history.
                          The 6.8 mile Bus-Rapid Transit system, located along Euclid
                          Avenue, will transport more than 22,000 riders a day and
                          provide valuable linkage between Greater Cleveland’s
                          top two employment hubs – downtown Cleveland and
                          University Circle.

                          In addition to improving public transportation service
                          along one of Cleveland’s busiest corridors, the HealthLine
                          will play an integral role in transforming the physical
                          and socioeconomic landscape of downtown Cleveland.
                          HealthLine shows that investment in public transportation
                          generates significant economic benefits. To date, the
                          HealthLine has spurred more than $4.3 billion in capital
                          investment along the Euclid Corridor.

                          RTA’S MAJOR CONSTRUCTION PROJECTS

                          While the completion of the HealthLine was RTA’s top
                          priority in 2008, it has also engaged in a host of other
                          major construction projects that strongly solidified public
                          transportation’s vital role in the contribution of long-term
                          economic and community development benefits that are
                          destined to lead Greater Cleveland on path toward growth
                          and prosperity. RTA spent more than $26 million for capital
                          projects in 2008. Its investment in the HealthLine accounted
                          for more than 41% of that total. Additional projects:


                          RTA:
                          2008 TOP FIVE PROJECTS ($’s IN THOUSANDS)
                                                                      Additional Funding Sources

                                    Project               RTA           Federal         State      Total

                           HealthLine                     $ 2,148        $ 8,594                   $ 10,742
                           Four Transit Track
                           Bridges Reconstruction         $ 795          $ 3,182                   $ 3,977

                           West Park Substation           $ 398          $ 1,592                   $ 1,990
                           Replacement
                           Shaker Truck Line              $ 337          $ 1,346                   $ 1,683
                           Reconstruction
                           Light Rail Vehicles
                           Audio / Video Surveillance     $ 237          $ 949                     $ 1,186




Ohio City Rapid Station
                                                                                                              15
CHALLENGES

Although RTA was experiencing historic ridership gains in 2007 and 2008, it
found itself trying to navigate a “Perfect Storm” in 2008 - increased ridership,
escalating fuel costs and insufficient funding. Since the majority of RTA funding
comes from local sources - farebox revenue and a 1% local sales tax – its larger
capital improvement projects require substantial federal investment. Recent
studies conducted by the Ohio Public Transit Association show there is an
unmet need for $30 million annually to maintain and improve performance
of the state’s transit systems. With an unsolicited designation as the nation’s
fourth poorest big city, Cleveland is in dire need of funds that will create jobs,
stimulate economic activity, and generate additional tax revenues for the city.
                                                                                     Downtown Trolley
The impact of reduced driving – and thus reduced federal gasoline tax
revenues – has had a significant impact on the State of Ohio. While nearly all
state funding for transit originates as General Revenue Funds, no gasoline
revenues can go to public transit. In 2008, high diesel fuel costs and reduced
funding placed RTA in an extremely compromised financial state. RTA
expenses for diesel fuel have increased from $4 million in 2004 to $21
million in 2008. In 2008, the transit agency was faced with the decision of
having to cut services, increase fares, defer capital projects and postpone the
replacement of buses.

Ohio Governor Ted Strickland and the Northeast Ohio Areawide Coordinating
Agency (NOACA) provided a one-time infusion of funds and RTA
implemented a modified fuel surcharge and service reduction in November              Euclid Corridor                W. 65th Street Rapid Station
2008 to keep the transit authority’s fiscal year 2009 budget solvent.

LOOKING AHEAD . . . CAPITAL PROJECTS

RTA’s five-year Capital Improvement Plan (2008-2012) serves as a blueprint
for assessing the future transit needs of the region and exploring strategies
to redefine transit policy. The five-year capital plan calls for the investment
of more than $443 million in capital improvements. RTA will allocate funds
toward the acquisition, construction, replacement, repair and renovation
of major capital facilities, vehicles and equipment. Significant capital
improvements planned for the five-year period include: rail projects, local
capital projects, bridge rehabilitation and other improvements, bus purchases,
paratransit vehicles and circulator buses, transit centers and shelters, Euclid      HealthLine Bus
Corridor Transportation Project, equipment and non revenue vehicles, and
operating expenses and other expenses. RTA plays a vital role in the resurgence
of Cleveland as a hub for economic prosperity. Its sustained investment in
transportation infrastructure encourages new development, supports existing
business, promotes the creation of sustainable communities, and improves the
quality of life of Greater Clevelanders.


QUALITY SERVICE: EVERY CUSTOMER, EVERY DAY

                                                                                     W. 65th Street Rapid Station

16
OHIO DEPARTMENT OF TRANSPORTATION
The Ohio Department of Transportation (ODOT) maintains all state and federal
roadways in the state of Ohio with the exception of the Ohio Turnpike. ODOT is
divided into 12 regional districts. Cuyahoga, Geauga and Lake counties are within
District 12. ODOT’s District 12 is responsible for the planning, design, construction
and maintenance of Interstate Routes and State and U.S. Routes within Cuyahoga,
Geauga and Lake counties.

In existence for more than 100 years, ODOT’s new mission reflects a greater emphasis
on a multi-modal approach to modernizing the state’s transportation system. Its               Each	dollar	
transformative shift is best illustrated by its commitment to strategically reinvest in
its current inventory. District 12 oversaw more than $260 million worth of capital        invested	in	highway	
improvements in 2007 and 2008. More than 70 percent ($183 million) of that work was
allocated toward road and bridge improvements in Cuyahoga County (see appendix).
                                                                                             construction	
Major capital improvements throughout District 12 consisted of:                            generates	$1.80	of	
ODOT - DISTRICT 12:
2007 TOP FIVE PROJECTS ($’s IN THOUSANDS)                                                   GDP	in	the	short	
                                            Additional Funding Sources                           term.
       Project              State                    Federal             Total
                                                                                                 -Standard	&	Poor’s	DRI
 Lake IR-90                   $ 25,491                                   $ 25,491
 Cuyahoga US-322              $ 3,862                $ 15,448            $ 19,310
 Cuyahoga IR-480              $ 1,488                $ 13,391            $ 14,879
 Geauga US-422                $ 2,009                 $ 8,035            $ 10,044
 Lake SR-283                  $     500               $ 6,563            $ 7,063

Construction activity in Cuyahoga County accounted for 99 percent of District 12
projects in 2008. The major reconstruction in Cuyahoga County at a cost of $90 million
represented ODOT’s largest allocation of funds accounting for 70% of the total.

