					                                       SCHEDULE 22




                            SPAA METERING SCHEDULE




                                         Version :   1.2
                                          Status :   Mandatory Schedule
                                    Release Date :   7 November 2008 2007




SPAA Metering Schedule_v1.2 Final                                           Page 1 of 17
                                     SPAA Metering Schedule

1.       Introduction

1.1 This SPAA Metering Schedule shall be regarded as a Mandatory Schedule for Domestic Suppliers
     and Industrial and Commercial Suppliers.

1.2 Paragraphs 4 & 7 of this SPAA Metering Schedule shall be regarded as a Mandatory Schedule for
    Large Transporters and an Elective Schedule for Small Transporters.

1.3 This SPAA Metering Schedule represents the obligations placed on Parties to operate in
    accordance with the RGMA Baseline.

1.4 For the purposes of clarification an Appendix to the SPAA Metering Schedule has been produced
    to highlight the obligations placed on Parties by the SPAA Metering Schedule at a RGMA
    Baseline Transaction level.

1.5 In the event of any inconsistency between the obligations placed on Parties by this SPAA Metering
    Schedule and the Appendix, the obligations under this SPAA Metering Schedule shall prevail to
    the extent of such inconsistency.



2.       Definitions and Interpretation

2.1 Definitions used in this SPAA Metering Schedule shall have the meanings as set out below:

     "Agent or Supplier's Agent"     means either a Shipper or a MAM as the case may be;

     "Gas Act Owner or GAO"          means the person that is either a Supplier, a GT or a Consumer
                                     that is responsible for providing an installed Meter at a Supply
                                     Meter Point and maintaining the Meter in good working order as
                                     required by the Act;

     "electronic file"               means a collection of data in electronic form capable of being
                                     machine read without manual intervention;

     "GT"                            means a Gas Transporter;

     "MAM"                           means a Meter Asset Manager as defined in Standard Condition
                                     34.2.A of the Gas Suppliers Licence;

     "Meter"                         means a measuring instrument that measures the volume of
                                     natural gas passing through it, with a specific badged capacity
                                     that is in accordance with Schedule 2B of the Act;

     "Meter Related Services"        shall have the same meaning as that term defined in Standard
                                     Condition 34.2.A of the Gas Suppliers Licence;

     "Originator"                    means the GT, MAM or Supplier that initiates the sending of the
                                     relevant RGMA Baseline Transaction whilst undertaking a
                                     RGMA Baseline Process;

     "RGMA Appendix document"        means a SPAA Product of the same name that constitutes part of
                                     the RGMA Baseline;

     "RGMA Baseline"                 means the currently prevailing version of the RGMA Baseline
                                     documentation comprised within Schedule 6 of the SPAA
                                     incorporating the RGMA Processes and Data document, the

SPAA Metering Schedule_v1.2 Final                                                         Page 2 of 17
                                     RGMA Appendix document and the RGMA Market Domain
                                     Data document;

    "RGMA Baseline Process"          any of the following processes:
                                     Process 1 – Asset Installation
                                     Process 2 – Asset Removal
                                     Process 3 – Asset Exchange
                                     Process 6 – Change of Supplier with Change of MAM
                                     Process 8 – Change of Meter Asset Manager (without Change in
                                     Supplier)
                                     as described and depicted in the RGMA Baseline;

    "RGMA Baseline Transaction" means any of the following transaction formats:
                                ORJOB – Request Metering Job
                                ONJOB – Notify Metering Job
                                ORQUO – Request Metering Quote
                                ONQUO – Notify Metering Quote
                                ONAGE – Notify Agent Change
                                ORDET – Request Metering Details
                                ONDET – Notify Metering Details
                                ONUPD – Notify Update Metering Details
                                RRJOB – Response Request Metering JOB
                                RNJOB – Response Notify Metering Job
                                RRQUO – Response Request Metering Quote
                                RNQUO – Response Notify Metering Quote
                                RNAGE – Response Notify Agent Change
                                RRDET – Response Request Metering Details
                                RNDET – Response Transfer of Metering Detail
                                RNUPD – Response Update
                                as described in the RGMA Baseline;

"RGMA Market Domain Data document"         means a SPAA Product of the same name that constitutes
                                           part of the RGMA Baseline;

"RGMA Processes and Data document" means a SPAA Product of the same name that constitutes part
                                of the RGMA Baseline;

"Shipper"                            means a person licensed under Section 7A (2) of the Act to
                                     arrange with any GT for gas to be conveyed in or offtaken from
                                     the pipe-line system operated by that GT for purposes connected
                                     with the supply of gas;

"Supply Meter Point"                 means a Supply Meter Point as described in the currently
                                     prevailing version of the relevant GT’s Network Code;

"Supply Point Registration Date"     means a Supply Point Registration Date as described in the
                                     currently prevailing version of the relevant GT’s Network Code;

"valid"                              where used in paragraphs 5 and 6 in the context of a RGMA
                                     Baseline Transaction shall mean an RGMA Baseline Transaction
                                     that complies with paragraph 4.4.


