Bharat Sanchar Nigam Ltd.
(A Govt. of India Enterprise)
[ B-148 Statesman House, Barakhamba Road, New Delhi-1]
(MMT Section)
File No.11-8/2005-MMT(OF) Dated:24.02.2006
To
All Prospective Bidders,
Subject: Clarification for Procurement of STM-1 ADMs/STM-1 CPE ADMs Tender No.
MM/OF/122006/000297 issued on 28.12.2005
Dear Sir,
Kindly find herewith clarifications to the queries raised by some of the prospective bidders
in connection with the above mentioned subject tender.
The receipt of the letter may please be acknowledged.
Thanking you,
Encl: Eighteen pages.
STM-1 – Tender clarifications for MM/OF/122005/000297 issued on 28.12.2005
Sl. Clause No. Description Clarification
No.
1 Section-II In previous BSNL tenders, it used to be NIT / Tender document is self-
Clause - 2 mentioned that eligible bidder must have explanatory.
supplied at least 25% of the tendered quantity
to one or more operators in the world. However Request is regretted.
in the current tender this clause does not appear
in the above-mentioned section. Since this
tender is expected to be identical / similar to
the previous one and it also helps BSNL weed
out the non serious players and leave only the
serious ones (those with the capability to
execute the bulk orders) in the fray, you are
requested to kindly re-introduce this clause.
The clause may be reworded as below.
The bidder/his collaborator/technology
provider should have supplied minimum 25%
of tendered quantity of same technology to be
offered in this tender to any telecom service
provider and a certificate given by the
competent authority be submitted along with
the bid. For this purpose experience of supply
of any of the SDH family equipment (STM-
1/STM-4/STM-16) will be considered.
2 Section II As per the eligibility clause bidder should have Eligibility conditions published in
Clause – 2 TAC/TSEC certificate either for STM-1 ADM NIT are self explanatory and the
or STM-1 CPE. However, tender requires both same shall prevail over clause-2
types of SDH equipment. Therefore you are Section-II
requested to kindly confirm that eligible bidders
should have TAC/TSEC certificate for both
STM-1 ADM and STM-1 CPE.
3 Section IV As per above mentioned clause, the bidders Revised Clause 12(i) is at
Clause – 12 must have obtained Type Approval Certificate annexure-II
from Telecommunication Engineering Centre,
Department of Telecommunications / TSEC
from Quality Assurance circle, BSNL against
the STM-1 equipment conforming to TEC GR
No. GR/SDH-04/02.MAR 2002 with
amendment No. 1 to 4 for STM-1 Synchronous
Multiplexer for Long Haul applications and
GR No. GR/SDH-13/01.JUL.2003 with
amendment No. 1 for STM-1 CPE Synchronous
Multiplexer for Long Haul applications.
However as per eligibility criteria of the tender
TSEC against any P.O. issued by BSNL after
31.3.2003 are also acceptable. In view of this,
we request you to kindly modify this clause in
line with NIT eligibility criterion / Section 2
instruction to bidders clause 2 eligible bidder as
follows.
The bidder should have got Type Approval
Certificates (TAC) from TEC New Delhi or
should have got technical specification
evaluation certificate (TSEC) from Quality
Assurance circle BSNL, Bangalore against TEC
Gr No. GR/SDH-04/02 .MAR.2002 with
amendment no.1 to 4 for STM-1 Synchronous
Multiplexer for long haul applications and GR
No.GR/SDH-13/01 JUL 2003 with amendment
no.1 for STM-1 CPE Synchronous Multiplexer
for long haul applications. The bidder must
have obtained TAC/TSEC certificate as
mentioned above for the same products which
are offered in this tender.
Or
The bidder should have obtained TAC/TSEC
against any PO issued by BSNL after 31.3.2003
for STM-1 and STM-1 CPE equipment
conforming to TEC GR No. GR/SDH-04/02
MAR 2002 with amendment no.1 to 4 for STM-
1 Synchronous Multiplexer for long haul
applications and GR No.GR/SDH-13/01 JUL
2003 with amendment no.1 for STM-1 CPE
Synchronous Multiplexer for long haul
applications.
4 Section IV As per the above mentioned clause the delivery No change please.
Clause No. of goods shall be completed within 6 (Six)
12.ii months from the date of issue of Advance
Purchase Order (APO). You are requested to
kindly change the delivery schedule from the
date of issue of Purchase Order since the
intervening time is very little.