ODOT’s 2008-2009 construction season was by many accounts an “historic” feat.
ODOT managed $2.5 billion in construction contract awards, which is the largest
amount ever awarded over an 18-month period in its 100 years of existence. The
capital investment consists of the commencement of nearly 1,000 construction projects
across Ohio - 80 Interstate construction projects totaling approximately $605 million
and 823 paving and rehabilitation projects on state and U.S. routes totaling more than
$1.1 billion. The scope of ODOT’s 2008-2009 investment in Cuyahoga County will
encompass 175 capital improvement projects totaling more than $281 million. While
the sheer volume of projects commenced is impressive, the fact that ODOT completed
493 construction projects on time is equally impressive.
                                                                                                                      17
     SUMMARY                                                                               In	2007	and	2008,	
     This report is packed with facts about recent, substantial accomplishment and
     investment in Greater Cleveland. With BUGC’s help, billions of dollars of public
                                                                                          BUGC	stakeholders	
     funds have been spent – and will continue to be spent – improving our roads,         invested	more	than	
     bridges, waterlines, sewage treatment plants and mass transit system. Ensuring
     that these projects are done well – and the money spent on them is done so as          $638	million	in	
     efficiently as possible – requires deliberate, dedicated work. Much has been        capital	infrastructure	
     accomplished, but much remains to be done. Acquiring the funding for these
     projects is oftentimes a grueling and difficult mission. BUGC, its stakeholders     projects	throughout	
     and its partners will continue to strive for efficiency, regional cooperation and
     quality work as we continue to improve and maintain Greater Cleveland’s vast
                                                                                           Cuyahoga	County.
     and vital infrastructure.

     Additional detail about recent Greater Cleveland infrastructure improvement
     projects can be reviewed in the appendix that follows.




18
APPENDICES




             19
20
                                                                       City of Cleveland - Engineering and Construction
                                                                               2007 Contracts Let for Capital Projects
                                                                                         ($ in Thousands)
                                                                                                                                 ADDITIONAL FUNDING SOURCES                          Total
     TYPE            PROJECT NAME                  LOCATION                             CITY OF CLEVELAND        FEDERAL       ODOT   ODOD        Brook Park    ISSUE 1               Cost
     Roads
                     Avenue District Phase I         Superior - East 13th Street                         1,715                                                                          1,715
                     Concrete Contract               Citywide                                            1,000                                                                          1,000
                     Kamm's Corner Duct Bank         Kamm's Corner Neighborhood                          2,308                                                                          2,308
                     Ward Resurfacing                Citywide                                            4,400                                                                          4,400
                     West 150 St Reconstruction      W 150 St                                              657                        500        1,093          3,013                   5,263

                     Subtotal Roads                                                                   $10,080                         $500       $1,093         $3,013              $14,686

     Bridges
                     Cornell Road Bridge             Cornell Road                                        1,745                                                  4,081                   5,826

                     Subtotal Bridges                                                                  $1,745                                                   $4,081                $5,826

     TOTAL CITY OF CLEVELAND - Engineering & Construction Let 2007 Construction                                                                                                     $20,512

     Source: City of Cleveland - Engineering & Construction Division, Capital Contracts 2007




                            Capital Funding Distribution                                                             Capital Funding Distribution by Source

                              Bridges
                                                                                                                                                               City of Cleveland - $11,825
                               28%
                                                                                                                         35%
                                                                                                                                                               State - $500
                                                                                Roads -$14,686
                                                  Roads
                                                   72%                          Bridges - $5,826                                                58%            Local - $1,093

                                                                                                                                                               Issue 1 - $7,094

                                                                                                                   5%
                                                                                                                         2%
                                                                          City of Cleveland - Engineering and Construction
                                                                                     2008 Contracts Let for Capital Projects
                                                                                               ($ in Thousands)
                                                                                                                                    ADDITIONAL FUNDING SOURCES
                                                                                         CITY OF                                                                        ISSUE 1      ISSUE 1         TOTAL
     TYPE      PROJECT NAME                    LOCATION                               CLEVELAND          FEDERAL   ODOT    ODOD* CUY CO. Lakewood                NEORSD (Loan)       (Grant)         COST
     Roads
               Avenue District - Phase II       E 12th: Lakeside-St.Clair Ave.                  2,611                                                                                                    2,611
               Avenue District - Phase III      E 12th: St. Clair-Superior Ave.                 2,045                                                                                                    2,045
               Bellaire Road (W 105- W 117)     West 105 St - W 117 St                            454                                        346                                           1,551         2,351
               Berea Rd. Rehabilitation         Detroit to Triskett                               257                                      2,820         1,840                               282         5,199
               Big Creek Watershed              West branch of Big Creek                        1,412                                                            517    900                2,036         4,865
               Detroit Avenue Streetscape       Detroit Avenue                                  1,640     1,600    104                                                                                   3,344
               E. 78th Street Workaround        East 78th Street                                  364                      350                                                                             714
               Kamm's Corner                    Kamm's Corner Neighborhood                      2,329                                                                                                    2,329
               Pavement Management              Citywide                                          532      200                                                                                             732
               Quincy Avenue Rehab              Quincy Avenue                                   2,112                                                                                      4,929         7,041
               Stonebridge Streetscape - Ph1    Stonebridge Development                           215                                                                                                      215
               Tremont Point                    Valleyview Hope VI                              1,146                                                                                                    1,146
               2008 Concrete Contract           Citywide                                        1,000                                                                                                    1,000
               Ward Resurfacing                 Citywide                                        4,400                                                                                                    4,400

               Subtotal Roads                                                              $20,517       $1,800    $104    $350           $3,166     $1,840      $517   $900            $8,798       $37,992


     TOTAL CITY OF CLEVELAND - Engineering & Construction Let 2008 Construction                                                                                                                      $37,992

     Note: ODOD* - Ohio Department of Development
     Source: City of Cleveland - Engineering & Construction Division Capital Contracts 2008



                    Capital Funding Distribution by Project                                                                    Capital Funding Distribution by Source
                                                                     Avenue District - Phase II & III

                                                                     Bellaire Road (W 105- W 117)

