30 DRAWINGS

Shared by: gabyion
-
Stats
views:
21
posted:
7/5/2010
language:
English
pages:
21
Document Sample
scope of work template
							  JOINT ASTRONOMY CENTRE

UKIRT UPGRADES PROGRAMME


DOME ACTIVE VENTILATION

       (Facility Work 1)


 MECHANICAL DOCUMENTATION

            May 1997
            Prepared by
           Chas Cavedoni
UKIRT UPGRADES PROGRAMME

DOME ACTIVE VENTILATION
(Facility Work 1)

MECHANICAL DOCUMENTATION

May 1997



TABLE OF CONTENTS


1.0    PROJECT OVERVIEW

2.0    SYSTEM HARDWARE

3.0    KEY PERSONNEL

4.0    DESIGN DOCUMENTATION

5.0    PURCHASED EQUIPMENT

6.0    OPERATIONS MANUAL

7.0    MAINTENEANCE MANUAL

8.0    PHOTOGRAPHS

9.0    PERFORMANCE TESTING

10.0   PUBLICATIONS
1.0   PROJECT OVERVIEW

      In 1995 and 1996, the UKIRT Upgrades Project implemented a number of facility
      improvements of which Dome Active Ventilation was most notable. The improvements,
      collectively called Facility Work 1 (FW1), upgrades UKIRT in the following four ways:

             It   provides active dome ventilation especially for near-still nights of
              approximately 12 dome volumes per hour with a heat removal capacity of 6.5
              kW/C,

             It allows the plant room exhaust make-up air to by-pass the dome chamber when
              the ambient air is warmer than the dome chamber air,

             It increases the heat removal capacity of the plant room exhaust system by
              almost 250%, and

             It nearly doubles the useable floor space of the plant room for the Primary Mirror
              Cooling Chiller and future instrument chillers.

      To complete the above work, a number of other significant projects had to be
      undertaken. The Project had to relocate the telephone exchange, phone box and fire
      alarm. In addition, the upgrades required Hawaiian Tel to install a new phone entry on
      the north computer room wall adjacent to the existing fiber optics pull box.

      The estimated total project cost was $225,000.
2.0   SYSTEM HARDWARE

      The functional components of the UKIRT Active Dome Ventilation System (formally
      called the Plant Room Exhaust System) consist of:
                a double-damper air flow control system,
                a dome by-pass inlet,
                a dome active ventilation inlet,
                an air filtration system,
                (2) single-speed plant room supply fans (SF1 and SF2), and
                (1) 2-speed plant room exhaust fan (EF1)

      The airflow control system allows one to remotely select one of two sources of plant
      room exhaust make-up air. One can select either make-up air drawn directly from the
      outside of the building through the “dome by-pass inlet” or make-up air drawn indirectly
      through the UKIRT dome, down through the north and south telescope pier floor
      openings, into the plant room through the “dome ventilation inlet” and eventually out of
      the building through the plant room exhaust tunnel.

      The air enters the dome during the day through the brush seals and miscellaneous
      penetrations on and around the dome slit. During the night the area of the open slit
      dominates.

      The plant room air handling equipment consist of (2) single-speed supply fans located
      near the south wall of the plant room and located at the opposite end of the plant room in
      the north, (1) 2-speed exhaust fan. The (2) single-speed supply fans working in parallel
      balance the flow rate of the exhaust fan set at high speed. Either supply fan working
      alone balances the flow rate of the exhaust fan set at low speed. The measured
      performance of the system operating in high and low speeds is 29,000 m3/hr and 14,500
      m3/hr (17,000 cfm and 8,500 cfm).

      The project provided the half-speed mode of operation in an effort to mitigate the
      concern of excessive noise when working in the plant room at maximum flow rate. The
      project also conservatively selected fan types and an air filtration system using double
      dogleg ductwork to further reduce concerns of excessive noise. The as-built system
      operating at almost 2-1/2 times the old flow rate is quieter than the old system; i.e. the
      half speed mode of operation was not really necessary.


              To achieve maximum Dome Active Ventilation it is critical that all
              doors leading in and out of the coude room and plant room are closed.