5 Section V As per this configuration, managed STM-1 Every STM-1 ADM must be
Requirement ADM with L1.1 optical aggregate interface, supplied with two numbers of
Configuration STM-1 electrical interface is required. We L1.1 optical line aggregate
1 understand that offered equipment should be interfaces. STM-1 electrical
equipped with one STM-1 L1.1 optical interface needs to be supplied as
aggregate and one STM-1 electrical aggregate per the GR wherever sought in the
interface along with required tributary SOR. However, revised SOR is
interfaces as per item no. 1.2. Kindly confirm. attached as annexure-I.
Further we understand that BSNL wants to use
the STM-1 ADM in the ring topology which
would comprise of STM-1 CPE equipment also.
Hence all the STM-1 CPE Aggregate interface
only. In previous tenders, all STM-1 ADM
and STM-1 CPE equipment were configured
with STM-1 Optical Aggregate interface only.
Considering the BSNL’s network application
and the fact that all the equipment procured in
the past were equipped with STM-1 Optical
interfaces only and the distance of few Kms
can be bridged by STM-1 Optical interface
only, we request you to kindly confirm that
STM-1 ADM should be equipped with 2
STM-1 optical interfaces instead of one
STM-1e and one STM-1o interface.
6 Section IV As per this clause trans/receive optical power Equipment needs to be supplied
Clause No. 47 should be displayed on EMS and LCT. We as per the requirements of the
would like to inform you that this feature is tender & GR specifications.
neither part of TEC GR nor part of any of the
previous tenders issued by BSNL.
Development of this feature requires re-design
of the equipment which means a delay of 6-8
months. Further support of this feature would
call for a fresh TSEC testing for all the vendors
as this feature was neither part of the TEC GR
nor pat of any of the previous tender
(MM/OF/102004/000278 dated 11.10.2004)
issued by BSNL. In view of this, we request
you to please confirm that this feature is not
required in the current tender in line with the
TEC GR.
7 Section VI The minimum value of the differential delay The minimum value of
Technical that needs to be supported is not specified by differential delay should be 14.2
Specifications TEC in its GRs. However in the previous msec.
tenders, BSNL has clarified that a value of 14.2
ms is sufficient for India. In view of this, we
request you to please confirm that same is
applicable to the current tender as well.
8 Section V Please also note that the quantity of all the The quantity shall remain 10Q
Configuration optional configurations in the tender is `Q’ but only.
No. 6 the quantity of Configuration 6 which is also
optional is `10Q’. We request you to please
confirm that the quantity of Optional
Configuration 6 is also Q in line with the
quantity of other Optional Configurations.
9 Section V As per this configuration, managed STM-1 It is a terminal. Revised SOR is
Configuration ADM with L1.1 optical aggregate interface, attached as annexure-I.
No. 6 Order wire, Power unit etc. is required. We
understand that offered equipment should be
equipped with 2 x L1.1 STM-1 optical
aggregate interfaces (2 ports) along with
required tributary interfaces as per item no. 6.2.
Kindly confirm. Also please confirm / clarify
that it is a managed STM –ADM & not
Terminal.
10 Section V We understand that bidders must configure Equipment is to be supplied as per
Schedule of each STM-1 ADM & STM-1 CPE equipment the tender requirements and GR.
Requirement with 2 STM-1 optical interfaces for all the
configurations and each STM-1 aggregate
interface must be available on separate card.
This will ensure greater reliability / availability
of in BSNL network. However if both the
STM-1 aggregate interfaces are available on
the same card, failure of the card will result in
complete traffic failure for that particular node.
Hence you are requested to kindly confirm, for
all configurations of STM-1 ADM and CPE,
two aggregate STM-1 interfaces should be
available on two different cards.
11 Section V As per the schedule of requirement, bidder STM-1 CPE shall be supplied as
Schedule of should equip STM-1 CPE equipment with per the equipment type II, III &
Requirement different types of interfaces as per different IV of STM-1 CPE GR. The cards
Configuration configurations mentioned therein. WE in one configuration should be
for STM-1 understand that BSNL wants to have only a usable in another configuration of
CPE single type of STM-1 CPE box which shall be the same equipment type.
equipment capable of equipping all types of tributary
interfaces asked in the current tender for STM-1
CPE equipment i.e. tributary / interfaces cards
of one configuration of STM-1 CPE equipment
should be able to be used in other
configurations mentioned in the Schedule of
requirement. This will increase the flexibility
in the BSNL network and BSNL network will
be ready with IP backbone. This clause was
mentioned in the last BSNL tender as well at
the footnote of Schedule of Requirement.
Hence you are requested to kindly add the
following clause in line with last BSNL STM-1
tender:
12 Scheduled of You are requested to kindly confirm that Yes please with respect to STM-1,
Requirement bidder must offer the same equipment / chassis / ADM/Terminal.
