					Enterprise Intelligence System (EIS) Project – Stage Plan



                                 Worcestershire ICT Services
     Enterprise Intelligence System (EIS) Project

   Stage Plan – Stage 0 (Technical Installations)
                                          (Draft)

Purpose of this document
It is important that work commences on a stage only when the Project Board says it should; this avoids
the problems of projects continuing just because no one thinks to stop them.
To enable this to happen the project should be broken down into manageable sections (stages), at the
end of which the Project Board has to approve whether work is to continue or not.

The Stage Plan will include the following:
 identifies all the products which the stage must produce
 provides a statement of how and when a stage’s objectives are to be achieved, by showing the
   deliverables, activities and resources required
 identifies the stage’s control and reporting points and frequencies
 provides a baseline against which stage progress will be measured
 records the stage tolerances
 specifies the quality controls for the stage and identifies the resources needed for them.

The document should be assessed against the following quality criteria:
 is the plan achievable?
 do any Team Managers involved in its operation believe that their portion is achievable?
 does it support the Project Plan?
 does it take into account any constraints of time, resources and budget?
 has it been taken down to the level of detail necessary to ensure that any deviations will be
   recognised in time to react appropriately?
 has it been developed according to the planning standard?
 does the Stage Plan contain activities and resource effort to review the Issue Log?


Version History.

     Version        Issue & Circulation Date                    Brief Summary of Change
                   th
01                8 July 2005
                     th
02                13 July 2005                     Additional information relating to stages




                                                   Worcestershire Health ICT Services
                                                   Worcester Royal Hospital
                                                   Charles Hastings Way
                                                   Worcester WR5 1DD
                                                      th
Date of Issue                                      14 July
Reference                                          eis_pid_v02_app_14.doc




Produced by: Chris Greening                                             (<Date>) (<Version X>)

                                               i
Enterprise Intelligence System (EIS) Project – Stage Plan


Contents

1.      Plan Description .................................................................................... 3
2.      Quality Plan ............................................................................................ 4
3.      Plan Prerequisites / Dependencies & Assumptions ......................... 6
4.      Tolerances .............................................................................................. 7
5.      Controls & Reporting ............................................................................ 7
6.      Activity Plan ........................................................................................... 7
7.      Resource Requirements ....................................................................... 7
   7.1    Manpower ............................................................................................. 7
   7.2    Financial ............................................................................................... 7
8.      Management of Risk .............................................................................. 7
9.      Stage 1 (ClearNet / SUS / PbR Info. Capture) (outline delivery 26 Sep –
31 Oct) 7
10.     Stage 2 (Comm. & MH PAS Info. Capture) (outline delivery 26 Sep – 31
Oct) 9
11.     Appendix 1 – Data Server Specification ........................................... 11
12.     Appendix 2 – Web Server Specification ........................................... 11
13.     Appendix 3 – Client PC Specification ............................................... 12




Produced by: Chris Greening                                                            (<Date>) (<Version X>)

                                                          ii
Enterprise Intelligence System (EIS) Project – Stage Plan




1. Plan Description
This next stage plan follows on from Initiation of the project and covers the generic stage called
Stage 0 - Technical Installations.
    Stage 0 – Technical Installations (outline delivery Aug 05)
        Stage 0a – Establish hardware requirements
        Stage 0b – Hardware procurement
        Stage 0c – Software installation
Where possible, it is recommended that some of Stage 1 planning and deliverables are also
considered due to the training elements included in that stage. Stage 1 includes the following
deliverables:
    Stage 1 – ClearNet / SUS / PbR Information capture. (outline delivery Oct 05)
        Stage 1a – Confirmation of anticipated users
        Stage 1b – Confirmation of customer quality expectations
        Stage 1c – Key technical post training
        Stage 1d - End User Training
        Stage 1e - Replication of existing ClearNet (or Secondary User Services – SUS when
        available) extracts (e.g. waiting list, inpatient, outpatient).
        Stage 1f – Creation of PbR reports
        Stage 1g – Data Quality & Reporting Sign off
However, focus will be concentrated on Stage 0 as:
       it constitutes a pre-requisite to all other stages.
       Requires considerable input from IT Operations which are experiencing resource
        pressures in other system critical areas. Board members are reminded that this project is
        a Priority 5 (‘LHC wide non clinical improvement’) project (scale 1 highest – 7) and is
        currently requesting resources against two priority 1 projects (Choose & Book, and
        Community & Mental Health PAS replacement) and three priority 2 projects (Pathology
        system replacement, A&E system replacement, Acute PAS electronic duplicates removal).
       The stage will take place over the main summer holiday period and therefore has to
        accept that it will take longer to achieve than normally expected due to staff annual leave
        absences. This includes the project manager (NHS).
For these reasons the stage is focussed on the three clear deliverables listed above. However, it
is Stage 0 that requires the most significant IT Operations technical input, after which the
emphasis shifts significantly to the Information and Financial Directorates / Departments across
the county.