              If all doors are not closed an open pathway in down either the north or
              south stairwell or in through the lower floor back doors can short
              circuit the dome ventilation system and dramatically reduce the flow
              rate passing through the dome enclosure.
3.0   KEY PERSONNEL

3.1   Engineering Consultants

      The following engineering firms, under the overall responsibility of Benjamin S.
      Notkin/Hawaii, provided the detail design effort and bid document specifications:

      Mechanical Engineer:
      Benjamin S. Notkin/Hawaii                Keith Chan
      210 Ward Ave. Suite 220                  (808) 523-1363
      Honolulu, HI 96814                       (808) 526-3584 fax

      Architect:
      TRB Architects, LTD.                     Clifford Terry
      Pauahi Tower, Suite 1110                 (808) 528-2020
      1001 Bishop St.                          (808) 523-1264 fax
      Honolulu, HI 96813

      Structural Engineer:
      Martin and Brave, Inc.                   Gary Chock
      Pacific Tower, Suite 2660                (808) 521-4513
      1001 Bishop St.                          (808) 531-4508 fax
      Honolulu, HI 96813

      Electrical Engineer:
      Wallace T. Oki, P.E., Inc.               Wally Oki
      PO Box 4070/688                          (808) 961-9666
      Kinoole St. Suite 115b                   (808) 935-2549 fax
      Hilo, HI 96720

3.2   Contractors

      The following contractors provide construction effort for the project.

      General Contractor:
      Keauhou Construction L.P.                Tom Broadhurst
      73-1254 Old Hawaii Belt Rd.              (808) 325-0199
      Kailua-Kona, HI 96740                    (808) 325-7460 fax

      Mechanical Contractor:
      Kona-Industries, Inc.                    Bill Gram
      73-5563 Olowalu St.                      (808) 329-7789
      Kailua-Kona, HI 96740                    (808) 329-8799 fax
      Contractor’s Lic. # C-14542

      Balancing Contractor:
      Certified Testing                        Tom McCowan
      350 Ward Ave. Suite 106                  (808) 523-9953
      Honolulu, Hawaii 96814                   (808) 531-1105
3.3   JAC UKIRT Upgrades Mechanical Support

      Chas Cavedoni provided JAC overall project management and mechanical engineering
      effort.

      Ivan Look provided JAC mechanical design and construction over site effort.
4.0   DESIGN DOCUMENTATION

4.1   JAC Requirement Drawings by UKIRT Upgrades

      Ivan Look, the UKIRT Upgrades mechanical designer, provided the following in-house
      drawings to identify, develop and specify the in-house project requirements. These
      drawings were not used for construction!

      -   FAC-001    Proposed Dome Exterior                          April 12, 1995
      -   FAC-002    Proposed Dome Section                           May 25, 1995
      -   FAC-003    Proposed First Floor                            April 12, 1995
      -   FAC-004    Existing First Floor                            April 10, 1995
      -   FAC-005    Exhaust Fan System Vie         w A (existing)           April 10, 1995
      -   FAC-006    Exhaust Fan System Vie w B (existing)           April 10, 1995
      -   FAC-007    Plant Room Wall View C                          April 10, 1995
      -   FAC-008    Duct Removal Layout                             April 11, 1995
      -   FAC-009    Proposed First Floor (lay out)                  April 10, 1995
      -   E-1        UKIRT (Site Plan)                               June 2, 1995
      -   E-2        UKIRT (Computer Room)                           June 28, 1995
      -   E-3        UKIRT (North Elevation)                         June 28, 1997
      -   E-4        Detail (Site Plan)                              June 28, 1995
      -   E-5        Site Plan (Section)                             June 29, 1995
      -   E-6        Detail (Site Plan)                              June 30, 1995
      -   E-1        One-line Diagram                                May 9, 1995
      -   E-3        One Line (Telephone) Diagram                    May 15, 1995

      Kent Tsutsui, the UKIRT Upgrades electrical engineer, provide the following system
      control drawings:

      - UKIRT Exhaust Fans System; Stage 1 Controls, 2 sheets        Dec. 6, 1995.

