					                        Capital Budgeting Analysis for                              Supplemental Material for Short Course 3:
                        Medical Services USA                                        Budgeting Analysis, located on the internet
                                                                                    www.exinfm.com/training. Prepared by: Ma
Purpose of Spreadsheet                                                              Evans, CPA, CMA, CFM

Illustrate concepts related to capital budgeting analysis of projects. Certain aspects of a capital
project may have not been included in order to help highlight basic concepts, such as
Net Present Value. The spreadsheet is setup to evaluate six different projects and summarize
all projects based on both economic analysis and risk factors assigned.
Note: The Solver feature of Excel is used in an example at the end. Please make sure that you
have installed Solver: Solver add-on feature (Tools => Add-Ins => Solver).

Economic Analysis

Three economic criteria are applied to projects: Net Present Value, Modified Internal Rate of
Return and Discounted Payback Period. If your project(s) have non-periodic payments
(payments are not equal over the life of the project), then you should use these Excel Functions:
=XNPV for Net Present Value by entering specific dates of cash flows
=XIRR for Internal Rate of Return by entering specific dates of cash flows

Cell Indicators

Certain cells are highlighted as follows:

                        Selected input cells (not all input cells are highlighted since each project is unique)
                        Cell includes a comment - move mouse and point over cell for comment
                        Indication of an error in calculation or a red flag that a criteria has not been met

Organization of Spreadsheet

                        Lead Worksheet
                        Project A Analysis - Example with Annual Cash Flow Calculations
                        Project B Analysis - Example with Sunk Costs & Projected Financials
                        Project C Analysis - Example of Upgrade Investment
                        Project D Analysis - Example of Project Financing
                        Project E Analysis - Example of Foreign Investment
                        Project F Analysis - Example of Monthly Inflows / Outflows
                        Summary and Example of Using Excel Solver
                        Answer Report 1 - Output from Using Excel Solver in Summary Example

General Input
          The following general inputs have been used on different worksheets:

                  A     Diesel Generation System            <= Enter project name
                  B     New Clinic in Kansas City           <= Enter project name
                  C     Upgrade to DuBois Center            <= Enter project name
                  D     Southeastern Upgrades               <= Enter project name
                  E     Canadian Partnership                <= Enter project name
                  F     Regulatory Compliance NE            <= Enter project name
                                                  27.50%    <= Marginal Tax Rate *
                                                   9.50%    <= Weighted Average Cost of Capital
                                                $10,000 <= Threshold investment amount where formal project analysis
                                                        is not required - general expenditure item.

          * If you expect changes in future tax rates, you may want to consider these changes
          in your analysis.

Project Codes (Used to help categorize various capital projects)

          Project Classification Codes:
                   1 Land
                   2 Buildings
                   3 Leasehold Improvement
                   4 Equipment
                   5 Furniture and Fixtures
                   6 Vehicles
                   7 Acquisitions
                   8 Investments
                   9 Other

          Primary Justification for Project:
                   A Cost Reduction
                   B Replacement
                   C Expansion / Addition
                   D Service Improvement
                   E Safety & Compliance
                   F Operating Necessity
                  G Other

          Priority Code:
                    1 Carry over project, already in progress, requires additional funding
                    2 Essential for continued operations, regulatory compliance, etc.
                    3 Economically desired for revenue growth, cost reductions, etc.
                    4 General improvement for building or expanding the business
ental Material for Short Course 3: Capital
g Analysis, located on the internet at
nfm.com/training. Prepared by: Matt H.
PA, CMA, CFM
                       Lead Wks
                       Project A
                       Project B
                       Project C
                       Project D
                       Project E
                       Project F
                       Summary




oject is unique)
where formal project analysis
            Capital Budgeting Analysis for
            Medical Services USA
    A       Diesel Generation System
Project Information

Project Description > New diesel backup system for high volume medical plant
Project Benefits >      Eliminate downtime, improve efficiency, better service
Project Location >      Mobile, AL
Responsible Division >              Southern
Responsible Department >            Plant Engineering
Contact Person Name >               John Pearson, Southern Div Manager
Estimated Project Start Date >         01/01/92
Classification >                  4
Justification >                   F
Priority >                        2

Preliminary Review

Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.

Financial Attributes:
    F1      Project improves overall profitability of the company                               2
    F2      Project lowers cost structure                                                       3
    F3      Project will generate a rate of return                                              3
    F4      Project improves asset utilization                                                  1
    F5      Other Financial Attribute __________________________________                        0
    F6      Other Financial Attribute __________________________________                        0

Operating Attributes:
   O1      Improves operating efficiencies                                                      4
   O2      Increases the customer base                                                          0
   O3      Improves overall customer service                                                    0
   O4      Improves competitive position of company                                             0
   O5      Other Operating Attribute _________________________________                          0
   O6      Other Operating Attribute _________________________________                          0

Contingency Attributes:
   C1     Project has options that allow for change during life                                 2
   C2     Project will positively impact company even if value is negative                      4
   C3     Project can be abandoned easily with some positive value                              1
   C4     Project permits several options to maximize value                                     2
   C5     Other Cont Attribute _____________________________________                            0

Miscellaneous Attributes:
   M1      Expands Human Resource Capital                                                       0
   M2      Enhances workforce productivity                                                      0
   M3      Project meets a critical regulatory, security or specific need                       0
   M4      Project fits with company strategy and goals                                         1
   M5        Probability of project success is very high / low risk                         4
   M6        Other Misc Attribute _____________________________________                     0
   M7        Other Misc Attribute _____________________________________                     0
   M8        Other Misc Attribute _____________________________________                     0

                                                   Total Preliminary Points               27

Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.

Financial Analysis


             Proposed Project Expenditure:
         *   Equipment & Facilities (purchase price)                165,000
         *   Installation Cost                                           650
         *   Labor                                                     4,500
         *   Materials                                                   250
         *   Shipping                                                  1,280
         *   Taxes                                                   11,550
             Other Costs (expensed)                                      350
             Intial Cash Outlay for Project                         183,580
             Tax Breaks for Investment                                (1,500)
             Sale of Existing Assets                                       0
             Tax Benefit on Loss - Sale of Assets                          0
             Total Project Investment                               182,080
             Project Analysis Required?                              Yes

         * capitalized costs subject to depreciation using double declining method over 8 years with $ 8,000 salvag
           NOTE: Depreciation for tax purposes is considered the same for accounting purposes. If tax depreciatio
           different than accounting depreciation, deduct tax depreciation in calculating taxes.

             Cash Flows associated with Project:
             Year 1:
             Reductions in annual operating costs                    28,900
             New revenues from higher output volumes                  6,200
             Eliminate third party vendor service                    35,000
             Annual service and maintenance                          (4,600)
             Annual fuel costs                                       (1,500)
             Depreciation:
                          Cost                     183,230
                          Salvage Value              8,000
                          Useful Life                    8
                          Depreciation in Yr              1         (45,808)
             Operating Cash Flow in Year 1                           18,193
             Less Taxes                                              (5,003)
             Net Income - Year 1                                     13,190
             Add Back Non Cash Depreciation                          45,808
             Change to Net Working Capital                           (3,500)
             Net Cash Flow - Year 1                                  55,497
Year 2:
Reductions in annual operating costs             32,100
New revenues from higher output volumes           6,900
Eliminate third party vendor service             35,000
Annual service and maintenance                   (5,000)
Annual fuel costs                                (1,800)
Depreciation:
             Cost                     183,230
             Salvage Value              8,000
             Useful Life                    8
             Depreciation in Yr              2   (34,356)
Operating Cash Flow in Year 2                     32,844
Less Taxes                                        (9,032)
Net Income - Year 2                               23,812
Add Back Non Cash Depreciation                    34,356
Change to Net Working Capital                       (650)
Net Cash Flow - Year 2                            57,518

Year 3:
Reductions in annual operating costs             34,800
New revenues from higher output volumes           7,100
Eliminate third party vendor service             35,000
Annual service and maintenance                   (5,000)
Annual fuel costs                                (2,000)
Depreciation:
             Cost                     183,230
             Salvage Value              8,000
             Useful Life                    8
             Depreciation in Yr              3   (25,767)
Operating Cash Flow in Year 3                     44,133
Less Taxes                                       (12,137)
Net Income - Year 3                               31,997
Add Back Non Cash Depreciation                    25,767
Change to Net Working Capital                       (550)
Net Cash Flow - Year 3                            57,213

Year 4:
Reductions in annual operating costs             37,200
New revenues from higher output volumes           7,900
Eliminate third party vendor service                  0
Annual service and maintenance                   (5,200)
Annual fuel costs                                (2,100)
Depreciation:
             Cost                     183,230
             Salvage Value              8,000
             Useful Life                    8
             Depreciation in Yr              4   (19,325)
Operating Cash Flow in Year 4                     18,475
Less Taxes                                        (5,081)
Net Income - Year 4                               13,394
Add Back Non Cash Depreciation                    19,325
Change to Net Working Capital                      (250)
Net Cash Flow - Year 4                           32,469

Year 5:
Reductions in annual operating costs             40,900
New revenues from higher output volumes           8,900
Eliminate third party vendor service                  0
Annual service and maintenance                   (5,300)
Annual fuel costs                                (2,200)
Depreciation:
             Cost                     183,230
             Salvage Value              8,000
             Useful Life                    8
             Depreciation in Yr              5   (14,494)
Operating Cash Flow in Year 5                     27,806
Less Taxes                                        (7,647)
Net Income - Year 5                               20,160
Add Back Non Cash Depreciation                    14,494
Change to Net Working Capital                       (350)
Net Cash Flow - Year 5                            34,303