Produced by: Chris Greening                                       (<Date>) (<Version X>)

                                                 3
Enterprise Intelligence System (EIS) Project – Stage Plan



2. Quality Plan
Stage 0 includes the following main deliverables

Stage 0a – Establish hardware requirements
        Servers
               Direct
                      Data Warehouse Server
                             Requirements established prior to project start up
                             Quality verified via IT Operations
                      Web Server (established)
                             Requirements established via Ardentia (Appendix 2)
                             Quality verified via IT Operations
              Indirect
                      ‘Tumbleweed’ Community & Mental Health PAS data feed
        Desktops
              Standard User (type established)
                             Type of PC required established via Ardentia (Appendix 3)
                             Quality to be verified via checklist sent to identified users of the
                             system and followed up if necessary by Project Manager and IT
                             Operations.
                             Replacement of equipment when not to specification via county
                             Rolling Replacement Programme via Block Capital allocation of
                             relevant organisation. If funds unavailable then case made to
                             organisation to release further funding.
              ‘Power’ User
                             Type of PC required to be established via Ardentia (Appendix 3)
                             Quality to be verified via checklist sent to identified users of the
                             system and followed up if necessary by Project Manager and IT
                             Operations.
                             Replacement of equipment when not to specification via county
                             Rolling Replacement Programme via Block Capital allocation of
                             relevant organisation. If funds unavailable then case made to
                             organisation to release further funding.
        WAN Connectivity
              Quality to be verified via checklist sent to identified users of the system and
              followed up if necessary by Project Manager and IT Operations. Metric for
              performance to be considered.
              Upgrade of connection if not to required performance to be discussed . If funds
              unavailable then case made to organisation to release further funding.
        LAN Connectivity
              Quality to be verified via checklist sent to identified users of the system and
              followed up if necessary by Project Manager and IT Operations. Metric for
              performance to be considered.
              Upgrade of connection if not to required performance to be discussed . If funds
              unavailable then case made to organisation to release further funding.




Produced by: Chris Greening                                    (<Date>) (<Version X>)

                                                 4
Enterprise Intelligence System (EIS) Project – Stage Plan




Stage 0b – Hardware Procurement& Installation
        Hardware Procurement
        Servers
               Direct
                      Data Warehouse Server (procured)
                              Quality to be verified by IT Operations against ordered specification.
                              Server to be tested (General system functioning) by IT Operations
                              within contract time scale.
                      Web Server (procured)
                              Quality to be verified by IT Operations against ordered specification.
                              Server to be tested (General system functioning) by IT Operations
                              within contract time scale.
              Indirect
                      ‘Tumbleweed’ Community & Mental Health PAS data feed. To be verified
                      by Community & MH PAS Project as deliverable.
        Desktops
              Standard User
                      Quality to be verified by IT Operations against ordered specification.
                      PC to be tested (General system functioning) by IT Operations within
                      contract time scale.
              ‘Power’ User
                      Quality to be verified by IT Operations against ordered specification.
                      PC to be tested (General system functioning) by IT Operations within
                      contract time scale.
        WAN Connectivity
              If upgrade to WAN considered necessary quality to be verified by IT Operations
              against ordered specification.
              Connection to be tested (General system functioning) by IT Operations within
              contract time scale.
        LAN Connectivity
              If upgrade to WAN considered necessary quality to be verified by IT Operations
              against ordered specification.
              Connection to be tested (General system functioning) by IT Operations within
              contract time scale.




