PROGRESS SCHEDULE CHART EXAMPLE
PROJECT NO: 12345.3.2
TIME PERCENT 90 % TIME (WORK OR AVAILABLE DAYS) 0 0 0 0 0 60 65 60 40 65 60 100 100 40 100 50 % 20 50 0 0 Begin Trout Morat. 11-15-05 0 Date of Availability 4-4-05 70 100 End Trout Morat. 4-15-06 ICT#2 Completion Date10-31-06 ICT#1 Completion Date 12-2-05 15 15 50 100 85 100 30 % 100
CONTRACTOR’S SIGNATURE
COUNTY: Buncombe
CONTRACTOR: ABC Contracting
DATE: 2/2/05
100 %
STATE CONSTRUCTION ENGINEER
BID ITEM & PRORATA PERCENT OF TOTAL BID
80 %
Mob, Tr.Co. 9% Grading 22% Drainage, C&G 11% Paving 28% Signs, Markings 5% Culvert 4% Signals 7% Seeding, E.C. 9% Utilities 5%
100
70 % PROGRESS PERCENT (CURVE)
60 %
20
100 40 %
0
Completion Date12-31-06
20 %
10 %
TIME CALENDAR DAYS
0%
16.5%
31.0%
49.4%
51.9%
68.4%
92.6%
99.4%
100%
30
60
90
120
150
180
210
240
270
300
330
360
390
420
450
480
510
540
570
600
630
635
RESIDENT ENGINEER