Year 6:
Reductions in annual operating costs             44,200
New revenues from higher output volumes           9,700
Eliminate third party vendor service                  0
Annual service and maintenance                   (5,400)
Annual fuel costs                                (2,300)
Depreciation:
             Cost                     183,230
             Salvage Value              8,000
             Useful Life                    8
             Depreciation in Yr              6   (10,870)
Operating Cash Flow in Year 6                     35,330
Less Taxes                                        (9,716)
Net Income - Year 6                               25,614
Add Back Non Cash Depreciation                    10,870
Change to Net Working Capital                       (150)
Net Cash Flow - Year 6                            36,334

Year 7:
Reductions in annual operating costs             50,100
New revenues from higher output volumes          10,200
Eliminate third party vendor service                  0
Annual service and maintenance                   (5,500)
Annual fuel costs                                (2,400)
Depreciation:
             Cost                     183,230
             Salvage Value              8,000
             Useful Life                    8
             Depreciation in Yr              7    (8,153)
Operating Cash Flow in Year 7                     44,247
Less Taxes                                       (12,168)
           Net Income - Year 7                                        32,079
           Add Back Non Cash Depreciation                              8,153
           Change to Net Working Capital                                (150)
           Net Cash Flow - Year 7                                     40,082

           Year 8:
           Reductions in annual operating costs                       55,500
           New revenues from higher output volumes                    11,000
           Rebuild / Repair Unit Option                              (25,000)
           Annual service and maintenance                             (4,600)
           Annual fuel costs                                          (2,600)
           Depreciation:
                        Cost                     183,230
                        Salvage Value              8,000
                        Useful Life                    8
                        Depreciation in Yr              8             (6,115)
           Operating Cash Flow in Year 8                              28,185
           Less Taxes                                                 (7,751)
           Net Income - Year 8                                        20,434
           Add Back Non Cash Depreciation                              6,115
           Change to Net Working Capital                                 (50)
           Net Cash Flow - Year 8                                     26,499

           Terminal Year 9
           Salvage Value of Asset                                      5,000
           Working Capital Reversed                                    2,500
                                  Terminal Value                       7,500

           At the end of Year 8, a decision will be made to either rebuild the asset or outsource to third party.

Economic Analysis

Summarize Cash Outflows and Inflows for Project:
                        Cash       Present       Recovery
            Year       Flows         Value       Payback
              0       (182,080)     (182,080)
              1         55,497        49,997      (132,083)
              2         57,518        46,683       (85,400)
              3         57,213        41,834       (43,566)
              4         32,469        21,389       (22,177)
              5         34,303        20,357        (1,820)
              6         36,334        19,426        17,606 <= payback
              7         40,082        19,306        36,912
              8         26,499        11,499        48,410
              9          7,500          2,932       51,342
         Net Present Value            51,342

Required Rate of Return for Project =>                  11.00%
Reinvestment Rate for Project =>                         6.00%

Net Present Value                        $51,342
Modified IRR                              11.03%
Discounted Payback (years)                    6.1


Economic Assessment

Project has positive Net Present Value?             Yes
Project has IRR in excess of cost?                  Yes
Project has a positive payback?                     Yes

Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.


Risk Analysis

Risk Premium Applied to Project           1.50%

Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
          Probability of Accurate and Reliable Information - Gov't T Bond        1.00 (a)
          Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)                   1 (b)
          Exponential power to apply to Risk Ranking is 2 - (a)                     1 (c)
          Risk Factor = (b) raised to the power (c)                                 1

           Probability of Accurate and Reliable Information for Project                0.6
           Risk Ranking assigned to project (1 to 10)                                    5
           Exponential power to apply to Project                                       1.4
           Risk Factor for Project                                                     10

Assign probabilities to three possible outcomes for project:
         P Pesimistic outlook, declining growth, slower volumes, etc.               25.00%
        N Normal expected outlook as applied in analysis                            60.00%
        O Optomistic outlook, better than expected growth                           15.00%
                          Total should equal          100.00%                      100.00%

Enter Expected Cash Flows for different outcomes:

                                                                  Standard     Coeff of
                      Net Cash Flows                 Expected     Deviation    Variation
  Year       Pesimist     Normal    Optomist          Value      (Abs Risk)   (Rel Risk)
   1           41,800      55,497     64,900           53,483        17,758        0.332
   2           39,750      57,518     67,300           54,543        21,584        0.396
   3           37,400      57,213     66,100           53,593        22,854        0.426
   4           26,200      32,469     41,050           32,189        10,699        0.332
   5           21,050      34,303     40,900           31,979        15,679        0.490
   6           13,200      36,334     39,800           31,071        22,531        0.725
   7           11,800      40,082     40,800           33,119        25,430        0.768
   8            8,100      26,499     35,700           23,279        21,793        0.936
Terminal        1,000       7,500       8,500           6,025         6,346        1.053
 Totals       200,300     347,416    405,050          319,282       164,674        0.516

           Absolute Risk of Project (Std Deviation)                164,674
         Relative Risk of Project (Coeff of Variation)        0.516


Revised Economic Analysis using Expected Values

                      Expected     Present     Recovery
             Year      Value        Value      Payback
              0       (182,080)    (182,080)
              1         53,483       48,183     (133,897)
              2         54,543       44,268      (89,628)
              3         53,593       39,187      (50,442)
              4         32,189       21,204      (29,238)
              5         31,979       18,978      (10,259)
              6         31,071       16,612        6,352 payback
              7         33,119       15,952       22,304
              8         23,279       10,102       32,406
              9          6,025        2,355       34,761
            Totals                   34,761

Net Present Value                   $34,761
Modified IRR                         10.07%
Discounted Payback (years)               6.6
d over 8 years with $ 8,000 salvage value
unting purposes. If tax depreciation is
or outsource to third party.
            Capital Budgeting Analysis for
            Medical Services USA
    B       New Clinic in Kansas City
Project Information

Project Description > New Walk In Clinic - Kansas City
Project Benefits >      Toehold market position, profit center, business expansion
Project Location >      Kansas City
Responsible Division >              Mid West
Responsible Department >            Business Development
Contact Person Name >               Bill Watson, Operations Director
Estimated Project Start Date >           04/01/92
Classification >                 2
Justification >                 C
Priority >                       3

Preliminary Review

Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.

Financial Attributes:
    F1      Project improves overall profitability of the company                               3
    F2      Project lowers cost structure                                                       2
    F3      Project will generate a rate of return                                              4
    F4      Project improves asset utilization                                                  2
    F5      Other Financial Attribute __________________________________                        0
    F6      Other Financial Attribute __________________________________                        0

Operating Attributes:
   O1      Improves operating efficiencies                                                      2
   O2      Increases the customer base                                                          3
   O3      Improves overall customer service                                                    3
   O4      Improves competitive position of company                                             2
   O5      Other Operating Attribute _________________________________                          0
   O6      Other Operating Attribute _________________________________                          0

Contingency Attributes:
   C1     Project has options that allow for change during life                                 0
   C2     Project will positively impact company even if value is negative                      0
   C3     Project can be abandoned easily with some positive value                              0
   C4     Project permits several options to maximize value                                     0
   C5     Other Cont Attribute _____________________________________                            0

Miscellaneous Attributes:
   M1      Expands Human Resource Capital                                                       0
   M2      Enhances workforce productivity                                                      0
   M3      Project meets a critical regulatory, security or specific need                       0
   M4      Project fits with company strategy and goals                                         3
   M5      Probability of project success is very high / low risk                                    0
   M6      Other Misc Attribute _____________________________________                                0
   M7      Other Misc Attribute _____________________________________                                0
   M8      Other Misc Attribute _____________________________________                                0

                                                    Total Preliminary Points                        24

Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.

Financial Analysis

           Proposed Project Expenditure:
           Rework / Upgrade Existing Building                           85,000 (1)
           Equipment and Fabrication                                    45,000 (2)
           Marketing and Promotion of Clinic                             7,500
           Contingency Costs                                             3,500
           Market Study / Research                                       2,500 <= exclude since sunk cost, not relevan
                      Total Project Investment                         141,000
                      Project Analysis Required?                        Yes

           (1): Depreciated over 30 years using the straight line method with no salvage value.
           (2): Depreciated over 12 years using the declining balance method with no salvage value.
           Tax depreciation and accounting depreciation are considered the same.