2.2 To the extent that definitions used in this SPAA Metering Schedule are also used in the SPAA
    their meanings as defined in the SPAA shall apply.




SPAA Metering Schedule_v1.2 Final                                                       Page 3 of 17
2.3 In the event of any inconsistency between the obligations placed on Parties by this SPAA Metering
    Schedule and the RGMA Baseline itself, the obligations under this SPAA Metering Schedule shall
    prevail to the extent of such inconsistency.

2.4 In the event of any inconsistency between this SPAA Metering Schedule and the SPAA itself the
    SPAA shall prevail to the extent of such inconsistency.

2.5 To the extent that any of the definitions in this SPAA Metering Schedule or in the SPAA are used
    in the RGMA Baseline their meaning shall be the same.

3.       General Supplier Obligations with regard to the RGMA Baseline

3.1 In the event a Supplier’s Agent fails to comply with any of the requirements listed in this SPAA
    Metering Schedule, the Supplier shall use all reasonable endeavours to ensure their Agent rectifies
    the said failure.


4.       General Obligations with regard to RGMA Processes and RGMA Baseline Transactions

4.1 Whilst engaging in a RGMA Baseline Process where a Supplier uses any of the RGMA Baseline
    Transactions to provide electronic files to their Agent, they shall ensure that the requirements
    stated in paragraph 4.4 are met.

4.2 Whilst engaging in a RGMA Baseline Process, where a GT uses any of the RGMA Baseline
    Transactions to provide electronic files to Shippers, they shall ensure that the requirements stated
    in 4.4 are met.

4.3 Whilst engaging in a RGMA Baseline Process, where a Supplier appoints an Agent to act on their
    behalf they shall ensure that the Agent uses the appropriate RGMA Baseline Transaction to
    provide electronic files to other Supplier’s Agents or GTs. Suppliers shall also ensure that their
    Agents comply with the requirements stated in paragraph 4.4.

4.4 The requirements referred to in paragraphs 4.1, 4.2 and 4.3 above are that:
                a) the structure of any electronic file containing a RGMA Baseline Transaction
                     shall conform with Chapter 14.2.1 of the RGMA Processes and Data document
                b) a RGMA Baseline Transaction will include datasets which conform with the
                     sequence described in Chapter 14.4.1 of the RGMA Processes and Data
                     document
                c) any electronic file containing a RGMA Baseline Transaction shall include a
                     header and trailer conforming with Chapter 14.4.2 of the RGMA Processes and
                     Data document
                d) the characters and delimiters used within an electronic file containing a RGMA
                     Baseline Transaction will conform with Appendix G of the RGMA Appendix
                     document
                e) each RGMA Baseline Transaction within a file shall include all datasets defined
                     as being mandatory and/or mandatory by virtue of a conditional rule as stated in
                     the description of that RGMA Baseline Transaction in Chapter 15 of the RGMA
                     Processes and Data document
                f) each dataset within a RGMA Baseline Transaction shall include all data
                     attributes defined as being mandatory and/or mandatory by virtue of a
                     conditional rule as stated in the description of that dataset included in the
                     description of the relevant RGMA Baseline Transaction in Chapter 15 of the
                     RGMA Processes and Data document
                g) all data attributes and their values used within a RGMA Baseline Transaction
                     shall comply with the description and format of the data attributes defined in
                     Appendix D of the RGMA Appendix document
                h) all data attributes used within a RGMA Baseline Transaction which are market
                     Domain Data attributes, as defined in the current RGMA Market Domain
                     document, shall have a valid value


SPAA Metering Schedule_v1.2 Final                                                            Page 4 of 17
4.5 Notwithstanding paragraph 4.1, Suppliers are not obligated to use RGMA Baseline Transactions
    when sending data to their Agents and their Agents are not obligated to use RGMA Baseline
    Transactions when sending data to their Supplier whilst undertaking RGMA Baseline Processes.
    Nor shall a Supplier or their Agent be obligated to exchange data between themselves by way of
    electronic files. This shall not absolve or detract a Supplier from its obligations to comply with
    paragraph 4.3.

5.       Suppliers obligations to ensure efficient operation of the RGMA Baseline Processes

5.1 Suppliers shall use all reasonable endeavours to ensure that they appoint a MAM to act as their
    agent in providing Meter Related Services for the entire period during which they supply gas to a
    Meter installed at a Supply Meter Point.

5.2 Except where a Meter is owned by the Consumer, Suppliers shall use all reasonable endeavours to
    issue appointment requests to their MAM(s) within a timescale sufficient to ensure that they have a
    MAM appointed by the Supply Point Registration Date.

5.3 When a Supplier takes over the supply of gas to a Meter and as a result there is a change in the
    MAM appointed by the New Supplier to provide Meter Related Services to the Meter installed at
    that Supply Meter Point, or where a Supplier becomes aware of a change of MAM, the Supplier
    will use their reasonable endeavours to notify the relevant Gas Transporter (via their Shipper) of
    the appointed MAM within two Working Days following receipt of acceptance of the MAM
    appointment.