      All of the above mentioned drawings on 8-1/2” x 11” sheets are included at the end of
      this section.
4.2   Engineering Design Drawings

      The engineering consultants provide the following bid document drawings which are
      available as an appendix in D-size format:

      T-1    Title Sheet, Location and Site Plan                           Aug. 4, 1995
      A-1    Demolition and Improvement Plans, Elevations and Details      Aug. 4, 1995
      A-2    Enlarged Plans, Elevations, Sections and Details              Aug. 4, 1995
      S-1    General Notes and Typical Details                             Aug. 4, 1995
      S-2    First Floor Plan and Typical Details                          Aug. 4, 1995
      S-3    Elevations, Sections and Details                              Aug. 4, 1995
      M-1    Mechanical Legend and Schedules                               Aug. 4, 1995
      M-2    First Floor Mechanical Demolition Plan                        Aug. 4, 1995
      M-3    First Floor New Mechanical Plan                               Aug. 4, 1995
      M-4    Mechanical Details and Sections                                       Aug. 4,
      1995
      E-1    Electrical Work (for review only)                             June 16, 1995
      E-2    Electrical Work (for review only)                             June 16, 1995
      E-3    Electrical Work (for review only)                             undated
      E-4    Electrical Work (for review only)                             undated

      The engineering consultants released for construction Addendum 2 containing (16)
      drawings on 8-1/2 x 11 sheets labeled SK1 through SK16. These drawings are included
      at the end of this section.

      Please note that the mechanical contractor deviated substantially from the bid
      document drawings and no as-built drawings were made.


4.3   Bid Documents Technical Specifications

      UKIRT Upgrades - Facility Work 1
      Mauna Kea, Hawaii
      Prepared by Benjamin S. Notkin/Hawaii, Ltd.
      August 4, 1995

         The documents are available as an appendix.
5.0   PURCHASED EQUIPMENT


5.1   List of Purchased Equipment

      Air Filtration System         Section 5.2

      Supply Fans 1 & 2             Section 5.3

      Exhaust Fan                   Section 5.4

      Exterior Inlet Louvers               Section 5.5

      Control Dampers               Section 5.6
5.2   Air Filtration System ECO AIR SUREFLOW Filter Assembly
5.3   Supply Fan 1 & 2   GREENHECK Tubular Centrifugal Fan
5.4   Exhaust Fan   GREENHECK Backward Inclined Centrifugal Utility Fan
5.5   Exterior Inlet louvers C/S Storm Resistant Louvers
5.6   Control Dampers   RUSKIN Counter Balanced Back Draft Damper
6.0   OPERATIONS MANUAL

6.1   Maximum Ventilation

      To achieve maximum ventilation through the plant room and the dome enclosure set the
      system as follows:
               Control Dampers set to Dome Active Ventilation,
               Supply Fan 1 and 2 both on,
               Exhaust Fan 1 set to high-speed, and
               Close all coude room, plant room and lower floor back doors.

      To achieve maximum ventilation through the plant room with no dome enclosure
      ventilation set the system as described above except now set the control dampers to
      Dome By-Pass mode.

      To achieve maximum improvements in dome seeing the following course of action is
      suggested:

6.2   Day Operation

      Whenever inside dome air is warmer than ambient air, one should draw-in the maximum
      amount of cool ambient air through the dome chamber by selecting the Active
      Ventilation Inlet with the system operating at maximum flow rate as described in Section
      6.1.

      Whenever the inside dome air is colder than the ambient air, one should not actively
      ventilate the dome chamber by selecting the By-Pass Inlet as described in Section 6.1.
      Drawing warm air into the dome would degrade the nights dome seeing.

             The benefits of mixing the warm daytime stratified dome air with
             even warmer ambient dome active ventilation has not been
             determined.

6.3   Night Operation

      As early in the evening as possible and all night long, one should always use maximum
      Dome Active Ventilation to minimize dome seeing especially on near-still air nights.



             To achieve maximum Dome Active Ventilation it is critical that all
             doors leading in and out of the coude room and plant room are closed
             as well as the lower floor back doors.