           Working Capital Requirements:
           Historical analysis of other similar clinics indicates that clinics require:

                        Cash                                             3,500
                        Accounts Receivable                              7,500
                        Inventories                                      5,000
                                    Total Current Assets                16,000
                        Accounts Payable                                 6,000
                        Other accruals                                   4,000
                                    Total Current Liab                  10,000
                        Net Working Capital                              6,000
                        Sales Revenues                                  60,000
                        Ratio (NWC / Sales)                             10.00%

           The above Ratio will be applied to estimate working capital requirements

           Opportunity Cost Analysis:

           As a result of this project investment, the company expects some negative impact to its
           Topeka, Kansas facility as follows:
                                                                  Year 1     Year 2      Year 3
           Reduction to Sales Revenues                              (4,000)    (5,000)     (3,000)
           Reductions in overall cost                                1,500      2,000       1,200
           Net Reduction to Income                                  (2,500)    (3,000)     (1,800)
         Five Year Financial Forecast:
                                                             Year       Year        Year
                                                               1         2           3
         Sales Revenues                                       65,000    75,000     100,000
         Cost of Services:
                      Personnel / Labor                      (15,000)   (18,000)   (22,000)
                      Supplies, Vendors, etc.                 (8,000)   (10,000)   (15,000)
                      Adm Overhead Increases                 (22,000)   (28,000)   (30,000)
         Opportunity Cost (per above)                         (2,500)    (3,000)    (1,800)
         Profit before Tax                                    17,500     16,000     31,200
         Taxes                                                (4,813)    (4,400)    (8,580)
         Investment Credits                                       50          0          0
         Net Profit                                           12,738     11,600     22,620
         Depreciation:
                      Upgrade to Building
         Useful Life =>                     30                 2,833     2,833       2,833
                      Equipment
                                            12                 6,923     6,346       5,769
         Operating Cash Flow                                  22,494    20,779      31,223
         Net Working Capital                                  (6,500)   (7,500)    (10,000)
         Planned Critical Cash Outlays                        (1,500)   (2,500)     (3,500)
                      Total Cash Flow                         14,494    10,779      17,723


Economic Analysis

         Summarize Cash Outflows and Inflows for Project:
                                  Cash        Present
                      Year        Flows         Value       Payback
                            0    (141,000)     (141,000)
                            1      14,494        12,883     (128,117)
                            2      10,779         8,517     (119,599)
                            3      17,723        12,447     (107,152)
                            4      30,696        19,163      (87,989)
                            5      30,634        17,000      (70,990)
                            6      34,197        16,868      (54,121)
                            7      33,845        14,840      (39,282)
                            8      35,043        13,658      (25,624)
                            9      36,604        12,681      (12,943)
                           10      36,914        11,368       (1,575)
                           11      31,450         8,609        7,033 payback
                           12      31,450         7,652       14,686
                           13      31,450         6,802       21,488
                           14      31,450         6,046       27,534
                           15      31,450         5,374       32,908
                           16      31,450         4,777       37,686
                           17      31,450         4,246       41,932
                           18      31,450         3,775       45,707
                           19      31,450         3,355       49,062
                           20      31,450         2,982       52,044
                   Net Present Value             52,044
                           Required Rate of Return for Project =>                   12.50%
                           Reinvestment Rate for Project =>                          7.50%

                           Net Present Value                                       $52,044
                           Modified IRR                                             11.36%
                           Discounted Payback (years)                                 11.18


Economic Assessment

          Project has positive Net Present Value?                   Yes
          Project has IRR in excess of cost?                        No
          Project has a positive payback?                           Yes

          Project must meet at least two of the three Economic Criteria, otherwise special
          approval is required.


Risk Analysis

          Risk Premium Applied to Project                  3.00%

          Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
          Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
                     Probability of Accurate and Reliable Information - Gov't T Bond       1.00
                     Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)                  1
                     Exponential power to apply to Risk Ranking is 2 - (a)                    1
                     Risk Factor = (b) raised to the power (c)                                1

                           Probability of Accurate and Reliable Information for Project              0.5
                           Risk Ranking assigned to project (1 to 10)                                  7
                           Exponential power to apply to Project                                     1.5
                           Risk Factor for Project                                                   19

          Assign probabilities to three possible outcomes for project:
                   P Pesimistic outlook, declining growth, slower volumes, etc.                 35.00%
                   N Normal expected outlook as applied in analysis                             60.00%
                   O Optomistic outlook, better than expected growth                             5.00%
                                    Total should equal            100.00%                      100.00%

          Enter Expected Cash Flows for different outcomes:

                                                                                  Standard     Coeff of
                                     Net Cash Flows                  Expected     Deviation    Variation
                Year        Pesimist    Normal      Optomist          Value      (Abs Risk)   (Rel Risk)
                       1       8,650      14,494      26,800           13,064        13,845       1.060
                       2       6,800      10,779      27,500           10,223        15,031       1.470
                       3       7,900      17,723      33,200           15,059        19,774       1.313
                       4       8,600      30,696      37,800           23,317        25,865       1.109
                       5       8,100      30,634      43,900           23,410        30,422       1.300
                       6       7,500      34,197      42,100           25,248        30,794       1.220
                       7       7,100      33,845      41,850           24,884        30,908       1.242
          8       6,200       35,043       40,950       25,243    31,501   1.248
          9       6,000       36,604       40,200       26,072    31,630   1.213
         10       5,500       36,914       39,900       26,068    31,993   1.227
         11       5,100       31,450       37,750       22,543    29,386   1.304
         12       4,900       31,450       35,950       22,383    28,367   1.267
         13       4,250       31,450       34,150       22,065    27,779   1.259
         14       3,705       31,450       32,990       21,816    27,520   1.261
         15       3,250       31,450       31,650       21,590    27,054   1.253
         16       2,680       31,450       31,280       21,372    27,349   1.280
         17       2,005       31,450       31,000       21,122    27,806   1.316
         18       1,490       31,450       30,850       20,934    28,197   1.347
         19       1,105       31,450       29,990       20,756    27,986   1.348
         20         790       31,450       28,750       20,584    27,454   1.334
Totals          101,625      595,428      698,560      427,753   540,660   1.264

              Absolute Risk of Project (Std Deviation)           540,660
              Relative Risk of Project (Coeff of Variation)        1.264


Revised Economic Analysis using Expected Values

                           Expected      Present     Recovery
                 Year       Values        Value      Payback
                       0 (141,000)      (141,000)
                       1      13,064       11,612     (129,388)
                       2      10,223        8,077     (121,311)
                       3      15,059       10,576     (110,734)
                       4      23,317       14,557      (96,177)
                       5      23,410       12,991      (83,186)
                       6      25,248       12,454      (70,732)
                       7      24,884       10,911      (59,821)
                       8      25,243        9,838      (49,983)
                       9      26,072        9,032      (40,951)
                      10      26,068        8,028      (32,923)
                      11      22,543        6,171      (26,752)
                      12      22,383        5,446      (21,306)
                      13      22,065        4,772      (16,534)
                      14      21,816        4,194      (12,340)
                      15      21,590        3,689       (8,651)
                      16      21,372        3,246       (5,404)
                      17      21,122        2,852       (2,552)
                      18      20,934        2,513          (40)
                      19      20,756        2,214        2,175 payback
                      20      20,584        1,952        4,127
              Net Present Value             4,127

Net Present Value                          $4,127
Modified IRR                                9.68%
Discounted Payback (years)                   19.02
since sunk cost, not relevant




alvage value.




                Year 4     Year 5
                 (1,500)     (500)
                    700       100
                   (800)     (400)
                                                                             Terminal
 Year       Year       Year       Year       Year       Year       Year        Flow
  4          5          6          7          8          9          10       11 to 20
125,000    135,000    140,000    145,000    149,000    153,000    155,000     160,000

(25,000)   (30,000)   (32,000)   (35,000)   (36,000)   (36,500)   (37,000)    (40,000)
(18,000)   (19,000)   (15,000)   (15,000)   (15,000)   (15,000)   (15,000)    (18,000)
(32,000)   (35,000)   (36,000)   (37,000)   (37,000)   (37,000)   (37,000)    (40,000)
   (800)      (400)         0          0          0          0          0           0
 49,200     50,600     57,000     58,000     61,000     64,500     66,000      62,000
(13,530)   (13,915)   (15,675)   (15,950)   (16,775)   (17,738)   (18,150)    (17,050)
      0          0          0          0          0          0          0           0
 35,670     36,685     41,325     42,050     44,225     46,763     47,850      44,950


  2,833      2,833      2,833      2,833      2,833      2,833      2,833      2,500

  5,192      4,615      4,038      3,462      2,885      2,308      1,731           0
 43,696     44,134     48,197     48,345     49,943     51,904     52,414      47,450
(12,500)   (13,500)   (14,000)   (14,500)   (14,900)   (15,300)   (15,500)    (16,000)
   (500)         0          0          0          0          0          0           0
 30,696     30,634     34,197     33,845     35,043     36,604     36,914      31,450
t Risk Factor:

             (a)
             (b)
             (c)
              Capital Budgeting Analysis for
              Medical Services USA
     C        Upgrade to DuBois Center
Project Information

Project Description >    Upgrade DuBois for unused capacity
Project Benefits >       Better use of facility, more income
Project Location >       Iowa
Responsible Division >                  Mid West
Responsible Department >                Finance
Contact Person Name >                   Cheryl Strickland, Controller
Estimated Project Start Date >                03/15/92
Classification >                     4
Justification >                     C
Priority >                           3

Preliminary Review

Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.

Financial Attributes:
    F1         Project improves overall profitability of the company
    F2         Project lowers cost structure
    F3         Project will generate a rate of return
    F4         Project improves asset utilization
    F5         Other Financial Attribute __________________________________
    F6         Other Financial Attribute __________________________________

Operating Attributes:
    O1       Improves operating efficiencies
    O2       Increases the customer base
    O3       Improves overall customer service
    O4       Improves competitive position of company
    O5       Other Operating Attribute _________________________________
    O6       Other Operating Attribute _________________________________

Contingency Attributes:
    C1      Project has options that allow for change during life
    C2      Project will positively impact company even if value is negative
    C3      Project can be abandoned easily with some positive value
    C4      Project permits several options to maximize value
    C5      Other Cont Attribute _____________________________________

Miscellaneous Attributes:
    M1      Expands Human Resource Capital
    M2      Enhances workforce productivity
    M3      Project meets a critical regulatory, security or specific need
    M4      Project fits with company strategy and goals
    M5       Probability of project success is very high / low risk
    M6       Other Misc Attribute _____________________________________
    M7       Other Misc Attribute _____________________________________
    M8       Other Misc Attribute _____________________________________

                                                       Total Preliminary Points

Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.