5.4 In the event a Supplier receives a valid ONJOB transaction from its MAM notifying it of an Asset
    Installation, Asset Removal or Asset Exchange at a Supply Meter Point, or in the event a Supplier
    receives a valid ONUPD transaction from its MAM notifying it of a change to the Meter details
    recorded at a Supply Meter Point, it shall use its reasonable endeavours to pass such relevant
    notification to the GT (via its Shipper) within six Working Days.

5.5 Asset Installation, Asset Removal and Asset Exchange as referred to in paragraph 5.4, shall be
    deemed to consist of actions undertaken by Suppliers and their MAM(s) in the sequence and
    manner described within RGMA Baseline Processes 1, 2 and 3 respectively.

5.6 Wherever possible, Suppliers should seek to avoid installation or exchange of a new Meter at a
    Supply Meter Point if it has been agreed between the Old Supplier and New Supplier that the
    change of gas supply that took place was erroneous.

6.       MAMs obligations to ensure efficient operation of the RGMA Baseline Processes

6.1 Suppliers must ensure that when they appoint a MAM to provide Meter Related Services the
    MAM is bound to comply with the requirements of paragraphs 6.2, 6.3, and 6.4.

6.2 In the event the Meter installed at a Supply Meter Point is not intended to be replaced during the
    course of a change of gas Supplier at a Supply Meter Point, a MAM must be able to accept and act
    upon a valid ORDET or RNDET transaction sent to them by another MAM by way of an
    electronic file

6.3 In the event the Meter installed at a Supply Meter Point is not intended to be replaced during the
    course of a change of gas Supplier at a Supply Meter Point, a MAM must be able to send ONDET
    and/or RRDET transactions to another MAM by way of an electronic file.

6.4 In the event a MAM receives a valid ORDET transaction from another MAM during the course of
    a change of gas Supplier at a Supply Meter Point, the MAM shall use reasonable endeavours to
    send an ONDET transaction to the other MAM within two Working Days of receipt of the
    ORDET.

6.5 MAMs may exchange data equivalent to that defined as being mandatory within an
    ORDET,ONDET,RRDET and/or RNDET without using electronic files, by mutual agreement.

SPAA Metering Schedule_v1.2 Final                                                           Page 5 of 17
6.6 A change of gas Supplier at a Supply Meter Point, as referred to in paragraphs 6.2, 6.3, and 6.4,
    shall be deemed to consist of actions undertaken by Suppliers and their MAM(s) in the sequence
    and manner described within RGMA Baseline Process 6.


7.       General obligations regarding data quality and data validation under the RGMA
         Baseline

7.1 Where Suppliers receive RGMA Baseline Transactions from their Agents whilst undertaking
    RGMA Baseline Processes they shall use reasonable endeavours to ensure that invalid and/or
    inaccurate information, which prevents the relevant RGMA Baseline Process being undertaken, is
    wherever possible identified promptly and communicated back to the Agent.

7.2 In the event Suppliers, Supplier’s Agents or GTs validate RGMA Baseline Transactions they
    receive by way of electronic files, they will be required to identify exceptions within the RGMA
    Baseline Transaction using the response codes set out in Appendix F of the RGMA Appendix
    document.

7.3 Where the GT, MAM, Supplier or the Originator is shown as the owner of a data attribute they are
    responsible for ensuring they hold valid and accurate information in relation to that data attribute.
    To the extent they become aware that information in relation to that data attribute is invalid or
    inaccurate they shall use their reasonable endeavours to send valid and accurate information to
    other parties as provided for in the RGMA Baseline Processes as soon as reasonably practicable.

7.4 Where the GT, MAM, Supplier or the Originator is made aware of valid changes to information
    relating to data attributes for which they are not the owner, they shall update their records
    accordingly and send this updated information to other parties as provided for in the RGMA
    Baseline Processes as soon as reasonably practicable.

7.5 In the event the GT, MAM, Supplier or the Originator has reasonable grounds for assuming the
    information referred to in paragraph 7.4 to be inaccurate, they shall notify the owner of this.

7.6 The extent to which the GT, MAM, Supplier or Originator is the owner of a data attribute as
    referred to in this paragraph 7 is defined in Appendix D.7 of the RGMA Appendix document.

7.7 Invalid information in relation to data attributes and/or datasets as referred to in this paragraph 7 is
     that information which fails to comply with:
                   a) the Data Dictionary in Appendix D.2 of the RGMA Appendix document, or;
                   b) the Data Set and Attribute Rules in Appendix A.2 of the RGMA Appendix
                       document, or;
                   c) the Data Set and Attribute Optionality for Transaction Types in Appendix B.3 of
                       the RGMA Appendix document, or;
the Market Domain Data Items in Appendix E of the RGMA Appendix document, and valid
information as referred to in this paragraph 7 shall have the opposite meaning.

7.8 Inaccurate information in relation to data attributes and/or datasets as referred to in this paragraph
    7 is valid information but which in itself does not reflect the reality of the situation, and accurate
    information as referred to in this paragraph 7 shall have the opposite meaning.