             If all doors are not closed an open pathway in down either the north or
             south stairwell or in through the lower floor back doors can short
             circuit the dome ventilation system and dramatically reduce the flow
             rate passing through the dome enclosure.
6.4   Dome Active Ventilation Heat Capacity

      The heat removal capacity of the Dome Active Ventilation system is 6.5 kW / C at
      29,000 m3/hr (~ 12 dome-volumes-per-hour) based on the following assumptions and
      calculations:

      Assumptions:
          Dome ventilation flow rate      29,000 m3/hr
          Dome volume                     2,600 m3
          Air density at summit           0.82 kg/m3
          Air specific heat                       1.01 kJ/kg-K

      Calculations:
          Mass flow rate 29,000 m3/hr x 1/3600 s/hr x 0.82 kg/m3=        6.6 kg/s
          Heat flow rate 6.6 kg/s x 1.01 kJ/kg-K=                        6.7 kJ/s-K or

                                           Heat Removal Capacity          6.5 kW / C
7.0   MAINTENANCE MANUAL


7.1   Air Filtration System

      The air filters require periodic replacement on the order of every 6 months with:

                      C35H Extended Surface Pleated Filters
                      ECO-AIR Products, Inc.
                      San Diego, CA 92126

      One should change the filters before the accumulation of dirt increases the pressure drop
      across the filter by 0.5 to 0.7 in of water. A pressure gauge located next to the filter bank
      should be used to monitor the condition of the filters.

      Please see the product literature provide in Section 5.2 for replacement details.


7.2   Supply Fan 1 & 2 and Exhaust Fan 1

      The suggested routine maintenance for SF1, SF2 and EF1 is as follows:

      Bearings:
      The manufacturer recommends lubricating the bearings every 5 months with high lithium
      grease conforming to NLGI Grade 2.

      V-Belt:
      The manufacturer recommends checking the belts regularly for wear, tension, alignment
      and dirt accumulation.

      Motor:
      The manufacturer recommends cleaning the motor exterior surfaces.

      Fasteners:
      All fasteners should be checked no more than every 6 months to assure proper tightness.

      Please see the product literature provided in Section 5.3 and 5.4 for routine maintenance
      details.

7.3   Exterior Inlet louvers

      Periodically inspect the inside of the Dome By-Pass Assembly (chimney) for excessive
      accumulation of dirt and cinder. Clean as required.
8.0   PHOTOGRAPHS

      The project documented the condition of the plant room prior to the facility work as well
      as during various stages of construction. Seven pages of photos follow as listed below.
      The full set is available bound in a burgundy 7” x 13” photo album.

      8.1     Dome By-pass Inlet with Storm Resistance Louvers.

      8.2     Dome By-Pass penetration during construction.

      8.3     Dome By-Pass frame during construction.

      8.4     Plant Room Air Filtration System.

      8.5     Dome Air Supply Inlet and Plant Room Supply Fans and Ductwork.

      8.6     Plant Room Supply Fans (SF1 and SF2).

      8.7     Plant Room Exhaust Fan (EF).
9.0   PERFORMANCE TESTING

      The project contracted Certified Testing, Inc. to adjust, balance and certify the
      performance of the plant room exhaust system. Their report follows starting on the next
      page.
10.0   PUBLICATIONS

       The project produced an SPIE paper describing this project and the overall telescope
       thermal environment control system. The paper follows starting on the next page.
11.0   LIST OF APPENDIE


11.1   Bid Document Drawings

11.2   Bid Document Technical Specifications

11.3   Photograph Book

						
Related docs
Other docs by gabyion
Icelandic Bank Default
Views: 48  |  Downloads: 2
WASHINGTON State Independent Living Council
Views: 37  |  Downloads: 0
Net Debt Op Ed
Views: 2  |  Downloads: 0
Turnaround your health in 3 days
Views: 1  |  Downloads: 0
CITY OF LAREDO CITY OF
Views: 97  |  Downloads: 0
CAREERTECHNICAL PROGRAMS
Views: 10  |  Downloads: 0
Recipes - Download Now DOC
Views: 40  |  Downloads: 1