Cost Volume Profile of DuBois Facility

Personnel & Labor                                              37.50
Supplies and Inventory                                          2.65
Variable Adm Overhead                                           3.60
Fixed Overhead Costs                                           10.50
Total Unit Costs per Billable Hour                             54.25

Current Operating Capacity =>                    60%
Maximum Capacity per month                     15,000 billable hours
Sales growth rates over the next ten years are estimated at 4% per year with increases to costs
estimated at 1.5% per year for each variable component.

Estimated Changes from Upgrade Investment

Upgrade Investment will result in additional 5,000 billable hours per month
New Services from Upgrade Investment are billable to customers at $ 50.00 per hour
Capacity after upgrade =>                       14,000
Does upgrade project exceed max?                    No

Financial Analysis

             Proposed Project Expenditure:
             Upgrade Systems & Facilities                                 1,150,000
             Executive Management Time                                      405,000
             Training and Promotion                                         135,000
             Contingency Costs                                               90,000
                         Total Investment                                 1,780,000
                         Project Analysis Required?                        Yes

                               Annual   < - - relevant annual costs to project - - >
                            Incremental Personnel         Supplies        Var Adm        Profits
                 Year        Revenues      & Labor       & Inventory     Overhead      before Tax
                        1     3,000,000   (2,250,000)       (159,000)      (216,000)      375,000
                        2     3,090,000   (2,283,750)       (161,385)      (219,240)      425,625
                        3     3,182,700   (2,318,006)       (163,806)      (222,529)      478,359
                        4     3,278,181   (2,352,776)       (166,263)      (225,867)      533,275
                        5     3,376,526   (2,388,068)       (168,757)      (229,255)      590,447
                        6     3,477,822   (2,423,889)       (171,288)      (232,693)      649,952
                        7     3,582,157   (2,460,247)       (173,857)      (236,184)      711,868
                     8     3,689,622    (2,497,151)      (176,465)         (239,727)    776,279
                     9     3,800,310    (2,534,608)      (179,112)         (243,322)    843,267
                    10     3,914,320    (2,572,627)      (181,799)         (246,972)    912,921

                         Due to the rapid changes in services provided by this upgrade investment project, no term
                         calculated for the periods beyond year 10.

Economic Analysis

           Summarize Cash Outflows and Inflows for Project:
                                      Cash          Present
                         Year         Flows          Value             Payback
                                0 (1,780,000) (1,780,000)
                                1      256,875        233,523         (1,546,477)
                                2      295,578        244,279         (1,302,198)
                                3      334,811        251,548         (1,050,650)
                                4      374,625        255,874           (794,776)
                                5      416,074        258,349           (536,427)
                                6      459,215        259,215           (277,212)
                                7      504,105        258,685            (18,527)
                                8      550,802        256,953            238,427 payback
                                9      599,369        254,191            492,618
                               10      649,868        250,552            743,170
                     Net Present Value                743,170

                         Required Rate of Return for Project =>                          10.00%
                         Reinvestment Rate for Project =>                                 4.00%

                         Net Present Value                                             $743,170
                         Modified IRR                                                    11.24%
                         Discounted Payback (years)                                         8.07

Economic Assessment

           Project has positive Net Present Value?                   Yes
           Project has IRR in excess of cost?                        Yes
           Project has a positive payback?                           Yes

           Project must meet at least two of the three Economic Criteria, otherwise special
           approval is required.


Risk Analysis

           Risk Premium Applied to Project                  0.50%

           Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
           Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
                      Probability of Accurate and Reliable Information - Gov't T Bond
                      Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
                      Exponential power to apply to Risk Ranking is 2 - (a)
                      Risk Factor = (b) raised to the power (c)
                          Probability of Accurate and Reliable Information for Project
                          Risk Ranking assigned to project (1 to 10)
                          Exponential power to apply to Project
                          Risk Factor for Project

           Assign probabilities to three possible outcomes for project:
                     P Pesimistic outlook, declining growth, slower volumes, etc.
                    N Normal expected outlook as applied in analysis
                    O Optomistic outlook, better than expected growth
                                       Total should equal               100.00%

           Enter Expected Cash Flows for different outcomes:

                                                                                          Standard
                                        Net Cash Flows                  Expected          Deviation
              Year          Pesimist        Normal     Optomist          Value           (Abs Risk)
                      1       212,500        256,875     285,700          252,324            54,978
                      2       242,500        295,578     324,300          289,271            62,301
                      3       301,200        334,811     362,050          332,174            44,892
                      4       326,700        374,625     401,200          369,026            56,638
                      5       370,900        416,074     441,300          410,823            53,493
                      6       411,800        459,215     483,700          453,405            54,949
                      7       461,900        504,105     533,100          500,013            53,239
                      8       510,200        550,802     582,200          547,391            53,323
                      9       561,300        599,369     631,100          596,515            51,374
                     10       615,100        649,868     677,700          647,089            46,230
                            4,014,100      4,441,320   4,722,350        4,398,031           531,419

                          Absolute Risk of Project (Std Deviation)                         531,419
                          Relative Risk of Project (Coeff of Variation)                      0.121


Revised Economic Analysis using Expected Values

                                         Expected         Present       Recovery
                              Year        Values           Value        Payback
                                     0 (1,780,000)       (1,780,000)
                                     1      252,324         229,385     (1,550,615)
                                     2      289,271         239,067     (1,311,548)
                                     3      332,174         249,568     (1,061,981)
                                     4      369,026         252,050       (809,931)
                                     5      410,823         255,089       (554,842)
                                     6      453,405         255,935       (298,907)
                                     7      500,013         256,586        (42,321)
                                     8      547,391         255,362        213,041 payback
                                     9      596,515         252,980        466,021
                                   10       647,089         249,481        715,502
                          Net Present Value                 715,502

           Net Present Value                               $715,502
           Modified IRR                                      11.12%
Discounted Payback (years)   8.17
3
3
4
4
0
0


4
3
3
2
0
0


0
0
0
0
0


0
0
0
2
       3
       0
       0
       0

      31




                 1.03
                1.015




 Less       Project      Adj to      Cash
Taxes       Income      Income       Flow
(103,125)     271,875     (15,000)    256,875
(117,047)     308,578     (13,000)    295,578
(131,549)     346,811     (12,000)    334,811
(146,651)     386,625     (12,000)    374,625
(162,373)     428,074     (12,000)    416,074
(178,737)     471,215     (12,000)    459,215
(195,764)     516,105     (12,000)    504,105
                  (213,477)      562,802       (12,000)   550,802
                  (231,898)      611,369       (12,000)   599,369
                  (251,053)      661,868       (12,000)   649,868

de investment project, no terminal value was




roject Risk Factor:

                      1.00 (a)
                         1 (b)
                         1 (c)
                         1
        0.7
          4
        1.3
         6


   20.00%
   65.00%
   15.00%
  100.00%



 Coeff of
 Variation
(Rel Risk)
      0.218
      0.215
      0.135
      0.153
      0.130
      0.121
      0.106
      0.097
      0.086
      0.071
      0.121
            Capital Budgeting Analysis for
            Medical Services USA
    D       Southeastern Upgrades
Project Information

Project Description >    Upgrade to various Southeastern facilities
Project Benefits >       Better use of facility, more income
Project Location >       Atlanta
Responsible Division >                  Southeast
Responsible Department >                Engineering
Contact Person Name >                   Bob Ferrell
Estimated Project Start Date >                 02/05/92
Classification >                     4
Justification >                      C
Priority >                           3

Preliminary Review

Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.

Financial Attributes:
    F1      Project improves overall profitability of the company
    F2      Project lowers cost structure
    F3      Project will generate a rate of return
    F4      Project improves asset utilization
    F5      Other Financial Attribute __________________________________
    F6      Other Financial Attribute __________________________________

Operating Attributes:
   O1      Improves operating efficiencies
   O2      Increases the customer base
   O3      Improves overall customer service
   O4      Improves competitive position of company
   O5      Other Operating Attribute _________________________________
   O6      Other Operating Attribute _________________________________

Contingency Attributes:
   C1     Project has options that allow for change during life
   C2     Project will positively impact company even if value is negative
   C3     Project can be abandoned easily with some positive value
   C4     Project permits several options to maximize value
   C5     Other Cont Attribute _____________________________________

Miscellaneous Attributes:
   M1      Expands Human Resource Capital
   M2      Enhances workforce productivity
   M3      Project meets a critical regulatory, security or specific need
   M4      Project fits with company strategy and goals
   M5      Probability of project success is very high / low risk
   M6      Other Misc Attribute _____________________________________
   M7      Other Misc Attribute _____________________________________
   M8      Other Misc Attribute _____________________________________

                                                        Total Preliminary Points

Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.