7.9 Suppliers must ensure that Agents appointed to act on their behalf shall comply with the
    requirements stated in paragraphs 7.2 – 7.5.

8.       Suppliers Reporting Obligations

8.1 Suppliers shall be required to report their performance against paragraphs 5.3, 5.4 and 6.4 each
    calendar month to the Secretary of the SPAA.

8.2 Such reports shall be compiled for each individual Supplier who is a Party and sent to the
    Secretary on the last Working Day of the month following the calendar month being reported on.

SPAA Metering Schedule_v1.2 Final                                                              Page 6 of 17
8.3 The Secretary shall make the reports compiled by each individual Supplier in accordance with
    paragraph 8.2 available to the SPAA Executive Committee such that they can assess suppliers
    collective performance against these reporting obligations.

8.4 A Supplier’s obligation to report information against paragraph 5.3 shall be determined based on
    the number of K08 transactions sent to the GT in the MAM file by their Shipper and shall be
    calculated as follows:
                  a) count the number of K08 transactions in each MAM file sent within the
                       calendar month where the date the MAM file was sent was > than 2 Working
                       Days after the MAM Effective from Date included within the K08 transaction
                       and report the figure
                  b) count the total number of K08 transactions included within MAM files that have
                       been sent within the calendar month and report the figure
                  c) divide 8.4a by 8.4.b and report the result as a percentage

8.5 A Supplier’s obligation to report information against paragraph 5.4 shall be determined based on
    the number of ONJOB transactions sent to the GT by their Shipper and shall be calculated as
    follows:
                 a) count the number of ONJOB transactions that have been sent within the calendar
                     month where the date the file was sent was > than 6 Working Days after the Date
                     of Notice included within the ONJOB and report the figure
                 b) count the total number of ONJOB transactions that have been sent within the
                     calendar month and report the figure
                 c) divide 8.5.a by 8.5.b and report the result as a percentage

8.6 A Supplier’s obligation to report information against paragraph 6.4 shall be determined based on
    the number of ONDET transactions sent by their MAM to other MAMs and shall be as follows:
                 a) for each Supply Meter Point for which an ORDET transaction was received
                      during the calendar month count the instances where an ONDET transaction was
                      sent in response > 2 Working Days later and report the figure
                 b) count the number of ORDET transactions that have been received in the calendar
                      month and report the figure
                 c) divide 8.6.a by 8.6.b and report the result as a percentage

8.7 The reference to the K08 transaction in paragraph 8.4 refers to the electronic transaction used by
    Shippers to record MAM and Gas Act Owner details for the benefit of Large Transporters. The
    reference to the MAM file in paragraph 8.4 refers to the electronic file including one or more K08
    transaction used by Shippers to convey MAM and Gas Act Owner recorded details to Large
    Transporters. The reference to MAM Effective from Date in paragraph 8.4 refers to a data attribute
    of that name within the K08 transaction. To the extent these references change over time, or to the
    extent different references are given to the transactions and/or files used by Shippers to record and
    convey such information to Small Transporters, these alternative references shall also apply to
    paragraph 8.4.




SPAA Metering Schedule_v1.2 Final                                                           Page 7 of 17
                 Appendix - Obligations placed on Parties by the SPAA Metering Schedule at RGMA Baseline Transaction level

This Appendix has been produced to provide clarification of the SPAA Metering Schedule obligations at RGMA Baseline Transacti on level and
is designed to highlight the obligations Parties have directly, and that they must place on their Agents, to comply with the SPAA Metering
Schedule. In the event of any inconsistency between the SPAA Metering Schedule and the Appendix, the SPAA Metering Schedule shall
prevail to the extent of such inconsistency.

Transaction     From           To         Process          Obligation                                                                         Clause
                                          Flow Ref(s)
All relevant    As per the     Supplier   As per the       In the event the Supplier, MAM, Shipper or GT validate RGMA Baseline               7.2
transactions    relevant       MAM        relevant         Transactions they receive by way of electronic files they shall identify
                transaction    Shipper GT transaction      exceptions within the RGMA Baseline Transaction using the defined RGMA
                                                           Baseline response codes.
All relevant    Supplier       As per the    As per the    Where the Supplier, MAM or GT becomes aware that information in relation to        7.3
transactions    MAM GT         relevant      relevant      data attributes of which they are the owner is invalid or inaccurate they shall
                               transaction   transaction   use their reasonable endeavours to send valid and accurate information to
                                                           other parties as provided for in the RGMA Baseline Processes as soon as
                                                           reasonably practicable
All relevant    As per the     Supplier      As per the    Where the GT, MAM, Supplier or the Originator is made aware of valid               7.4
transactions    relevant       Shipper       relevant      changes to information relating to data attributes for which they are not the
                transaction    MAM GT        transaction   owner, they shall update their records accordingly and send this updated
                                                           information to other parties as provided for in the RGMA Baseline Processes
                                                           as soon as reasonably practicable.
All relevant    As per the     Supplier      As per the    Where the GT, MAM, Supplier or the Originator has reasonable grounds for           7.5
transactions    relevant       Shipper       relevant      assuming that information relating to data attributes for which they are not the
                transaction    MAM GT        transaction   owner is inaccurate they shall notify the owner of this.
ORJOB           Supplier       MAM           1B, 2B, 3B    Suppliers are not obligated to use this transaction to request meter work from     4.5
                                                           their MAMs. Nor does this request need to be communicated by way of
                                                           electronic files.