                                                                     Berea Rd. Rehabilitation

               3%                                                    Big Creek Watershed Storm water                                                                              City of Cleveland -$20,517
                          12%          12%                                                                                                          5%     1%
      0% 3%                                                                                                                         1%
                                                 6%                  Detroit Avenue Streetscape                                5%
                                                                                                                                               8%                                 Federal - $1,800
                                                                     E. 78th Street Workaround                                                                   26%
                                                      14%                                                                                                                         State - $454
        18%
                                                                     Kamm's Corner
                                                                                                                                                                                  County - $3,166
                                               13%                   Pavement Management System
                    6%                                                                                                                   54%
                                  9%                                                                                                                                              Local - $1,840
                                                                     Quincy Avenue Rehab
          2%                                                         Stonebridge Streetscape - Phase I                                                                            NEORSD - $517
                         2%                                          Tremont Point                                                                                                Issue 1 - $9,698
                                                                     2008 Concrete Requirements Contract

                                                                     Ward Resurfacing




21
22
                                                                                    City of Cleveland - Division of Water
                                                                                      2007 Contracts Let for Capital Projects
                                                                                                ($ in Thousands)
     WATER PROJECT NAME and DESCRIPTION                                                                                              FUNDING SOURCE                                 TOTAL COST

     Highland-Trebisky Water Main Rehabilitation                                                                                        Operating Revenue                                    1,799
     Morgan East Reservoir Project                                                                                              WSRLA Loan/Revenue Bonds                                    42,906
     Installation of Chlorine and Water Quality Monitors                                                                                   Revenue Bonds                                       627
     Cleaning & Cement Mortar Lining of Distribution Mains - Area A                                                                        Revenue Bonds                                     3,545
     Cleaning & Cement Mortar Lining of Distribution Mains - Area B                                                                        Revenue Bonds                                     2,843
     Water Quality Initiatives Assistance                                                                                               Operating Revenue                                      299
     General Engineering Services IV                                                                                                    Operating Revenue                                    2,895

     TOTAL City of Cleveland -Division of Water Let 2007 Construction                                                                                                                     $54,914


     Source: City of Cleveland - Division of Water, Capital Projects Contracts Let 2007



                 Capital Funding Distribution by Source                                                                             Capital Funding Distribution
                                         Operating                                                                                                          Highland-Trebisky Water Main
                                                                                                                            1%           3%
                                         Revenue                                                                                                            Rehabilitation
                                           9%                                                                                       5%
                                                                                                             1%          12%                                Morgan East Reservoir Project

                                                                                                                                                            Installation of Chlorine and Water
                                                                  Operating Revenue - $4,993                                                                Quality Monitors
                  Revenue Bonds                                   Revenue Bonds - $49,921                                                                   Cleaning & Cement Mortar Lining of
                       91%                                                                                                                     78%          Distribution Mains - Area A & B
                                                                                                                                                            Water Quality Initiatives Assistance

                                                                                                                                                            General Engineering Services IV
                                                                           City of Cleveland - Division of Water
                                                                             2008 Contracts Let for Capital Projects
                                                                                       ($ in Thousands)
     WATER PROJECT NAME and DESCRIPTION                                                               FUNDING SOURCE                               TOTAL COST

     Design Engineering Services for Baldwin Residuals & Fairmount Reservoir                          Operating Revenue                                      2,215
     First Contract Modification - Project Management for CIS/CRM System                              Operating Revenue                                      1,502
     Test, Evaluate, Repair or Replace Roofs and Appurtenances                                        Operating Revenue                                      1,539
     Kirtland Pump Station Rehabilitation                                                                Revenue Bonds                                      17,981
     Professional Consulting Services for Warehouse Improvements                                         Revenue Bonds                                       1,300
     Professional Consulting Services for Meter Automation & Replacement Program                      Operating Revenue                                      3,200
     Cleaning & Cement Mortar Lining of Distribution Mains - Area 2008-A                                 Revenue Bonds                                       3,598
     Cleaning & Cement Mortar Lining of Distribution Mains - Area 2008-B                                 Revenue Bonds                                       2,602
     Design Engineering Services for Morgan Chemical Facility                                         Operating Revenue                                      2,381
     General IT Consulting Services                                                                   Operating Revenue                                        425
     Professional Consulting Services for Hosting and Managed Services Project                        Operating Revenue                                      6,048
     Fairmount Pump Station Rehabilitation                                                               Revenue Bonds                                      24,059
     Crown Waterworks Filter and Masonry Project                                                         Revenue Bonds                                         768
     Morgan Water Works Plant Pretreatment and Residuals                                      WSRLA Loan/Revenue Bonds                                      42,456

     TOTAL City of Cleveland - Division of Water Let 2008 Construction                                                                                 $110,074

     Source: City of Cleveland - Division of Water, Capital Projects Contracts 2008



                            Capital Funding by Source                                                                  Capital Funding Distribution
                                                    Operating                                                                              Design Engineering
                                                    Revenue                                                              6%   4% 1%        Services
                                                      16%                                                     10%
                                                                                                                                           Contract Modification

                                                                Operating Revenue - $17,310
                                                                                                                                           Rehabilitation
                   Revenue Bonds                                Revenue Bonds - $92,764                                        79%
                        84%                                                                                                                Professional
                                                                                                                                           Consultation
                                                                                                                                           Distribution Mains




23
24
                                                                                        Cuyahoga County Engineer
                                                                                     2007 Contracts Let for Capital Projects
                                                                                               ($ in Thousands)
                                                                                                                                   ADDITIONAL FUNDING SOURCES                TOTAL
     TYPE            PROJECT NAME                            LOCATION                                             COUNTY       FEDERAL ODOT      ISSUE 1   LOCAL/OTHER        COST
     Roads
                     Warrensville Center Road                 Cleveland Heights / South Euclid                          373       3,311                              454           4,138
                     Eastland Road                            Berea, Brook Park, Middleburg Heights                   3,481      14,853                            1,296          19,630
                     Bagley Road                              Olmsted Falls                                             273                                           68             341
                     Berea Road                               Cleveland / Lakewood                                      550                        2,463           1,913           4,926
                     Wilson Mills                             Highland Hts. / Richmond Hts.                           1,604                                          401           2,005
                     Ridge Road                               Brooklyn                                                  339                                           85             424
                     Stearns-Bagley Intersection              Olmsted Township                                          594                                        1,183           1,777
                     Crocker Road                             Westlake                                                  995                                          249           1,244

