Waiver of Subrogation - PowerPoint
Description
Waiver of Subrogation document sample
Document Sample


Understanding Killer
Contract Language
The Dreaded Contract
Unfortunately, none of the
parties typically discuss
the nature of the contract
and its provisions until
after they have agreed
upon the scope of work
and the price.
Your Call!
Sometimes bad contract language
must be considered; risk should not
include the future of your company
Buddy’s
Top 7 Deal Breakers
1. Contingency payment clauses
Pay If Paid; Pay When Paid
Red Flag Pay If Paid
• Under a "pay-if-paid" provision, the
subcontractor will be paid only if the
GC is first paid by the owner for the
specific subcontractors work.
• A pay-if-paid provision creates a
condition precedent to the GC’s duty to
pay its subcontractor and the risk of an
owner’s non-payment is shared by the
contractor and the subcontractor.
Red Flag Pay If Paid
Typical Contract Language
• Contractor’s obligation to pay Sub any sum
due under the contract is subject to the
condition precedent that Contractor has first
received from Owner payment for Sub’s
work. Contractor shall have no obligation to
pay Sub for any particular work unless and
until Owner first pays Contractor for such
work. Sub expressly assumes the risk of
nonpayment by the Owner to Contractor for
any reason.
Red Flag Pay If Paid Examples
• Examples of these clauses might read:
• "Notwithstanding any provision to the
contrary, payment by Owner to Contractor is
a condition precedent to payment to
Subcontractor;"
• "Receipt of payment from the Owner is a
condition precedent to payment to
Subcontractor and payment to Subcontractor
will only be made after the Contractor is paid
by Owner."
Pay When Paid
• With a pay-when-paid clause, so long as the
cause for non-payment to the general
contractor from the owner is not related to
the subcontractor’s work, the general
contractor should be liable to the
subcontractor immediately following the
expiration of a reasonable time period.
• If the general contractor does not receive
payment from the owner, and it is through no
fault of the subcontractor, the general
contractor is still going to be ultimately liable
to the subcontractor.
Pay When Paid
• These types of clauses deal only with the
timing of payment and are construed merely
as timing mechanisms, rather than as
waiver/forfeiture clauses.
• They are referred to as pay-when-paid
clauses, but they do not operate to preclude
payment indefinitely. In other words, the
clauses merely provide a GC with some
reasonable period within which to make
payment.
• The AIA 401 and the AGC 650 subcontract
forms contain pay-when-paid payment terms.
Lien Rights
• Subcontractors should always
retain their lien rights in their
contracts with general contractors.
This is especially important when
the parties’ contract contains the
pay-if-paid language.
2. Waiver of Lien or
Bond Rights
Waiver of Lien and Bond Rights
• Subcontractors should vigorously resist
giving up the payment security provided by
lien and Bond Rights.
• Most states have lien laws that require a
“Notice to Owner” when a lien is filed – most
states have specific lien notice and filing
timelines – know state lien laws.
• However, some courts have upheld such "no
lien" provisions against contractors that sign
them.
Pass Down
• If a contractor agrees to a no lien
provision, the contractor must put
the same language in any
contracts he enters into with lower
tiered contractors or material
suppliers.
Partial Lien Waiver
• Upon making progress payments, the owner
or general contractor may require the
contractor to waive all lien claims that the
contractor may have for the work invoiced.
• Such partial lien waiver requirement must be
contained in the contract.
• Only waive liens through the date of the
invoice, not through the date of the payment.
Final Lien Waiver
• Upon completing the job, the GC asks the
Sub complete a final lien waiver.
• The requirement to sign a final waiver of
claims in order to obtain final payment is
against public policy in most states if the
contractor has asserted a claim or request
for an adjustment to the contract price.
• Subs should not be caught between waiving
a previously asserted claim, and getting paid
for its work.
Protecting Lien Rights
• Look for no lien clauses in your
contract, and in the contract with the
owner, if that contract is incorporated
by reference.
