MONITORING OFFICERS QUARTERLY REPORT by lonyoo

VIEWS: 3 PAGES: 11

									THE TECHNOLOGY PROGRAMME                                        Project Monitoring Form


                                                Project Quarterly Progress Report




  SUSTAINABLE PRODUCTION & CONSUMPTION: ENERGY
             EFFICIENCY TECHNOLOGIES


       Integration and Demonstration of Energy Efficient Dwelling
                         Network (IndeedNET)


                              DTI Project No: TP/J3521A


                                       Q3 Report

                     Period 1st August 2007 to 31st October 2007

                             COMMERCIAL RESTRICTED


Date: 9th November 2007                                     Ref: Q3 progress
                                                            Vs: Version 1


                                  Responsible Authors:
                       Project Leader: Len Eastell, Advantica Ltd.
                       Monitoring Officer: Mike Patterson, Digital Living Ltd

Circulation: All Project Partners
             Monitoring Database



Project Quarterly Progress                  1
Report
Template Issue 3.0
                                                             th
DTI TECHNOLOGY PROGRAMME                               Date: 9 Nov 2007
Project Quarterly Progress Report Q3                   Ref: Q3progress
Project Title IndeedNET                                Version: 1

                                 Project Partners’ Report


Overall Progress and Key Achievements

  Provide an assessment of the composite project achievements (lead and partners contributions)
  since the last progress report. Detail the project key achievements during the reporting period.
  Highlight any exceptions and provide recommendations to Monitoring Officer/Contractor as
  necessary.

  In the third quarter Loughborough University, the technical lead partner, is reporting the
  following progress:

  Task 2.1 - Individual sensor development: This task has been modified as individual
  sensor selection. Lighting and temperatures are the two kinds of sensors we have
  identified at the moment. More kinds of sensors might be identified during carrying out
  Task 2.5 ‘Energy saving control system development’.

  Task 2.2 - Individual actuator development: This task is still on-going. The prototypes of
  two versions of the wireless lighting switch have been developed and used in the
  demonstration. The initial investigation to Honeywell central heating radiator valve CM
  Zone has been made, which is not open to any non-Honeywell wireless module. A
  mechanic design of the radiator valve is on-going. An experimental rig has been set-up
  for the radiator valve testing.

  Task 2.4 - Routing algorithm development: As the source code of the Jennic wireless
  library is not open to the user it will be difficult for us to develop a complete new routing
  algorithm for the IndeedNet. The AODV (ad hoc on-demand distance vector) has been
  implemented by using the Jennic wireless library, and need to be tested in a multi-end
  devices and multi-router environment.

  Task 2.5 - Energy saving control system development: This task has not been started.

  Part of the deliverable of Work package 2 is a wireless light switch design report which
  will be uploaded in the project web site after approved by the consortium.



Exceptions
                                                NONE




Recommendations

                                                NONE




Project Quarterly Progress                         2
Report
Template Issue 3.0
                                                              th
DTI TECHNOLOGY PROGRAMME                                Date: 9 Nov 2007
Project Quarterly Progress Report Q3                    Ref: Q3progress
Project Title IndeedNET                                 Version: 1

Technical Progress


NOTE: Only work packages WP2 and WP5 have been worked on during Q2


 Work Package Number : WP2 - System components implementation

 Actual Starting month: August 2007
 Predicted / Actual End month : January 2008

 Work Package Objectives:
   1. Design individual sensors
   2. Design individual actuators
   3. Design routing algorithms for wireless sensors and actuators
   4. Design two-way communication of wireless sensors and actuators
   5. Design safety and security system for IndeedNET system
   6. Design energy saving control system

 Description of work this period

 Loughborough University and Sure Technology with other industrial partners in the consortium are
 working on the objectives 1, 2, and 3 during this period.



 Progress towards the Deliverables for this Work Package
 1. Lighting and temperature sensors have been identified and used in the experiments (D3).
 2. Two versions of wireless lighting switches have been designed. The prototypes work well (part of
 D4).
 3. AODV routing algorithms have been implemented in the wireless network (D6).


 Summarise any variations from the Second Level Plan, giving reasons and action to recover
 situation if necessary.
 - Variations: Task 2.1 has been modified. Focus on selecting sensors from the market rather than
 developing sensors
 - Reason: many sensors are available in the market.
 - Recovery plan: no effect to the project.


 Description of planned activity for next quarter
  Task 2.2: Produce a prototype of the wireless central heating radiator valve.
 Task 2.3: Demonstrate two-way communication between wireless sensors and actuators
 Task 2.5: Develop an energy saving control system algorithm.




Project Quarterly Progress                          3
Report
Template Issue 3.0
                                                               th
DTI TECHNOLOGY PROGRAMME                                 Date: 9 Nov 2007
Project Quarterly Progress Report Q3                     Ref: Q3progress
Project Title IndeedNET                                  Version: 1




 Work Package Number : WP 5 – Project Management

 Actual Starting month : February 2007
 Predicted / Actual End month : January 2009

 Work Package Objectives:

             Project Coordination
             Project Risk Management
             Financial Management
             Technical Management
             Knowledge Management.