SOR Section subrack for any of the above configuration
V mentioned in the Schedule of requirement and
interface cards (both aggregate and tributary)
of one configuration must be used in all other
configurations as well.
13 Section IV We understand that the bidder shall supply one Yes please.
Clause No. 20 pair of 20 meter length patch cords with every
optical aggregate and tributary interface
including for Ethernet media converter. Kindly
confirm.
14 Clause No. We understand that this is an open tender and Suggestion regretted.
11.iii the prices quoted by the L1 bidder as per the
Section IV tender conditions shall prevail and allocation
of quantity will be done accordingly, as such
purchase preference for the Central Public
Sector Enterprises may be dealt by the
application of Reserve Quota for the same. In
view of this, we request you to please delete
the clause related to the preference of Central
Public Sector Enterprises.
15 Eligibility 1. Please confirm that the PO specific type Already explained at S.No.2
Clause – 1 approval or GR specific approval must be for
Section II both STM-1 and STM-1 CPE. This will
remove any uncertainty to BSNL regarding the
conformance of the equipment being bid to the
specs of the tender. Secondly since you have
asked for both the products in the tender and
the evaluation is going to on a package basis. It
is important to ask for TEC/TSEC approval for
both the products to remove any uncertainty /
ambiguity.______________________________ ____________________________
2. Please confirm that the Type Approval
against the eligibility requirement should be for
the same technology that is being bid in this Yes, please.
tender._________________________________ ____________________________
3.Also please confirm that the PO specific Type
Approvals should be against the TEC GR No.
GR/SDH-04/02 March 2002 with amendment No change, please.
no. 1 to 4 for STM-1 and GR No. GR/SDH-
13/01 JUL 2003 with amendment no. 1 for
STM-1 CPE.
16 Clause 19 Q3 and SNMP V2 are independent standards. Yes please.
Section IV Since TEC requires compliance to either one of
these standards. Please confirm that it is OK to
support ANY ONE of these interfaces.
17 Clause 20 As we understand, the CPE configs require a Only 20 Mtr. Patch cords may be
Section IV pair of 30m length patch cords with every supplied.
optical interface and the STM-1 ADM
requires a pair of 20m patch cords with every
optical interface. Please confirm.
18 Clause 21 In case the equipment uses another type of Yes Acceptable. However as per
Section IV connector (LC) then please confirm that the clause one additional set of the
optical patch cords with one end as LC and patch cords are to be supplied.
other end as FC is acceptable.
19 Clause 38 Please confirm our understanding that the EMC The clause is self explanatory.
Section IV and 100 Base FX ports are required to work on
single mode fiber and not on single fiber.
20 Clause 40 We understand that the EMS will be directly EMS shall be connected to the
Section IV connected to the same vendor’s equipment same vendor’s equipment which
which will act as a gateway node. The EMS will act as a gateway node. For
should then be able to access other nodes of the balance part of query, please refer
same vendor in the ring even if other 3rd party to GR which is self explanatory.
nodes are present. This will mean that either
E1/VC12 management is supported or DCC
Transparency is provided. Please confirm that
this is required.
21 Clause 43 1. The specs given against this clause is 1. Laptop shall be supplied as per
Section IV different from the one appearing in the clause no. 43 or with better
SOR. As the technology is rapidly configuration.
changing for Laptops, please confirm 2. Floppy drive is required.
that the spec mentioned against the
Clause 43 of the Section-IV is just a
sample configuration and that the
Laptop of Indian / International brand
can be supplied of an equivalent / better
configuration.
2) Also the 144 MB Floppy Drive no longer
comes integrated in Laptops. As you have
already called for DVD Combo drive, please
confirm that Floppy Drive is not required.
22 SOR The STM-1 Electrical Interface has been called Revised SOR is attached at
Section V for in Sl.No. 1.1 of the SOR however the same annexure-I. Further equipment is
is not called for in the remaining configurations to be supplied as per GR read with
at Sl. Nos. 6.1, 7.1, 8.1, 9.1, 10.1 and 11.1. tender conditions.
Please confirm that STM-1 Electrical Interface
is required against all the above configurations
also.
23 Section V Please confirm that STM-1 ADM is required to No. It is STM-1 Terminal.
Configuration be supplied against Sl. No. 6.1 Please refer to revised SOR at
6 annexure-I
Sl. No. 6.1
24 Section V Please confirm that 8 ports of 10/100 Base T One port only. The quantity shall
Configuration Ethernet interface would be required for each be 10Q.