Produced by: Chris Greening                                      (<Date>) (<Version X>)

                                                 5
Enterprise Intelligence System (EIS) Project – Stage Plan




Stage 0c – Software installation
        Server Base Software
               Data Warehouse Server
                      Quality of base software load to be verified by Ardentia.
                      Discrepancies to be managed through EIS project manager in consultation
                      with Ardentia and IT Operations Project Management.
               Web Server
                      Quality of base software load to be verified by Ardentia.
                      Discrepancies to be managed through EIS project manager in consultation
                      with Ardentia and IT Operations Project Management.
        Cassius Software
               Data Warehouse Server
                      Quality of base software load to be verified by Ardentia.
               Web Server
                      Quality of base software load to be verified by Ardentia.
        Tumbleweed Data Feed
               Quality of base software load to be verified by Ardentia in consultation with
               Community & Mental Health Information Manager.
        Desktop
               Standard User
                      Microsoft Internet Explorer 6 (ie6)
                             Quality to be verified via checklist sent to identified users of the
                             system and followed up if necessary by Project Manager and IT
                             Operations.
                      MS Office 2003
                             Quality to be verified via checklist sent to identified users of the
                             system and followed up if necessary by Project Manager and IT
                             Operations.
                ‘Power’ User
                      Microsoft Internet Explorer 6 (ie6)
                             Quality to be verified via checklist sent to identified users of the
                             system and followed up if necessary by Project Manager and IT
                             Operations.
                      MS Office 2003
                             Quality to be verified via checklist sent to identified users of the
                             system and followed up if necessary by Project Manager and IT
                             Operations.



3. Plan Prerequisites / Dependencies & Assumptions
<include any fundamental aspects which must be in place at the start of the stage, and which
must remain in place for the plan to succeed>




Produced by: Chris Greening                                    (<Date>) (<Version X>)

                                                 6
Enterprise Intelligence System (EIS) Project – Stage Plan


4. Tolerances
<tbd>



5. Controls & Reporting
As per PID

6. Activity Plan
As per Project Summary Spreadsheet

7. Resource Requirements

    7.1      Manpower
    <tbd>

    7.2      Financial
    <tbd>

8. Management of Risk
As per PID and Project Summary Spreadsheet

9. Stage 1 (ClearNet / SUS / PbR Info. Capture) (outline delivery 26 Sep – 31 Oct)
        Stage 1a – Confirmation of anticipated users
          Ref                         Task                               Responsible            Time
                                                                                                scale
                 Prepare access level lists (i.e. who gets
          1a1                                                       (NHS) Project Manager
                 access to what)
                 Prepare user list form – to incl name, tel, e-
          1a2    mail, org, level of access to system, what         (NHS) Project Manager
                 areas
                 Identify Organisational Lead to act as user list
          1a3                                                       (NHS) Project Manager
                 preparer (PCT to incl. GPs)
                 Identify specialist leads (e.g. pathology, A&E)
          1a4                                                       (NHS) Project Manager
                 to act as user list preparer
          1a5    Seek lists from contacts                           (NHS) Project Manager
                 Newsletter – incl. section on gaining user list
          1a6                                                       (NHS) Project Manager
                 and feedback section for mop up.
          1a7    Prioritise list if exceed licences                 (NHS) Project Manager
                 Confirm access list to users + organisational
          1a8                                                       (NHS) Project Manager
                 leads + specialist leads
                 Provide list to EIS Administrators to enter on
          1a9                                                       (NHS) Project Manager
                 system
          1a10   User list placed on system                         EIS Administrators
          1a11   Project Implementation Team Meeting                (NHS) Project Manager




Produced by: Chris Greening                                            (<Date>) (<Version X>)

                                                   7
Enterprise Intelligence System (EIS) Project – Stage Plan



        Stage 1b – Confirmation of Customer Quality Expectations
         Ref                         Task                             Responsible              Time
                                                                                               scale
         1b1     CQE form created                                (NHS) Project Manager
         1b2     CQE form distributed                            (NHS) Project Manager
                 Workshops planned (all invited):
                 General
                 Information Management + KPI
         1b3                                                     (NHS) Project Manager
                 Contracting & Commissioning
                 Payment by Results
                 Specialist areas (?)
         1b3     CQE form presented @ workshops                  (NHS) Project Manager
         1b4     CQE forms returned, analysed, grouped           (NHS) Project Manager
                                                                                               th
         1b5     Project Board – to incl. CQE presentation       (NHS) Project Manager        12 Oct