SPAA Metering Schedule_v1.2 Final                                            Page 8 of 17
                                                       To the extent Suppliers do enter into commercial agreements which provide           4.1
                                                       for them sending this transaction to their MAM by way of an electronic file they
                                                       shall be obliged to comply with all the requirements in 4.4. with respect to this
                                                       transaction.
ONJOB           MAM            Supplier   1J, 2J, 3J   Suppliers are not obligated to require their MAMs to send them this                 4.5
                                                       transaction for asset notification purposes. Nor does this notification need to
                                                       be sent to them by way of electronic files.
                                                       To the extent Suppliers do enter into commercial agreements which provide           4.3
                                                       for this transaction to be sent to them by their MAM, by way of an electronic
                                                       file the MAM shall be obliged to comply with all the requirements in 4.4. with
                                                       respect to this transaction.
                                                       Suppliers must ensure that their contractual arrangements with MAMs are             5.4
                                                       sufficient to allow them to receive and act on valid transactions received from
                                                       their MAM so as to allow them to notify the GT (via their Shipper) within 6
                                                       working days of a meter asset being installed, removed or exchanged.
                                                       Suppliers shall use reasonable endeavours to ensure that invalid and/or             7.1
                                                       inaccurate information received in the ONJOB which prevents the relevant
                                                       RGMA Baseline process being undertaken is wherever possible identified
                                                       promptly and communicated back to the MAM.
                Supplier       Shipper    1K, 2K, 3K   Suppliers are not obligated to use this transaction for asset notification          4.5
                                                       purposes to their Shipper. Nor does this notification need to be communicated
                                                       by way of electronic files.
                                                       To the extent Suppliers do enter into commercial agreements which provide           4.1
                                                       for them sending this transaction to their Shipper by way of an electronic file
                                                       they shall be obliged to comply with all the requirements in 4.4. with respect to
                                                       this transaction.
                Shipper        GT         1K, 2K, 3K   Suppliers must ensure that a Shipper they appoint to act on their behalf uses       4.3
                                                       this transaction to communicate relevant asset notification to the GT, where
                                                       the Supplier receives a valid ONJOB from their MAM, and that communication
                                                       is by way of an electronic file in accordance with existing communications
                                                       protocols between Shippers and GTs.



SPAA Metering Schedule_v1.2 Final                                         Page 9 of 17
                                                     Suppliers must ensure that their shipper is obliged to comply with all the          4.3
                                                     requirements in 4.4. with respect to this transaction.
                                                     Where the Supplier receives a valid ONJOB from their MAM they must ensure           5.4
                                                     that their contractual arrangements with Shippers are sufficient to allow them
                                                     to send this transaction to the GT (via their Shipper) within 6 working days of
                                                     a meter asset being installed, removed or exchanged.
                                                     Suppliers must ensure their Shippers are able to record the % of ONJOBS             8.5
                                                     sent to the GT within a month which were sent more than 6 working days after
                                                     the meter asset has been installed, removed or exchanged such that they can
                                                     report this to the SPAA Secretary each month.
ORQUO           Supplier       MAM        P6C        Suppliers are not obligated to use this transaction to request meter quotes         4.5
                                                     from their MAM. Nor does this request need to be communicated by way of
                                                     electronic files.
                                                     To the extent Suppliers do enter into commercial agreements which provide           4.1
                                                     for this transaction to be sent to their MAM by way of an electronic file they
                                                     shall be obliged to comply with all the requirements in 4.4. with respect to this
                                                     transaction.
ONQUO           MAM            Supplier   P6G        Suppliers are not obligated to require their MAM to use this transaction to         4.5
                                                     provide meter quotes. Nor does the quote need to be communicated by way
                                                     of electronic files.
                                                     To the extent Suppliers do enter into commercial agreements which provide           4.3
                                                     for this transaction to be sent to them by their MAM by way of an electronic
                                                     file, the MAM shall be obliged to comply with all the requirements in 4.4. with
                                                     respect to this transaction.
                                                     Suppliers shall use reasonable endeavours to ensure that invalid and/or             7.1
                                                     inaccurate information received in the ONQUO which prevents the relevant
                                                     RGMA Baseline process being undertaken is wherever possible identified
                                                     promptly and communicated back to the MAM.
ONAGE           Supplier       MAM        6N , 6P,   Suppliers are not obligated to use this transaction to notify agent change with     4.5
                                          8A, 8C     their MAM. Nor does this request need to be communicated by way of
                                                     electronic files.