6 ADM and that the total requirement of Ethernet
Sl. No. 6.2 interface for this particular configuration would
be 80Q.
25 Clause No. The tender has the requirement of having Type Please refer to clarification at
2(i) Approval Certificate / TSEC. It is requested point no. 2. Eligibility condition
Instructions to that obtaining the Type Approval as per the of NIT shall prevail over clause-2
bidders, clause may please be allowed within 60 days of Section-II
Section II from the date of opening of Tender.
OR
The bidders who have obtained TAC/TSEC
against any P.O. issued by BSNL/MTNL for
either STM-1 or STM-1 CPE equipment or
both may please be allowed to participate in the
tender.
This would enable more bidders to participate
in the tender who already have equipment
under QA testing or who have got TAC/TSEC
obtained against any P.O. issued by
BSNL/MTNL for either STM-1 or STM-1 CPE
equipment or both. As not many technologies
have Type Approval Certificate, this relaxation
will provide healthy competition and in turn
benefit BSNL.
We therefore propose clause No. 2 (i) Section
II to be modified as follows for your kind
consideration.
THE BIDDER SHOULD GET THE TYPE
APPROVAL CERTIFICATES (TAC) FROM
TEC NEW DELHI OR TECHNICAL
SPECIFICATION EVALUATION
CERTIFICATE (TSEC) FROM QUALITY
ASSURANCE CIRCLE, BSNL BANGALORE
AGAINST TEC GR NO.GR/SDH-
04/02.MAR.2002 WITH AMENDMENT NO.
1 TO 4 FOR STM-1 SYNCHRONOUS
MULTIPLEXER FOR LONG HAUL
APPLICATIONS AND GR NO. GR/SDH-
13/01 JUL 2003 WITH AMENDMENT NO. 1
FOR STM-1 CPE SYNCRONOUS
MULTIPLEXER FOR LONG HAUL
APPLICATIONS, WITHIN SIXTY DAYS
FROM THE DATE OF OPENING THE
TENDER.
OR
THE BIDDER SHOULD HAVE OBTAINED
TAC/TSEC AGAINST ANY P.O. ISSUED BY
BSNL/MTNL FOR EITHER STM-1 OR CPE
EQUIPMENT OR BOTH.
26 Clause No.11 As per clause 11(i) the total number of No change please.
(iii) Section technically and commercially responsive
IV, Special bidders are limited to three. With 10% price
conditions of preference given to PSEs, the other vendors
contract may not be able to get even short listed for
placement of orders, as 10% price difference is
huge in the extremely competitive market.
Hence they will not get a fair chance to
compete in a price sensitive market. We
therefore request you to kindly review this
condition.
27 Clause No. 15 We understand that we need to supply STM-1 Every ADM must be supplied
& 16, Section systems with Optical Aggregate interface of with two optical line aggregate
IV ( Special L-1.1, and with a provision to add an electrical STM-1e must be provided as per
Conditions of Tributary interface at a later date that will the GR specification (clause
contract) interoperate with other ITU-T standard No.2.20 of Amendment 4 of GR
SecV SOR STM-1e tributary interfaces. Kindly confirm. GR/SDH-04/02. MAR 2002
and Sec VII
Price Schedule
Item Nos. 1.1,
6.1,7.1,8.1,9.1,
10.1 and 11.1
28 Clause No. 28 We understand that only a soft copy of manual Both soft and hard copies of the
Section IV, needs to be furnished along with the bid, and manual needs to be supplied along
Special the hard copies of manuals (one set for every with the bid. Hard copy of the
conditions of 20 Nos.) will need to be supplied along with the manual needs to be supplied for
contract equipment by successful bidders only. every 20 Nes & soft copy of
Please confirm. manuals to be supplied for every
20 NE
29 Clause No. 38 We understand that the EMC and 100base FX Clause 38 is self explanatory.
Section IV, ports are required to work on single mode fiber
Special and not on single fiber. Please confirm.
Conditions of
contract
30 Clause No. 47 While the LCT/EMS software has the above Yes please. Optical line aggregate
Section IV, capability,the TEC GRs for STM-1 and STM-1 power monitoring is to be done in
Special CPE donot specify this feature for the optical both STM-1 ADM & STM-1 CPE
Conditions of line cards. Further, the LCT/EMS software
contract Do we need to provide this feature in the should have the capability to
hardware of both STM-1 and STM-1 CPE, monitor the transmit & receive
which is additional to the TEC GRs optical power on the line side.
requirement?
Kindly clarify.
31 Eligibility Please confirm that successful execution of Yes, please.
Clause (ii) commercial orders from Indian Railways is
acceptable.