                     Subtotal Roads                                                                                 $8,209      $18,164            $2,463         $5,649        $34,485
     Bridges
                     Eastland Bridge                          Berea, Brook Park, Middleburg Heights                      41         373                                                  414
                     Canal Road Culvert                       Valley View                                               594                                          148                 742
                     Warrensville Center Road Bridge          Warrensville Heights                                      352       2,056                                                2,408
                     Edgerton Road Culvert No.22              North Royalton                                            241                                           60                 301
                     Lewis Road Culvert No.7                  Olmsted Falls                                             221                                           55                 276
                     Bridge Deck Program - North                                                                        223                                                              223
                     Bridge Deck Program - South                                                                        148                                                              148
                     Whiskey Island                           Cleveland                                                                                            1,982               1,982
                     Falls Road Culvert Project                                                                         297                                                              297

                     Subtotal Bridges                                                                               $2,117       $2,429                           $2,245          $6,791
     Engineering
                     Stearns Road Grade Separation            Olmsted Township                                          123         491                               12                626
                     General Engineering Services                                                                       815                                          165                980
                     Construction Inspection Services                                                                   300                                                             300
                     Veterans Memorial Bridge Lighting                                                                  250                                                             250
                     Bainbridge Right-of-Way                                                                            807                                                             807
                     Bennett Road                             North Royalton                                            234                                                             234
                     Towpath Trail                            Cleveland - Harvard to Steelyard Commons                              750                                                 750
                     E.105 / MLK Intersection                 Cleveland                                                 800                                                             800
                     Bellaire Road Bridge                     Cleveland                                                 235                                                             235

                     Subtotal Engineering                                                                           $3,564       $1,241                            $177           $4,982

                     TOTAL COUNTY ENGINEER LET 2007 CONSTRUCTION                                                                                                                $46,258

     Source: Cuyahoga County Engineer, Fiscal Department Capital Projects Contracts 2007



                                Capital Funding by Source                                                                      Capital Funding Distribution
                                               Local                                    County - $13,890                                            Engineering
                                                                                                                                 Bridges
                          Issue 1              18%               County                                                                                10%
                                                                                        Federal - $21,834                         15%
                            5%                                    30%                                                                                               Roads - $34,485
                                 ODOT
                                                                                        ODOT - $0
                                  0%                                                                                                                                Bridges - $6,791
                                                   Federal                                                                                 Roads
                                                                                        Issue 1 - $2,463                                                            Engineering - $4,982
                                                    47%                                                                                     75%
                                                                                        Local - $8,071
                                                                                 Cuyahoga County Engineer
                                                                             2008 Contracts Let for Capital Projects
                                                                                       ($ in Thousands)
                                                                                                                        ADDITIONAL FUNDING SOURCES                TOTAL
     TYPE          PROJECT NAME                      LOCATION                                                  COUNTY FEDERAL         ISSUE 1 LOCAL/OTHER          COST
     Roads
                   Snow Road                         Parma                                                          289        2,310                    289                  2,888
                   Franklin Street                   Bainbridge Township, Bentleyville, Chagrin Falls                45          360                     45                    450
                   Cook Road / Stearns Road          Olmsted Township, North Olmsted                              1,019        2,290      2,387         300                  5,996
                   Cuyahoga Community
                   College Eastern Campus
                   Road Improvements                 Village of Highland Hills                                                   717                     71                   788
                   Eddy Road                         East Cleveland                                                    589                     220                            809

                   Subtotal Roads                                                                               $1,942       $5,677      $2,607       $705             $10,931

     Bridges
                   Rockside Road Bridge              Valley View                                                    197        1,786                      2                  1,985
                   Stearns Road Culvert              Olmsted Township                                               200                                                        200
                   Lewis Road Bridge                 Olmsted Township, N. Olmsted                                 1,123                        481                           1,604
                   Emery Road Bridge                 North Randall, Warrensville Hts.                               559                        240                             799
                   Shaker Blvd Bridge                Pepper Pike                                                    627                        209                             836

                   Subtotal Bridges                                                                             $2,706       $1,786       $930          $2               $5,424

     Engineering
                   Columbus Road Lift Bridge       Cleveland                                                      1,500                               1,500                  3,000
                   Old Royalton Bridge             Cleveland                                                        106                                                        106
                   Fitch Grade Separation                                                                           175                                                        175
                   Bainbridge Right-of-Way                                                                          100                                                        100
                   General Engineering Services                                                                     600                                                        600
                   Construction Materials Testing                                                                   200                                                        200
                   Towpath Trail - Stage Three     Cleveland                                                                     700                                           700
                   Veterans Memorial Bridge Lighting                                                                   150                                                     150
                   Crocker-Stearns                                                                                      26                                                      26
                   Whiskey Island/Drake                                                                                 40                                                      40
                   SR 82 / Shoreway/ Ridge                                                                             300                                                     300

                   Subtotal Engineering                                                                         $3,197         $700                  $1,500              $5,397

                   TOTAL COUNTY ENGINEER LET 2008 CONSTRUCTION                                                                                                         $21,752

     Source: Cuyahoga County Engineer, Fiscal Department Capital Projects Contracts 2008



                              Capital Funding by Source                                                                      Capital Funding Distribution
                        Issue 1                  Local
                          18%                    11%                                                           Engineering
                                                                                    County - $7,845               21%
                                            County                                                                                     Roads              Roads - $10,931
                                                                                    Federal - $8,163                                    57%
                                             35%                                                                             Bridges                      Bridges - $5,424
                                  Federal                                           Issue 1 - $3,537                          22%
                                   36%                                                                                                                    Engineering - $5,397
                                                                                    Local - $2,207




25
26
                                                   Cuyahoga County - Sanitary Engineer
                                                      2007 Contracts Let for Capital Projects
                                                                ($ in Thousands)
                                                                                           ADDITIONAL FUNDING SOURCE
     TYPE           PROJECT NAME                   LOCATION                    COUNTY               STATE*             TOTAL COST

     Sewers
                    Bagley Road 2                  Olmsted Township                1,700                                      1,700
                    Creekside WWTP                 Pepper Pike                        30                                         30
                    Echo Hills Phase 1             Brecksville                                       435                        435
                    Echo Hills Phase 2             Brecksville                                      1,372                     1,372
                    Creekside Pump Station         Pepper Pike                        30                                         30
                    Sewer Relining                 Various                           514                                        514
                    Valley Ranch Pump Station      Garfield Heights                  152                                        152
                    Richmond Bluffs Pump Station   Richmond Heights                  133                                        133

                    Subtotal Sewers                                              $2,559             $1,807                   $4,366


     TOTAL COUNTY SANITARY ENGINEER LET 2007 CONSTRUCTION                                                                    $4,366