• Such incorporation language is
usually enforced.
• If a no lien clause is in the contract,
try to negotiate it out of your contract
3. Waiver of
Subrogation Rights
Typical Waiver Language
• “Contractor shall and does hereby waive any
rights of subrogation that it or any of its
insurers may have against the owner, its
agents, employees or its insurers.”
• "The owner and Contractor waive all rights
against (1) each other and any of the
subcontractors, sub-subcontractors, agent
and employees, each of the other, [and] (2)
the architect, architect's consultants, . . . for
damage caused by fire or other perils to the
extent covered by property insurance
obtained pursuant to this contract.
Waiver of Subrogation
• The "waiver of subrogation" means that
by giving up its right of recovery, the
insurer accepts the fact that the
policyholder and the parties with whom
it has contracted have allocated the risk
of the insured event to the insurer - the
insurance would be the sole remedy and
that all risk would be on the insurer.
Insurance Policies
• If the owner has given up (i.e., waived) the right
to pursue certain claims in the contracts, the
legal effect is that the property insurer is bound
by that waiver.
• Many insurance policies state that the insured
may waive subrogation provided it is done as
part of the contract between the insured and its
client and is done at the outset of the job and not
after a claim or loss has arisen.
Deal Breakers
• Since builders risk policies are written on a great
variety of forms, it is especially critical for an insured
to determine whether the policy prohibits the insured
from waiving recovery rights against another.
• If the policy does prohibit such waivers and the
contractor enters into a typical construction contract
containing a mutual waiver of subrogation provision,
the contractor may have violated policy conditions and
voided the coverage. This is particularly true in the
case of waivers of recovery against architects and
engineers.
• In the case of design professionals, builders risk
insurers are hesitant to allow waivers of recovery
since design errors often cause other covered losses
under the policy.
Ask Insurer
• Waivers of subrogation should be entered into
by an owner or a contractor only after
permission is obtained from the builders risk
insurer.
• It is obviously prudent to seek a clarifying
endorsement from the insurer. This, of course, if
especially important where the policy form
strictly prohibits all waiver of recovery against
third parties, whether pre- or post- loss.
Good Waiver Language
• Waivers of subrogation to prevent the builders
risk insurer from bringing suit against the
contractor and the subcontractor – good.
• Another method to avoid that result would be to
add the contractor and all of its subcontractors
as named insureds to the policy since insurers
are generally not allowed to pursue subrogation
against their own insureds – OCIPs/CCIPs.
Deal Breaker Language
• Sub gives up right for its insurer to subrogate but
owner and GC can subrogate.
• Another frequently disputed issue regarding
waivers of subrogation is the length of time over
which the waiver extends. Typically, as is the
case with the AIA documents, the waiver is
intended to be coextensive with the length of
time during which the builders risk policy is in
place, that is, usually the completion of the
project.
4. Incorporation by
Reference
Incorporation By Reference
• Be alert to prime contract provisions
that contain “incorporation by
reference” clauses.
• Particularly inequitable are provisions
that incorporate only the contractor’s
responsibilities, but not your rights
against the owner.
Example of Concern
• An owner and contractor used an AIA contract
for a project. The contract incorporated by
reference AIA general conditions requiring the
parties to submit disputes to the project
architect for decision. The contract provided
that the architect's decision was "final and
binding on the parties subject to arbitration."
Under the contract, either party could demand
arbitration of the dispute by filing "notice of
demand for arbitration with the other party to
the Agreement, with the American Arbitration
Association and with the architect." The
contract also provided that failure to demand
arbitration within 30 days would result in "the
architect's decision becoming final and
binding."
5. Change Orders in
Writing.
Change Orders
• There is no such thing as a contract that
gets completed without change orders.
Just contractors who end up taking it on
the chin because of no change order
procedures in their contracts.
Change Orders
• Make certain that the key basic elements for change
orders is addressed in the contract:
– Who you have to notify and receive permission from for change
order work?