Project Summary

Several facilities in the Southeast area need to upgrade existing scanner equipment to better serve customers
and produce higher quality analysis / treatments. The Atlanta Bank has agreed to finance $ 500,000 towards
the investment at 9% over a five year period. The loan repayment schedule is as follows:

Interest   Number of                         Loan          Interest        Principal        Total
Rate       Installments       Year          Balance        Payment         Payment         Payment
      0.09             5              1       500,000        (45,000)         (83,546)      (128,546)
                                      2       416,454        (37,481)         (91,065)      (128,546)
                                      3       325,388        (29,285)         (99,261)      (128,546)
                                      4       226,127        (20,351)       (108,195)       (128,546)
                                      5       117,932        (10,614)       (117,932)       (128,546)

Financial Analysis

           Proposed Project Expenditure:

           Total Upgrade Acquisition Price                                 1,650,000 (1)
           Installation / Training / Other Costs                              65,000
                           Total Investment                                1,715,000
           Financed through Bank                                            (500,000)
                           Net Cash Outlay                                 1,215,000
                           Project Analysis Required?                        Yes

           (1): $ 650,000 of this price is subject to capitalization. Depreciation deducted on the tax return
           differs from depreciation for accounting purposes:              Tax Return     Accounting
                                                               Year       Depreciation Depreciation
                                                                        1       325,000         65,000
                                                                        2       162,500         65,000
                                                                        3        81,250         65,000
                                                                        4        40,625         65,000
                                                                        5        40,625         65,000
                                                                        6                       65,000
                                                                        7                       65,000
                                                                        8                       65,000
                                                                        9                       65,000
                                                                       10                       65,000
                                                          Total                 650,000       650,000
         Cash Flow Analysis #1 - Only Project Cash Flows
                                        Service       Other      Depreciation      Taxable
            Year       Revenues          Costs         Costs      Deduction        Income
                   1      535,800        (112,000)      (38,000)    (325,000)         60,800
                   2      585,900        (155,100)      (46,500)    (162,500)        221,800
                   3      612,600        (188,600)      (54,100)     (81,250)        288,650
                   4      636,050        (202,900)      (63,200)     (40,625)        329,325
                   5      644,112        (224,200)      (68,900)     (40,625)        310,387
                   6      653,500        (241,600)      (72,110)                     339,790
                   7      668,200        (258,800)      (77,800)                     331,600
                   8      677,400        (272,100)      (83,100)                     322,200
                   9      689,800        (287,800)      (88,900)                     313,100
                  10      705,300        (298,400)      (94,200)                     312,700
                  11      712,900        (309,100)      (97,800)                     306,000
                  12      719,600        (319,400)     (101,050)                     299,150
                  13      722,800        (325,400)     (104,900)                     292,500
                  14      729,100        (329,900)     (107,800)                     291,400
                  15      734,300        (334,100)     (110,100)                     290,100

Economic Analysis #1
                                        Present
             Year       Cash Flow        Value       Payback
                    0 (1,215,000)      (1,215,000)
                    1      339,580        303,875     (911,125)
                    2      290,205        232,386     (678,739)
                    3      254,921        182,668     (496,071)
                    4      241,486        154,846     (341,225)
                    5      227,256        130,400     (210,825)
                    6      207,148        106,364     (104,461)
                    7      200,010         91,901      (12,560)
                    8      192,395         79,107       66,547        payback
                    9      185,098         68,104      134,651
                  10       184,408         60,716      195,367
                  11       179,050         52,754      248,120
                  12       173,284         45,686      293,807
                  13       167,963         39,627      333,434
                  14       166,665         35,187      368,621
                  15       165,223         31,214      399,835
         Net Present Value                399,835

         Required Rate of Return for Project =>                        11.75%
         Reinvestment Rate for Project =>                               4.50%

         Net Present Value                            $399,835
         Modified IRR                                    9.25%
         Discounted Payback (years)                        8.16


         Cash Flow Analysis #2 - Include Financing Flows / Discount Rate = Cost of Borrowing:
                                        Service        Other         Taxable          Less
            Year       Revenues          Costs         Costs         Income          Taxes
                   1      535,800        (112,000)      (38,000)       385,800       (106,095)
                     2     585,900        (155,100)       (46,500)         384,300      (105,683)
                     3     612,600        (188,600)       (54,100)         369,900      (101,723)
                     4     636,050        (202,900)       (63,200)         369,950      (101,736)
                     5     644,112        (224,200)       (68,900)         351,012       (96,528)
                     6     653,500        (241,600)       (72,110)         339,790       (93,442)
                     7     668,200        (258,800)       (77,800)         331,600       (91,190)
                     8     677,400        (272,100)       (83,100)         322,200       (88,605)
                     9     689,800        (287,800)       (88,900)         313,100       (86,103)
                    10     705,300        (298,400)       (94,200)         312,700       (85,993)
                    11     712,900        (309,100)       (97,800)         306,000       (84,150)
                    12     719,600        (319,400)      (101,050)         299,150       (82,266)
                    13     722,800        (325,400)      (104,900)         292,500       (80,438)
                    14     729,100        (329,900)      (107,800)         291,400       (80,135)
                    15     734,300        (334,100)      (110,100)         290,100       (79,778)

Economic Analysis #2
                                         Present
             Year       Cash Flow         Value        Payback
                    0 (1,215,000)       (1,215,000)
                    1      223,409         209,724     (1,005,276)
                    2      171,966         151,544       (853,731)
                    3      134,428         111,208       (742,523)
                    4      118,536          92,054       (650,469)
                    5      101,628          74,089       (576,380)
                    6      207,148         141,766       (434,614)
                    7      200,010         128,496       (306,118)
                    8      192,395         116,033       (190,085)
                    9      185,098         104,794        (85,291)
                  10       184,408          98,008         12,718 payback
                  11       179,050          89,332        102,050
                  12       173,284          81,159        183,209
                  13       167,963          73,849        257,058
                  14       166,665          68,790        325,848
                  15       165,223          64,017        389,865
         Net Present Value                 389,865

         After Tax Cost of Borrowing =>                                      6.53%
         Reinvestment Rate for Project =>                                    2.50%

         Net Present Value                              $389,865
         Modified IRR                                      6.38%
         Discounted Payback (years)                         10.87


Economic Assessment (based on Analysis #1)

         Project has positive Net Present Value?                     Yes
         Project has IRR in excess of cost?                          No
         Project has a positive payback?                             Yes

         Project must meet at least two of the three Economic Criteria, otherwise special
         approval is required.
Risk Analysis (based on analysis #1)

               Risk Premium Applied to Project                     2.25%

Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
          Probability of Accurate and Reliable Information - Gov't T Bond                         1.00
          Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)                                    1
          Exponential power to apply to Risk Ranking is 2 - (a)                                      1
          Risk Factor = (b) raised to the power (c)                                                  1

               Probability of Accurate and Reliable Information for Project                       0.65
               Risk Ranking assigned to project (1 to 10)                                            6
               Exponential power to apply to Project                                              1.35
               Risk Factor for Project                                                             11

Assign probabilities to three possible outcomes for project:
         P Pesimistic outlook, declining growth, slower volumes, etc.                          10.00%
        N Normal expected outlook as applied in analysis                                       70.00%
        O Optomistic outlook, better than expected growth                                      20.00%
                           Total should equal                100.00%                          100.00%

Enter Expected Cash Flows for different outcomes:

                                                                               Standard     Coeff of
                             Net Cash Flows                  Expected          Deviation    Variation
   Year          Pesimist       Normal      Optomist          Value           (Abs Risk)   (Rel Risk)
           1       321,100        339,580     361,200          342,056            30,106         0.088
           2       271,600        290,205     311,950          292,694            30,291         0.103
           3       237,200        254,921     276,705          257,506            29,762         0.116
           4       224,850        241,486     261,890          243,903            27,901         0.114
           5       211,800        227,256     248,605          229,980            27,951         0.122
           6       190,450        207,148     227,690          209,586            28,057         0.134
           7       184,100        200,010     220,280          202,473            27,325         0.135
           8       176,350        192,395     211,650          194,642            26,549         0.136
           9       169,150        185,098     204,880          187,459            26,935         0.144
          10       168,340        184,408     203,090          186,537            26,078         0.140
          11       163,100        179,050     197,450          181,135            25,763         0.142
          12       158,350        173,284     192,770          175,688            26,038         0.148
          13       153,300        167,963     185,200          169,944            23,958         0.141
          14       152,820        166,665     183,990          168,746            23,512         0.139
          15       152,650        165,223     183,690          167,659            23,671         0.141
Totals           2,935,160      3,174,689   3,471,040        3,210,006           403,897         0.126

                             Absolute Risk of Project (Std Deviation)                         403,897
                             Relative Risk of Project (Coeff of Variation)                      0.126


Revised Economic Analysis using Expected Values
                            Expected       Present      Recovery
                Year         Values         Value       Payback
                        0   (1,215,000)   (1,215,000)
                        1      342,056       306,090     (908,910)
                        2      292,694       234,379     (674,531)
                        3      257,506       184,520     (490,011)
                        4      243,903       156,396     (333,614)
                        5      229,980       131,963     (201,651)
                        6      209,586       107,616      (94,035)
                        7      202,473        93,032       (1,002)
                        8      194,642        80,030       79,028 payback
                        9      187,459        68,973      148,001
                      10       186,537        61,417      209,418
                      11       181,135        53,368      262,786
                      12       175,688        46,320      309,106
                      13       169,944        40,095      349,201
                      14       168,746        35,626      384,827
                      15       167,659        31,675      416,502
            Net Present Value                416,502