     Note: State - Water Pollution Control Loan Fund
     Source: Cuyahoga County Sanitary Engineer, Fiscal Department Capital Projects Contracts 2007




                         Capital Funding by Source

                     State
                     41%

                                                   County               County - $2,559
                                                    59%                 State - $1,807
                                                      Cuyahoga County - Sanitary Engineer
                                                         2008 Contracts Let for Capital Projects
                                                                   ($ in Thousands)
                                                                                  ADDITIONAL FUNDING SOURCE
     TYPE           PROJECT NAME                  LOCATION             COUNTY               STATE           TOTAL COST

     Sewers
                    Bradford Pump Station         Brecksville                                      560                          560
                    Carriage Hill Pump Station    Brecksville               100                                                 100
                    Greenbrook Pump Station       Olmsted Township          160                                                 160
                    Bernwood Pump Station         Beachwood                 160                                                 160
                    Cook Stearns                  Olmsted Township                                 560                          560
                    Cook Mackenzie                Olmsted Township                                 555                          555
                    Hemlock Falls Pump Station    Brecksville               230                                                 230
                    Hemlock Falls Pump Station    Brecksville                50                                                  50
                    Creekside WWTP                Pepper Pike                33                                                  33
                    Granite Road Pump Station     Maple Heights                                    300                          300
                    Thornapple Pump Station       Mayfield Village                                 900                          900

                    Subtotal Sewers                                       $733                 $2,875                      $3,608
     Other
                    Allied Technology             Various                   140                                                 140
                    Engineering Contract          Various                    13                                                  13
                    Emergency Repair Contract     Various                   125                                                 125
                    Newburgh Study                Newburgh Heights                                 200                          200

                    Subtotal Other Projects                               $278                     $200                      $478


     TOTAL COUNTY SANITARY ENGINEER LET 2008 CONSTRUCTION                                                                  $4,086

     * Water Pollution Control Loan Fund
     Source: Cuyahoga County Sanitary Engineer, Fiscal Department Capital Projects Contracts 2008


                 Capital Funding by Source                                        Capital Funding Distribution
                                                                              Other
                                                                             Projects
                                                                               12%
                              County
                               25%                                                                 Sewers   Sewer Improvements -
                                                     County - $1,011                                88%     $3,608
                  State
                                                     State - $3,075                                         Other Projects - $478
                  75%




27
28
                                                                                 Northeast Ohio Regional Sewer District
                                                                                    2007 Contracts Let for Capital Projects
                                                                                              ($ in Thousands)
                                                                                                                                             ADDITIONAL FUNDING SOURCE
     TYPE                   PROJECT NAME                                              LOCATION                                    NEORSD               STATE                 TOTAL COST
     Treatment Plant
     Improvements
                            Effluent Screw Pumps Rehabilitation                       Easterly                                       2,474                                          2,474
                            Final Clarifier Rehabilitation                            Easterly                                       3,422                                          3,422
                            Generator Closure Contract SPI-6                          Southerly                                        423                                            423
                            Second Stage Aeration Tank Rehabilitation                 Southerly                                      5,953                                          5,953
                            Substation Replacement: Design                            Southerly                                      1,399                                          1,399

                            Subtotal Treatment Plant Improvements                                                                 $ 13,671                                      $ 13,671

     Combined Sewer         CVI Lift Station Improvements: Design                     Cuyahoga Valley Interceptor                      482                                            482
     Sewer Overflow         Heights/Hilltop Interceptor Operational Evaluation        Heights Intercommunity Sewer                   4,245                                          4,245
     & Interceptor          Big Creek Interceptor Rehabilitation                      Big Creek Interceptor                            392                                            392
     Rehabilitation         Mill Creek Inteceptor Tunnel Contract MCT-3:              Mill Creek Interceptor                         1,100                                          1,100
                            Mill Creek Inteceptor: Broadway Area Relief Sewer         Mill Creek Interceptor                            18                                             18
                            Repair Projects at Landfill                                                                              1,510                                          1,510
                            Vista Leg Project                                                                                          753                                            753
                            Main Branch Project                                                                                      1,662                                          1,662
                            Lakeside Improvement at East 53rd                         Easterly Interceptor                             157                                            157
                            Service Ageement Contract: Design                         Easterly Interceptor                             287                                            287
                            Broadway Branch Emergency Repairs                         Southerly Interceptor                            179                                            179
                            Relining and Replacement Contract: Construction           Southerly/Westerly Districts Interceptors                        11,593                      11,593
                            Service Ageement Contract: CA/RE                          Southerly/Westerly Districts Interceptors        473                                            473
                            District-wide Manhole Rehabilitation                      District-wide                                  1,617                                          1,617
                            Spring/Jennings Control Structure Modification                                                             101                                            101
                            Westerly Interceptor Box Culvert Repair                   Westerly Interceptor                             522                                            522
                            West 45th/CSO 074 Outlet Emergency Repair                 Cleveland                                         84                                             84
                            Westerly Low Level Interceptor Emergency Repair           Westerly Interceptor                           2,306                                          2,306
                            Columbus Road Emergency Pump Station                      Cleveland                                        293                                            293
                            Huntington Garage CSO-093 Rehabilitation                                                                    35                                             35

                            Subtotal Combined Sewer Overflow & Interceptor Rehabilitation                                         $ 16,216            $11,593                   $ 27,809

     Other                  District-wide Roofing Renovation                                                                         1,629                                          1,629
     Projects               Plant Automation Additional Service & CA/RE               Easterly/Southerly/Westerly/EMSC                  77                                             77
                            Flats East Bank Neighborhood Project                      Flats East Bank Neighborhood Project           8,000                                          8,000
                            Information Technology: LABLynx & Web Upgrade                                                              115                                            115
                            Stormwater Mangement Program Implementation                                                              2,999                                          2,999
                            West Creek Stewardship Center                                                                            3,000                                          3,000
                            Easement and Property Acquisition                                                                        1,700                                          1,700
                            Net Project Change Orders                                                                                  773                                            773

                            Subtotal Other Projects                                                                               $ 18,293                                      $ 18,293

     TOTAL NEORSD Let 2007 Construction                                                                                                                                  $         59,773


     Source: NEORSD's Capital Projects Contracts 2007
                                             Northeast Ohio Regional Sewer District
                                                   2007 Contracts Let for Capital Projects
                                                             ($ in Thousands)