– When and how do you have to notify them of potential change
order work?
– What documents do you have to provide?
– How and when will the change order work get paid?
– Where will the additional funds come from for the change order
work?
– What is the reasonable time for approval and what is the
additional cost for your delays while you’re waiting for approval?
– How will you and the owner resolve the change order issue if
immediate approval for the work is not received in the agreed
time?
Change Orders
• Remember, change order work is not
“extra work”. It disrupts the progress and
productivity of the work as you had
originally planned for when you bid the
work. It is neither your fault nor your
responsibility, and you should be justly
compensated for this unanticipated
disruption.
Payment for Change Orders
• The owner has an obligation to build a building
in compliance with adopted codes and
standards. Subs should not pay for the owner’s
obligation.
• If it is a code required item – the owner should
pay.
• The only potentially open issue if it is our design
error is the difference between the cost to make
the change verses the cost if the original plans
addressed the item needing change.
Design Errors
• There exists a propensity for design team
members to reject change orders to fix
errors they have made.
• Be cautious of language in design concept
documents that shift or attempt to shift
design responsibility to contractors.
– “Successful bidder is responsible to
ensure the system is installed to code.”
6. Broad form
Indemnification.
Indemnity Clauses
• Three Different Forms of
Indemnity Clauses:
–1. Broad
–2. Intermediate
–3. Limited
Indemnity Clauses
• Broad: Sub shall indemnify and hold harmless
GC and Owner from and against any and all
claims, losses, damages, costs and expenses
relating to the performance of the subcontract
and involving personal injury, sickness,
disease, death or property damages, including
any resulting loss of use, REGARDLESS OF
WHETHER CAUSED IN WHOLE OR IN PART
BY THE NEGLIGENCE OF GC OR OWNER.
SUB ACKNOWLEDGES AND AGREES THAT IT
IS INDEMNIFYING GC AND OWNER FOR THEIR
OWN SOLE AND/OR PARTIAL NEGLIGENCE.
Indemnity Clauses
• Intermediate: Sub shall indemnify and hold harmless
GC and Owner from and against any and all claims,
losses, damages, and expenses relating to the
performance of the subcontract and involving
personal injury, sickness, disease, death or property
damages, including any loss of use, REGARDLESS
OF WHETHER CAUSED IN PART BY THE
NEGLIGENCE OF THE GC OR OWNER. Subs
indemnity obligation shall not extend to any claims,
losses, damages, or expenses for which the sole
cause is the negligence of GC or Owner.
Indemnity Clauses
• Limited: Sub shall indemnify and hold
harmless GC and Owner from and against
any and all claims, losses, damages, costs
and expenses relating to the performance of
the Subcontract and involving personal
injury, sickness, disease, death or property
damages, including any resulting loss of use,
but only to the extent caused by the
negligent acts or omissions of Sub, its
employees, or other persons or entities for
whose acts Sub may be liable.
Indemnification
• Insurers refusing to cover indemnification
clauses particularly indemnification of sole
negligence.
• Refusing to sign indemnification because of
no insurance is good argument.
• READ CONTRACTS – hold harmless
requirements can be worded many different
ways.
• Laws to protect us.
Indemnity Clauses
• 1. Express Negligence
Test.
• 2. Conspicuousness
Requirement.
Express Negligence Test
• In Ethyl Corp. v. Daniel Construction,
the Texas Supreme Court adopted the
Express Negligence Test for
indemnitee agreements.
• “. . . parties seeking to indemnify the
indemnitee from the consequences of
its own negligence must express that
intent in specific terms.”
Express Negligence Test
• Furthermore, the court added,
“Under the doctrine of express
negligence, the intent of the
parties must be specifically
stated within the four corners
of the contract.”
Conspicuousness Requirement
• The Conspicuousness Test states that a
clause is conspicuous when a reasonable
person against whom the clause is to
operate ought to have noticed it.