 Description of work this period

       Advantica
        Advantica will coordinate the research and dissemination activities and ensure that partners
        perform their respective activities accordingly.

      Loughborough University
       Loughborough University will prepare all the technical documents for project management

       EMHA, Sure
        EMHA and Sure will collaborate with Advantica and Loughborough in all the research and
        dissemination activities in their specialist areas, and produce their reports.

 Progress towards the Deliverables for this Work Package

  In the role as Project Manager, Advantica organised and chaired the second project
                                       th
 progress project meeting on the 30 of October 2007. The meeting was held at the
 offices of Sure Technology and was attended by representatives from Loughborough
 University and Sure Technology. Apologies were received from the EMHA; this was not
 considered to be an issue for the group as this partner’s involvement is not critical in
 these initial stages of the project. EMHA have offered to host the next meeting planned
 for January 2008.

 The DTI appointed Monitoring officer; Mike Patterson also attended the meeting.

 Minutes of the meeting have been circulated. A final copy will be sent to the Monitoring
 Officer.

 Actions arising from the meeting are being dealt with as appropriate.

 During this reporting period Advantica has successfully submitted a grant claim to the
 Technology Strategy Board covering the first two quarters of the project.




Project Quarterly Progress                           4
Report
Template Issue 3.0
                                                               th
DTI TECHNOLOGY PROGRAMME                                 Date: 9 Nov 2007
Project Quarterly Progress Report Q3                     Ref: Q3progress
Project Title IndeedNET                                  Version: 1

 Summarise any variations from the Second Level Plan, giving reasons and action to recover
 situation if necessary.
 - variations        NONE
 - reason
 - recovery plan


 Description of planned activity for next quarter
 Continue working through the tasks 5.1 to 5.5 as outlined in the Second Level Project Plan.
  The next project progress meeting is planned for mid January 228 and will be hosted by EMHA




Project Management and Collaboration
  Summarise any management concerns and activities to recover the situation.

   No concerns at this stage of the project. The relevant parts of Work Package 2 were completed on
  schedule to support the deliverables planned for January 2008




  Detail any liaison activities with other projects and with the wider programme activities.

  The consortium and DTI Monitoring Officer have recognised that the full development of a wireless
  radiator valve might not be realistic in this project. It was agreed that a prototype valve would be
  sufficient for the demonstration phase of the project.




  Detail any publication or other dissemination activity.

  The IndeedNET project web site is operational and documents are regularly added to the site.

  Loughborough University has help prepare an article covering the project for the Carbon Innovation
  Bulletin




Project Quarterly Progress                           5
Report
Template Issue 3.0
                                                                   th
DTI TECHNOLOGY PROGRAMME                                     Date: 9 Nov 2007
Project Quarterly Progress Report Q3                         Ref: Q3progress
Project Title IndeedNET                                      Version: 1




Milestone and Deliverable Status
Summarise the composite project progress against all project milestones and deliverables, noting any
discrepancies against the Second Level Plan and action to recover situation if necessary.

Use Green text for completed, Red for late and Blue for items due in the next quarter.

Ref        Title                       WP    Responsibility      Due    Actual   Comments
                                                                 Date   Date
M1         Completion of               WP1   LU                  7/07   7/07     Deliverable report issued
           IndeedNET simulation
M2         Completion of IndeedNET     WP2   LU / Sure           1/08            The prototypes of lighting
           components design                                                     switches has been produced.
M3         Completion of integrated    WP3   LU / Advantica      7/08
           IndeedNET
M4         Completion of testing and   WP4   LU / Advantica      1/09
           demonstration




Updated Schedule

Provide an updated Gantt chart for the entire project as an attachment if necessary.

Gantt Chart in the second level project plan has not changed


Project Spend Profile

Attach the latest Project Financial Spreadsheet with up to date actual and forecast expenditure.

  Explain the reasons for any deviations in spending from the baseline or previous forecast
  expenditure.

Project Quarterly Progress                               6
Report
Template Issue 3.0
                                                              th
DTI TECHNOLOGY PROGRAMME                                Date: 9 Nov 2007
Project Quarterly Progress Report Q3                    Ref: Q3progress
Project Title IndeedNET                                 Version: 1


  Waiting cost statements from the Partners. Once received, consideration will be given to updating the
  project spend profile




Updated Project Risk Register

Some changes were agreed to the Risk Register at the progress meeting held in October 2007. A
revised copy is to be circulated fro review and when confirmed will be posted on the website.



Updated Project Issue Register

No project issues at this stage.




Partner Progress Reports

Attach all partner progress reports to this report, including one from the Lead Partner.

Attach Minutes of Progress Meetings and other supporting evidence (presentations etc) as appropriate.




Project Quarterly Progress                          7
Report
Template Issue 3.0
                                                              th
DTI TECHNOLOGY PROGRAMME                                Date: 9 Nov 2007
Project Quarterly Progress Report Q3                    Ref: Q3progress
Project Title IndeedNET                                 Version: 1

                                Monitoring Officer’s Report
Overall Assessment
  Provide an assessment of the overall project achievements since the last progress report. Highlight
  any deviation from the Second Level Plan and provide recommendations to Contractor/DTI as
  necessary.