32 Eligibility Since for supplies to Indian Railways, RDSO is No, please.
Clause (iii) the nodal inspecting agency, Hence kindly
confirm that Inspection Certificate issued by
RDSO will be acceptable as proof of execution
of commercial orders.
33 Section-IV Section V, item 1.1 calls for managed STM-1 Please refer to revised SOR at
Clause No.15 ADM with L-1.1 Optical aggregate Interface, Annexure-I
& 16 STM-1 Electrical Interface, Order Wire, Power
Unit, Installation Material and manuals etc.
Section V & However, STM-1 systems in the optical items
Section VII do not ask for electrical interface and only ask
item no. 1.1, for managed STM-1 ADM with L-1.1 optical
6.1, 7.1, 8.1, aggregate interface, order wire, power unit,
9.1, 10.1, installation material & manual etc.
&11.1 Section IV, clause-15 states that each vendor
shall ensure direct interconnection of the STM-
1 optical and electrical tributary signals to other
suppliers equipment obtained by BSNL against
this tender and other tenders.
Further Section-IV, clause-16 states that each
vendor shall ensure direct interconnection of the
STM-1 optical aggregate and electrical tributary
signals between STM-1 equipments sought
against the two GRs. The STM-1 ADM and
CPE ADMs shall be capable of working in
linear, ring fashion and also in any
combination.
We trust that we need to supply STM-1 systems
with optical aggregate interfaces of L-1.1, and
with a provision to add an electrical tributary
interface at a later date that will inter operate
with ITU –T standard STM-1e tributary
interfaces. Kindly confirm.
34 Section IV Section IV, clause 28 states that soft copy of One soft copy and one hard copy
Clause no.28 the operations, installations, hardware, software of the complete technical literature
and maintenance manuals for all the equipments needs to be furnished along with
(STM-1, CPE STM-1, EMS, LCT, Ethernet the bid. One set of soft copy and
Adaptor/Ethernet Media Converter) shall be hard copy of the complete
submitted by the bidder. The bidder shall also technical literature needs to be
supply operation, installation & maintenance supplied along with every twenty
manuals in hard copy for every twenty NE. The ADMs ( including STM-1 ADMs
bid shall be considered technically not and STM-1 CPE ADMs).
responsive and the bid shall be summarily
rejected if any of these details are not furnished
along with the bid document.
We trust we need to furnish only a soft copy
along with the bid, and the hard copies of
manuals (One set for every twenty NEs) will
need to be supplied along with the equipment
by successful bidders only.
Kindly confirm.
35 Section IV Section IV, clause –47 states that the LCT/ The hardware of STM-1 ADM
Clause no.-47 EMS software should be capable of monitoring and STM-1 CPE ADMs must have
the transmit and receive optical power on line the transmit and receive optical
side. power monitoring facility. The
While the LCT/EMS software has the above LCT and EMS software should be
capability, the TEC GRs og STM-1 and STM-1 capable of monitoring the same in
CPEs do not specify this feature for the optical the LCT (Laptop) and EMS
line cards. respectively
Do we need to provide this feature in the
hardware of both STM-1 and STM-1 CPE,
which is additional to the TECGRs
requirement ?
Kindly clarify.
36 Annexure 1 Warranty of EMS should also be limited to 18 The request is regretted.
Section IV months from receipt or 12 months from date of
Clause no. 1.2 commissioning, as is the case for STM-1
equipment. (If EMS installation is delayed by
the user, supplier cannot be held responsible
and extend warranty on this account)
Kindly clarify.
37 Annexure 1 Extension of the agreement beyond 5 years The clause is self explanatory.
Section IV shall be negotiable and on mutually acceptable
Clause no. terms. Please clarify.
1.4
38 Annexure 1 Consumables (such as batteries, floppy disks, The clause is self explanatory.
Section IV CDs, tapes, printer ribbons, IPM, surge However, the following
Clause no.1.8 suppressors, cables connecting the system to consumables shall not be covered
customer’s other equipment, patch cords, etc.) under AMC :
that may need replacement from time to time Batteries, floppy disks, CDs, tapes,
are excluded. Systems / equipments or any part printer ribbons & patch cords.
of it burnt / damaged due to surge voltage,
lightening, accidents, exposure to corrosive
chemicals / gasses, mishandling or natural
calamities will not be covered under AMC.
BSNL and Supplier can separately discuss and
decide the restoration of such systems /
equipment. Please clarify.