Net Present Value                          $416,502
Modified IRR                                  9.33%
Discounted Payback (years)                      8.01
2
2
4
5
0
0


5
1
2
3
0
0


0
1
1
0
0


0
2
0
2
                         2
                         0
                         0
                         0

                         32




better serve customers
 e $ 500,000 towards


              Tax Benefit
              of Interest
                   12,375
                   10,307
                    8,053
                    5,597
                    2,919




d on the tax return
                Tax Benefit
               Depreciation
                    89,375
                    44,688
                    22,344
                    11,172
                    11,172
 Less         Net     Add Back      Working       Cash
Taxes       Income   Depreciation   Capital       Flow
 (16,720)     44,080    325,000      (29,500)     339,580
 (60,995)    160,805    162,500      (33,100)     290,205
 (79,379)    209,271     81,250      (35,600)     254,921
 (90,564)    238,761     40,625      (37,900)     241,486
 (85,356)    225,031     40,625      (38,400)     227,256
 (93,442)    246,348                 (39,200)     207,148
 (91,190)    240,410                 (40,400)     200,010
 (88,605)    233,595                 (41,200)     192,395
 (86,103)    226,998                 (41,900)     185,098
 (85,993)    226,708                 (42,300)     184,408
 (84,150)    221,850                 (42,800)     179,050
 (82,266)    216,884                 (43,600)     173,284
 (80,438)    212,063                 (44,100)     167,963
 (80,135)    211,265                 (44,600)     166,665
 (79,778)    210,323                 (45,100)     165,223




   Net    Tax Benefit Tax Benefit     Loan       Working     Cash
Income    Depreciation Interest     Payment      Capital     Flow
  279,705     89,375      12,375     (128,546)    (29,500)   223,409
278,618   44,688   10,307   (128,546)   (33,100)   171,966
268,178   22,344    8,053   (128,546)   (35,600)   134,428
268,214   11,172    5,597   (128,546)   (37,900)   118,536
254,484   11,172    2,919   (128,546)   (38,400)   101,628
246,348                                 (39,200)   207,148
240,410                                 (40,400)   200,010
233,595                                 (41,200)   192,395
226,998                                 (41,900)   185,098
226,708                                 (42,300)   184,408
221,850                                 (42,800)   179,050
216,884                                 (43,600)   173,284
212,063                                 (44,100)   167,963
211,265                                 (44,600)   166,665
210,323                                 (45,100)   165,223
(a)
(b)
(c)
            Capital Budgeting Analysis for
            Medical Services USA
    E       Canadian Partnership
Project Information

Project Description > Expand Toronto Urban Centers
Project Benefits >     Market expansion, new source of revenues, leverage of assets
Project Location >     Toronto
Responsible Division >             Canadian Division
Responsible Department >           Marketing
Contact Person Name >              Allen J. Herbert
Estimated Project Start Date >           04/01/92
Classification >                 8
Justification >                  C
Priority >                       3

Preliminary Review

Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.

Financial Attributes:
    F1      Project improves overall profitability of the company
    F2      Project lowers cost structure
    F3      Project will generate a rate of return
    F4      Project improves asset utilization
    F5      Other Financial Attribute __________________________________
    F6      Other Financial Attribute __________________________________

Operating Attributes:
   O1      Improves operating efficiencies
   O2      Increases the customer base
   O3      Improves overall customer service
   O4      Improves competitive position of company
   O5      Other Operating Attribute _________________________________
   O6      Other Operating Attribute _________________________________

Contingency Attributes:
   C1     Project has options that allow for change during life
   C2     Project will positively impact company even if value is negative
   C3     Project can be abandoned easily with some positive value
   C4     Project permits several options to maximize value
   C5     Other Cont Attribute _____________________________________

Miscellaneous Attributes:
   M1      Expands Human Resource Capital
   M2      Enhances workforce productivity
   M3      Project meets a critical regulatory, security or specific need
   M4      Project fits with company strategy and goals
   M5          Probability of project success is very high / low risk
   M6          Other Misc Attribute _____________________________________
   M7          Other Misc Attribute _____________________________________
   M8          Other Misc Attribute _____________________________________

                                                       Total Preliminary Points

Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.

Project Summary

In order to establish a toehold position in the Toronto area, a joint venture investment will be
made since the current major provider in Toronto needs improved child care services for the
urban areas of Toronto. Medical Services USA will provide personnel and overall management
for urban child care. In return, Medical Services USA will share in the profits 50% / 50%. The Joint
Venture Agreement has a ten year term period.

Financial Analysis (all amounts are expressed in Canadian Dollars)
                                                           Convert
                                                           to U.S.$ *
Initial Relocation / Setup Costs                  $750,000          1.12              $840,000

Ten Year Projected Income Statement
                                                                                     Adj to
   Year          Sales       Cost of      Income           Less          Net         Cash
                (100%)       Service     before Tax       Taxes        Income        Flow
        1 **     637,500      270,000        367,500        79,500       288,000        42,000
           2     895,000      366,000        529,000       119,000       410,000        82,000
           3     912,000      377,000        535,000       101,000       434,000        55,000
           4     942,000      378,000        564,000       104,000       460,000        68,000
           5     977,000      370,000        607,000       112,000       495,000        88,000
           6   1,015,000      368,000        647,000       129,000       518,000        90,000
           7   1,045,000      362,000        683,000       140,000       543,000       110,000
           8   1,088,000      355,000        733,000       138,000       595,000       115,000
           9   1,135,000      350,000        785,000       151,000       634,000       122,000
         10    1,180,000      348,000        832,000       157,000       675,000       135,000


               * convert from Canadian Dollars to U.S. Dollars
               ** partial year in 1992

Economic Analysis (U.S. Dollars)

               Summarize Cash Outflows and Inflows for Project:
                                         Cash         Present
                           Year         Flows           Value         Payback
                                   0     (840,000)     (840,000)
                                   1      189,750       167,181        (672,819)
                                   2      290,280       225,333        (447,486)
                               3       295,845       202,338       (245,148)
                               4       316,800       190,898        (54,250)
                               5       341,055       181,069        126,819
                               6       355,680       166,374        293,193
                               7       382,005       157,434        450,626
                               8       415,350       150,816        601,442
                               9       442,260       141,486        742,929
                              10       473,850       133,562        876,491
                     Net Present Value               876,491

                     Required Rate of Return for Project =>                            13.50%
                     Reinvestment Rate for Project =>                                   3.50%

                     Net Present Value                                               $876,491
                     Modified IRR                                                      16.95%
                     Discounted Payback (years)                                           5.30

Economic Assessment

          Project has positive Net Present Value?               Yes
          Project has IRR in excess of cost?                    Yes
          Project has a positive payback?                       Yes

          Project must meet at least two of the three Economic Criteria, otherwise special
          approval is required.


Risk Analysis

          Risk Premium Applied to Project               4.00%

          Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
          Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
                    Probability of Accurate and Reliable Information - Gov't T Bond
                    Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
                    Exponential power to apply to Risk Ranking is 2 - (a)
                    Risk Factor = (b) raised to the power (c)

                     Probability of Accurate and Reliable Information for Project
                     Risk Ranking assigned to project (1 to 10)
                     Exponential power to apply to Project
                     Risk Factor for Project

          Assign probabilities to three possible outcomes for project:
                   P Pesimistic outlook, declining growth, slower volumes, etc.
                  N Normal expected outlook as applied in analysis
                  O Optomistic outlook, better than expected growth
                                     Total should equal              100.00%

          Enter Expected Cash Flows for different outcomes:

                                                                                    Standard
                                     Net Cash Flows               Expected       Deviation
            Year         Pesimist        Normal     Optomist       Value        (Abs Risk)
                    1      132,000         189,750   198,500        177,500          55,685
                    2      227,300         290,280   311,100        279,740          66,708
                    3      239,100         295,845   315,200        286,498          60,421
                    4      244,050         316,800   340,500        304,538          76,871
                    5      267,800         341,055   368,500        329,603          79,304
                    6      285,200         355,680   387,500        346,015          79,171
                    7      307,900         382,005   416,900        372,203          84,006
                    8      329,100         415,350   460,900        405,175        100,391
                    9      363,300         442,260   484,800        433,155          92,352
                   10      380,050         473,850   517,100        461,213        105,845
                         2,775,800       3,502,875 3,801,000      3,395,638        800,754

                        Absolute Risk of Project (Std Deviation)                   800,754
                        Relative Risk of Project (Coeff of Variation)                0.236


Revised Economic Analysis using Expected Values

                                       Expected       Present     Recovery
                           Year         Values         Value      Payback
                                  0      (840,000)    (840,000)
                                  1       177,500      156,388      (683,612)
                                  2       279,740      217,152      (466,461)
                                  3       286,498      195,945      (270,516)
                                  4       304,538      183,509       (87,007)
                                  5       329,603      174,989        87,982
                                  6       346,015      161,853       249,835
                                  7       372,203      153,394       403,228
                                  8       405,175      147,121       550,350
                                  9       433,155      138,574       688,923
                                 10       461,213      130,000       818,923
                        Net Present Value              818,923

         Net Present Value                            $818,923
         Modified IRR                                   16.58%
         Discounted Payback (years)                        5.50
3
2
4
4
0
0