SPAA Metering Schedule_v1.2 Final                                      Page 10 of 17
                                              To the extent Suppliers do enter into commercial agreements which provide           4.1
                                              for this transaction to be sent to their MAM by way of an electronic file they
                                              shall be obliged to comply with all the requirements in 4.4. with respect to this
                                              transaction.
                                              Suppliers shall use reasonable endeavours to issue appointment requests to          5.2
                                              their MAMs within a timescale sufficient to ensure they have a MAM
                                              appointed by the Supply Point Registration Date. This does not obligate the
                                              Supplier to use the ONAGE transaction to request MAM appointments but to
                                              the extent they do, this will have to be taken into account with regard to the
                                              timing of ONAGEs are sent.
ORDET           MAM            MAM   6R       A Supplier must ensure that any MAM they appoint to act on their behalf is          4.3, 6.2
                                              capable of using this transaction to request meter details from other MAMs by
                                              way of electronic files.
                                              Suppliers must ensure that their MAM is obliged to comply with all the              4.3
                                              requirements in 4.4. with respect to this transaction.
                                              Suppliers must ensure their MAMs are able to accept and act upon ORDETs             6.1, 6.2
                                              sent to them by other MAMs by way of electronic files in the event a meter is
                                              not intended to be replaced during the course of a change of supplier. This
                                              will not preclude MAMs exchanging data which is equivalent to that defined as
                                              being mandatory within an ORDET without using electronic files by mutual
                                              agreement

                                              Suppliers must ensure that their MAMs are able to report the % of ORDET             8.6
                                              transactions received each month for which an ONDET was sent in response
                                              greater than 2 working days such that the Supplier can report this to the
                                              SPAA Secretary each month.
ONDET           MAM            MAM   6T, 8D   A Supplier must ensure that any MAM they appoint to act on their behalf is          4.3, 6.3
                                              capable of using this transaction to notify meter details to other MAMs by way
                                              of electronic files.
                                              Suppliers must ensure that their MAM is obliged to comply with all the              4.3
                                              requirements in 4.4. with respect to this transaction.



SPAA Metering Schedule_v1.2 Final                               Page 11 of 17
                                                       Suppliers must ensure their MAMs are able to send ONDETs to other MAMs              6.1, 6.3
                                                       by way of electronic files in the event a meter is not intended to be replaced
                                                       during the course of a change of supplier. This will not preclude MAMs
                                                       exchanging data which is equivalent to that defined as being mandatory within
                                                       an ONDET, without using electronic files by mutual agreement.
                                                       Suppliers must ensure their MAMs shall be obliged to use reasonable                 6.1, 6.4
                                                       endeavours to ensure that when their MAM receives an ORDET from another
                                                       MAM during the course of a change of supplier they send an ONDET to the
                                                       other MAM within two working days.
ONUPD           MAM            Supplier   6U, 8E, 8F   Suppliers are not obligated to require their MAM to use this transaction to         4.5
                                                       update meter details. Nor do the meter details need to be communicated by
                                                       way of electronic files.
                                                       To the extent Suppliers do enter into commercial agreements which provide           4.3
                                                       for this transaction to be sent to them by their MAM by way of an electronic
                                                       file the MAM shall be obliged to comply with all the requirements in 4.4. with
                                                       respect to this transaction.
                                                       Suppliers must ensure that their contractual arrangements with MAMs are             5.3
                                                       sufficient to allow them to recognise the appointment of a new MAM in order
                                                       that they can notify the GT (via their Shipper) within 2 working days of
                                                       acceptance of the MAM appointment.
                                                       Suppliers must ensure that their contractual arrangements with MAMs are             5.4
                                                       sufficient to allow them to receive and act on valid ONUPD transactions
                                                       received from their MAM so as to allow them to notify the GT (via their
                                                       Shipper) within 6 working days of a change in meter details.
                                                       Suppliers shall use reasonable endeavours to ensure that invalid and/or             7.1
                                                       inaccurate information received in the ONUPD which prevents the relevant
                                                       RGMA Baseline process being undertaken is wherever possible identified
                                                       promptly and communicated back to the MAM.
                Supplier       Shipper    6V           Suppliers are not obligated to use this transaction notify their Shipper of asset   4.5
                                                       updated. Nor does this notification need to be communicated by way of
                                                       electronic files



SPAA Metering Schedule_v1.2 Final                                        Page 12 of 17
                                                      To the extent Suppliers do enter into commercial agreements which provide           4.1
                                                      for them sending this transaction to their Shipper by way of an electronic file
                                                      they shall be obliged to comply with all the requirements in 4.4. with respect to
                                                      this transaction
                Shipper        GT         6W          Suppliers must ensure that a Shipper they appoint to act on their behalf uses       4.3
                                                      this transaction to communicate relevant asset notification to the GT, where
                                                      the Supplier receives a valid ONUPD from their MAM, and that
                                                      communication is by way of an electronic file in accordance with existing
                                                      communications protocols between Shippers and GTs.
                                                      Suppliers must ensure that their Shipper is obliged to comply with all the          4.3
                                                      requirements in 4.4. with respect to this transaction