39 Annexure 1 Supplier commitment under this contract shall The clause is self explanatory.
Section IV be fulfilled if the supplied and fitted AMC is limited to the equipment
Clause replacement part (or parts) results in the supplied by the tenderer.
no.1.9(i) concerned unit of system again becoming
operational. Supplier’s obligation of
maintenance services are limited only to the
equipments/systems listed above and do not
include any obligation towards the maintenance
of any other attachments or accessories or
works external to the equipment / system such
as electrical work, input supply, outdoor
cabling and switch room faults.
Please clarify.
40 Annexure 1 Reports from EMS will be available as per The clause is self explanatory.
Section IV software standard. Please clarify.
Clause
no.1.9(vii)
41 Annexure 1 The performance bank guarantee for AMC The clause is self explanatory. No
Section IV should equal the amount of AMC charges for change, please.
Clause no.2.2 half year only. Also, the initial performance
bank guarantee submitted on receipt of APO
should be returned immediately on submission
of PBG equal to AMC charges for half year.
Please clarify.
42 Annexure 1 Faulty card / unit should be returned to The clause is self explanatory.
Section IV SUPPLIER support center available in the
Clause no.4.3 Circle or else to be sent to the national repair
center at BSNL’s cost. The repaired unit will
be returned to BSNL at supplier’s cost. Please
clarify.
43 Annexure 1 The turn around time shall be calculated from The clause is self explanatory.
Section IV the date of receipt of faulty equipment / unit by
Clause supplier’s support center / repair center. Please
no.4.4.2 clarify.
44 Annexure 1 System / equipment or any part of it burnt / The clause is self explanatory.
Section IV damaged due to surge voltage, lightening,
Clause accidents, exposure to corrosive chemicals /
no.4.10 gases, mishandling or natural calamities will
not be covered under AMC. BSNL and
supplier can separately discuss and decide the
restoration of such systems / equipment. Please
clarify.
45 Annexure 1 The bills for AMC of EMS and repair charges The clause is self explanatory.
Section IV must be paid by BSNL maximum within 30
Clause no.7.2 days of the receipt of bills. If any payment
remains outstanding for more than 30 days
from the due date, Vendor shall have the right
to withhold the maintenance services without
prejudice to all it’s other rights and remedies.
Please clarify.
46 Annexure 1 The performance report by the incharge of the 15 days period is too short.
Section IV designated repair window of the Circle shall However it will be done within
Clause no.7.3 have to issue the report within 15 days from reasonable time.
completion of the half year period. Please add
this to the Clause.
47 Annexure 1 Either BSNL or Supplier at their option may The clause is self explanatory.
Section IV terminate this contract at any time by giving to
Clause no.7.5 the other party in writing 90 days notice of
their intent to do so, in case there is a serious
breach of contract by the other party. The pro-
rata advance pending with Vendor will be
returned to the BSNL within 30 days. Any
outstanding charges, if payable to Vendor, will
be paid by the BSNL within 30 days.
48 Annexure 1 Either BSNL or Supplier at their option may The clause is self explanatory.
Section IV terminate this contract at any time by giving to
Clause no.8.3 the other party in writing 90 days notice of
their intent to do so. In case there is a serious
breach of contract by the other party. The pro-
rata advance pending with Vendor will be
returned to the BSNL within 30 days. Any
outstanding charges, if payable to Vendor, will
be paid by the BSNL within 30 days. Please
clarify.
Annexure-I
Revised Schedule of Requirement
Sl. No. DESCRIPTION Quantity
1.0 STM-1 ADM (2 Fibre Linear/Ring Topology) (Type 5) consisting of
1.1 Managed STM-1 ADM with L-1.1 Optical Aggregate interface (2 2800
nos.), STM-1 electrical aggregate interface (2 nos.),order Wire,
Power Unit, Installation Material and Manuals etc.
1.2 2 Mb /s Trib Interface (63 interface per ADM) 176400
1.3 Wired Rack for one STM-1 ADM 2800
1.4 3 Years maintenance Spares Set consisting of complete 280
equipment from 1.1 to 1.2 including installation materials etc.)
2.0 STM-1 CPE ADM consisting of
2.1 Managed CPE ADM-1 with L-1.1 Optical Aggregate 11200
interface,Power Unit, Installation Material and Manuals etc.DC
operated only
2.2 2 Mb /s Trib Interface ( 8 interface per ADM ) 89600
2.3 Wired Rack for one CPE ADM 11200
2.4 3 Years maintenance Spares Set consisting of complete 1120
equipment as mentioned in item no.2.1to 2.2 including
installation materials etc.)