  The project is continuing to make good technical progress and is now starting to focus on
  exploitation matters, which are raising commercial discussions between the partners. A register of
  IP is now necessary to facilitate the sharing of technology within the project.

  Q3 technical effort has focused on WP2 and is slightly ahead of plan.

  The project team has made a grant claim for Q1 and Q2, and await the payment from the
  Technology Strategy Board. Detailed finances were not available for the Q3 review but are being
  collated for discussion in November.




Exceptions and Issues
    Technical progress is slightly ahead of plan.




Recommendations

   To formalise the ownership of background IP through a risk register to facilitate the sharing of
  technology in the project. The register can be used to record foreground IP as well.




Project Quarterly Progress                          8
Report
Template Issue 3.0
                                                               th
DTI TECHNOLOGY PROGRAMME                                 Date: 9 Nov 2007
Project Quarterly Progress Report Q3                     Ref: Q3progress
Project Title IndeedNET                                  Version: 1

Technical Progress
  Assess the progress of the technical work on a work package by work package basis.
   Q3 technical effort has focused on WP2 and is slightly ahead of plan. The Loughborough University
  team have now demonstrated how to switch a light by either Zigbee or manual means. Sure
  Technology has background IP relating to this that will be adopted. Having investigated the possible
  use of the Honeywell CRM radiator valve and found the manufacturers resistant to revealing
  commercial information, LU have designed a valve that although impractical for volume production,
  will adequately demonstrate system functionality. Sure Technology have innovative background
  ideas as to how a low power commercial valve might be constructed. These may be incorporated into
  the system in due course.


Partners and Project Management
  Assess the adequacy of the project management arrangements.
   Project management by Advantica continues to be professional and commensurate with the
  collaboration needs. Formal governance procedures have now been agreed.




Collaboration
 Assess the level of collaboration between partners and between the project and related projects and
 KTN activities.
  It is evident that partners have met between formal meetings and the collaboration between Sure
 technology and Loughborough University is now the technical focus of the project.

  East Midlands Housing Association have expressed a wish to become more engaged and the next
  meeting will be held at their offices and examine areas of prospective need and potential IndeedNet
  applications



Equipment and Facilities
  Assess the benefit to the project of any purchases, facility rental etc

  Not applicable.




Progress against Deliverables, Milestones and Schedule
 Note any variations from schedule. Identify any impact on the overall timescales and dependencies.
 No variations.




Project Quarterly Progress                           9
Report
Template Issue 3.0
                                                                th
DTI TECHNOLOGY PROGRAMME                              Date: 9 Nov 2007
Project Quarterly Progress Report Q3                  Ref: Q3progress
Project Title IndeedNET                               Version: 1


Project Spend Profile - See Spreadsheet Provided by Lead Partner

  Assess whether the grant claim for each partner is consistent with the deliverables achieved, noting
  that monies must be committed and defrayed before claim.

  Note any variation in the spend categories and profile and assess its likely impact.
  The Q1 grant claim was consistent with progress.

  The forward spend profile will be revised in Q4 2007.




Human Resources

  Assess whether the project resources appear satisfactory and are being effectively deployed.
  The resources appear to be deployed effectively.




IPR, Beneficial Ownership, Publications and Confidentiality

  Note any issues regarding IPR or beneficial ownership.
  Note any issues regarding publications and confidentiality.
  None as yet but a risk register is to be created.




Dissemination
  Comment on any dissemination, publication or involvement in KTN or other activities.
  Loughborough University has published a press release on its website. Advantica has published a
  brief article; both articles were cleared through the Technology Strategy Board Media Relations
  Manager.

  The project team is aware of the Technology Strategy Board’s wish to promote projects.




Project Quarterly Progress                         10
Report
Template Issue 3.0
                                                             th
DTI TECHNOLOGY PROGRAMME                              Date: 9 Nov 2007
Project Quarterly Progress Report Q3                  Ref: Q3progress
Project Title IndeedNET                               Version: 1



Exploitation Plans
  Detail the progress on development of exploitation plans and assess their likely impact.
   The project team is now actively engaged in discussing exploitation planning issues. This has led to
  their recognising the need for a formal register of background and foreground IP.

  The team recognises that partnering will be critical to the successful exploitation of the system and the
  concept will be introduced in outline form in November, to a major energy supplier. This will gain useful
  feedback as to market needs.
  An approach has been received from a boiler controls innovator who wishes to collaborate with the
  team – this is being considered.


Financial Evidence
  Note any concerns over the adequacy of the supporting financial evidence and make
  recommendations to the Contractor/DTI.

  Note whether the 85% spend limit has been reached by any partner.
  No concerns for Q1 and Q2. Finances for Q3 will be reviewed with Len Eastell




Problems
   Summarise any concerns over the project. Assess the likely impact of these concerns and make
  recommendations as necessary to the Contractor/DTI for resolution of the problems.
  No major concerns.




Project Quarterly Progress                         11