                                                      Suppliers must ensure that their contractual arrangements with Shippers are         5.4
                                                      sufficient to allow them to send this transaction to the GT (via their Shipper)
                                                      within 6 working days of notification of a change to meter details.
RRJOB           MAM            Supplier   1BR, 2BR,   Suppliers are not obligated to require their MAM to use this response               4.5
                                          3BR         transaction to communicate in response to ORJOBs they send them. Nor
                                                      does this response need to be communicated by way of electronic files.
                                                      To the extent Suppliers do enter into commercial agreements which provide           4.3
                                                      for this response transaction to be sent to them by their MAM by way of an
                                                      electronic file in response to an ORJOB they have sent, the MAM shall be
                                                      obliged to comply with all the requirements in 4.4. in respect of this
                                                      transaction.
                                                      Suppliers shall use reasonable endeavours to ensure that invalid and/or             7.1
                                                      inaccurate information received in the RRJOB which prevents the relevant
                                                      RGMA Baseline process being undertaken is wherever possible identified
                                                      promptly and communicated back to the MAM.
RNJOB           Supplier       MAM        1JR, 2JR,   Suppliers are not obligated to use this response transaction to communicate         4.5
                                          3JR         in response to ONJOBs sent to them by their MAM. Nor does this response
                                                      need to be communicated by way of electronic files.



SPAA Metering Schedule_v1.2 Final                                       Page 13 of 17
                                                      To the extent Suppliers do enter into commercial agreements which provide          4.1
                                                      for this transaction to be sent to their MAM by way of an electronic file in
                                                      response to an ONJOB they have sent, the Supplier shall be obliged to
                                                      comply with all the requirements in 4.4. with respect to this transaction.
                Shipper        Supplier   1KR, 2KR,   Suppliers are not obligated to require their Shipper to use this response          4.5
                                          3KR         transaction to communicate in response to ONJOBs they send them. Nor
                                                      does this response need to be communicated by way of electronic files.
                                                      To the extent Suppliers do enter into commercial agreements which provide          4.3
                                                      for this transaction to be sent to them by their Shipper by way of an electronic
                                                      file in response to an ONJOB they have sent, the Shipper shall be obliged to
                                                      comply with all the requirements in 4.4. with respect to this transaction.
                                                      Suppliers shall use reasonable endeavours to ensure that invalid and/or            7.1
                                                      inaccurate information received in the RNJOB which prevents the relevant
                                                      RGMA Baseline process being undertaken is wherever possible identified
                                                      promptly and communicated back to the Shipper.
                GT             Shipper    1KR, 2KR,   GTs must ensure they use this response transaction to communicate with             4.2
                                          3KR         Shippers in response to ONJOBs sent to them and that communication is by
                                                      way of an electronic file in accordance with existing communications protocols
                                                      between GTs and Shippers.
                                                      GTs must also ensure that they comply with all the requirements in 4.4. with       4.2
                                                      respect to this transaction.
RRQUO           MAM            Supplier   6PCR        Suppliers are not obligated to ensure their MAM uses this response                 4.5
                                                      transaction to communicate with them in response to ORQUOs they send to
                                                      them. Nor does this response need to be communicated by way of electronic
                                                      files.
                                                      To the extent Suppliers do enter into commercial agreements which provide          4.3
                                                      for this transaction to be sent to them by MAMs by way of an electronic file in
                                                      response to an ORQUO the MAM shall be obliged to comply with all the
                                                      requirements in 4.4. with respect to this transaction.




SPAA Metering Schedule_v1.2 Final                                      Page 14 of 17
                                                      Suppliers shall use reasonable endeavours to ensure that invalid and/or           7.1
                                                      inaccurate information received in the RRQUO which prevents the relevant
                                                      RGMA Baseline process being undertaken is wherever possible identified
                                                      promptly and communicated back to the MAM.
RNQUO           Supplier       MAM        6PGR        Suppliers are not obligated to use this response transaction to communicate       4.5
                                                      in response to ONQUOs sent to them by their MAM. Nor does this response
                                                      need to be communicated by way of electronic files.
                                                      To the extent Suppliers do enter into commercial agreements which provide         4.1
                                                      for this transaction to be sent to their MAM by way of an electronic file in
                                                      response to an ONQUO they have sent, the Supplier shall be obliged to
                                                      comply with all the requirements in 4.4. with respect to this transaction.
RNAGE           MAM            Supplier   6Q (6PR),   Suppliers are not obligated to ensure their MAM uses this response                4.5
                                          6S (6NR),   transaction to communicate with them in response to ONAGEs they send
                                          8B (8AR)    them. Nor does this response need to be communicated by way of electronic
                                                      files.
                                                      To the extent Suppliers do enter into commercial agreements which provide         4.3
                                                      for this transaction to be sent to them by MAMs by way of an electronic file in
                                                      response to an ONAGE the MAM shall be obliged to comply with all the
                                                      requirements in 4.4. with respect to this transaction.
                                                      Suppliers shall use reasonable endeavours to ensure that invalid and/or           7.1
                                                      inaccurate information received in the RNAGE which prevents the relevant
                                                      RGMA Baseline process being undertaken is wherever possible identified
                                                      promptly and communicated back to the MAM.
RRDET           MAM            MAM        6RR         A Supplier must ensure that any MAM they appoint to act on their behalf uses      4.3
                                                      this response transaction to communicate in response to ORDETs received
                                                      from other MAMs by way of an electronic file.
                                                      Suppliers must ensure that their MAM is obliged to comply with all the            4.3
                                                      requirements in 4.4. with respect to this transaction.
                                                      Suppliers must ensure their MAMs are able to send RRDETs by way of an             6.1, 6.3
                                                      electronic file in response to ORDETs received from other MAMs in the event
                                                      a meter is not intended to be replaced during the course of a change of
                                                      supplier.