3.0 Element Management System (HW + SW) 40
4.0 Local Control Terminal (LCT)
4.1 LCT - Laptop (Hardware+Software) should contain STM-1 100
ADMs & CPE ADMs Software
4.2 LCT - Desktop (Hardware+Software) should contain STM-1 100
ADMs & CPE ADMs Software *
4.3 LCT - Software and associated cable accessories STM-1 400
ADMs
4.4 LCT - Software and associated cable accessories CPE ADMs 1000
5.0 Comprehensive Repair Charges
5.1 Comprehensive Repair Charges for the equipment/PCBs indicating all
inclusive rates as percentage of its costs for the quantity mentioned in the 3
Years Mtce, Spares Sets in all the STM-1 CPE and STM-1 configurations
above
5.2 AMC charges for EMS for one year after warranty as a 40
percentage of the cost of the EMS
5.3 AMC charges for EMS for second year after warranty as a 40
percentage of the cost of the EMS
5.4 AMC charges for EMS for third year after warranty as a 40
percentage of the cost of the EMS
5.5 AMC charges for EMS for fourth year after warranty as a 40
percentage of the cost of the EMS
5.6 AMC charges for EMS for fifth year after warranty as a 40
percentage of the cost of the EMS
OPTIONAL ITEMS
6.0 STM-1 TM
6.1 Managed STM-1 TM with one L-1.1 Optical Aggregate interface 10Q
and one STM-1 electrical aggregate interface, Power Unit,
Installation Material and Manuals etc.
6.2 10/100 Base T Ethernet interface ( 1 interface for TM) 10Q
6.3 100 Base Fx Interface (1 interface per TM) 10Q
6.4 Wired Rack 10Q
6.5 3 Years maintenance Spares Set consisting of complete Q
equipment from 6.1 to 6.3 including installation materials etc.
7.0 STM-1 ADM (2 Fibre Linear/Ring Topology) (Type 5) consisting of
7.1 Managed STM-1 ADM with L-1.1 Optical Aggregate interface (2 Q
nos.), STM-1 electrical aggregate interface (2 nos.),order Wire,
Power Unit, Installation Material and Manuals etc.
7.2 2 Mb /s Trib Interface (42 interface per ADM) 42Q
7.3 Wired Rack for one STM-1 ADM Q
7.4 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment from 7.1 to 7.2 including installation materials etc.)
8.0 STM-1 ADM (2 Fibre Linear/Ring Topology) (Type 5) consisting of
8.1 Managed STM-1 ADM with L-1.1 Optical Aggregate interface (2 Q
nos.), STM-1 electrical aggregate interface (2 nos.),order Wire,
Power Unit, Installation Material and Manuals etc.
8.2 2 Mb /s Trib Interface (21 interface per ADM) 21Q
8.3 10/100 Base T Ethernet Interface (2 interface per ADM) 2Q
8.4 100 Base FX Interface (1 interface per ADM) Q
8.5 Ethernet Media Converters with 100 base FX interface ( min 10 Q
Km reach, 230V AC) (1 interface per ADM) ##
8.6 Wired Rack for one STM-1 ADM Q
8.7 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment from 8.1 to 8.5 including installation materials etc.)
9.0 STM-1 ADM (2 Fibre Linear/Ring Topology) (Type 5) consisting of
9.1 Managed STM-1 ADM with L-1.1 Optical Aggregate interface (2 Q
nos.), STM-1 electrical aggregate interface (2 nos.),order Wire,
Power Unit, Installation Material and Manuals etc.
9.2 2 Mb /s Trib Interface (21 interface per ADM) 21Q
9.3 34 Mb Trib Interface (1 interface per ADM) Q
9.4 Wired Rack for one STM-1 ADM Q
9.5 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment from 9.1 to 9.3 including installation materials etc.)
10.0 STM-1 ADM (2 Fibre Linear/Ring Topology) (Type 5) consisting of
10.1 Managed STM-1 ADM with L-1.1 Optical Aggregate interface (2 Q
nos.), STM-1 electrical aggregate interface (2 nos.),order Wire,
Power Unit, Installation Material and Manuals etc.
10.2 2 Mb /s Trib Interface (21 interface per ADM) 21Q
10.3 DS3 Trib Interface (1 interface per ADM) Q
10.4 Wired Rack for one STM-1 ADM Q
10.5 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment from 10.1 to 10.3 including installation materials
etc.)
11.0 STM-1Regenator(Type 5) consisting of
11.1 Managed STM-1 REG with L-1.1 Optical Aggregate interface, Q
Order Wire, Power Unit, Installation Material and Manuals etc.