• Language in CAPITAL HEADINGS,
language in contrasting type or color, and
language in an extremely short document,
such as a telegram, is conspicuous.
Indemnity Clause Satisfying the
Conspicuousness Test
• Broad: Sub shall indemnify and hold harmless GC
and Owner from and against any and all claims,
losses, damages, costs and expenses relating to
the performance of the subcontract and involving
personal injury, sickness, disease, death or
property damages, including any resulting loss of
use, REGARDLESS OF WHETHER CAUSED IN
WHOLE OR IN PART BY THE NEGLIGENCE OF
GC OR OWNER. SUB ACKNOWLEDGES AND
AGREES THAT IT IS INDEMNIFYING GC AND
OWNER FOR THEIR OWN SOLE AND/OR
PARTIAL NEGLIGENCE.
7. Additional Insured
Endorsements.
Additional Insured
Endorsements
• Sub shall, at no expense to GC, maintain in
full force at all times Commercial General
Liability Insurance. This insurance shall be
written for not less than (limits specified) or
required by law. The following AIE shall be
furnished to GC prior to the commencement
of the work. In consideration of the premium
charged, GC is named as additional insured
with respect to all liabilities arising out of the
performance of the work.
Additional Insured
Endorsements
• Sub shall, at no expense to GC, maintain in full
force at all times Commercial General Liability
Insurance. This insurance shall be written for not
less than (limits specified) or required by law,
and this insurance shall be primary to any
other insurance of the GC. The following AIE
shall be furnished to GC prior to the
commencement of the work. In consideration of
the premium charged, GC is named as
additional insured with respect to all liabilities
arising out of the performance of the work.
Additional Insured
Endorsements
• . . . . insurance shall be written for not less than
(limits specified), and this insurance shall be
primary to any other insurance of the GC. In
consideration of the premium charged, GC is
named an additional insured with respect to all
liabilities arising out of the performance of the
work. Sub shall waive all rights against GC, its
agents, and employees for all damages covered
by insurance pursuant to this contract.
Flow Through Provisions
• BROAD: Sub is bound to
Contractor by all terms of the Prime
Contract and assumes toward
Contractor all of the obligations and
responsibilities that Contractor by
those instruments assumes toward
Owner.
Flow Through Provisions
• The Subcontract consists of this Agreement and
any Exhibits attached hereto, and, to the extent
applicable to the Subs work, the Prime Contract
consisting of the Agreement between Owner and
Contractor . . . . Sub is bound to Contractor by
all terms of the Prime Contract and assumes
toward Contractor all of the obligations and
responsibilities pertaining to the Sub’s work that
Contractor by those instruments assumes
toward Owner and Sub shall have the same
rights and remedies against the Contractor as
the Contractor has against the Owner.
Where to we go
from here?
Buddy’s Recommendations
Use Conditional Bids
• One way to avoid the unpleasant experience
of receiving an inequitable subcontract “after
the fact” is to condition the bid “upon
acceptable contract language.”
• “This bid is conditioned upon the use of the
AIA A401 Subcontract (2003 edition).”
• A GC who accepts a bid is therefore not
only accepting the price but also the level of
risk found in A401. Can’t force bad contract.
Use ASA Addendum
• The ASA has prepared a “generic”
addendum intended to defuse the typical
proprietary bad contract language.
• While the ASA Addendum is not perfect, it
will address most of the offensive contract
provisions typically encountered.
Educate Your Customer
• GCs want subs not only with low prices
but also that read and strictly follow the
details in the plans and specifications.
• Let the GC know your professionalism up
front but also advise what subcontract
terms are acceptable and be prepared to
explain why certain language is one-sided
and unfair.
Walk Away From Unfair Contracts
• It is hard to lose a job but it is worst to lose
your company. Look at past losses and
determine if bad contract language was a
factor.
• Unfair risk shifting have long-range
implications on your company’s future.
Questions?
NFSA Regional
Operations
On a Path Towards Excellence
Related docs
Get documents about "