     Capital Funding by Source                                                               Capital Funding Distribution
     State
     19%
                                                                                                         23%
                                                                               31%
                                                                                                                   Treatment Plant Improvements - $13,671

                                                                                                                   CSO & Interceptor Rehab - $27,809
                                 NEORSD - $48,180
                                 State - $11,593                                                                   Other Projects - 18,293
              NEORSD
               81%                                                                                 46%




29
30
                                                                               Northeast Ohio Regional Sewer District
                                                                                  2008 Contracts Let for Capital Projects
                                                                                            ($ in Thousands)
                                                                                                                                             ADDITIONAL FUNDING SOURCE
     TYPE                 PROJECT NAME                                                      LOCATION                            NEORSD                 STATE                     TOTAL COST
     Treatment Plant
     Improvements
                          Bridge Rehabilitation                                             Southerly                             7,604                                                      7,604
                          Final Clarifier and Aeration Rehabilitation                       Easterly                              2,376                                                      2,376
                          Final Clarifier and Aeration Rehabilitation                       Easterly                              3,161                                                      3,161
                          Paging System Replacement                                         Easterly, Southerly, Westerly           274                                                        274
                          Primary Settling Tanks Rehabilitation                             Easterly                              2,574                                                      2,574
                          Digester Dome Removal                                             Southerly                               457                                                        457
                          Southerly Digester "A" - Decommissioning Project                  Southerly                               853                                                        853
                          Canal Road Modifications - Ash Lagoon Access Drive                Southerly                                73                                                         73

                          Subtotal Treatment Plant Improvements                                                                 $17,372                                                 $17,372

     Combined             Westerly Interceptor Box Culvert Repair/Replacement               Westerly                              5,117                                                      5,117
     Sewer Overflow       Big Creek Interceptor Trestle                                     Big Creek                             3,837                                                      3,837
     & Interceptor        Primary Effluent Pump & CSO Treatment Facility                    Westerly                                627                                                        627
     Rehabilitation       Easterly Interceptor Lakeside Contract at East 53rd Street        Easterly                              1,677                                                      1,677
                          Valley Belt Gravity Sewer                                                                               6,056                                                      6,056
                          Vista Branch Connection Sewer                                                                           1,571                                                      1,571
                          Miles Avenue Relief Sewer                                                                               1,644                                                      1,644
                          Spring and Jennings Road Storm Water Outlet Replacement                                                   737                                                        737

                          Subtotal Combined Sewer Overflow & Interceptor Rehabilitation                                         $21,266                                                 $21,266

     Other Projects       Walworth Run Outfall Repair Project                                                                          249                                                    249
                          Division Avenue Pump Station Building Restoration                                                             76                                                     76
                          Westerly Generator Closure Plan                                   Westerly                                   424                                                    424

                          Subtotal Other Projects                                                                                 $749                                                       $749

     TOTAL NEORSD Let 2008 Construction                                                                                                                                                 $39,387

     Source: NEORSD's Capital Projects Contracts 2008



                      Capital Funding by Source                                                                      Capital Funding Distribution
                                                                                                                     2%


                                                                                                                                 44%                Treatment Plant Improvements - $17,372

                         NEORSD                          NEORSD - $39,387
                                                                                               54%                                                  CSO & Interceptor Rehab - $21,266
                          100%                           State - $0
                                                                                                                                                    Other Projects - $749
                                                               Greater Cleveland Regional Transit Authority
                                                                      2007 Contracts Let for Capital Projects
                                                                                ($ in Thousands)
                                                                                                                          ADDITIONAL FUNDING SOURCES
     TYPE      PROJECT NAME                                                   LOCATION                             RTA        FEDERAL            STATE   TOTAL COST
     Roads
               E. 118th/Wade Park & Rocky River Bus Loop                       Cleveland/ Rocky River               77                                              77
               Euclid Corridor Transportation Project - Land Acquisition, Road
               Work, and Utilities                                                                               1,402           4,221            191             5,814

                 Subtotal Road Improvements                                                                     $1,479          $4,221           $191            $5,891
     Bridges
               Rockefeller Bridge Demolition                                  Cleveland                            162                                              162
               Abbey Road Bridge Reconstruction                               Cleveland                          1,968                                            1,968

                 Subtotal Bridge Improvements                                                                   $ 2,130                                      $    2,130
     Rail
               Rail Fleet Spare Parts                                         n/a                                  364           1,457                            1,821
               Moreland Pocket Track Signalization                                                                  25              99                              124
               Warrensville Station (Green Line) Drainage                                                           55                                               55
               Miscellaneous Rail - Audio Track Boards, Brush Chipper,
               Sprinkler Installation & Public Art                                                                  97            226                               323
               University Circle Red Line Station                             Cedar /UC                            449            796                             1,245
               Avalon Station Landscaping Improvements                                                              23             92                               115
               W. 65th St. Red Line Station Elevator                          Cleveland                            173                                              173
               Boiler Replacement at Central Rail Facility                    Cleveland                            122                                              122
               Red Line Airport Tunnel                                        Cleveland                             36            144                               180

                 Subtotal Rail Improvements                                                                     $1,344          $2,814                           $4,158
     Buses
               Harvard Garage Pavement Repairs                                                                      33            132                              165
               N. Olmsted Park-n-Ride Lot                                     North Olmsted                        154                            616              770
               Miscellaneous Equipment - Fleet Spare Parts, 4-wheel
               Alignment System, Dynamometer                                                                        68            271                               339
               Westlake Park-N-Ride - Environmental Services                  Westlake                              32                                               32
               Purchase of Vehicles - Commuter Coaches & Paratransit                                               830           3,322                            4,152
               Park-N-Ride Expansion                                          Westlake                             122             487                              609
               Bus Lift Repairs #17                                           Cleveland                             59                                               59
               HVAC Upgrade at Central Bus Maint.                             Cleveland                            108                                              108
               Bus Passenger Shelters                                         n/a                                   34            138                               172
               Brooklyn Garage - Environmental Services                                                             12             51                                63
               Hayden Garage Wall Repair                                      East Cleveland                        55                                               55

                 Subtotal Bus Improvements                                                                      $1,507          $4,401           $616            $6,524
     Other
               Fare Collection Equipment                                      Various                            2,468           9,873                           12,341
               Ticket Vending Machines & Equipment                            Various                            2,139           8,555                           10,694
               Transit Waiting Environment Consulting Services                n/a                                   40             160                              200
               Purchase of Vehicles: Vans , Trucks, & Police                  Various                            1,555                                            1,555
               Portable Radios                                                n/a                                   79            315                               394
               Automatic Switching Gear                                       Cleveland                             61                                               61
               Data Center Equipment Upgrade                                  Cleveland                            450                                              450
               Main Office - Miscellaneous                                    Cleveland                            482                                              482
               IT Consulting/Implementation Services                          n/a                                  319                                              319
               Woodhill Garage Sign & Shelter Shop Renovations                Cleveland                             12             50                                62