1
4
4
3
0
0


0
2
0
0
0


0
0
0
3
                    2
                    0
                    0
                    0

                  32




50%. The Joint




           Estimated
              Cash        50%    Convert
               Flow      Share to U.S.$ *
               330,000   165,000      1.15   189,750
               492,000   246,000      1.18   290,280
               489,000   244,500      1.21   295,845
               528,000   264,000      1.20   316,800
               583,000   291,500      1.17   341,055
               608,000   304,000      1.17   355,680
               653,000   326,500      1.17   382,005
               710,000   355,000      1.17   415,350
               756,000   378,000      1.17   442,260
               810,000   405,000      1.17   473,850
Project Risk Factor:

                       1.00 (a)
                          1 (b)
                          1 (c)
                          1

                        0.6
                          6
                        1.4
                        12


                 25.00%
                 50.00%
                 25.00%
                100.00%



               Coeff of
 Variation
(Rel Risk)
     0.314
     0.238
     0.211
     0.252
     0.241
     0.229
     0.226
     0.248
     0.213
     0.229
     0.236
                  Capital Budgeting Analysis for
                  Medical Services USA
       F          Regulatory Compliance NE
Project Information

Project Description >         Regulatory Compliance in NE
Project Benefits >            Compliance
Project Location >            Northeast Regional Office - Boston, MA
Responsible Division >                     Finance
Responsible Department >                   Finance
Contact Person Name >                      Carl Jackson, V.P. Finance
Estimated Project Start Date >                01/01/92
Classification >                         9
Justification >                         E
Priority >                               2


Preliminary Review

Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.

Financial Attributes:
      F1          Project improves overall profitability of the company
      F2          Project lowers cost structure
      F3          Project will generate a rate of return
      F4          Project improves asset utilization
      F5          Other Financial Attribute __________________________________
      F6          Other Financial Attribute __________________________________

Operating Attributes:
     O1          Improves operating efficiencies
     O2          Increases the customer base
     O3          Improves overall customer service
     O4          Improves competitive position of company
     O5          Other Operating Attribute _________________________________
     O6          Other Operating Attribute _________________________________

Contingency Attributes:
      C1         Project has options that allow for change during life
      C2         Project will positively impact company even if value is negative
      C3         Project can be abandoned easily with some positive value
      C4         Project permits several options to maximize value
      C5         Other Cont Attribute _____________________________________

Miscellaneous Attributes:
      M1        Expands Human Resource Capital
      M2        Enhances workforce productivity
      M3        Project meets a critical regulatory, security or specific need
                   M4           Project fits with company strategy and goals
                   M5           Probability of project success is very high / low risk
                   M6           Other Misc Attribute _____________________________________
                   M7           Other Misc Attribute _____________________________________
                   M8           Other Misc Attribute _____________________________________

                                                                       Total Preliminary Points

             Projects with point totals less than 15 may represent poor investments and require additional
             approval before further analysis and processing. Projects with point totals between 15 and 20
             require caution and careful analysis. Projects with point totals greater than 20 may proceed
             with analysis and submission.

             Project Summary

             A major regulatory change is expected to change certain services in the Northeastern United States.
             In order to meet this new mandate, an investment is required in field personnel, training, and
             equipment. Revenues from the new services are also forecasted based on demand in California
             which adopted this regulatory change two years ago. The regulatory change is subject to future
             modification and therefore, the project is only projected over two years on a month to month basis.
             There is no initial investment required for this project.

             Economic Analysis (Cash Flows by Month)

                                 Monthly
                                 Period       Setup       Service         Misc /       Total       Net Cash
                  Date          Revenues      Costs        Costs          Taxes       Outflows       Flow

         1        31-Jan-92         35,200     -16,000        -3,500         -2,500      -22,000      13,200
         2        28-Feb-92         39,400      -5,000        -3,500         -2,000      -10,500      28,900
         3        31-Mar-92         41,000      -3,500        -3,500         -2,000       -9,000      32,000
         4         30-Apr-92        42,550      -1,500        -4,000         -1,750       -7,250      35,300
         5        31-May-92         43,990      -1,500        -4,000         -1,750       -7,250      36,740
         6        30-Jun-92         44,550      -2,000        -4,000         -1,750       -7,750      36,800
         7          31-Jul-92       45,100                    -4,500         -1,650       -6,150      38,950
         8        31-Aug-92         46,990                    -4,500         -1,650       -6,150      40,840
         9        30-Sep-92         47,800                    -4,500         -1,650       -6,150      41,650
        10         31-Oct-92        48,650                    -5,100         -1,500       -6,600      42,050
        11        30-Nov-92         49,280                    -5,100         -1,500       -6,600      42,680
        12        31-Dec-92         48,300                    -5,100         -1,500       -6,600      41,700
1992 Total                         532,810                                              -102,000
        13        31-Jan-93         47,100     -10,000        -5,800         -1,350      -17,150      29,950
        14        28-Feb-93         45,500      -2,000        -5,800         -1,350       -9,150      36,350
        15        31-Mar-93         44,100                    -5,800         -1,350       -7,150      36,950
        16         30-Apr-93        42,400                    -6,200         -1,275       -7,475      34,925
        17        31-May-93         41,000                    -6,200         -1,275       -7,475      33,525
        18        30-Jun-93         39,100                    -6,200         -1,275       -7,475      31,625
        19          31-Jul-93       38,500                    -6,750         -1,205       -7,955      30,545
        20        31-Aug-93         37,900                    -6,750         -1,205       -7,955      29,945
        21        30-Sep-93         37,100                    -6,750         -1,205       -7,955      29,145
        22         31-Oct-93        36,800                    -7,000         -1,170       -8,170      28,630
        23        30-Nov-93         36,400                    -7,000         -1,170       -8,170      28,230
        24        31-Dec-93       36,000          -5,000       -7,000        -1,170      -13,170           22,830
1993 Total                       481,900                                                -109,250
Total                          1,014,710                                                -211,250

                                                                                                     Annual
                                            Required Rate of Return for Project =>                     6.50%

                                            Net Present Value
                                            Rate of Return (IRR Annual Basis)
                                            Discounted Payback                                     Immediate


             Economic Assessment

                              Project has positive Net Present Value?                 Yes
                              Project has IRR in excess of cost?                      Yes
                              Project has a positive payback?                         Yes

                              Project must meet at least two of the three Economic Criteria, otherwise special
                              approval is required.


             Risk Analysis

                              Risk Premium Applied to Project                0.00% (Required for Compliance)

                              Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
                              Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
                                         Probability of Accurate and Reliable Information - Gov't T Bond
                                         Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
                                         Exponential power to apply to Risk Ranking is 2 - (a)
                                         Risk Factor = (b) raised to the power (c)

                                            Probability of Accurate and Reliable Information for Project
                                            Risk Ranking assigned to project (1 to 10)
                                            Exponential power to apply to Project
                                            Risk Factor for Project

                              Assign probabilities to three possible outcomes for project:
                                        P Pesimistic outlook, declining growth, slower volumes, etc.
                                        N Normal expected outlook as applied in analysis
                                        O Optomistic outlook, better than expected growth
                                                          Total should equal           100.00%

                              Enter Expected Cash Flows for different outcomes:

                                                                                                    Standard
                                                       Net Cash Flows                  Expected     Deviation
                                Month         Pesimist     Normal     Optomist          Value      (Abs Risk)
                                        1       12,050      13,129      13,700           13,081         1,200
                                        2       26,200      28,589      29,900           28,493         2,684
                                        3       28,830      31,486      32,920           31,374         2,971
                       4       31,390        34,545      36,050       34,373    3,417
                       5       32,710        35,761      37,430       35,637    3,425
                       6       32,600        35,626      37,250       35,497    3,379
                       7       34,170        37,505      39,250       37,354    3,699
                       8       35,870        39,113      40,900       38,984    3,648
                       9       36,275        39,673      41,470       39,523    3,780
                      10       36,510        39,839      41,680       39,708    3,748
                      11       36,810        40,218      42,050       40,073    3,808
                      12       35,860        39,083      40,920       38,967    3,660
Annual Sub Total                                                     413,063
                      13       25,620        27,919      29,200       27,830    2,594
                      14       30,850        33,702      35,240       33,582    3,189
                      15       31,170        34,074      35,630       33,950    3,242
                      16       29,350        32,033      33,510       31,926    3,017
                      17       27,960        30,583      31,920       30,457    2,889
                      18       26,300        28,695      30,010       28,599    2,691
                      19       25,120        27,565      28,850       27,456    2,715
                      20       24,470        26,878      28,140       26,769    2,672
                      21       23,690        26,019      27,300       25,926    2,619
                      22       23,150        25,422      26,700       25,337    2,570
                      23       22,660        24,932      26,200       24,845    2,565
                      24       18,230        20,054      21,100       19,990    2,075
Annual Sub Total                                                     336,665
                              687,845       752,443     787,320      749,729   72,259

                           Absolute Risk of Project (Std Deviation)            72,259
                           Relative Risk of Project (Coeff of Variation)        0.096


Revised Economic Analysis using Expected Values

                                           Expected    Present
                              Dates         Values      Value
                                       1     13,129      13,058
                                       2     28,589      28,282
                                       3     31,486      30,979
                                       4     34,545      33,807
                                       5     35,761      34,808
                                       6     35,626      34,490
                                       7     37,505      36,113
                                       8     39,113      37,458
                                       9     39,673      37,791
                                      10     39,839      37,744
                                      11     40,218      37,898
                                      12     39,083      36,629
                                      13     27,919      26,025
                                      14     33,702      31,247
                                      15     34,074      31,422
                                      16     32,033      29,381
                                      17     30,583      27,900
                                      18     28,695      26,036
                                      19     27,565      24,876
                    20      26,878       24,126
                    21      26,019       23,229
                    22      25,422       22,573
                    23      24,932       22,019
                    24      20,054       17,615
           Net Present Value            705,507

Net Present Value                                 $705,507
Rate of Return (IRR Annual Basis)                  298.86%
Discounted Payback                   Immediate            0
2
3
4
3
0
0


2
3
3
2
0
0


3
1
0
0
0


0
0
5
                            2
                            1
                            0
                            0
                            0

                           34




rn United States.

in California

o month basis.