11.2 2 Mb /s Trib Interface (21 interface per ADM) 21Q
11.3 Wired Rack for one STM-1 ADM Q
11.4 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment from 11.1 to 11.2 including installation materials
etc.)
12.0 STM-1 CPE ADM consisting of
12.1 Managed CPE ADM-1 with L-1.1 Optical Aggregate Q
interface,Power Unit, Installation Material and Manuals etc.DC
operated only
12.2 2 Mb/s Trib. Interface (8 interface per ADM) 8Q
12.3 10/100 Base T Ethernet Interface (2 interface per ADM) 2Q
12.4 100 Base FX Interface (1 interface per ADM) Q
12.5 Ethernet Media Converters with 100 base FX interface ( min 10 Q
Km reach, 230V AC) (1 interface per ADM) ##
12.6 Wired Rack for one CPE ADM Q
12.7 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment as mentioned in item no.12.1 to 12.5 including
installation materials etc.)
13.0 STM-1 CPE ADM consisting of
13.1 Managed CPE ADM-1 with L-1.1 Optical Aggregate Q
interface,Power Unit, Installation Material and Manuals etc.DC
operated only.
13.2 DS3 Trib Interface (1 interface per ADM) Q
13.3 Wired Rack for one CPE ADM Q
13.4 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment as mentioned in item no.13.1& 13.2 including
installation materials etc.)
14.0 STM-1 CPE ADM consisting of
14.1 Managed CPE ADM-1 with L-1.1 Optical Aggregate Q
interface,Power Unit, Installation Material and Manuals etc.DC
operated only.
14.2 34 Mb /s Trib Interface (1 interface per ADM) Q
14.3 Wired Rack for one CPE ADM-1 Q
14.4 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment as mentioned in item no.14.1 & 14.2 including
installation materials etc.)
15.0 STM-1 Terminal Multiplexer
15.1 Managed STM-1 TM with STM-1 Electrical Aggregate 20Q
interface, Power Unit, Installation Material and Manuals etc.
15.2 2 Mb /s Trib Interface ( 63 per TM ) 1260Q
15.3 Wired Rack 5Q
15.4 3 Years maintenance Spares Set consisting of complete 2Q
equipment from 15.1 to 15.2 including installation materials
etc.
16.0 STM-1 Terminal Multiplexer
16.1 Managed STM-1 TM with L1.1 optical aggregate interface, Q
STM 1 Electrical Aggregate interface, Power unit, Installation
Material and Manuals etc.
16.2 2 Mb /s Trib Interface ( 63 interface per TM ) 63Q
16.3 Wired Rack 0.25Q
16.4 3 Years maintenance Spares Set consisting of complete 0.1Q
equipment from 16.1 to 16.2 including installation materials
etc.
* LCT Software shall be supplied alongwith the necessary cable accessories
required for connecting the PC to the network element. No software lock shall
be incorporated in the LCT software. The software shall be re-usable on other
equipment in case of LCT failure.
Laptop/Desktop: Pentium IV 2 Ghz and above / 15" LCD screen / 40 GB /256
MB RAM /48X CD ROM drive/ 1.44 mb floppy drive /lan port/inbuilt Modem/2
Nos USB Port/printer port/video output to LCD projecter / mouse port/ PS-2
Keyboard port/ lincesed operating software preloaded in the laptop / recovery
CD. The laptop shall be supplied with LCT software installed in it.
## Ethernet media convertor shall be located in the customer permises and
connected to 100 base FX interface of the SDH equipment through G.652
SMS. The fast ethernet code on the EMC shall be 10/100 Base T auto sense
port. 100 Base FX of STM-4 equipment shall also be able drive for minimum 2
Kms on G.652 single Mode Fibre. All the ADMs / Regs. have to be supplied
with two optical aggregates.
STM-1
Annexure-II
1. Section IV Clause 12 (i) is modified as given below:
“ The bidder must supply equipment, which is type approved against the TEC GR No.
GR/SDH-04/02 MAR 2002 with amendment 1 to 4 for Long Haul applications for STM-1
equipment and against the TEC GR No. GR/SDH-13/01 JUL 2003 with amendment No.1 for
STM-1 CPE for Long Haul applications read along with tender conditions”.
The type approval certificate obtained from TEC New Delhi or the TSEC obtained
from QA circle BSNL Bangalore shall only be acceptable against the above specification
along with tender conditions.
Additional Clarification :
1. Section IV Clause 35 ( C) : As per clause 2.2 of Annexure-I, PBG needs to be submitted
two months before expiry of the warranty, while clause 35(C ) requires three months before
expiry of warrantee. . The clause 35(C) stands amended as per clause 2.2 of annexure-I