31
32
                                                                      Greater Cleveland Regional Transit Authority
                                                                           2007 Contracts Let for Capital Projects
                                                                                     ($ in Thousands)
                                                                                                                               ADDITIONAL FUNDING SOURCES
     TYPE             PROJECT NAME                                                LOCATION                             RTA         FEDERAL            STATE     TOTAL COST

     Other Con't      On Call A/E Services                                        n/a                                    9                37                                   46
                      Installation of an In-Building Antenna System               E. Cleveland/ Cleveland               11                45                                   56
                      Electrical Arc Flash Safety Analysis                        Various                              197                                                    197
                      Communications Upgrades                                     Various                                7                                                      7
                      Centralized Public Address System Services                  n/a                                   22                88                                  110
                      Tower City Multi-Threat Detection System                    Cleveland                             30               118                                  148
                      Video Conferencing System                                   n/s                                   12                50                                   62
                      On Street Signage                                           n/s                                   74               294                                  368
                      Red Line Stations - Security Enhancements                   Various                               28               112                                  140
                      Tower City Paging System Upgrade                            Cleveland                            152                                                    152

                         Subtotal Other Improvements                                                                 $8,147           $19,697                           $27,844

     TOTAL GCRTA Let 2007 Construction                                                                                                                                  $46,547

     Source: GCRTA 2007 Listing of Capital Contracts Let




                               Capital Funding Distribution                                                                Capital Funding by Source
                                                                                                                              State
                                              4%                                                                               2%
                                    13%
                                                           14%                                                                              RTA
                         9%                                                                                                                 32%
                                                                             BRIDGES - $2,130
                                                                             BUS - $6,524                                                                     RTA - $14,607
                                                                             OTHER - $27,844                                                                  Federal - $31,133
                                                                                                                 Federal
                                                                             RAIL - $4,158                                                                    State - $807
                                                                                                                  66%
                                                                             ROADS - $5,891
                                                60%
                                                                    Greater Cleveland Regional Transit Authority
                                                                           2008 Contracts Let for Capital Projects
                                                                                     ($ in Thousands)
                                                                                                                              ADDITIONAL FUNDING SOURCES
     TYPE      PROJECT NAME                                       LOCATION                                             RTA         FEDERAL          STATE   TOTAL COST
     Roads
               Euclid Corridor Transportation Project             Cleveland                                           2,148           8,594                       10,742

               Subtotal Road Improvements                                                                            $2,148         $8,594                       $10,742

     Bridges
               Four Transit Track Bridges Reconstruction          East Cleveland                                        795           3,182                        3,977
               MLK Transit Track Bridge Rehab                     Cleveland                                              29             114                          143

               Subtotal Bridge Improvements                                                                           $824          $3,296                        $4,120
     Buses
               A/E Services for Paratransit District Garage                                                              37            146                           183
               Central Bus Maintenance Facility Lift Repairs                                                             23             93                           116
               Hayden Garage Rehab                                                                                        8             31                            39

               Subtotal Bus Improvements                                                                               $68            $270       -                 $338

     Rail
               HRV Video Surveillance System                      Red Line Cars                                         179             715                          894
               Railroad Ties: Rail                                Various / Central Rail                                 21              84                          105
               West Park Substation Replacement                   West Park                                             398           1,592                        1,990
               LRV Audio/Video Surveillance System                Blue/Green Line Cars                                  237             949                        1,186
               Lee-Van Aken Station - A/E Services                Lee Rd. & Van Aken                                     65             260                          325
               Consolidated Train Dispatch System                 Central Rail                                           89             354                          443
               Railroad Crossties: Rail - Equipment               Various / Central Rail                                 20              80                          100
               Rail Service Building - Boiler Controls                                                                   14              56                           70
               E. 55 Street Rapid Transit Station                                                                        69             277                          346
               Mayfield Transit Station & Transit Track Bridge                                                          220             880                        1,100
               W. 92nd Street Flyover                                                                                    16              62                           78
               Rail Shop & Service Building                                                                              31             124                          155
               Shaker Trunk Line Reconstruction                                                                         337           1,346                        1,683
               Woodhill & Harvard - Environmental                                                                        19              75                           94

               Subtotal Rail Improvements                                                                            $1,715         $6,854                        $8,569
     Other
               IT Server Equipment: Info. Tech.                   n/a                                                    47                                           47
               IT Storage Area Network: Info. Tech.               n/a                                                    37                                           37
               Parts Retrieval Machine                            Inventory/Central Bus Equipment                       150            600                           750
               Passenger Vans (Non-Rev. Vehicles)                 n/a                                                    41                                           41
               On-call Services                                                                                          80            320                           400
               IT Room Utilities Expansion                                                                               19             77                            96
               Fare Vending Machines - Installation & Additions                                                          66            264                           330
               RTA main office - Rooftop Generator                                                                       31            122                           153
               Main Office Building Interior Painting                                                                     6             26                            32
               Update Long Range Plan                                                                                    54            216                           270
               Host Servers and Workstation Upgrades                                                                     89            354                           443

               Subtotal Other Improvements                                                                            $620          $1,979                        $2,599

     TOTAL GCRTA Let 2008 Construction                                                                                                                           $26,368

     Source: GCRTA 2008 Listing of Capital Project Contracts Let




33
                              Greater Cleveland Regional Transit Authority
                                   2008 Contracts Let for Capital Projects
                                             ($ in Thousands)




      Capital Funding Distribution                                             Capital Funding by Source