SPAA Metering Schedule_v1.2 Final                                      Page 15 of 17
RNDET           MAM            MAM        6TR         A Supplier must ensure that any MAM they appoint to act on their behalf uses        4.3
                                                      this response transaction to communicate in response to ONDETs received
                                                      from other MAMs by way of an electronic file.
                                                      Suppliers must also ensure that their MAM is obliged to comply with all the         4.3
                                                      requirements in 4.4. in respect of this transaction.
                                                      Suppliers must ensure their MAMs are able to send RNDETs by way of an               6.1, 6.2
                                                      electronic file in response to ONDETs sent to them by other MAMs in the
                                                      event a meter is not intended to be replaced during the course of a change of
                                                      supplier.
RNUPD           Supplier       MAM        6UR, 8ER,   Suppliers are not obligated to use this response transaction to communicate         4.5
                                          8FR         with their MAM. Nor does this response need to be communicated by way of
                                                      electronic files.
                                                      To the extent Suppliers do enter into commercial agreements which provide           4.1
                                                      for this response transaction to be sent to them by their MAM by way of an
                                                      electronic file they shall be obliged to comply with all the requirements in 4.4.
                                                      with respect to this transaction.
                Shipper        Supplier   6VR         Shippers are not obligated to use this response transaction to communicate          4.5
                                                      with their Supplier. Nor does this response need to be communicated by way
                                                      of electronic files
                                                      To the extent Shippers do enter into commercial agreements which provide            4.1
                                                      for them sending this response transaction to their Supplier by way of an
                                                      electronic file they shall be obliged to comply with all the requirements in 4.4.
                                                      with respect to this transaction
                GT             Shipper    6WR         A GT must ensure they use this response transaction to communicate with             4.3
                                                      the Shipper and that communication is by way of an electronic file in
                                                      accordance with existing communications protocols between Shippers and
                                                      GTs
                                                      GTs must ensure they comply with all the requirements in 4.4. with respect to       4.3
                                                      this transaction




SPAA Metering Schedule_v1.2 Final                                       Page 16 of 17
MAM file1       Shipper        GT            6W             Suppliers must ensure that their contractual arrangements with Shippers are           5.3
                                                            sufficient to allow them to send this file to the GT (via their Shipper) within 2
                                                            working days of acceptance of a MAM appointment.
                                                            Suppliers must ensure their Shippers are able to record the % of K08                  8.4
                                                            transactions within the MAM files sent to the GT within a month which were
                                                            sent more than 2 working days after the MAM Effective from Date included
                                                            within the K08 transaction so that they can report this to the SPAA Secretary
                                                            each month.
MAS file2       GT             Shipper       6WR            A GT will be expected to use this file to communicate with the Shipper in
                                                            response to the MAM files as stated in the RGMA Baseline Process 6.
                                                            However, there is no obligation within the SPAA Metering Schedule requiring
                                                            them to do so.




1
  The MAM file is the file Shippers use to convey MAM and GAO details to Large Transporters whilst undertaking RGMA Baseline Process 6 (Change of
Supplier with Change of MAM). Although referenced in the RGMA Baseline and the SPAA Metering Schedule, it is not a RGMA Baseline Transaction and its
format is not subject to SPAA governance. However, Suppliers do have obligations under the SPAA Metering Schedule to ensure their Shippers use and
report on the MAM file as described within this Appendix.
2
  The MAS file is the response file used by Large Transporters to respond to MAM files sent to them by Shippers whilst undertaking RGMA Baseline Process
6 (Change of Supplier with Change of MAM). Although referenced in the RGMA Baseline and the SPAA Metering Schedule, it is not a RGMA Baseline
Transaction and its format is not subject to SPAA governance. GTs have no obligations under the SPAA Metering Schedule to ensure they use the MAS file
although they are expected to do so.


SPAA Metering Schedule_v1.2 Final                                              Page 17 of 17

				
DOCUMENT INFO
Shared By:
Categories:
Stats:
views:11
posted:5/30/2010
language:English
pages:17
Jun Wang Jun Wang Dr
About Some of Those documents come from internet for research purpose,if you have the copyrights of one of them,tell me by mail vixychina@gmail.com.Thank you!