        Stage 1c – Key technical post training
         Ref                         Task                             Responsible              Time
                                                                                               scale
         1c1     Administrator Role identified                   Worcs Dir. ICT Services
         1c2     Developer Roles identified                      (NHS) Project Manager
         1c3     Available training dates gained from Ardentia   (Ardentia) Project Manager
         1c4     Dates confirmed with Admin and Dev roles        (NHS) Project Manager
         1c5     EIS Administrator Training                      Ardentia Training
         1c6     Developer Training                              Ardentia Training


        Stage 1d - End User Training
         Ref                         Task                             Responsible              Time
                                                                                               scale
         1d1     End Users confirmed via stage 1a                (NHS) Project Manager
         1d2     Available training dates gained from Ardentia   (Ardentia) Project Manage
         1d3     Dates confirmed with End User roles             (NHS) Project Manager
         1d4     End User Training                               Ardentia Training


        Stage 1e - Replication of existing ClearNet (or Secondary User Services – SUS when
        available) extracts (e.g. waiting list, inpatient, outpatient).
         Ref                         Task                             Responsible              Time
                                                                                               scale
                 Information in existing systems (e.g. HPS) to
         1e1                                                     (NHS) Project Manager
                 be replicated identified
         1e2     Structures developed by EIS Developers          (NHS) Project Manager
         1e3     Information populated by EIS Administrators     (NHS) Project Manager
         1e4     Information validated by respective leads       (NHS) Project Manager




Produced by: Chris Greening                                         (<Date>) (<Version X>)

                                                 8
Enterprise Intelligence System (EIS) Project – Stage Plan


        Stage 1f – Creation of PbR reports
         Ref                          Task                               Responsible              Time
                                                                                                  scale
         1f1     PbR module loaded into EIS                         (Ardentia) Project Manager
                 PbR module populated (assumed exists from
         1f2     stage 1e, however local costs may be wished        (NHS) Project Manager
                 to be uploaded? - tbc) by EIS Administrators
         1f3     PbR reports validated by PbR Leads                 (NHS) Project Manager


        Stage 1g – Data Quality & Reporting Sign off
         Ref                          Task                               Responsible              Time
                                                                                                  scale
                 Data Quality Reports and Reporting
         1g1                                                        (NHS) Project Manager
                 functionality signed off by Leads
                 Data Quality Reports and Reporting
         1g1                                                        (NHS) Project Manager        10th Nov
                 functionality signed off by Project Board

10.     Stage 2 (Comm. & MH PAS Info. Capture) (outline delivery 26 Sep – 31 Oct)
        Stage 2a – Confirmation of anticipated users
         Ref                          Task                               Responsible              Time
                                                                                                  scale
                 Prepare access level lists (i.e. who gets
         1a1                                                        (NHS) Project Manager
                 access to what)
                 Prepare user list form – to incl name, tel, e-
         1a2     mail, org, level of access to system, what         (NHS) Project Manager
                 areas
                 Identify Organisational Lead to act as user list
         1a3                                                        (NHS) Project Manager
                 preparer.
         1a4     Seek lists from contacts                           (NHS) Project Manager
         1a5     Prioritise list if exceed licences                 (NHS) Project Manager
                 Newsletter – incl. section on gaining user list
         1a6                                                        (NHS) Project Manager
                 and feedback section for mop up.
                 Confirm access list to users + organisational
         1a7                                                        (NHS) Project Manager
                 leads + specialist leads
                 Provide list to EIS Administrators to enter on
         1a8                                                        (NHS) Project Manager
                 system
         1a9     User list placed on system                         EIS Administrators
         1a10    Project Implementation Team Meeting                (NHS) Project Manager




Produced by: Chris Greening                                            (<Date>) (<Version X>)