                 16%     1%                                                            RTA
41%                                       BRIDGES - $4,120                             20%
                        10%
                                          BUS - $338
                                                                                                           RTA - $5,375
                                          OTHER - $2,599
                                                                             Federal                       Federal - $20,993
                                          RAIL - $8,569                       80%
                  32%
                                          ROADS - $10,742
                                                                  Ohio Department of Transportation - District 12
                                                                2007 Contracts Let for Capital Projects in Cuyahoga County
                                                                                     ($ in Thousands)
                                                                                                                                  ADDITIONAL FUNDING SOURCES
     TYPE   PROJECT NAME                 LOCATION                                                                    STATE            FEDERAL            LOCAL TOTAL COST
      Roads
            CUY IR - 480                 Cleveland                                                                     1,488            13,391                           14,879
            CUY US - 6                   Lakewood                                                                      1,342                                              1,342
            CUY SR - 21                  Brecksville                                                                   1,056                                              1,056
            CUY IR - 71                  Cuyahoga County                                                                 958                                                958
            CUY IR - 90                  Cuyahoga County                                                               1,961                                              1,961
            CUY US - 322                 Mayfield Heights                                                              3,862            15,448                           19,310
            CUY SR - 252                 City of Olmsted Falls and Olmsted Township                                      498                                                498
            CUY IR - 271                 Bedford Heights                                                                 542             4,933                            5,475

               Subtotal Road Improvements                                                                          $11,707             $33,772                        $45,479
     Bridges
               CUY IR - 77               City of Independence                                                            639             5,747                            6,386
               CUY IR - 90               Cleveland                                                                       207             1,864                            2,071
               CUY US - 6                Cuyahoga County; Cleveland                                                      241                                                241
               CUY IR - 490              Cleveland                                                                       253             2,276                            2,529
               CUY IR - 90               Cleveland                                                                     1,000             1,247                            2,247
               CUY West 3rd St. Bridge   Cleveland                                                                        12                48                               60
               CUY IR - 77               Cuyahoga County                                                               1,085                                              1,085
               CUY SR - 2                Cuyahoga County                                                                 150                                                150

               Subtotal Bridge Improvements                                                                         $3,587             $11,182                        $14,769
      Other
               CUY LG FY2008             District 12 - Cuyahoga County                                                   355                                                355
               CUY IR - 90 Noise Wall    Cuyahoga County                                                                  75                                                 75
               D12 Landscape FY2008      District 12 - Cuyahoga County                                                   369                                                369
               CUY IR - 480 New Wall     North Olmsted                                                                 2,599                                              2,599
               CUY MOW FY2008            Cuyahoga County                                                                 329                                                329

               Subtotal Other Improvements                                                                          $3,727                                              $3,727

     TOTAL ODOT Let 2007 Cuyahoga County Construction                                                                                                                 $63,975

     Source: ODOT-District 12 List of 2007 Construction Sales


                             Capital Funding Sources                                                                 Capital Funding Distribution
                                                                                                                               Other
                                                                                                                                6%
                                              State
                                              52%                                                                Bridges
                                                                                                                  23%
                                                                                                                                                             Roads - $45,479
                                                                          State - $19,021
                   Federal                                                                                                                                   Bridges - $14,769
                                                                          Federal - $44,954                                                  Roads
                    48%                                                                                                                       71%            Other - $3,727




35
36
                                                              Ohio Department of Transportation - District 12
                                                           2008 Contracts Let for Capital Projects in Cuyahoga County
                                                                                ($ in Thousands)
                                                                                                                        ADDITIONAL FUNDING SOURCES
     TYPE      PROJECT NAME                 LOCATION                                                       STATE           FEDERAL             LOCAL TOTAL COST

     Roads
               CUY IR - 90                  Cuyahoga County; Cleveland                                      4,790                                               4,790
               CUY SR - 94                  Parma                                                           1,888                                               1,888
               CUY IR - 271                 Cuyahoga County                                                 8,542                                               8,542
               CUY SR - 175                 Cuyahoga County                                                   723                                                 723
               CUY IR - 77                  Cuyahoga County                                                90,369                                              90,369
               CUY US - 42                  Cuyahoga County                                                 3,438                                               3,438
               CUY US - 6                   Lakewood                                                        1,709                                               1,709

               Subtotal Road
               Improvements                                                                              $111,459                                           $111,459

     Bridges
               D12 BH FY2008 Misc 2         Cleveland: along I-90 east of downtown                            989                                                 989
               CUY US - 42                  Cleveland                                                         618                                                 618
               D12 BH FY2008 Misc 3         Cuyahoga County District 12                                       528                                                 528
               CUY IR - 480 Bin Wall        Cuyahoga County                                                   483                                                 483
               CUY US - 322                 Village of Gates Mills                                          1,734                                               1,734

               Subtotal Bridge
               Improvements                                                                                $4,352                                              $4,352

     Other
               CUY EUCLID SIGNALS           City of Euclid                                                                     1,495            544             2,039
               CUY INNERBELT Demolition     Cleveland                                                       1,110                                               1,110
               CUY SR - 10 Slope            City of Fairview Park                                             564                                                 564

               Subtotal Other                                                                              $1,674             $1,495            $544        $3,713
               Improvements

     TOTAL ODOT Let 2008 Cuyahoga County Construction                                                                                                      $119,524

     Source: ODOT-District 12 List of 2008 Construction Sales



                       Capital Funding by Source                                                                Capital Funding Distribution
                                           Local                                                              Bridges
                                 Federal                                                                                     Other
                                            1%                                                                  3%
                                   1%                                                                                         9%


                                                                    State - $117,485                                                               Roads - $111,459

                              State                                 Federal - $1,495                                                               Bridges - $4,352
                                                                                                                              Roads
                              98%                                   Local - $544                                                                   Other - $3,713
                                                                                                                               88%
BUGC STAKEHOLDERS & PARTNERS

CITY OF CLEVELAND
   www.city.cleveland.oh.us

CLEVELAND-CUYAHOGA COUNTY PORT AUTHORITY
   www.portofcleveland.com

CLEVELAND ENGINEERING SOCIETY
   www.cesnet.org

CUYAHOGA COUNTY ENGINEER
   www.cuyctyengineers.org

GREATER CLEVELAND PARTNERSHIP
   www.gcpartnership.com

GREATER CLEVELAND REGIONAL TRANSIT AUTHORITY
   www.riderta.com

NORTHEAST OHIO AREA WIDE COORDINATING AGENCY
   www.noaca.org

NORTHEAST OHIO REGIONAL SEWER DISTRICT
   www.neorsd.org

OHIO DEPARTMENT OF TRANSPORTATION - DISTRICT 12
   www.dot.state.oh.us/Districts/D12/Pages/default.aspx



                                                          37
 GREATER CLEVELAND PARTNERSHIP
                      The Higbee Building
              100 Public Square, Suite 210
                    Cleveland, Ohio 44113

                    www.gcpartnership.com
http://gcpartnership.com/phys_impact.aspx

								
To top