Documenting skills is value-add

VIEWS: 3 PAGES: 2

The following question comes from the CAP study guide, Performance Domain I, Feasibility Study, Identify scope and justify the automation project CAP question MOST initial project budgetary cost estimates have an acceptable margin of error of plus or minus: A. 10% B. 30% C. 50% D. 70% CAP answer The best answer is B, 30%.