                                                   9
Enterprise Intelligence System (EIS) Project – Stage Plan



        Stage 2b – Confirmation of Customer Quality Expectations
         Ref                          Task                            Responsible             Time
                                                                                              scale
         2b1     CQE form created                                (NHS) Project Manager
         2b2     CQE form distributed                            (NHS) Project Manager
         2b3     CQE form presented @ workshops (see 1b3)        (NHS) Project Manager
         2b3     CQE forms returned, analysed, grouped           (NHS) Project Manager
         2b4     Project Board – to incl. CQE presentation       (NHS) Project Manager       12th Oct


        Stage 2c - End User Training (see stage 1d – should align)
         Ref                          Task                            Responsible             Time
                                                                                              scale
         2c1     End Users confirmed via stage 1a                (NHS) Project Manager
         2c2     Available training dates gained from Ardentia   (Ardentia) Project Manage
         2c3     Dates confirmed with End User roles             (NHS) Project Manager
         2c4     End User Training                               Ardentia Training


        Stage 2d - Extraction and uploading to user defined Cassius ‘cube’ of Community &
        Mental Health PAS (Damadian release) information.
         Ref                          Task                            Responsible             Time
                                                                                              scale
         2d1     Community data spec confirmed                   (NHS) Project Manager
         2d2     MH data spec confirmed                          (NHS) Project Manager
         2d3     Extracts from ipm completed and validated       ipm Project Manager
         2d4     Information uploaded into EIS                   (NHS) Project Manager
         2d5     Information validated by respective leads       (NHS) Project Manager


        Stage 2e – Data Quality & Reporting Sign off
         Ref                          Task                            Responsible             Time
                                                                                              scale
                 Data Quality Reports and Reporting
         2e1                                                     (NHS) Project Manager
                 functionality signed off by Leads
                 Data Quality Reports and Reporting                                            th
         2e1                                                     (NHS) Project Manager       10 Nov
                 functionality signed off by Project Board




Produced by: Chris Greening                                         (<Date>) (<Version X>)

                                                  10
Enterprise Intelligence System (EIS) Project – Stage Plan



11.     Appendix 1 – Data Server Specification
    The minimum hardware specification for the data server is given below.


    Data Server – Minimum Requirements
    Operating System            Windows 2000 Server.
    Processor                   2 * Intel-compatible 3-gigahertz (GHz) processor or higher
    Memory                      3 GB
                                1 * 10GB IDE or SCSI HDD (System Disk)
    Hard Disk                   4 * Ultra 320 15k 72GB hot plug drives configured in a RAID
                                0+1 mirror set
                                DAT Tape Drive - DDS 3+ (backup device)
    Other Requirements          CDROM (software load)
                                Floppy Disk Drive


    The Trust should consider the use of a RAID storage solution to provide enhanced
    performance and resilience.
    The Trust should consider further processors and memory to improve performance and
    should ensure that the Server can be extended as demand increases and data volumes
    increase

12.     Appendix 2 – Web Server Specification
    Ardentia recommends that separate hardware be used to host the application – a Web
    Server. While the data server and the web server may be combined within the same physical
    device, this may lead to a reduction in performance. Also, the use of separate servers may be
    beneficial from a security and scalability point of view.
    The Web Server needs similar processing power and memory to the data server but obviously
    does     not      require       a       similar    level      of      data       storage.


    Web Server – Minimum Requirements
    Operating System    Windows 2000 Server.
    Processor           2 * Intel-compatible 2-gigahertz (GHz) processor or higher
    Memory              2 GB
    Hard Disk           1 * 10GB IDE or SCSI HDD (System Disk)
                        CDROM (software load)
    Other Requirements
                        Floppy Disk Drive




Produced by: Chris Greening                                    (<Date>) (<Version X>)

                                                 11
Enterprise Intelligence System (EIS) Project – Stage Plan



13.     Appendix 3 – Client PC Specification
    Confirmation has been given by Ardentia (e-mail 14th July 2005) that the current specification
    used by Worcestershire ICT Services exceeds that required by the system. The current ICT
    Services specification is:
           Pentium P4 2.8GHz
           40Gb Hard Disk Drive
           512 Mb 133 MHz SDRAM memory (1 X 512Mb)
           17” Flat Panel Monitor
           CD-RW
           Smartcard Reader Keyboard
           Mouse




Produced by: Chris Greening                                     (<Date>) (<Version X>)

                                                 12

				
DOCUMENT INFO