                    Present        Present
                     Value          Value
                 (simple calc)   (functional)
                        13,129        13,129
                        28,589        28,590
                        31,486        31,488
                        34,545        34,551
                        35,761        35,771
                        35,626        35,642
                        37,505        37,527
                        39,113        39,144
                        39,673        39,714
                        39,839        39,889
                        40,218        40,280
                        39,083        39,155

                       27,919        27,980
                       33,702        33,788
                       34,074        34,173
                       32,033        32,140
                       30,583        30,698
                       28,695        28,815
                       27,565        27,695
                       26,878        27,018
                       26,019        26,168
                       25,422        25,582
                       24,932        25,103
                       20,054            20,204

                     752,443            754,244

                  Monthly
                      0.54%                       Calculate IRR (annual basis):

                      752,443                       Annual        Annual
                        419%                        Outflow       Inflow
                            0
                                                     -102,000      532,810
                                                     -109,250      481,900




 rwise special




 Compliance)

k) to Project Risk Factor:

                             1.00 (a)
                                1 (b)
                                1 (c)
                                1

                             0.75
                                4
                             1.25
                               6


                      15.00%
                      65.00%
                      20.00%
                     100.00%



                  Coeff of          Adjusted       Adjusted
                  Variation          Inflows       Outflows
                 (Rel Risk)
                        0.092
                        0.094
                        0.095
0.099
0.096
0.095
0.099
0.094
0.096
0.094
0.095
0.094

0.093
0.095
0.095
0.095
0.095
0.094
0.099
0.100
0.101
0.101
0.103
0.104

0.096
Calculate IRR (annual basis):

  Annual        Annual
  Outflow       Inflow

   -102,000      413,063
   -109,250      336,665
                           Capital Budgeting Analysis for
                           Medical Services USA
              Summarize Economic and Risk Analysis for All Projects

                Project                                         Required      Preliminary    Justification   Priority
                 Ref                 Project Name              Investment       Points          Code          Code

                   A       Diesel Generation System               $182,080              27              F               2
                   B       New Clinic in Kansas City              $141,000              24              C               3
                   C       Upgrade to DuBois Center             $1,780,000              31              C               3
                   D       Southeastern Upgrades                $1,215,000              32              C               3
                   E       Expand Toronto Urban Centers           $840,000              32              C               3
                   F       Regulatory Compliance in NE                  $0              34              E               2

              * Provide additional narrative information on "strategic" reasons for making this investment since the return is less th


              Using Solver for Program Constraints

              Financial Modeling Textbooks provide useful examples of how Excel Solver can be used to solve for capital budgeti
              set of constraints. The following example will illustrate how we could apply Solver for finding the right set of projects

              Example:
              Objective: Maximize Net Present Value of Projects
              Contraints: Year 1: Only $ 200,000 can be spent on all capital projects
                          Year 2: Only $ 150,000 can be spent on all capital projects
                          Year 3: Only $ 120,000 can be spent on all capital projects
                          Year 4: Only $ 100,000 can be spent on all capital projects
                          Year 5: Only $ 75,000 can be spent on all capital projects

              Five Projects require investments over five years and have the following Net Present Values:

                Select?
Project       0 = No                                                         < - - - - - Five Year Capital Budgets for Each Project - -
 Ref          1 = Yes                Project Name                    NPV         Year 1          Year 2       Year 3

          A        1       Annual Marketing Program                650,000         45,000         40,000       38,000
          B        0       IT Infrastructure Development           820,000         55,000         60,000       60,000
          C        1       Executive Leadership                    540,000         25,000         20,000       20,000
          D        1       HR Capital Improvement                  701,000         35,000         30,000       30,000
          E        0       Product Research                        490,000         50,000         45,000       42,000
                           Total (SumProduct)                    1,806,385         99,051         85,282       83,672
                           Maximum Allowed Budget                                 200,000        150,000      120,000

              We will enter the following constraints into Solver:

              $ 45,000 A + $ 55,000 B + $ 25,000 C + $ 35,000 D + $ 50,000 E .LE. $ 200,000
              $ 40,000 A + $ 60,000 B + $ 20,000 C + $ 30,000 D + $ 45,000 E .LE. $ 150,000
              $ 38,000 A + $ 60,000 B + $ 20,000 C + $ 30,000 D + $ 42,000 E .LE. $ 120,000
              $ 35,000 A + $ 58,000 B + $ 18,000 C + $ 28,000 D + $ 40,000 E .LE. $ 100,000
$ 35,000 A + $ 55,000 B + $ 17,000 C + $ 27,000 D + $ 40,000 E .LE. $ 75,000

Each of the above constraints recognizes that we can spend no more than what is budgeted each year. We also
have the equation we are trying to solve for:

Maximize NPV = $ 650,000 A + $ 820,000 B + $ 540,000 C + $ 701,000 D + $ 490,000 E

We will also use as our variables "0" for No and "1" for Yes as to which projects we should select given the above
constraints and equation. The "maximum" NPV will show up in our "set" cell which is cell D43.

Now go to the main toolbar, select Tools -> Solver and enter the following:

1. Target Cell is D43
2. Equal to: Select the Max button since we are solving for maximum values.
3. By Changing Cells: Select the range B38:B42 as our variables.
4. Subject to Constraints: Add two contraints as follows:
             B38:B42 .EQ. Binary                  EQ or = (equal)
             E43:I43 .LE. E44:I44                 LE or <= (less than or equal to)
5. Click on Solve. The Find Solution dialog box may pop up. Click on Answer. Solver will change the variables
(which we first entered all as zero's in cells B38:B42) and produce a report (Answer Report 1)

Using Excel Solver, we would select Projects A, C, and D!
                                   9.50% <= weighted average cost of capital
                                         rate of return is less than weighted average cost of capital *
                                            (years)
                 Project        Rate of    Payback           Risk        Relative     Absolute
                 Value          Return      Period          Factor         Risk         Risk

                 $34,761          10.07%             6.6            9.5         0.52     $164,674
                  $4,127           9.68%            19.0           18.5         1.26     $540,660
                $715,502          11.12%             8.2            6.1         0.12     $531,419
                $416,502           9.33%             8.0           11.2         0.13     $403,897
                $818,923          16.58%             5.5           12.3         0.24     $800,754
                $705,507         298.86%             0.0            5.7         0.10      $72,259

ent since the return is less than the cost of investments (cost of capital).




d to solve for capital budgeting program decisions given a
ding the right set of projects given a set of contraints:




Budgets for Each Project - - - - - >
               Year 4           Year 5

                    35,000         35,000
                    58,000         55,000
                    18,000         17,000
                    28,000         27,000
                    40,000         40,000
                    77,154         75,000
                   100,000         75,000



              LE: Less than or Equal to
eted each year. We also




uld select given the above




l change the variables
Microsoft Excel 9.0 Answer Report
Worksheet: [CBAnalysis.xls]Summary
Report Created: 2/26/2003 9:58:29 AM


Target Cell (Max)
    Cell          Name                 Original Value     Final Value
  $D$43 Total (SumProduct) NPV                       0        1,806,385


Adjustable Cells
    Cell          Name                 Original Value     Final Value
  $B$38 A 1 = Yes                                    0                  1
  $B$39 B 1 = Yes                                    0                  0
  $B$40 C 1 = Yes                                    0                  1
  $B$41 D 1 = Yes                                    0                  1
  $B$42 E 1 = Yes                                    0                  0


Constraints
    Cell          Name                   Cell Value          Formula           Status        Slack
  $E$43 Total (SumProduct) Year 1               99,051   $E$43<=$E$44       Not Binding   100948.6953
  $F$43 Total (SumProduct) Year 2               85,282   $F$43<=$F$44       Not Binding    64717.9446
  $G$43 Total (SumProduct) Year 3               83,672   $G$43<=$G$44       Not Binding   36328.20554
  $H$43 Total (SumProduct) Year 4               77,154   $H$43<=$H$44       Not Binding   22846.15817
  $I$43 Total (SumProduct) Year 5               75,000   $I$43<=$I$44       Binding                 0
  $B$38 A 1 = Yes                                    1   $B$38=binary       Binding                 0
  $B$39 B 1 = Yes                                    0   $B$39=binary       Binding                 0
  $B$40 C 1 = Yes                                    1   $B$40=binary       Binding                 0
  $B$41 D 1 = Yes                                    1   $B$41=binary       Binding                 0
  $B$42 E 1 = Yes                                    0   $B$42=binary       Binding                 0

				